e uranium (usa) international corporation co ...unt*ot/nt tskuis takcs units hrs cost/unit task...
Post on 01-Mar-2021
1 Views
Preview:
TRANSCRIPT
E INTERNATIONAL
URANIUM (USA)
CORPORATION
Independence Plaza, Suite 950 * 1050 Seventeenth Street * Denver, CO 80265 * 303 628 7798 (main) * 303 389 4125 (fax)
March 1, 2001
Certified Mail Z 141 553 864 Return Receipt Requested
Philip Ting, Chief Fuel Cycle Licensing Branch ADDRESSEE ONLY U.S. Nuclear Regulatory Commission Mail Stop T-8A33 Washington, D.C. 20555
Re: International Uranium (USA) Corporation SUA-1358 Docket No. 40-8681 White Mesa Mill, Blanding, Utah License Condition Number 9.5 - Surety
Dear Mr. Ting:
Pursuant to License Condition No. 9.5 of Source Materials License No. SUA-1358, Docket No. 40-8681, and appropriate revisions of 10 CFR Part 40, Appendix A, Criterion
9, please find enclosed an updated reclamation and decommissioning cost estimate in support of the Surety Bond on the White Mesa Mill.
The attached reclamation estimate is based on the plan approved by License Amendment 15, issued on July 15, 2000. The revised reclamation estimate and surety amount is
$10,365,457, which is an increase from the current surety amount of $10,064,794. The
attached estimate represents a total revision to Attachment C of Revision 3.0 to the approved July 2000 Reclamation Plan.
The revised estimate was based on updated quotes for equipment rental, labor rates, fuel,
and subcontractor services. In addition, the estimate takes credit for reclamation work recently completed on a portion of the current tailing cells, and the installation of
ancillary facilities projected to be used during final reclamation and decommissioning. A summary of the updated unit costs and the work credits is included with the revised estimate.
Mr. Philip Ting March 1, 2001 Page 2 of 2
If you have any questions on the attached revised reclamation and decommissioning cost estimate, please feel free to contact me at the letterhead phone or address.
Very truly yours,
Ron F. Hochstein President and Chief Executive Officer
RFH:-smc
Attachments
cc: William von Till David C. Frydenlund Michelle R. Rehmann William N. Deal Ron E. Berg
International Uranium (USA) Corporation
WHITE MESA MILL - RECLAMATION COST ESTIMATE
Comparison of January 2001 Estimate to July 2000 Estimate
Mill Decommissioning
Cell 2
Cell 3
Cell 4A
Cell 1
Miscellaneous
Subtotal Direct Costs
Profit Allowance
Contingency
Licensing & Bonding
Long Term Care Fund
Total Reclamation
January 2001 Estimate
$1,530,031
$1,152,941
$1,624,184
$127,165
$1,308,315
$1,913,204
$7,655,840
10.00% $765,584
15.00% $1,148,376
2.00% $153,117
$642,541
$10,365,457
July 2000 Estimate
$ 1,505,167
$ 1,082,870
$ 1,565,444
$ 120,128
$ 1,234,212
$ 1,939,480
$7,447,301
$744,730
$1,117,095
$148,946
$606,721
$10,064,793
Increase (Decrease)
$ 24,864
$ 70,071
$ 58,740
$ 7,037
$ 74,103
$ (26,276)
$208,539
$ 20,854
$ 31,281
$ 4,171
$ 35,820
$ 300,664
ATTACHMENT C
COST ESTIMATES
FOR
RECLAMATION
OF
WHITE MESA FACILITIES
BLANDING, UTAH
PREPARED BY
INTERNATIONAL URANIUM (USA) CORP.
1050 17th STREET, SUITE 950
DENVER, COLORADO 80265
January 2001
H :\USERS\WMRCPLN\ATTC.RPT\January 2001
International Uranium (USA) Corp.
