ECMS SUBCONTRACTOR REQUESTSMatthew R. Weaver, P.E.
Engineering District 8-0 Winter SchoolHarrisburg, PA
February 23, 2012
www.dot.state.pa.us2
Outline
• Policy Overview– PUB 408 Specifications– PUB 2 Project Office Manual
• Request Types/Examples– Subcontractor– Trucking (Service)– Equipment Rental/Operator (Service)– Other Services– Suppliers
www.dot.state.pa.us3
Outline
• Other Requirements– Sub on Prime’s Payroll Requirements– 2nd Tier Requirements
• Summary
www.dot.state.pa.us4
POLICY OVERVIEW
ECMS SUBCONTRACTOR REQUESTS
www.dot.state.pa.us5
PUB 408 Specifications
108.01 SUBLETTING OR ASSIGNMENT OF CONTRACTS
(a) General. Do not sublet, sell, transfer, assign, or otherwise dispose of the contract or contracts or any portion or rights, title, or interest, without the written consent of the Representative…
The ECMS subcontractor request must be approved prior to the start of the subcontractor’s work.
(e) Subcontract Approval. Do not allow any work on the project that is assigned to others (including services) until a copy of the executed subcontract…has been reviewed and acknowledged by the Department…
www.dot.state.pa.us6
PUB 2 Project Office Manual
PARTC
SECTION1
PAGE7-4
DATEMarch 1, 2011
REQUIREMENTS/References
SUBCONTRACTORS TRUCKING EQUIPMENTRENTAL FIRMS
(WITH OPERATOR)
ALL OTHER SERVICES SUPPLIERS
DBE’S NON-DBE’S DBE’S NON-DBE’S DBE’S NON-DBE’S DBE’S NON-DBE’S DBE’S NON-DBE’S
PREQUALIFICATION/Section 102.01, Publication 408 YES YES NO NO NO NO NO NO NO NO
SUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES YES YES (1) YES YES YES YES YES NO
CONTRACTOR RESPONSIBILITY PROGRAM/Management Directive 215.9 YES YES YES (1) YES YES YES YES NO NO
PAST PERFORMANCE REPORTS/Prequalification Regulations, Section 457.10
YES YES (2) (2) (2) (2) (2) (2) NO NO
PURCHASE ORDERS AND AGREEMENTS/Section 108.01(e), Publication 408 (3) (3) (3) (3) (3) (3) (3) (3) (3) NO
PREVAILING WAGE RATES/Section 107.22, Publication 408 YES YES (4) (4) YES YES (5) (5) NO NO
www.dot.state.pa.us7
REQUEST TYPES AND EXAMPLES
ECMS SUBCONTRACTOR REQUESTS
www.dot.state.pa.us8
PUB 2 Project Office Manual
REQUIREMENTS/References
SUBCONTRACTORS
DBE’S NON-DBE’SSUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES YES
www.dot.state.pa.us9
PUB 2 Project Office Manual
REQUIREMENTS/References
SUBCONTRACTORS
DBE’S NON-DBE’SSUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES YES
www.dot.state.pa.us10
PUB 2 Project Office Manual
REQUIREMENTS/References
TRUCKING
DBE’S NON-DBE’SSUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES (1)
Notes: (1) NOT REQUIRED FOR TRUCKING OWNER OPERATORS EMPLOYED BY A BROKER.
www.dot.state.pa.us11
PUB 2 Project Office Manual
Notes: (1) NOT REQUIRED FOR TRUCKING OWNER OPERATORS EMPLOYED BY A BROKER.
