February 2013
Consultant Delivery Guide
data migration starter pack for SAP solutions
WE LISTEN • WE PARTNER • WE SUCCEED
» Project Planning■ Service Organization
■ Service Delivery Team (Coeus / Customer)
■ Timelines
» Rapid Data Migration Overview■ Service Description
■ Key Deliverables
■ Service Building Blocks
» Step-by-Step Guidelines for Service Delivery■ Detailed guidelines can be found in RDS Step-by-step guide
» Further Information■ On-boarding information for the project team
■ FAQ
■ Tips & Tricks
Consultant Delivery Guide
WE LISTEN • WE PARTNER • WE SUCCEED
Data migration starter pack for SAP solutionsHigh-Level Service Description
What is the data migration starter pack for SAP solutions?Designed for SAP Rapid Deployment Solution (RDS) customers looking to migrate their current data to SAP ERP, CRM or Utilities
A jump-start on data migration with a mature information management infrastructure & proven implementation methods
An approach based on Rapid Deployment Solution packages with fixed scope and fixed price
A service targeted to small and midsize enterprises as well as dedicated business units of large enterprises
What is the data migration starter pack for SAP solutions?Designed for SAP Rapid Deployment Solution (RDS) customers looking to migrate their current data to SAP ERP, CRM or Utilities
A jump-start on data migration with a mature information management infrastructure & proven implementation methods
An approach based on Rapid Deployment Solution packages with fixed scope and fixed price
A service targeted to small and midsize enterprises as well as dedicated business units of large enterprises
Customer AdvantagesOriented toward customer needs
Fast and cost-effective solution reducing project risks
Based on predefined business content and user-friendly SAP BusinessObjects Data Services Tool
Professional consultancy
Customer AdvantagesOriented toward customer needs
Fast and cost-effective solution reducing project risks
Based on predefined business content and user-friendly SAP BusinessObjects Data Services Tool
Professional consultancy
Rapid Data Migration
SAP DATA SERVICES
RDS RDS CONTENT & CONTENT & APPROACHAPPROACH
TARGET TARGET PREDEFINED PREDEFINED
BUSINESS BUSINESS CONTENTCONTENT
WE LISTEN • WE PARTNER • WE SUCCEED
Rapid Data Migration ContentMajor Components of SAP Data Migration software SAP Data Services: Data management platform to support all migration tasks
SAP BusinessObjects BI*: Includes Xcelsius, Webi, Crystal for reporting
SAP Information Steward*: Source data profiling
Software components
Rapid data migration content components
Migration content loaded into Data Services.
WebIntelligence reports for monitoring the data migration.
Migration services to map source data to SAP business context.
Migration content for reconciling what was loaded in the target from the source.
*optional component
WE LISTEN • WE PARTNER • WE SUCCEED
Software Requirements for ERP/CRM PackageProduct Product Version Component Logical Component in
SAP Solution Manager*Comments
SAP ERP SAP ECC6 EHP3 or above SAP_APPL release 603 or above Not required For ERP objects
SAP ERP SAP ECC6 EHP4 or above SAP_HR release 604 or above Not required For HCM objects
SAP ERP SAP ECC6 EHP3 or above EA-RETAIL release 603 or above Not required For Retail objects
SAP CRM SAP CRM 7.01 or above Not required For CRM objects
SBOP BI Platform 4.0 - ENTERPRISE Server
SP04 or above Not required
SBOP BI Platform 4.0 – Enterprise Client Tools
SP04 or above Not required
SBOP Data Services 4.1 SP00 Patch2 or above Not required
SBOP Information Steward 4.1
SP01 or above Not required For Data Profiling and Data Quality
WE LISTEN • WE PARTNER • WE SUCCEED
Software Requirements for Utilities PackageProduct Product Version Component Logical Component in
SAP Solution Manager*Comments
SAP Solution Manager SAP Solution Manager 7.0 SAP EHP 1 for SAP Solution Manager 7.0
Not required Optional implementation tool
SAP ERP SAP ERP 6.0 SAP ECC Server ERP60_ECCSERVER
SAP ERP ENHANCE PACKAGE
EHP4 FOR SAP ERP 6.0 SAP ECC Server Pack successor
ERP60_EHP4_ECCSERVER
SAP Utilities/Telecommunication
SAPK-60401INISUT SAP IS-UT Not required
Fast-Track Implementation for SAP Utilities
EHP4 FOR SAP ERP 6.0 Not Applicable Logical SOLMAN Component
Contact SAP Consulting for details
SBOP BI Platform 4.0 - ENTERPRISE Server
SP04 or above Not required
SBOP BI Platform 4.0 – Enterprise Client Tools
SP04 or above Not required
SBOP Data Services 4.1 SP00 Patch2 or above Not required
SBOP Information Steward 4.1 SP01 or above Not required For Data Profiling and Data Quality
WE LISTEN • WE PARTNER • WE SUCCEED
Data migration to SAP systemArchitectureLegacy Data Environment
XML
Applications
Databases
Flat Files/Excel
Loading
Extract & Profile
Data Staging and Test Environment
Staging Area
Data Services Platform
Cleanse
Name Parsing
Address Parsing & CorrectionMaterial/Product ParsingMatching
SAP Configuration
Extraction
Reconciliation
Performance Analysis
Dashboards and Business Reporting
Validate & Load
Business Validation
RulesAutomatic SAP Config Validation
Transform
TransformData into SAP
structure
Transparency, Communication and
Governance
Target Environment
SAP
ISMW file or iDocs
Pre-Built load routines for SAP
Objects
WE LISTEN • WE PARTNER • WE SUCCEED
This solution provides data migration to the SAP Rapid Deployment Solution (RDS) for ERP, CRM or Utilities. The solution covers the migration of a different number of objects depending on the selected scenario(s). The solution will include
All required components, mapping and migration content in Data Services,
Reports & dashboards for performance analysis Software installation (optional)
Includes implementation in 2 environments (Development and Production) Possible scenario:
ERP and/or CRM can be selected Utilities can be selected
Number of migrated objects: ERP: 5 (3 masters and 2 transactionals) CRM: 8 object types including 19 objects Utilities: 25 objects
Opportunities Customer has chosen SAP ERP, CRM or Utilities to replace their legacy
system Customer has to make decision on ETL vendor to extract and transform data
from legacy sources to be ready for loading into SAP system.