Cost Estimates forCost Estimates for
Reclamation
Of
White Mesa Mill
Blanding, Utah
January 2001
Source Material License No. SUA-1 358 Docket No. 40-8681
International Uranium (USA) Corp,
Cost Estimates for Reclamation of White Mesa Mill
Table of Contents
1. Cost Summary
2. Mill Decommissioning
3. Cell 2 Calculations
4. Cell 3 Calculations
5. Cell 4A Calculations
6. Cell 1 Calculations
7. Miscellaneous Cost Calculations
8. Rock Production Costs
9. Equipment Costs
10. Labor Costs
11. Long Term Care Calculation
Summary of Changes in January 2001 Reclamation Cost Update
Unit Cost Factors
* Update Equipment rental, mobilization, and maintenance costs, Butler Machinery
Company, January 25, 2001
* Update Labor costs, "Utah General Decision No. 000009, November 10, 2000"
* Update Fuel cost, #2 Red Diesel and 85 Octane Unleaded gas, BCL Distributing Company, Blanding, Utah, January 23, 2001
* Update Screen Plant rental costs, Power Motive Corporation, Denver, Colorado, January 23, 2001
* Update Trackhoe and Metal Shear rental costs, Power Motive Corporation, Denver, Colorado, January 23, 2001
• Update Crane rental costs, Crane Services, Inc., Albuquerque, New Mexico, January 23, 2001
* Update Highway Truck rental costs, Cosby Trucking, Inc., Blanding, Utah, January 24, 2001
* Escalate Long Term Care Fund by December 2000 CPI-U factor (174.0)
Plan Modifications
" Revised Cell 3 Reclamation Cost to reflect installation of Platform Fill completed since
1998. Area covered by Platform Fill increased from 25 acres to 34 acres based on aerial
photograph of White Mesa Mill Site, June 21, 2000, and field observation from White Mesa Mill staff, January 2001.
"* Revised cost of Miscellaneous items to reflect current installation of decontamination/wheel jwash pad. Installation completed summer 1999.
* Revised Mill Decommissioning cost to reflect lower, more realistic, unit costs for concrete
demolition of Office Building concrete.
WHITE MESA MILL RECLAMATION COST ESTIMATE January 2001
Mill Decommissioning
Cell 2
Cell 3
Cell 4A
Cell 1
Miscellaneous
Subtotal Direct Costs
Profit Allowance
Contingency
Licensing & Bonding
Long Term Care Fund
Total Reclamation
Revised Bond Amount
January 2001 Estimate
$1,530,031
$1,152,941
$1,624,184
$127,165
$1,308,315
$1,913,204
$7,655,840
10.00% $765,584
15.00% $1,148,376
2.00% $153,117
$642,541
$10,365,457
$10,365,457
01/31/2001 - 2:28 PM - WM.RecPlanEst.Jan2001International Uranium (USA) Corp.
White Mesa Mill
I
I
I I
:4
I 3
I I
ii I'.4
r
I
. .. . I • - , , •
: I " : ',' . ' : : • ' -• ; i S•-! : • i : i • : ! : ! : -'- ' ; .i
............... ....
......... ....
............... ....
.......... .........
........... .........
.......... .........
.......... .........
. ..............
.............
.................
..................
..................
..................
12j!•,
SI II
! If
I..
................................................................................................
.................. ....................................................... ............................
.......................................................................................................
........................................................................................................
.......................................................................................................
.......................................................................................................
..................................................... ....... ... ............
................................... i .0 .4- .ni ... .......................
..... ..................................... ......................... .............................................................................. .......................
.................................................................. ......................
........................................................................................................
.........................................................................................................
S. 0 0 ,
pm
--I tl &I e -1el °11 gl el, l se l r • 1 81 tgl l 31 ýg NJ %!I NJ sl 21 1 ;;1 ;;1 ::.1 al •l ;:I • l - I 1 81 -1 -1 -1 -1-1-1-1
-: .. ' .3L iU U _. " : i i : *
44444441• 4 2,, j444f 4.= 4-4I;
1I112 L�
F Li. i � w
h' 5.
if J ; �, .c 0
2 S.!
'S 5. a a 0' 2
U �A V 4 4 4 4 41* 3 3K3
2 '222 I iii-:: i�
F
I I
I 0
I if a
I -4 I
-'A
""'7
LA'
U! I I I
C- D
ro CD
(3"0
•- 0
ag 0
0) 0)
0
IQ
-.4
I: I
"• i ; . . .:_ , '
Li Li C Li * L * : UV '. i C i •.
