EAST SIDE COASTAL RESILIENCYCB3/CB6 JOINT WATERFRONT TASK FORCEJune 20th, 2017

2

EAST SIDE COASTAL RESILIENCYCB3/CB6 JOINT WATERFRONT TASK FORCEJune 20th, 2017

1. Project Overview2. Project Updates - Substantial Action Plan Amendment - Interior Drainage Analysis - 24th/25th Street Alignment Update - Field Work - Other Project Activities 3. Next Steps

2

EAST SIDE COASTAL RESILIENCYCB3/CB6 JOINT WATERFRONT TASK FORCEJune 20th, 2017

1. Project Overview2. Project Updates

- Substantial Action Plan Amendment - Interior Drainage Analysis - 24th/25th Street Alignment Update - Field Work - Other Project Activities

3. Next Steps

- 2016­2017 Stakeholder Meetings

3

1. Project Overview2. Project Updates

- Substantial Action Plan Amendment - Interior Drainage Analysis - 24th/25th Street Alignment Update - Field Work - Other Project Activities

3. Next Steps

EAST SIDE COASTAL RESILIENCYCB3/CB6 JOINT WATERFRONT TASK FORCEJune 20th, 2017

- 2016­2017 Stakeholder Meetings

3 DRAFT 7/26/2016

EAST SIDE COASTAL RESILIENCYProject Goals

• Provide a reliable, integrated flood protection system; minimize use of closure structures and deployables

• Improve waterfront open spaces and access

• Respond quickly to the urgent need for increased flood protection and resiliency

• Achieve implementation milestones and project funding allocations as established by HUD

4

MONTGOMERY STREET

E. 25TH STREET

EAST SIDE COASTAL RESILIENCYProject Goals

+

RESILIENCY INFRASTRUCTURE

PEOPLE

5

EAST SIDE COASTAL RESILIENCYProject Approach: Designing Social Infrastructure

Double Swing Gates (x1)

Double Roller Gates (x1)Single Roller Gates (x5)

Pedestrian Gates (x4)

*18 Total Closure Structures

Single Swing Gate (x7)

3

MONTGOMERY STREET TIEBACK

25TH STREET TIEBACK

Closure Areas

Floodwall/Levee

33

FLOOD GATES ARE LOCATED ACROSS PEDESTRIAN, CYCLISTS, AND VEHICULAR ACCESSWAYS.

6

BASELINE FLOOD PROTECTION

Existing Active Program

Existing Circulation

Existing Buildings

Existing Maintenance Areas

Existing Passive Program

EXISTING PROGRAMUSES ALONG THE WATERFRONT

DDDDDDDDDDDDDDDDEEEEEEEEEEEEEEELLLLLLLLLLLLLLAAAAAAAAAAAAAANNNNNNNNNNNNNCCCCCCCCCCCCCCCCEEEEEEEEEEEEEEEYYYYYYYYYYYYYY SSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

HHHHHHHHHHHHOOOOOOOOOOOOOUUUUUUUUUUUUUSSSSSSSSSSSSSTTTTTTTTTTTTTOOOOOOOOOOOOOOONNNNNNNNNNNNN SSSSSSSSSSSSSTTTTTTTTTTTTTTTT

6666666666666 THTHTHTHTHTHTHTHTHTHTHTTHTHTHSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

111111111111110000000000000000 THTHTHTHTHTHTHHTHTHTHTHSSSSSSSSSSSSTTTTTTTTTTT

222222222222222000000000000000 THTHTHTHTHTHTHHHTHTHSSSSSSSSSSSSSTTTTTTTTTTTTT

2222222222223333333333333 RDRDRDRRDRDRDRDRRDRDDDSSSSSSSSSSSSSSTTTTTTTTTTTTTTTT

2222222222255 THSSSSSSSSSTTTTTTTTTT

AAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEENNNNNNNNNNUUUUUUUUUEEEEEEEEEEEEE CCCCCCCCCCCCCAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEENNNNNNNNNNNNNNNUUUUUUUUUUUUUUUEEEEEEEEEEEE BBBBBBBBBB

AAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUUUEEEEEEEEEEEEEEEE AAAAAAAAAAAAAAAAA111111111111SSSSSSSSSSSSSSSSSSSTTTTTTTTTTTTTTTTTT AAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUEEEEEEEEEEEEEEE

FFFFFFFFFDDDDDDDDDRRRRRRRRR DDDDDDDRRRRRRRRRIIIIIIVVVVVVVVVEEEEEEEEFDR DRIVEFDDDDRRRR DDDDDRRRRRIIIIVVVVVVEEEEEEFDR DRIVEFDR DRIVEEEEEEEEEEFDR DRIVE

MO

MO

MO

MO

MO

MO

MO

MO

MMO

MOO

NT

NT

NT

NT

NT

NT

NT

NTT

NTTTTTTG

OGG

OGGG

OGGGG

ME

ME

ME

ME

MEE

MEEERYRYRYRYRYRYRYRRYRRY

SSSSSSTT

DR DRIVEFDFDFDFFDFFFFFF RR DRRRIVIVIVEEEFDR DRIVE

157

Existing Trees

Manhattan GreenwayGravity Wall

Relieving Platform

DESIGN CONSIDERATIONSCRITICAL GROUND LEVEL FEATURES

DDDDDDDDDDDDDDDEEEEEEEEEEEEEEELLLLLLLLLLLLLLLAAAAAAAAAAAAAANNNNNNNNNNNNNNNNCCCCCCCCCCCCCCCCEEEEEEEEEEEEEEEEEYYYYYYYYYYYYYYY SSSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

HHHHHHHHHHHHHOOOOOOOOOOOOUUUUUUUUUUUUSSSSSSSSSSSSTTTTTTTTTTTTTOOOOOOOOOOOOOOOOONNNNNNNNNNNNNNN SSSSSSSSSSSSSSTTTTTTTTTTTTTTTT

66666666666666 THTHTHTHTHTHTHTHTHTHTHTTTHTHTHSSSSSSSSSSSSSSSSTTTTTTTTTTTTTTT

1111111111111111100000000000000000 THTHTHTHTHTHTHTHTHTHHTHHSSSSSSSSSSSSSSTTTTTTTTTTTT

2222222222222000000000000000 THTHTHTHTHTHTHTHHTHHSSSSSSSSSSSSSSTTTTTTTTTTTTTT

222222222222333333333333 RDRDRDRDRDRDRDRDRDRDRDRDDSSSSSSSSSSSSSSSTTTTTTTTTTTTTTT

222222222255 THSSSSSSSSSTTTTTTTTTTT

AAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEENNNNNNNNNNNNUUUUUUUUUUUEEEEEEEEEEEEE CCCCCCCCCCCCAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEENNNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUEEEEEEEEEEEEEE BBBBBBBBB

AAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUUEEEEEEEEEEEEEEEE AAAAAAAAAAAAAAA111111111111SSSSSSSSSSSSSSSSSSTTTTTTTTTTTTTTTTTT AAAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUUEEEEEEEEEEEEEEEE

FDR DRIVEVEVEIVEIVERIVRIVRIVRIVRIDRIDRDRR DR DDR DDRFDRFDRDRFDFDFDFDDRDRDDRDRFDFDRFDFDDDRFFDFDFFDFDFDFDEEIVEIVVEVEVEVERIVRIVRIVRIVRIVRIVRIVRIVRIVRIRIRIDRDRDRIRIRIRIVDRDRDRDDRDRR DDDDR DR