Best practice functionality based on prescriptive scope
Reduced implementation costs and realization time
Fast to deploy
Benefits
Efforts
Further Information
Service Description
Delivery Method: Remote & Onsite with local region and GD Implementation:
ERP : up to 11 weeks CRM: up to 15 weeks; Utilities: up to 34 weeks
SBO Software: Data Services 4.1 Enterprise BI 4.0 (optional), Information Steward 4.1
Contact: Global – Jerome.Delune@sap.com ,
Experienced, qualified consultants Automation of extraction and
transformation logic. Fixed-price model and
preconfigured processes
Content of Service
Related ServicesAfter this service, you can add the following services: IT SDO RDS Implementation of Data Archiving Strategy Implementation of Data Cleansing Strategy Data Governance & Master Data Management
Rapid Data Migration to SAP ERP/CRM/UtilitiesMaster Service Description
Start phase includes: Workshops to confirm predefined requirements
Deploy phase optionally includes: Software Installation services as a part of this Service for
twoenvironments (dev and prod) Deploy phase includes:
Installation and configuration of the RDS content Data profiling, mapping workshops, mapping of the selected
objects and testing in DEV environment Training to key users Up to three mock-up test runs
Run phase (Go-Live): Support a pilot go-live for data migration
WE LISTEN • WE PARTNER • WE SUCCEED
Service Building Blocks (On Premise)SAP ERP-CRM Package (RDM_ERP_CRM_DS41)
Possible Service Flavors: Base Module + Install Module (if required) + Starter Module for ERP and/or CRM (at least 1 based on scope customer chooses)
Installation Module
Base Module (Common to all Options Modules)
Installation of SAP Data Services 4.1, BI 4.0 (optional), Information Steward 4.1
Base/Frame Service to kick off the service and define the scope for the implementing modules. The Base includes standard project activities that are generic and can be combined with all described modules
Note: No common deployment activities of the Migration Starter Service
Specific set up of the Migration Starter Service
Migration implementation of the objects defined in the Base Module
Test and Go-live Support
Note: 5 objects (3 masters + 2 transactions) out of the ERP list of objects
ERP Starter Module
Specific set up of the Migration Starter Service
Migration implementation of the objects defined in the Base Module
Test and Go-live Support
Note: Migration of the 8 object types in the list of CRM objects
CRM Starter Module
WE LISTEN • WE PARTNER • WE SUCCEED
Service Building Blocks (On Premise)SAP Utilities Package (RDM_CRM_UTIL_DS41)
Possible Service Flavors : Base Module + Install Module (if required) + Starter Module for Utilities
Installation Module
Base Module (Common to all Options Modules)
Installation of SAP Data Services 4.1, BI 4.0 (optional), Information Steward 4.1
Base/Frame Service to kick off the service and define the scope for the implementing modules. The Base includes standard project activities that are generic and can be combined with all described modules
Note: No common deployment activities of the Migration Starter Service
Specific set up of the Migration Starter Service
Migration implementation of the objects defined in the Base Module
Test and Go-live Support
Note: Migration of 25 objects
Utilities Starter Module
WE LISTEN • WE PARTNER • WE SUCCEED
List of Objects for the ERP Starter Module■ Service Master
■ Accounts Payable/Receivable
■ Work Centers
■ Service Master
■ Equipment
■ Standard hierarchy
■ Profit Centers
■ Cost Centers
■ Exchange Rates
■ Object Dependencies
■ Sales Orders
■ Purchase Orders
■ Internal Order
■ Source List
■ Work Breakdown Structure
■ Functional Locations
■ Bank
■ Configuration Profiles for Material
■ Fixed Assets
■ Functional Location
■ Purchasing Requisitions
■ Contracts
■ Scheduling agreements
■ Material stocks WM
■ Reference operation set
■ Order reservation
■ Planned independents requirements
■ Open deliveries
Master Data ObjectsTransactional Data Objects
■ Secondary Cost Elements
■ Characteristic Master
■ Class Master
■ Activity Types
■ Activity Prices
■ Customer Master
■ Vendor Master
■ Material Master
■ Material Classification
■ Material QM Inspection Type
■ Material External Customer Replenishment
■ Purchasing Info Records
■ Inspection Methods
■ Master Inspection Characteristics
■ Inspection Plans
■ Bill of Materials
■ Routings
■ SD Pricing