1I
K
.............................. .................................
...................................................
.. ...........................................................
.. ....................................... ...........
.. ...................................... .....................
. ............................................................
. ............................................................
................................................ ............
----------------- --------
............................................................
..................................................... ....... ...
............................................................. ...
............... ............................................
............................................................. ...
............................................................. ...
....................................................................
....................................................................
..............................................................................................................................
.............................................................................................................................. ........
......................................................................................... .................................... ........
.............................................................................................................................. ........
................................. ............................................................................................ ----
......................................... .....................................................................................
.................................................................................................................................
..........................................................................................................................................
.......................................................................................................................................... J1
......................................
.............................
............................. --
.............................. ...
............................. ...
................................. ...
.......... ................
.............................. ....
........................----------------------------- ............................... ........................................................... ... .............................................
.......................................................... ... ............................................. 1 1 ............ I ...................................................... - * 91 iý A ............................
........................................................... ... ..... ........... .............. .................................
............................................................ ... ..... ...... .............. I -f ............................ ............................................................ ... ...... ............................. .................................
.................................. ......................... .... ..... ............................. .................................
............................................................ .... ..... ............................. .................................
...... ............................................. .... .... ..... ............................. .................................
...... ............................................. ........ ...... ... ......................... .......... I ......................
...... ........................................ ........ ..... ........ ... ... ........... .................................