DRDRDRRR DR DFDR DRIVEEFDR DRIVE

MO

MO

MO

MO

MO

MO

MMO

MMO

MOOOO

NTNTNTNTNTNTNTNTNTNTTN

TTGOGGOGGGGGOGGGGM

EM

EM

EM

EM

EM

EEEEEERYRYRYRYRYRYRYRYRYRRYRSSSSSSTT

FDFDFFDFDFFF R DRIVEEEIVEIVER DRIR DRIRRFDRFDR EEEEEVEVEVEVVIVIVIVVRRIRIRIDRRDRDRDRDDDDRDR DR DR DDDRRRRRRDRDDDDRDRDFDFDDDFDFFFDFDFDR DRIVE

168

DESIGN CONSIDERATIONSCRITICAL BELOW-GROUND FEATURES

DDDDDDDDDDDDDDDEEEEEEEEEEEEEEELLLLLLLLLLLLLLLAAAAAAAAAAAAAANNNNNNNNNNNNNNNNCCCCCCCCCCCCCCCCEEEEEEEEEEEEEEEEEYYYYYYYYYYYYYYY SSSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

HHHHHHHHHHHHHOOOOOOOOOOOOUUUUUUUUUUUUSSSSSSSSSSSSTTTTTTTTTTTTTOOOOOOOOOOOOOOOOONNNNNNNNNNNNNNN SSSSSSSSSSSSSSTTTTTTTTTTTTTTTT

66666666666666 THTHTHTHTHTHTHTHTHTHTHTTTHTHTHSSSSSSSSSSSSSSSSTTTTTTTTTTTTTTT

1111111111111111100000000000000000 THTHTHTHTHTHTHTHTHTHHTHHSSSSSSSSSSSSSSTTTTTTTTTTTT

2222222222222000000000000000 THTHTHTHTHTHTHTHHTHHSSSSSSSSSSSSSSTTTTTTTTTTTTTT

222222222222333333333333 RDRDRDRDRDRDRDRDRDRDRDRDDSSSSSSSSSSSSSSSTTTTTTTTTTTTTTT

222222222255 THSSSSSSSSSTTTTTTTTTTT

AAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEENNNNNNNNNNNNUUUUUUUUUUUEEEEEEEEEEEEE CCCCCCCCCCCCAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEENNNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUEEEEEEEEEEEEEE BBBBBBBBB

AAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUUEEEEEEEEEEEEEEEE AAAAAAAAAAAAAAA111111111111SSSSSSSSSSSSSSSSSSTTTTTTTTTTTTTTTTTT AAAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUUEEEEEEEEEEEEEEEE

FFFFFFFFFFDDDDDDDRRRRRRRRRR DDDDDDDDRRRRRRRRRRIIIIIIIIIVVVVVVVVVVEEEEEEFDR DRIVEFDFD

EFDR DRIVEFDR DRIVEFDR DRIVEEFDR DRIVE

MO

MO

MO

MO

MO

MO

MMO

MMO

MOOOO

NTNTNTNTNTNTNTNTNTNTTN

TTGOGGOGGGGGOGGGGM

EM

EM

EM

EM

EM

EEEEEERYRYRYRYRYRYRYRYRYRRYRSSSSSSTT

FDFDFDFDFF R DRIVEEEFFDRRR DRIRIRIVEFFFFDR VEFFDR VEFDR DRIV

17

Con Ed StationDEP Regulators

Electrical Transmission LinesDEP Conveyance

Watermains

9

EAST RIVER PARK

STUYVESANT COVE PARK

THE PROJECT CREATES AN ELEVATED EDGE 8’-9’ ABOVE EXISTING GROUND LEVEL.

NOTE: FEATURES ARE SUBJECT TO VALUE ENGINEERING

CON ED TIE-IN

MONTGOMERY ST. TIE-BACK

25TH ST. TIE-BACK

MURPHY BROTHERS PLAYGROUND

ASSER LEVY PLAYGROUND

10

A PROTECTED COMMUNITYAND IMPROVED WATERFRONT!

