engro sindh coal power project project overview by misl
Post on 21-Dec-2015
223 Views
Preview:
TRANSCRIPT
Engro Sindh Coal Power ProjectProject Overview by MISL
2
Company Structure Overview
Engro Powergen was incorporated in 2008, as a fully owned subsidiary of Engro, to develop power projects in Pakistan.
The Sindh Engro Coal Mining Company Limited (SECMC) is a JV between the Government of Sindh and Engro Powergen, to mine coal from Thar Block II.
MISL Confidential
3
Sindh Engro Coal Mining Company
40
60
SECMCL Ownership Stake
Government of Sindh (GoS)Engro PowerGen Limited (EPL)
MISL Confidential
4
Feasibility Studies
Study Company
Detailed Feasibility Study Sinocoal, China
Hydrological Study Northeast Coal Bureau, China
Drilling Fieldwork Deep Rock Drilling, Pakistan
Environmental & Social Impact Assessment
Hagler Bailly Pakistan/ SRK, UK
Ground Water Modeling & Mitigating Strategy for ESIA
RWE, Germany
Financial Model and Economic Viability Assessment
RWE, GermanyMISL Confidential
5
Thar Coal Reserves
Thar Desert contains the world’s 7th largest coal reserves, totaling an estimated 175 billion tons of Lignite grade coal.
This is equivalent to 50 billion ton of crude oil, more than Iran & Saudi Arabia’s combined oil reserves.
Phased development can lead to 400 – 600 mt /year coal mining in 20 years
MISL Confidential
6
Coal Quality
The coal beds of variable thickness ranging from 0.20 – 22.81 meters are developed. The maximum number of coal seams found in some of the drill holes is 20. The cumulative thickness of the coal beds range from 0.2 to 36 meters. Claystone invariably forms the roof and the floor rock of the coal beds.
The coal is brownish black, black and grayish black in colour. It is poorly to well cleared and compact. The quality of coal is better where percentage of clay is nominal.
MISL Confidential
7
Project Scope
Mine & Power plant to be developed in parallel :
The production capacity of Coal mine will be 22.5 Mt/a to support 4000 MW of power generation capacity for 70 years
Phase 1 will be development of a 6.5 Mt/a Coal mine in parallel with 1200 MW Power Plant
In subsequent phases, chemical and fertilizer plants would be set-up as part of a Mega Petro-Chemical Complex which would be supported by additional coal mining
MISL Confidential
8
Project Scope (continued)
Power transmission line of 500 KV will be planned and constructed for 1000 mw power dispersal to power grid network.
Coal Gasification System with a 36”-42” Hi-Pressure Gas Transmission Pipeline will be planned and constructed to connect to the SSGC Network at Hyderabad / Jamshoro.
MISL Confidential
9
Project Timeline
Detailed Feasibility Study completed by September 2010
Financial Close is expected by December 2012
Coal Mining and Power Generation Project will start operation by December 2016
MISL Confidential