...... ...... ............ ..... ...... .. .. .................. ..... ........ .. ............. ........ .. ........ .... ......... - * ... ..................................
....... ...................... .................................. I ..........................................................................
...... ........... ...... .. .. .......................................................................... ..... .....
................................................................... 4 .................. ............................................ ............
................................................................................................................................................
................................................................................................................. ..................
.................................................................................................................................... ........... , ..........
.............................
...................
..................... ...
.............................. ...
.............................. --
.............................. ...
.............................. ...
......................................
......................................
.............. .......................
....................
..................
..................
............................. ............................
......................
........................................................................................ I
-r-
a 1 ft
I
!1
I
i i : "
I .................................. I I .................... I'... ................................. I ........................... I ..........I.......................... I • "I ......................................................... I •.-H ,a ..................................................... I............... Uff"Im
I
r
3, I- # -
F
if
,,,
is
MILL DECOMMISSIONING
MILL DECOMMISSIONING
Mill Building Demolition
Resource Description Units Cost/Unit Task Units Task CostEquipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears 65 Ton Crane 30 Ton Crane Equipment Maintenance (Butler) Concrete Removal
Total Mill Building Demolition
Ore Feed Demolition Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears 30 Ton Crane Equipment Maintenance (Butler)
Total Ore Feed Demolition
hrs $13.86 640 $8,872 hrs $10.35 320 $3,311 hrs $1.25 960 $1,200 hrs $66.18 640 $42,354 hrs $12.74 640 $8,154 hrs $104.70 160 $16,752 hrs $132.76 160 $21,241 hrs $163.62 160 $26,179 hrs $62.80 160 $10,049 hrs $40.66 80 $3,253 hrs $10.56 1,360 $14,356 sf $3.30 37,500 $123,750
$292,227
Units Cost/Unit Task Units Task CostS T - -- -r
$17.72 46 $850hrshrs $13.86 64 $887 hrs $10.35 32 $331 hrs $1.25 96 $120 hrs $66.18 64 $4,235 hrs $12.74 64 $815 hrs $104.70 16 $1,675 hrs $132.76 16 $2,124 hrs $163.62 16 $2,618 hrs $40.66 $0 hrs $10.56 112 $1,182
$14,839
SX Building Demolition Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears 65 Ton Crane 30 Ton Crane Equipment Maintenance (Butler) Concrete Removal
Total SX Building Demolition
CCD Circuit Removal Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears 65 Ton Crane 30 Ton Crane Equipment Maintenance (Butler) Concrete Removal
Total CCD Circuit Removal
Units Cost/Unit Task Units Task Cost
hrs $13.86 320 $4,436 hrs $10.35 160 $1,655 hrs $1.25 480 $600 hrs $66.18 320 $21,177 hrs $12.74 320 $4,077 hrs $104.70 80 $8,376 hrs $132.76 80 $10,621 hrs $163.62 80 $13,089 hrs $62.80 $0
hrs $40.66 $0 hrs $10.56 560 $5,911 Sf $3.30 55,970 $184,701
$258,896
Units Cost/Unit Task Units Task CostI - -
hrs $13.86 120 $1,664 hrs $10.35 60 $621 hrs $1.25 180 $225 hrs $66.18 120 $7,941 hrs $12.74 120 $1,529 hrs $104.70 30 $3,141 hrs $132.76 30 $3,983 hrs $163.62 30 $4,909 hrs $62.80 30 $1,884 hrs $40.66 15 $610 hrs $10.56 315 $3,325 sf $3.30 15,000 $49,500
$82,786