11

ESCR NEXT STEPSCurrent Project Schedule

BID AWARD

GROUNDBREAKING

EAST SIDE COASTAL RESILIENCY PROJECTWINTER2017/18

WINTER2015/16

WINTER2016/17 TBD TBD

ULURP

ENVIRONMENTAL / EIS

DESIGN PROCESS

COMMUNITY ENGAGEMENT

PREPARATION &SUBMISSION CONSTRUCTIONCOMMUNITY &

TECHNICAL REVIEWS

DRAFT EIS REPORT

PUBLIC REVIEWS &FINAL EIS REPORT

DRAFT STATEMENT OF WORK

PRELIMINARY DESIGN PHASE

FINALDESIGN PHASE

CONCEPTDESIGN PHASE

12

1. Project Overview2. Project Updates

- Interior Drainage Analysis - 24th/25th Street Alignment Update - Field Work - Other Project Activities

3. Next Steps

EAST SIDE COASTAL RESILIENCYCB3/CB6 JOINT WATERFRONT TASK FORCEJune 20th, 2017

- Substantial Action Plan Amendment- 2016­2017 Stakeholder Meetings

8

APRIL 25THJANUARY 17TH

GOUVERNEUR GARDENS BOARD

PHOTO? PHOTO? PHOTO?

NYC.GOV/ESCR WEBSITE FOR PUBLIC INPUT

APRIL 27TH

EAST SIDE COASTAL RESILIENCY2016 - 2017 Stakeholder Meetings

STUYVESANTTOWN

ASSER LEVY

APRIL 22ND

EARTH DAY

8

APRIL 25THJANUARY 17TH

GOUVERNEUR GARDENS BOARD

PHOTO? PHOTO? PHOTO?

NYC.GOV/ESCR WEBSITE FOR PUBLIC INPUT

APRIL 27TH

EAST SIDE COASTAL RESILIENCY2016 - 2017 Stakeholder Meetings

STUYVESANTTOWN

ASSER LEVY

APRIL 22ND

EARTH DAY

13

APRIL 25th (2017)JUNE 15th (2017)

SEPTEMBER 15th (2016) JANUARY 17th (2017)

GOUVERNEUR GARDENS BOARD

NYC.GOV/ESCR WEBSITE FOR PUBLIC INPUT

APRIL 27th (2017) JUNE 14th (2017)

PROJECT UPDATES2016 - 2017 Stakeholder Meetings

STUYVESANTTOWN

GRAND STREETWELLNESS FAIR

CB6 TASK FORCE

EARTHDAY

APRIL 22nd (2017)

14

PROJECT UPDATESSubstantial Action Plan Amendment

• Published online March 24th, 2017

• Reflects most recent understanding of project design / costs

• Hearing held on April 4, 2017, at Manny Cantor Center in Manhattan

• City provided update on project status and Action Plan process

• Received public comments (oral and written)

• Comment period closed April 24, 2017

15

PROJECT UPDATESSubstantial Action Plan Amendment - Process with HUD

• Comments received include following topics: - Exploration of Alternative Elements/ Approaches - Sea Level Rise and Modeling - Flood Protection Alignment and Project Design - Maintenance and Operations - City Response to Future Floods -BenefitCostAnalysis - Funding - Outreach

• City responded to comments and submitted Action Plan Amendment to HUD on May 12, 2017

• HUD to review and approve Action Plan Amendment within 60 days

16

PROJECT UPDATESInterior Drainage Analysis

PREVIOUSLY, A 13M GALLON TANK WAS PLANNED TO BE CONSTRUCTED UNDER THE TENNIS COURTS.