REQUIREMENTS/References
TRUCKING
DBE’S NON-DBE’SSUBCONTRACTOR APPROVALSection 108.01, Publication 408
YES (1)
www.dot.state.pa.us12
PUB 2 Project Office Manual
REQUIREMENTS/References
EQUIPMENTRENTAL FIRMS
(WITH OPERATOR)
DBE’S NON-DBE’S
SUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES YES
www.dot.state.pa.us13
PUB 2 Project Office Manual
REQUIREMENTS/References
EQUIPMENTRENTAL FIRMS
(WITH OPERATOR)
DBE’S NON-DBE’S
SUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES YES
www.dot.state.pa.us14
PUB 2 Project Office Manual
REQUIREMENTS/References
ALL OTHER SERVICES
DBE’S NON-DBE’SSUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES YES
www.dot.state.pa.us15
PUB 2 Project Office Manual
REQUIREMENTS/References
ALL OTHER SERVICES
DBE’S NON-DBE’S
SUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES YES
www.dot.state.pa.us16
PUB 2 Project Office Manual
REQUIREMENTS/References
SUPPLIERS
DBE’S NON-DBE’S
SUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES NO
www.dot.state.pa.us17
PUB 2 Project Office Manual
REQUIREMENTS/References
SUPPLIERS
DBE’S NON-DBE’S
SUBCONTRACTOR APPROVALSection 108.01, Publication 408 YES NO
www.dot.state.pa.us18
OTHER REQUIREMENTS
ECMS SUBCONTRACTOR REQUESTS
www.dot.state.pa.us19
Sub on Prime’s Payroll
• Requirements– Union Hall Labor Solicitation Documentation (if
applicable)– Employment Application On-Site– W-4 Form– I-9 Form– Fringe Benefit Letter– Copy of Cancelled Check to Employee – Equipment Rental Agreement AND Copy of Cancelled
Check for Equipment Rental (if applicable)
www.dot.state.pa.us20
2nd Tier Subcontractor
• Requirements– Prime Submits 1st Tier Request– 1st Tier must be Approved– 1st Tier must Self-Perform at least 50% of Work– 1st Tier must be Prequalified to “Oversee” 2nd Tier– Prime Submits 2nd Tier Request with 1st Tier as
“Overseer”– 2nd Tier must be Prequalified– 2nd Tier must be Approved– 2nd Tier must Self-Perform 100% of Work
www.dot.state.pa.us21
2nd Tier Subcontractor
Requests Prime Contractor: The Whiting-Turner Contracting Company, Inc. ( 005103 )
Request Status Request Date Subcontractor Overseer Subcontract Amt Further Subcontracted Goal Code
31 Deleted 8/22/2011D. L. George & Sons Construction Company $209,537.50 $0.00
34 Approved 8/29/2011New Enterprise Stone & Lime Co., Inc. $529,240.55 $222,260.90
35 Approved 8/29/2011ALL Crane Rental of Pennsylvania L.L.C. $35,000.00 $0.00
37 Approved 8/30/2011D.W. Miller, Inc. New Enterprise Stone & Lime Co., Inc. $1,320.00 $0.00
39 Approved 8/30/2011Main Stream Industries, Inc. New Enterprise Stone & Lime Co., Inc. $750.00 $0.00 WBE
40 Approved 8/30/2011Swank Construction Company, LLC New Enterprise Stone & Lime Co., Inc. $3,000.00 $0.00
41 Approved 8/30/2011J.L. Hartley, Inc. New Enterprise Stone & Lime Co., Inc. $2,500.00 $0.00 WBE
42 Approved 8/30/2011Alpha Space Control Co., Inc. New Enterprise Stone & Lime Co., Inc. $2,163.00 $0.00
43 Approved 8/30/2011Surface Preparation Technologies, Inc. New Enterprise Stone & Lime Co., Inc. $2,990.40 $0.00
44 Approved 8/31/2011D. L. George & Sons Construction Company
New Enterprise Stone & Lime Co., Inc. $209,537.50 $0.00
47 Approved 11/17/2011Jilco, Inc. $26,550.00 $0.00
www.dot.state.pa.us22
SUMMARY
ECMS SUBCONTRACTOR REQUESTS
www.dot.state.pa.us23
Summary
• Subcontractor Request Policy– PUB 408 Section 108.01
• Approval Required PRIOR TO Start of Work– PUB 2 Part C Section 1 Page 7-4\
• Approval Required EXCEPT FOR Non-DBE Trucking Owner/Operators and Non-DBE Suppliers
• Sub on Prime’s Payroll– OK with Proper Paperwork for Hired Employee– OK with Proper Paperwork for Equipment Rental
www.dot.state.pa.us24
Summary
• 2nd Tier Subcontractors– 1st Tier must be Approved and Self-Perform at least 50%
of the Work– 2nd Tier must be Approved and Self-Perform 100% Work
www.dot.state.pa.us25
THANK-YOU!!
QUESTIONS?
www.dot.state.pa.us26
Prequalification Contacts
David DeMarkisBOPD
Prequalification Officer
(717) 787-7032ddemarkis@pa.gov
Matt Weaver, P.E.BOPD
Contractor Evaluations
Engineer(717) 787-3733
matweaver@pa.gov