■ Inventory Balances
WE LISTEN • WE PARTNER • WE SUCCEED
Deliverables
Servers and Software Installed
List of Options Selected
ERP/CRM: Licensee data cleansed (if needed)
Utilities: Licensee data cleansed (as per scope in section 1)
User Acceptance Testing
Switch to Production
End user Training
Go Live and go live support
Servers and Software Installed
List of Options Selected
ERP/CRM: Licensee data cleansed (if needed)
Utilities: Licensee data cleansed (as per scope in section 1)
User Acceptance Testing
Switch to Production
End user Training
Go Live and go live support
Customer
Kick Off Workshop
Installation Module : Installation of SAP Data Services, SAP Information Steward and SAP Business Intelligence
Confirm Installation
Activation of Solution
Confirm Activation of Solution
Key User Training Workshop
Go-Live assistance.
Kick Off Workshop
Installation Module : Installation of SAP Data Services, SAP Information Steward and SAP Business Intelligence
Confirm Installation
Activation of Solution
Confirm Activation of Solution
Key User Training Workshop
Go-Live assistance.
Coeus
WE LISTEN • WE PARTNER • WE SUCCEED
List of Objects for the CRM Starter Module (1/2)
# Migration Object Description Prerequisites
BUSINESS PARTNER Business Partner – Customers
BUSINESS PARTNER Business Partner – Contact Persons
BUSINESS PARTNER Business Partner – Employees
BUPA_HIER Business Partner Hierarchies
BUPA_REL Business Partner Relationships
BUSINESS TRANSACTION Business Transaction – Tasks
BUSINESS TRANSACTION Business Transaction – Activities
ORG STRUCTURE Enterprise Organizational Structure
EXCHANGE_RATE Exchange Rates
BUSINESS TRANSACTION Business Transaction – Knowledge Articles
BUSINESS TRANSACTION Business Transaction – Incidents
BUSINESS TRANSACTION Business Transaction – Problems
BUSINESS TRANSACTION Business Transaction – Service Requests
1
2
3
4
5
6
7
8
9
10
11
12
13
1
3
21 3
1
2
3
2
3
21 3
21 3
21 3
WE LISTEN • WE PARTNER • WE SUCCEED
List of Objects for the CRM Starter Module (2/2)
# Migration Object Description Prerequisites
BUSINESS TRANSACTION Business Transaction – Requests for Change
PRODUCT_MAT Product – Materials
PRODUCT_SRV Product – Services
BUSINESS PARTNER Business Partner – Prospects
BUSINESS TRANSACTION Business Transaction – Leads
BUSINESS TRANSACTION Business Transaction – Opportunities
15
14
16
17
18
19
2
17
31
9
9
15 162 171
WE LISTEN • WE PARTNER • WE SUCCEED
List of Objects for the Utilities Starter Module (1/2)
# Migration Object Description Prerequisites
PARTNER Business Partner
PART_REL Business Partner Relationship
ACCOUNT Contract Account
DEVICE Device
CONNOBJ Connection Object
PREMISE Premise
DEVLOC Device Location
NOTE_DLC Notes to Field Service for Connection Object
INSTLN Utility Installation
FACTS Individual Facts for Utility Installation
INSTMGMT_T Installation Management Technical
INSTMGMT_B Installation Management Billing – Related
MOVE_IN Move In Contract
1
2
3
4
5
6
7
8
9
10
11
12
13
1
5
7
6
9
4 7
4 9
3 9
1
4 9
2
5 6
5
WE LISTEN • WE PARTNER • WE SUCCEED
List of Objects for the Utilities Starter Module (2/2)
# Migration Object Description Prerequisites
DOCUMENT FI-CA Document
INSTPLAN Instalment Plan
SECURITY Security Deposit
STRT_ROUTE Meter Reading Sequence
METERREAD Meter Reading
BCONTACT Customer Contact
BCONT_NOTE Notes
PROPERTY Owner Assignment
BBP_EXT Budget Billing Plan with External Scheduling
DISC_DOC Disconnection Document
DISC_ORDER Disconnection Order
DISC_ENTER Disconnection
24
25
15
14
16
17
18
19
20
21
22
23
3
4
4
1
19
23
9
131
3 141
1 3
5 63 91
3 9 131
4 9 133
9 134
WE LISTEN • WE PARTNER • WE SUCCEED
» Project Planning■ Service Organization
■ Service Delivery Team (Coeus / Customer)
■ Timelines
» Rapid Data Migration Overview■ Service Description
■ Key Deliverables
■ Service Building Blocks
» Step-by-Step Guidelines for Service Delivery■ Detailed guidelines can be found in RDS Step-by-step guide
» Further Information■ On-boarding information for the project team
■ FAQ
■ Tips & Tricks
Consultant Delivery Guide
WE LISTEN • WE PARTNER • WE SUCCEED
Project Sponsor
Resourcing
CEMCustomer Project
Manager
Organization
Coeus Project Manager
Technology Consultant(s)
Application Consultant(s)
Technology Consultant(s)
Application Consultant(s)
WE LISTEN • WE PARTNER • WE SUCCEED
Customer Team Responsibilities–Project Manager
•Technical and functional project management
•Coordination of interfaces