01/31/2001 - 2:28 PM-WM.RecPlanEst.Jan2001International Uranium (USA) Corp.
White Mesa Mill
hrs $17.72 240 $4.252
hrs $17.72 720 $12.757
$17.72 48 $850
hrs $17.72 240 $4.252
hrs $17.721 195 $3.455
MILL DECOMMISSIONING
Sample Plant Removal Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears 30 Ton Crane Equipment Maintenance (Butler) Concrete Removal
Total Sample Plant Removal
Boiler Demolition Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears 65 Ton Crane 30 Ton Crane Equipment Maintenance (Butler) Concrete Removal
Units Cost/Unit Task Units24
Task Cost
hrs $13.86 32 $444 hrs $10.35 16 $166 hrs $1.25 48 $60 hrs $66.18 32 $2,118 hrs $12.74 32 $408 hrs $104.70 8 $838 hrs $132.76 8 $1,062 hrs $163.62 8 $1,309 hrs $40.66 $0 hrs $10.56 56 $591 sf $3.30 4,200 $13,860
$21,279
Unt*ot/nt TskUis TakCsUnits
hrsCost/Unit Task Units Task Cost
hrs $13.86 160 $2,218 hrs $10.35 80 $828 hrs $1.25 240 $300 hrs $66.18 160 $10,588 hrs $12.74 160 $2,038 hrs $104.70 40 $4,188 hrs $132.76 40 $5,310 hrs $163.62 40 $6,545 hrs $62.80 $0 hrs $40.66 $0 hrs $10.56 280 $2,956 sf $3.30 2,900 $9,570
Total Boiler Demolition
Vanadium Oxidation Circuit Removal Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears 65 Ton Crane 30 Ton Crane Equipment Maintenance (Butler) Concrete Removal
Units Cost/Unit Task Units Task Costhrshrs $13.86 64 $887 hrs $10.35 32 $331 hrs $1.25 96 $120 hrs $66.18 64 $4,235 hrs $12.74 64 $815 hrs $104.70 16 $1,675 hrs $132.76 16 $2,124 hrs $163.62 16 $2,618 hrs $62.80 $0 hrs $40.66 $0 hrs $10.56 112 $1,182 sf $3.30 1,200 $3,960
Total Vanadium Oxidation Circuit Removal $18,799
Main Shop/Warehouse Demolition Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears Equipment Maintenance (Butler) Concrete Removal
Units Cost/Unit Task Units Task Costhrshrs $13.86 128 $1,774 hrs $10.35 64 $662 hrs $1.25 192 $240 hrs $66.18 128 $8,471 hrs $12.74 128 $1,631 hrs $104.70 32 $3,350 hrs $132.76 32 $4,248 hrs $163.62 32 $5,236 hrs $10.56 224 $2,365 sf $3.30 19,300 $63,690
Total Main Shop/Warehouse Demolition $93,368
01/31/2001 - 2:28 PM-WM.RecPlanEst.Jan2001 International Uranium (USA) Corp. White Mesa Mill
$46,667
96 $1,701
hrs $17.721 $425
$17.72 120 $2.12
$17.72 48 $850
$17.72
MILL DECOMMISSIONING
Office Building Demolition Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears Equipment Maintenance (Butler) Concrete Removal
Units Cost/Unit Task Units Task Costhrs $17.72 72 $1,276 hrs $13.86 96 $1,331 hrs $10.35 48 $497 hrs $1.25 144 $180 hrs $66.18 96 $6,353 hrs $12.74 96 $1,223 hrs $104.70 24 $2,513 hrs $132.76 24 $3,186 hrs $163.62 24 $3,927 hrs $10.56 168 $1,773 Sf $1.25 12,100 $15,125
Total Office Building Demolition $37,383
Misc. Tankage & Spare Parts Removal Resource Description
Equipment Operators Mechanics Laborers Small Tools Cat 769 Haul Truck Truck Drivers Cat 988 Loader Cat 375 Excavator PC-400 with Shears Equipment Maintenance (Butler) Concrete Removal
Units Cost/Unit Task Units Task Costhrs $17.72 24 $425 hrs $13.86 32 $444 hrs $10.35 16 $166 hrs $1.25 48 $60 hrs $66.18 32 $2,118 hrs $12.74 32 $408 hrs $104.70 8 $838 hrs $132.76 8 $1,062 hrs $163.62 8 $1,309 hrs $10.56 56 $591 Sf $1.25 $0
Total Misc. Tankage & Spare Parts Removal $7,419
Mill Yard Decontamination Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 582 $10,312 Cat 637 Scraper hrs $154.47 257 $39,699 Cat 988 Loader hrs $104.70 65 $6,805 Cat D8N Dozer With Ripper hrs $74.64 65 $4,852 Cat D7 Dozer hrs $62.69 65 $4,075 Cat 651 Waterwagon hrs $79.92 65 $5,195 Cat 14G Motorgrader 1hrs 1 $53.301 65 $3,465 Equipment Maintenance (Butler) hrs $10.56 582 $6,143
Total Mill Yard Decontamination $80,545
Ore Storage Pad Decontamination Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 429 $7,601 Cat 637 Scraper hrs $154.47 189 $29,195 Cat 988 Loader hrs $104.70 48 $5,026 Cat D8N Dozer With Ripper hrs $74.64 48 $3,583 Cat D7 Dozer hrs $62.69 48 $3,009 Cat 651 Waterwagon hrs $79.92 48 $3,836 Cat 14G Motorgrader hrs $53.30 48 $2,558 Equipment Maintenance (Butler) hrs $10.56 429 $4,528
