DESCRIPTION

Presentation on Fairview Bridge refurbishment to Area Committee - 26/03/12

TRANSCRIPT

Presented by Gordon Rowland,

Road Design Division,

Roads & Traffic Department,

Dublin City Council.

Fairview FootbridgeFairview Footbridge

Fairview Footbridge Refurbishment Replace section of bridge across

carriageway Raise north end of bridge slightly to

increase clearance Shot blast, repair and paint existing ramps

and stairways Provide new surfacing to ramps Provide vehicle crash protection to bridge

PLAN OF EXISTING FOOTBRIDGE

Refurbishment SequenceFabricate new section of bridge across carriagewayErect temporary stairways to each end of bridgeReplace section of bridge across carriageway during night road closureRemove (during closure) one section of ramp on north side to adjust heightOpen bridge to pedestrians the next morningRefurbish existing ramps and stairwaysReinstall section of ramp on north side during night road closureInstall crash protection to bridgeOpen ramps and stairways to pedestriansRemove temporary stairways