•Risk Management
•Organization of project meetings and status update
•Controlling of the overall project
•Controlling of project progress and results (including project reporting)
•Main contact and reporting to the Project Sponsor
–Technology Consultant(s)
•Contribute to the implementation of the Rapid Data Migration
•Work alongside the Coeus team for the duration of the RDS to fast track skills.
•Be part of the customer Rapid Data Migration team once the RDS has been completed
•ABAP skills
•IDoc skills (ERP/CRM)
Application Consultant(s)
•Expert advice and guidance on ERP/CRM/Utilities business areas and processes
•A central point of contact for ERP/CRM/Utilities related questions
•Document requirements for TO BE gap analysis
•Expert advice and guidance on ERP/CRM/Utilities business areas and processes
•A central point of contact for ERP/CRM/Utilities related questions
WE LISTEN • WE PARTNER • WE SUCCEED
Coeus Team Responsibilities–Project Manager
•Technical and commercial project management
•Ensures delivery & status of Coeus’s deliverables
•Liaises with customer Project Manager for status reporting
•Controls Coeus resourcing
–Application Consultant(s)
•Lead the data quality assessment and data mapping between source and target system
•Provide key input on SAP target structure and business rules for the data mapping
•Support Customer in the configuration of SAP target environment
Lead Technology Consultant
•Serve as a central contact person throughout the RDS implementation
•Install and configure the EIM&BI software and best practices content
•Provide technical leadership on the use of tools to perform ETL and data profiling
•Implement the data mapping within Data Services
•Jointly responsible for the data mapping
•Present the data quality demonstration if in scope
•Run data migration end-to-end tests
•Provide knowledge transfer and RDS handover
Technology Consultants
•Implement the data mapping within Data Services
•Run data migration end-to-end tests
WE LISTEN • WE PARTNER • WE SUCCEED
SelectionERP + Install
ModulesCRM + Install
Modules
Utilities + Install
ModulesERP Module CRM Module
Utilities Module
ERP + CRM + Install
Modules
ERP + CRM Modules
Installation
ERP
CRM
Utilities
Duration 55 days 55 days 170 days 52 days 52 days 167 days 105 days 99 days
Modular Selection
WE LISTEN • WE PARTNER • WE SUCCEED
Summary: Organization, Roles, Effort EstimationBase Service + Installation Module + ERP Module Service (Delivery) Owner/s: Jerome Delune
Expected Service Delivery Time: 11 Weeks
WE LISTEN • WE PARTNER • WE SUCCEED
Summary: Organization, Roles, Effort EstimationBase Service + Installation Module + CRM Module
Service (Delivery) Owner/s: Jerome Delune
Expected Service Delivery Time: 15 Weeks
WE LISTEN • WE PARTNER • WE SUCCEED
Summary: Organization, Roles, Effort EstimationBase Service + Installation Module + Utilities Module Service (Delivery) Owner/s: Jerome Delune
Expected Service Delivery Time: 34 Weeks
WE LISTEN • WE PARTNER • WE SUCCEED
DEPLOYDEPLOYDEPLOYDEPLOY RUNRUNRUNRUN
Adapt and send pre-delivery requirements to the customer
Install DS & BI
Configure RDS
Extraction and Profiling
Conduct Data Migration Workshop
Data Mapping
Unit Test Solution
Train Key Users
Mock Runs
Hand over Solution
Go live
Prepare Project
Perform Kick-off Workshop
Select Options
Check Installation
Go-Live Support
Coeus involvement Customer involvement
2-6 weeks before
After Go-Live
STARTSTARTSTARTSTART
Week 1 Week 2 - 10 FINISHSTART
Project InvolvementBase Service + Installation Module + ERP Module
Week 11
WE LISTEN • WE PARTNER • WE SUCCEED
DEPLOYDEPLOYDEPLOYDEPLOY RUNRUNRUNRUN
Adapt and send pre-delivery requirements to the customer
Install DS & BI
Configure RDS
Extraction and Profiling
Conduct Data Migration Workshop
Data Mapping
Unit Test Solution
Train Key Users
Mock Runs
Hand over Solution
Go live
Prepare Project
Perform Kick-off Workshop
Select Options
Check Installation
Go-Live Support
Coeus involvement Customer involvement
2-6 weeks before
After Go-Live
STARTSTARTSTARTSTART
Week 1 Week 2 - 14 FINISHSTART
Project InvolvementBase Service + Installation Module + CRM Module
Week 15
WE LISTEN • WE PARTNER • WE SUCCEED
DEPLOYDEPLOYDEPLOYDEPLOY RUNRUNRUNRUN
Adapt and send pre-delivery requirements to the customer
Install DS & BI
Configure RDS
Extraction and Profiling
Conduct Data Migration Workshop
Data Mapping
Unit Test solution
Train Key Users