Total Ore Storage Pad Decontamination $59,336
Equipment Storage Area Cleanup Resource Description Units Cost/Unit Task Units Task Cost
Equipment uperators Cat 637 Scraper Cat 988 Loader Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader Equipment Maintenance (Butler)
hrs $17.72 154 $2,729 hrs $154.47 69 $10,658 hrs $104.70 17 $1,780 hrs $74.64 17 $1,269 hrs $62.69 17 $1,066 hrs $79.92 17 $1,359 hrs $53.30 17 $906 hrs $10.56 154 $1,626
Total Equipment Storage Area Cleanup
01/3112001 - 2:28 PM-WM.RecPlanEst.Jan2001 International Uranium (USA) Corp. WMite Mesa Miil
$21,392
MILL DECOMMISSIONING
Revegetate Mill Yard & Ore Pad Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 231 $4,093 Cat 637 Scraper hrs $154.47 132 $20,390 Cat 988 Loader hrs $104.70 0 $0 Cat DBN Dozer With Ripper hrs $74.64 33 $2,463 Cat D7 Dozer hrs $62.69 33 $2,069 Cat 651 Waterwagon hrs $79.92 $0 Cat 14G Motorgrader hrs $53.301 33 $1,759 Equipment Maintenance (Butler) hrs $10.56 231 $2,438
Total Revegetate Mill Yard & Ore Pad $33,212
Total Demolition and Decontamination $1,068,150
CLEANUP OF WINDBLOWN CONTAMINATION
Scoping Survey Resource Description Units Cost/Unit Task Units Task Cost
Soil Samples each $50.00I 1001 $5,000 Survey Crew hrs $13.32 752 $10,018 Sample Crew hrs $13.32 1,312 $17,479
Total Scoping Survey $32,497
Characterization Survey Resource Description Units Cost/Unit Task Units Task Cost
Soil Samples each $50.001 4721 $23,600 Sample Crew hrs $13.32 1,136 $15,134
Total Characterization Survey $38,734
Final Status Survey Resource Description Units Cost/Unit Task Units Task Cost
Soil Samples leach I $50.001 3001 $15,000 Sample Crew hrs $13.32 3,552 $47,320
Total Final Status Survey $62,320
Windblown Cleanup Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 1,190 $21,084 Cat 637 Scraper hrs $154.47 680 $105,040 Cat D8N Dozer With Ripper hrs $74.64 170 $12,689 Cat D7 Dozer hrs $62.69 170 $10,657 Cat 14H Motorgrader hrs $53.30 170 $9,061 Soil Samples each $50.00 500 $25,000 Survey Crew hrs $13.32 163 $2,172 Sample Crew hrs $13.32 83 $1,106 Equipment Maintenance (Butler) hrs $10.56 1,190 $12,561
Total Windblown Cleanup $199,370
Quality Control Resource Description Units Cost/Unit Task Units Task Cost
uuality Control lContractor
Total Quality Control
Imrs I $62.001 2,0801 $128,9601
$128,960
Total Cleanup Windblown Contamination
TOTAL MILL DECOMMISSIONING
01/31/2001 - 2:28 PM-WM.RecPlanEst.Jan2001 International Uranium (USA) Corp. White Mesa Mill
1 $461,881
r $1,630,0311
INTERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
..........................................V .............................................. 5) e...... ......
~i~~i.. P 6..r~''41~ ArL '-~Feo-iMR-j 'eeD
* vo .
4CAM ~ 4AS 4k 42
SZZ. 4 A40S
\J&A r 0 54, U16
1PA000
'8 haa" I'3 1
INTERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
o eA,4Arw PLA-0 (oc. 4ww- ~QxjvLJD4,*-) worm La~ Sas 4 l
* 6-r t75)-BMXI490 v-/ eP(.
@ 7&.F~ Qojr Ttucw-S (+ea.)
eomw up~ cw .- >aS To2.m OC
o Tgci'.t~yJ4~4 4ea - -7169D Tkuc..cS
* Lad.) I is / a4ws -*a ALA- 16, . E. Omt~r
7e*Cke D440S
INTERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
................... caic~ tv .............................. so et ..... OF .....
?VLm hj - 10 &~Cf%
I *O %A.16ce Nou sd -Jq
' CP-r ~.LOAJ 4cih
&.Q3 DW Th~lt S,'06X'n.a Wtk .j it~C
12, to& k;
6Ams Rur , zm -11340
The~a....d~ec VSz(0,&
/56, 1es
aLAW 4 dZ7T5 10 1~ _.55
V
klmmý mmmý - - I
Quip A.ss
IN[ERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
.,................................................... Vol. ........................ C8116 I ........................................... ........ o ..........
~L6
oe 4L(A.T~ 1~~-
v- ;+7 , -2. -7 Ax 48) szz ld 3
48)&00,4cl "I
, •,SA40,0J
COST ESTIMATE
/)/boo
zw
im/ 2 2,7~u1
75 72,6So o 0 C
C 7 ~ U,3 41,A
In5Itt2 Yoo A 3o a 645, co
onee4 xr. -77D~~
*~~-- 4o 0'-' -Z. 0 0~
Alzfz, 5Sgmflt d 4O d 76d4'
0
LI'
~N
4�, �1
-4" �4.