17

PROJECT UPDATESInterior Drainage Analysis

Existing Active Program

Existing Circulation

Existing Buildings

Existing Maintenance Areas

Existing Passive Program

EXISTING PROGRAMUSES ALONG THE WATERFRONT

DDDDDDDDDDDDDDDDEEEEEEEEEEEEEEELLLLLLLLLLLLLLAAAAAAAAAAAAAANNNNNNNNNNNNNCCCCCCCCCCCCCCCCEEEEEEEEEEEEEEEYYYYYYYYYYYYYY SSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

HHHHHHHHHHHHOOOOOOOOOOOOOUUUUUUUUUUUUUSSSSSSSSSSSSSTTTTTTTTTTTTTOOOOOOOOOOOOOOONNNNNNNNNNNNN SSSSSSSSSSSSSTTTTTTTTTTTTTTTT

6666666666666 THTHTHTHTHTHTHTHTHTHTHTTHTHTHSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

111111111111110000000000000000 THTHTHTHTHTHTHHTHTHTHTHSSSSSSSSSSSSTTTTTTTTTTT

222222222222222000000000000000 THTHTHTHTHTHTHHHTHTHSSSSSSSSSSSSSTTTTTTTTTTTTT

2222222222223333333333333 RDRDRDRRDRDRDRDRRDRDDDSSSSSSSSSSSSSSTTTTTTTTTTTTTTTT

2222222222255 THSSSSSSSSSTTTTTTTTTT

AAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEENNNNNNNNNNUUUUUUUUUEEEEEEEEEEEEE CCCCCCCCCCCCCAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEENNNNNNNNNNNNNNNUUUUUUUUUUUUUUUEEEEEEEEEEEE BBBBBBBBBB

AAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUUUEEEEEEEEEEEEEEEE AAAAAAAAAAAAAAAAA111111111111SSSSSSSSSSSSSSSSSSSTTTTTTTTTTTTTTTTTT AAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUEEEEEEEEEEEEEEE

FFFFFFFFFDDDDDDDDDRRRRRRRRR DDDDDDDRRRRRRRRRIIIIIIVVVVVVVVVEEEEEEEEFDR DRIVEFDDDDRRRR DDDDDRRRRRIIIIVVVVVVEEEEEEFDR DRIVEFDR DRIVEEEEEEEEEEFDR DRIVE

MO

MO

MO

MO

MO

MO

MO

MO

MMO

MOO

NT

NT

NT

NT

NT

NT

NT

NTT

NTTTTTTG

OGG

OGGG

OGGGG

ME

ME

ME

ME

MEE

MEEERYRYRYRYRYRYRYRRYRRY

SSSSSSTT

DR DRIVEFDFDFDFFDFFFFFF RR DRRRIVIVIVEEEFDR DRIVE

15

CHALLENGES - PARK IMPACTS AND RESTRICTIONS - CONTAMINATION - MAINTENANCE AND OPERATIONS

18

PROJECT UPDATESInterior Drainage Analysis

Existing Active Program

Existing Circulation

Existing Buildings

Existing Maintenance Areas

Existing Passive Program

EXISTING PROGRAMUSES ALONG THE WATERFRONT

DDDDDDDDDDDDDDDDEEEEEEEEEEEEEEELLLLLLLLLLLLLLAAAAAAAAAAAAAANNNNNNNNNNNNNCCCCCCCCCCCCCCCCEEEEEEEEEEEEEEEYYYYYYYYYYYYYY SSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

HHHHHHHHHHHHOOOOOOOOOOOOOUUUUUUUUUUUUUSSSSSSSSSSSSSTTTTTTTTTTTTTOOOOOOOOOOOOOOONNNNNNNNNNNNN SSSSSSSSSSSSSTTTTTTTTTTTTTTTT

6666666666666 THTHTHTHTHTHTHTHTHTHTHTTHTHTHSSSSSSSSSSSSSSSSTTTTTTTTTTTTTT

111111111111110000000000000000 THTHTHTHTHTHTHHTHTHTHTHSSSSSSSSSSSSTTTTTTTTTTT

222222222222222000000000000000 THTHTHTHTHTHTHHHTHTHSSSSSSSSSSSSSTTTTTTTTTTTTT

2222222222223333333333333 RDRDRDRRDRDRDRDRRDRDDDSSSSSSSSSSSSSSTTTTTTTTTTTTTTTT

2222222222255 THSSSSSSSSSTTTTTTTTTT

AAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEENNNNNNNNNNUUUUUUUUUEEEEEEEEEEEEE CCCCCCCCCCCCCAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVEEEEEEEEEEEEENNNNNNNNNNNNNNNUUUUUUUUUUUUUUUEEEEEEEEEEEE BBBBBBBBBB

AAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUUUUEEEEEEEEEEEEEEEE AAAAAAAAAAAAAAAAA111111111111SSSSSSSSSSSSSSSSSSSTTTTTTTTTTTTTTTTTT AAAAAAAAAAAAAAAAAVVVVVVVVVVVVVVVVVVVEEEEEEEEEEEEEEEEEEENNNNNNNNNNNNNNNNUUUUUUUUUUUUUUUEEEEEEEEEEEEEEE

FFFFFFFFFDDDDDDDDDRRRRRRRRR DDDDDDDRRRRRRRRRIIIIIIVVVVVVVVVEEEEEEEEFDR DRIVEFDDDDRRRR DDDDDRRRRRIIIIVVVVVVEEEEEEFDR DRIVEFDR DRIVEEEEEEEEEEFDR DRIVE

MO

MO

MO

MO

MO

MO

MO

MO

MMO

MOO

NT

NT

NT

NT

NT

NT

NT

NTT

NTTTTTTG

OGG

OGGG

OGGGG

ME

ME

ME

ME

MEE

MEEERYRYRYRYRYRYRYRRYRRY

SSSSSSTT

DR DRIVEFDFDFDFFDFFFFFF RR DRRRIVIVIVEEEFDR DRIVE

15

CURRENTLY EVALUATING ALTERNATIVES THAT MEET PROJECT OBJECTIVES BUT ARE LESS DISRUPTIVE AND MORE COST EFFECTIVE

TANK REMOVED FROM PROJECT DUE TO COMPLEXITY OF CHALLENGES AND INCREASING COSTS

15

~60 ft

E 23RD STREET

FDR DRIVE

E 25TH STREET

VA HOSPITAL

~170 ft

~50 ft

VA HOSPITAL FLOODWALL

~260 ft

9 ft

10 ft

SERVICEAREA

ASSER LEVY

RECREATION

CENTER

PLAYGROUND

TRACK

PROPOSED ALIGNMENT 1 (NORTH) PROPOSED ALIGNMENT 2 (SOUTH)

19

PROJECT UPDATES24th/25th Street Alignment

20

PROJECT UPDATESField Work

• Geotechnical borings: Investigating subsurface conditions to refine design and costs

- Flood protection foundations - Pedestrian bridges foundations - Sewer & drainage infrastructure - FDR Drive

• DEP sewer inspections: Determine need for floodproofing, rehabilitation, or reconstruction

• Updated tree inventory: Confirming current conditions

21

PROJECT UPDATESOther Project Activities

• Design Refinement -Parkplanrefinement - Materials, paving, and furnishing - Detailed planting strategy - Detailed wall and tie-back design -Walltreatments+finishes - Bridge alignment and detail design

• Advancing development of Maintenance & Operations plan

• Further technical analysis and engineering

22

1. Project Status2. Project Updates 3. Next Steps

EAST SIDE COASTAL RESILIENCYCB3/CB6 JOINT WATERFRONT TASK FORCEJune 20th, 2017

23

ESCR NEXT STEPSLook Ahead

• Future Engagement & Stakeholder Outreach/Meetings - Ongoing- Asser Levy site visit with CB6 Task Force- September Task Force Meeting

• Mass Mailing Plans - Fall / Winter 2017

• Community Board Meeting(s) – Related to PDC Design Review - Fall /Winter 2017

• PDC Design Review - Fall / Winter 2017

• EIS Hearing / ULURP - Winter 2017 /2018

24