Mock Runs
UAT
Hand over Solution
Go live
Prepare Project
Perform kick-off Workshop
Select Options
Check Installation
Go-Live Support
Coeus involvement Customer involvement
2-6 weeks before
After Go-Live
STARTSTARTSTARTSTART
Week 2 Week 3 - 31 FINISHSTART
Project InvolvementBase Service + Installation Module + Utilities Module
Week 32
WE LISTEN • WE PARTNER • WE SUCCEED
Project PlanningBase Service + Installation Module + ERP Module
START
Kick-off / Scope completed
DEPLOY
Solution activated and confirmed
2 Mock Runs
FINAL PREPARATION
Production cutover / Switch to Production
1
2
3
4
Week 1
Week 9
Week 10
Week 11
Software Installation
RDS Configuration
Extraction and Profiling
Data Mapping Workshop
Modifying DS Jobs & Unit Testing
Knowledge Transfer
Week 2
Week 4
Week 8
PILOT GO LIVE
WE LISTEN • WE PARTNER • WE SUCCEED
Project PlanningBase Service + Installation Module + CRM Module
START
Kick-off / Scope completed
DEPLOY
Solution activated and confirmed
2 Mock Runs
FINAL PREPARATION
Production cutover / Switch to Production
1
2
3
4
Week 1
Week 10
Week 14
Week 15
Software Installation
RDS Configuration
Extraction and Profiling
Data Mapping Workshop
Modifying DS Jobs & Unit Testing
Knowledge Transfer
Week 2
Week 4
Week 6
PILOT GO LIVE
WE LISTEN • WE PARTNER • WE SUCCEED
Project PlanningBase Service + Installation Module + Utilities Module
START
Kick-off / Scope completed
DEPLOY
Solution activation and confirmation
3 Mock Runs
FINAL PREPARATION
Production cutover / Switch to Production
1
2
34
Week 2
Week 31
Week 33
Week 34
Software Installation
Extraction and Profiling
Data Mapping Workshop
Modifying DS Jobs
Knowledge Transfer
Week 3Week 4
Week 8
RDS Configuration
Week 13
Week 18
String Test
Week 24Week 25
Mock Run 1
Week 27 Mock Run 2
Week 29
PILOT GO LIVE
WE LISTEN • WE PARTNER • WE SUCCEED
» Project Planning■ Service Organization
■ Service Delivery Team (Coeus / Customer)
■ Timelines
» Rapid Data Migration Overview■ Service Description
■ Key Deliverables
■ Service Building Blocks
» Step-by-Step Guidelines for Service Delivery■ Detailed guidelines can be found in RDS Step-by-step guide
» Further Information■ On-boarding information for the project team
■ FAQ
■ Tips & Tricks
Consultant Delivery Guide
WE LISTEN • WE PARTNER • WE SUCCEED
1. STARTFlow of activities
Customer Coeus Manager Coeus Technical Coeus Functional
1. Receive delivery activation notification
1. Receive delivery activation notification
DeployDeployDeployDeploy
2a. Call customer, confirm expectations, dates, and next
steps
2a. Call customer, confirm expectations, dates, and next
steps
3. Agree on all dates for scheduled activities
3. Agree on all dates for scheduled activities
4a. Update delivery team, send status e-mail
4a. Update delivery team, send status e-mail
5. Perform Kick -Off Workshop5. Perform Kick -Off Workshop
7. Complete Prerequisites7. Complete Prerequisites 6. Send Pre-Delivery Checklist6. Send Pre-Delivery Checklist
8. Confirm Prerequisites are Complete
8. Confirm Prerequisites are Complete
2b. Provide Personalization Information
2b. Provide Personalization Information
4b. Consultant Ramp Up4b. Consultant Ramp Up
9. Acceptance Sign Off9. Acceptance Sign Off
WE LISTEN • WE PARTNER • WE SUCCEED
1. START Phase Overview – Key Activities
1.1 Receive signed Statement of Work Yes / No
1.2a
Call customer, confirm expectations, agree on dates –•Review the detailed activity plan provided in the Schedule worksheet in the Schedule and Effort Estimation Excel. This will provide an overview of the task hierarchies for the service
•Review the key deliverables and the contractually stipulated deliverables listed in the WBS of Deliverables
Yes / No
1.2b Customer provides all the Personalization Information Yes / No
1.3 Agree on dates for all scheduled activities. Yes / No
1.4a Update delivery team, send status e-mail to sales/consulting manager / project manager… Yes / No
1.4b Ramp up the consultant Yes / No
1.5
Prepare for workshop. Coeus’s and the customer’s project manager jointly prepare for the project kick-off workshop. Coeus’s solution architect prepares the workshop content. Conduct Kick-off, Business Process Knowledge Transfer and Options workshop. A one day workshop is held to:
•Demonstrate the packages (as part of business process knowledge transfer) to be implemented and to define the project steps and basic configurations (such as master data replication).