)�\�
�44 'I �Aj
'I
� �'i'
z � b�. 'I
-'4 N N
I.,
* * ~ t~ DA
t~$\
04
V
flp.
a
I0
0
'I'
ti
"[44'A
11?
NK
X
Q)
%
�
�\ � '4
�. �:;'�
(� �t�I C' '� �.
C.
K
� �1
'�\ (>\
C,
4�4. N
'I '4%� �.\
V
Sp No. 5505 ITC>Engineae#sComputation Pad
0
4.
4' *1
I
4.
'4
N
Vr
L-Stj
N
Ii 'lb N
N
b
Nk
F.
goNk
96
0
(\J
T
LLI
J) 0
2 11
14"
Li
PBd uoileIndwoo sdoou16u3 9099'ON IC120
a A
................. C4 y............................... f)e~t. ......
0 WDp S04. LAU.X L6 iVMTO
12514OZ.A a2O 19A rK
21W~OOL10 o
rr I~S NJor 4*..0i' 6arý4Dh~ fecAw~
~~~~'~~~~~uIC A re L-*OP 3 .ii*. ~ hS C~
Z-n a 1 M. O-s
94 55i1k=QDi~oo~kw
lwtP
RECLAMATION OF CELL 2
RECLAMATION OF CELL 2
Obtain Permits for Clay Borrow Site - Section 16 Resource Description Units Cost/Unit Task Units Task Cost
Permits & Licenses lea I $10,000.001 51 $50,0001
Total Obtain Permits for Clay Borrow Site - Section 16 $60,000
Place Remainder of Bridging (Platform) Lift Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 178 $3,154 Cat 627F Scraper hrs $154.47 78 $12,049 Cat 815C Compactor hrs $75.09 20 $1,502 Cat D8N Dozer With Ripper hrs $74.64 20 $1,493 Cat D7 Dozer hrs $62.69 20 $1,254 Cat 651 Waterwagon hrs $79.92 20 $1,598 Cat 14G Motorgrader hrs $53.30 20 $1,066 Equipment Maintenance (Butler) hrs $10.56 178 $1,879
Total Place Remainder of Bridging (Platform) Lift $23,994
Place Lower Random Fill (12") Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 902 $15,981 Cat 637 Scraper hrs $154.47 402 $62,097 Cat 825 Compactor hrs $75.09 100 $7,509 Cat D8N Dozer With Ripper hrs $74.64 100 $7,464 Cat D7 Dozer hrs $62.69 100 $6,269 Cat 651 Waterwagon hrs $79.92 100 $7,992 Cat 14G Motorgrader hrs $53.30 100 $5,330 Equipment Maintenance (Butler) hrs $10.56 902 $9,521
Total Place Lower Random Fill (12") $122,164
Clay Layer Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader Cat 980 Loader 5000 Gallon Water Truck Highway Trucks Truck Drivers Equipment Maintenance (Butler)
hrs $75.09 320 $24,029 hrs $74.64 300 $22,393 hrs $62.69 0 $0 hrs $79.92 300 $23,976 hrs $53.30 320 $17,056 hrs $70.32 300 $21,097 hrs $45.09 150 $6,764 hrs $40.00 2,400 $96,000 hrs $12.74 2,400 $30,577 hrs $10.56 4,090 $43,173
Total Place Clay Layer
01/31/2001 - 2:29 PM - WM.RecPlanEst.Jan2001
$315,008
International Uranium (USA) Corp. White Mesa Mill
hrs; $17.72 1,690 $29,943
Page 1 of 2
RECLAMATION OF CELL 2
Upper Random Fill Resource Description