•Discuss and decide upon customer-specific options.
Yes / No
# Description Completed
WE LISTEN • WE PARTNER • WE SUCCEED
1. START Phase Overview – Key Activities
1.6Send prerequisites to the customer – •Read and review the Pre-delivery Requirements and Checklist and then send it to the customer
Yes / No
1.7
The customer should have installed the software components prior to the start of the project and created all necessary user IDs for the project team in the systems as defined in the pre-requisites.The customer ensures that they are all fulfilled (e.g. installed software, create support user/s, open remote connection).The customer confirms all the pre-requisites
Yes / No
1.8 Consultants confirm in turn that the pre-requisites are all met Yes / No
1.9 Start Phase Acceptance Sign-off Yes / No
• Pre-delivery Checklist
• Scoping Questionnaire
• Customer environment is ready for starting the Deploy phase
Key Outputs or Deliverables
# Description Completed
WE LISTEN • WE PARTNER • WE SUCCEED
2. DEPLOY Phase Flow of activities Customer Project Manager Coeus Technical Coeus Functional
1.1. Review and finalize outcome
from the workshop
1.1. Review and finalize outcome
from the workshop
1. 2 . Capture final design 1. 2 . Capture final design
4. Data ServicesInstallation and Configuration (DEV, PRD)
4. Data ServicesInstallation and Configuration (DEV, PRD)
3. Data Services Architecture Design
3. Data Services Architecture Design
5. Source Data Extraction & Profiling 5. Source Data Extraction & Profiling
6. Conduct Data Mapping Workshop 6. Conduct Data Mapping Workshop
7a. Complete BlueprintBy updating Mapping Template (XLS)
7a. Complete BlueprintBy updating Mapping Template (XLS)
7b. Answer open questions for scoping / setup7b. Answer open questions for scoping / setup
8b. Scope Acceptance / Sign Off
8b. Scope Acceptance / Sign Off
8a. Confirm Scope Fit / Gap
8a. Confirm Scope Fit / Gap
Deploy NextDeploy NextDeploy NextDeploy Next
WE LISTEN • WE PARTNER • WE SUCCEED
2. DEPLOY NEXT Flow of activities
Customer Coeus Manager Coeus Technical Coeus Functional
RunRunRunRun
10. Modify Workflows based on Blueprint & Unit Test 10. Modify Workflows based on Blueprint & Unit Test
14a. Mock Runs14a. Mock Runs
14b. User Acceptance / Sign Off14b. User Acceptance / Sign Off
9. Ensure access to Legacy data source
9. Ensure access to Legacy data source
12. Test & Troubleshoot:12. Test & Troubleshoot:
11. Map Input values in the Lookup Maintenance Application 11. Map Input values in the Lookup Maintenance Application
13. Knowledge Transfer
13. Knowledge Transfer
Deploy Deploy Deploy Deploy
WE LISTEN • WE PARTNER • WE SUCCEED
2. DEPLOY PhaseOverview – Key Activities
2.1 Review and finalize outcome from the workshop. Yes / No
2.2Capture final design. The joint project team initiates and completes the scope items decided during the workshop. Any additional scope not covered in RDS will be considered change request/change order.
Yes / No
2.3
Architecture Design must be completed for the Data Services set up. • Set up the connectivity to Source Data and conduct the Data Profiling of the legacy system.• Technical resources will deploy the Migration Services Web Application and Best Practices content• Required developer ids and admin ids will be created and updated in a configuration document.
Yes / No
2.4 Install Data Services on a 2 Tier Landscape (DEV, PRD) and Configuration of Best Practices Yes / No
2.5 Conduct the data extraction and profiling from the legacy system Yes / No
2.6 Conduct a data mapping workshop to finalize the data mapping and confirm the user defined options Yes / No
2.7Complete Blueprint by updating the Data Services mapping templatesGet feedback from the customer
Yes / No
2.8 Confirm scope and get acceptance of the scope Yes / No
# Description Completed
WE LISTEN • WE PARTNER • WE SUCCEED
2. DEPLOY PhaseOverview – Key Activities
2.9Customer to ensure that the required security access is set up properly on the Source and Target systems
Yes / No
2.10Modify the Workflows based on the updates from the Mapping WorkshopLeverage the Migration Services web application to update the Look-up Data within the database directly
Yes / No
2.11 Map Input values in the Lookup Maintenance Application Yes / No
2.12
Test & Troubleshoot:•Execute Object Processing Job•Review Invalid Output•Import SAP Data•Run Reconciliation Jobs•Business Process Check
Yes / No
2.13
Knowledge Transfer - Train Key UsersSAP consultants provide knowledge transfer to key users. The customer is responsible for developing end-user training content. Knowledge is transferred to the customer’s IT staff “on the job”. It is assumed that customer provides full-time IT personnel who can take up the ownership of production setup and support activities for going live.
Yes / No
2.14Mock Runs Customer will execute User Acceptance Testing and sign-off on UAT
Yes / No
# Description Completed
• Solution has been configured/developed• Key Users have been trained• Testing has been performed and issues resolved• Customer is ready to start the Run phase
Key Outputs or Deliverables
WE LISTEN • WE PARTNER • WE SUCCEED
3. RUN Phase
Flow of activities Customer Project Manager Senior Application Consultant Application Consultant
6. Project Acceptance and Closure
6. Project Acceptance and Closure
1.7. Sign-Off1.7. Sign-Off
Delivery Acceptance Criteria and Sign-off
1.1. Prepare End User training
1.1. Prepare End User training
5. Go-Live Support5. Go-Live Support
1.4. Set-up production system
1.4. Set-up production system
1.3. Approve tests and hand-over
1.3. Approve tests and hand-over
1.2. Execute UAT1.2. Execute UAT
WE LISTEN • WE PARTNER • WE SUCCEED
3. RUN Phase Overview – Key Activities
3.1 Customer prepares End User training and responsible for testing quality gates. Yes / No
3.2 Customer performs UAT tests. Yes / No
3.3Approve tests and hand-over solution – Customer approves tests and official hand-over of the RDS solution from consulting to customer.
Yes / No
3.4Customer prepares cut overCustomer executes cut-over plan to Production system.
Yes / No
3.5Go-Live SupportCoeus provides two to four days remote support following go-live.The customer is responsible for support after going live.
Yes / No
3.6Project Acceptance and Closure - Read and review the Delivery Acceptance Criteria and Sign-off document and then send it to the customer.
Yes / No
3.7Sign-off – Together with the customer, go through the Delivery Acceptance Criteria and Sign-off document and sign it off, capture any feedback / lessons learned.
Yes / No
• Delivery Acceptance Criteria and Sign-off
• Service Delivery completed and customer signed off
Key Outputs or Deliverables
# Description Completed
WE LISTEN • WE PARTNER • WE SUCCEED
When to Use the Templates/Guides
Start (Scoping / Setup)Start (Scoping / Setup)Start (Scoping / Setup)Start (Scoping / Setup) Deploy (Realization, Cutover & Final Prep)Deploy (Realization, Cutover & Final Prep)Deploy (Realization, Cutover & Final Prep)Deploy (Realization, Cutover & Final Prep)
Pre-Delivery Requirements and Checklist Qualification QuestionnaireSOW
Data Services Data Mapping Document Template
Data Services Quick and Configuration Guides
Business Process Documentations Test Plans and Scripts User Training
Delivery Acceptance Criteria and Signoff
Scoping Questionnaire Project Kick-off
Presentation
4 weeks before
Generic document relevant throughoutthe whole Service Delivery cycle :Generic document relevant throughoutthe whole Service Delivery cycle : Step by Step Guide Consultant Delivery Guide WBS Document
Please find the complete list accelerators in the Rapid Data Migration Bill of Material and when to use them…..
Start delivery
Run (Go-Live)Run (Go-Live)Run (Go-Live)Run (Go-Live)
WE LISTEN • WE PARTNER • WE SUCCEED
» Project Planning■ Service Organization
■ Service Delivery Team (Coeus / Customer)
■ Timelines
» Rapid Data Migration Overview■ Service Description
■ Key Deliverables
■ Service Building Blocks
» Step-by-Step Guidelines for Service Delivery■ Detailed guidelines can be found in RDS Step-by-step guide
» Further Information■ On-boarding information for the project team
■ FAQ
■ Tips & Tricks
Consultant Delivery Guide
WE LISTEN • WE PARTNER • WE SUCCEED
RDS On-boarding Information
Include engagement specific on-boarding documentation for consultants
Start Date
Location
Team/Project Introduction
Client Specific ID card application forms
Client Side Org Chart and Key members
Client Holidays
Milestone dates based on the then current date
Include engagement specific on-boarding documentation for consultants
Start Date
Location
Team/Project Introduction
Client Specific ID card application forms
Client Side Org Chart and Key members
Client Holidays
Milestone dates based on the then current date
To be prefilled before service delivery. The objective is to assure that team
members understand the customer and Logistics .
!! To be prefilled by Project Manager !!
WE LISTEN • WE PARTNER • WE SUCCEED
On-boarding documentation
Recommended Reading
<Links to customer website><Link to AIM Company Annual Report 2007>
Company Project LocationConsultants will work at the following locations:
Key Contacts at the customer site (to address logistic questions)
AccommodationAccommodations are provide by the client through an agreement with the <Hotel in City>. This hotel is located directly across the street from the client site. Every effort should be made to make Hotel reservations two weeks prior to an onsite visit and must be facilitated between the client representative and the hotel. Forward your arrival and departure date details to <Colleague> at <Mail>. <Colleague> will confirm the reservation with the client for you and send you a confirmation e-mail. When you arrive onsite take a taxi to the hotel location. <Link of Hotel>
Directions to the Company from the Hotel<Please add City Map>
To be prefilled before service delivery. The objective is to assure that team
members understand the customer and Logistics .
!! To be prefilled by Project Manager !!
<Service Phase> <Service Phase> <Service Phase>
<Address> <Address> <Address>
<Name> <Name> <Name>
<Role> <Role> <Role>
WE LISTEN • WE PARTNER • WE SUCCEED
Frequently Asked QuestionsCommon to all packages
Q: What is the value of the service to SAP?A: The RDS for Data Migration for SAP is designed to demonstrate the potential of SAP’s Data Migration products and Best Practice Content.This can lead to additional opportunities with the customer in terms of:•License sales•Consultancy revenue•Additional RDS sales
Q: There is only a few days of project management assigned to this RDS, who is responsible for day-to-day project management activities?A: As the majority of the work is undertaken by the SAP Data Migration Consultant they would be expected to assume the day-to-day project management activities, reporting to the part-time project manager.
Q: The delivery timescale is very tight for such a project, how do I ensure it is delivered on time?A: The project kick-off meeting is there to ensure all parties understand what they need to deliver and when. This is a good time to re-affirm the importance of meeting deadlines given the short timescales.
WE LISTEN • WE PARTNER • WE SUCCEED
Frequently Asked QuestionsRelated to ERP
Q: Why does the customer need to decide on their migration objects so far in advance of the project start?A: The objects to be migrated need to be decided early to enable resource teams to assign the correct SAP Functional Consultant to the project.
Q: What constitutes a “medium complexity” Data Migration object?A: There is no definitive answer to this, however it is important control customer expectation during the kick-off meeting to ensure what is agreed can be delivered within the allocated timescale.Limiting the number of attributes migrated for an object will still demonstrate the capability.
A possible example object selection might be: Vendor Master and open Purchase Orders & Customer Master and open Sales Orders & Bank
Q: Why are the data volumes limited?A: The limitation is there as a guide to control the duration of the migration and demo test runs. If volumes exceed this, the source data can be filtered and this will still demonstrate the capability.
WE LISTEN • WE PARTNER • WE SUCCEED
Tips & Tricks Ensure a broad selection of stakeholders, from senior management to end
users, executive sponsors (SAP & customer) to various team leads and members.
Ensure a well prepared, agreed and bought-in interview agenda, so attendees are available in time and agree to the review topics.
Conduct separate interview sessions with team leads, team members, customer and SAP project managers, stakeholders and business process owners; ideally 1 or 2 persons per session.
Focus on values delivered by this project: are customer expectations understood by the entire project team and properly transformed into a solution?
Actively listen to your interview partners. Avoid extensive discussions about solutions that may consume valuable time of your tightly scheduled interviews.
Join the team for lunch or dinner, more important information about the project may be available only outside the project premises, on a more informal basis.
Act independently and unbiased when evaluating risks and issues. Being external to the project is your key advantage and induces trust.
Follow your intuition and experience; don’t stick too close to the review guidelines and content in PMR Tool, use built-in questions as “door opener” only, to get better access to the real critical topics.
The pure presence of project documents does not give much information about the project status; the absence of project documents says so much more.
WE LISTEN • WE PARTNER • WE SUCCEED
Further Information
– Sales Kit
Link to Collaboration Room
Link to Service Browser
– ASAP Roadmap Composer
Add link to Roadmap or add instructions
– SAP Portal Page
Link to relevant cRoom or Portal Page
– …..
TBD
WE LISTEN • WE PARTNER • WE SUCCEED
Questions?
WE LISTEN • WE PARTNER • WE SUCCEED
Key Contacts
50 © Coeus Consulting, Inc .
Allan AgustinAccount Executiveaagustin@coeus-consulting.com+1 510 470 6469
Donna LeongDirectordleong@coeus-consulting.com+1 510-967-1908
Brandon ToombsArchitect btoombs@coeus-consulting.com+1 469-233-9509
top related