Equipment Operators Cat 637 Scraper Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader 5000 Gallon Water Truck Equipment Maintenance (Butler)
Total Place Upper Random Fill
Rock Armor Resource Description
Units Cost/Unit Task Units Task Cost
$256,978
Units Cost/Unit Task Units Task CostEquipment Operators hrs $17.72 825 $14,617 Cat D7 Dozer hrs $62.69 275 $17,239 Cat 651 Waterwagon hrs $79.92 275 $21,978 Cat 14G Motorgrader hrs $53.30 275 $14,658 Rock Cost Delivered CY $3.661 66,200 $242,497 Equipment Maintenance (Butler) hrs $10.56 825 $8,709
Total Place Rock Armor $319,697
Quality Control Resource Description Units Cost/Unit Task Units Task Cost
Quality Control Contractor
Total Quality Control
TOTAL RECLAMATION OF CELL 2
01/31/2001 - 2:29 PM - WM.RecPlanEst.Jan2001
$1,152,9411
International Uranium (USA) Corp. White Mesa Mill
hrs $154.47 796 $122,959 hrs $75.09 199 $14,943 hrs $74.64 199 $14,854 hrs $62.69 199 $12,474 hrs $79.92 199 $15,904 hrs $53.30 199 $10,607 hrs $45.09 199 $8,973 hrs $10.56 1,990 $21,006
1nrs I $2.001 1,0501 $65,1001
$65,100
!~ $62.001 "
hrs $17.721 1,990 $35,258
Page 2 of 2
*1 a 0
VI
~"k
Nr a
z -'
En i
z u 00
" to
0 04
() 0 ' 0 -(
II t I I
iItE4[INATIONAL URANIUM IUSAJ CORP. COST ESTIMATE
j -7)r. .4 c L-
�ie Ce-�- �-
" ,' 0 -A z 14
~7- + /C---~~~2 flOOJy
7) Ur,� � R�L � - 7*�,f �-,e �
F4L< ,4a.C.4 � Cec�.. � � .,4 rh�&
-2 21j2 ' 4c.y~ 22i 3acrc
2,l a G ,/o x
17) 742 4h ee (ce /) C - r' i-.
* ~~ e-j/Zh
2Z o
3.3: _76 S:,I
/2XZX/3] X( Z(.60
Z3741400 4+. 13,667 Cy
Soo 11pc
0~
0 U-)
- u~ J
4 �-r
1, 0 A z -1- 2-4
Z-7 -W3/Cj
,4/4,wofL - 7'Z>,,O evo-
Eiý,<S5) 30,7 'c/ -
)z 'y /,z x 2-
101
t
11-1 V
0
0
M 0
W W
uj
D 2
w
0
0
z a: ui Fz
X
P8d uoileindwoo sdG8ul6u3 9099 *ON <So-
X N rf)
0 V) rl to
t4l Ix V)
%n
INTERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
7,.
6�-4 �? 1�-'d�7
* A-v�r-?,,�,, '- 2
* �')v4* 5L�O 7'�.
a) �
r',2
K-S Zx
Q. E 0
Lo .C
-z
I;-I
10 J,
no4- rcý4JroJ -for :rý14 /0'/Z~o~o - nl,
/2?) 6q'-k t2 Ct I~i I~~ 'sc)
/250
= -4 ,1,C7 --,L z i27�37� 5
/
/9
q9m c', 4'Z'SQ _ýk3 ,
'Tý_Zx, r__
a) R11 Foe..,.z * /0
/ //ý,, x, /Z _-ýo -, =
of..,.. )cr// - W/o
3 7, s; 0 -ý/,: ý e > ( " ?_ s -, 0 / 7_1 -b =leo'o r-7 do 7ool Z7 w 1,00r7
7d-;w- - Aý
-,qqý O/V
00
17 ,ý )e 4 -P,
4
X-V w cw-%v,
r7
x s -74-R e7 77 (,F Z
Lýz
TO ý01
co -S
r-p4z-vd-rj ON
7ý1
-zoo W-j-t;K W
A
CIQý x C-S Y,6
CW2-ýU
Ltiý?- k -<-
LO) It =
x C T -XII2 --90
0
mz_ 0
CD Ln
LTI
0
.I- A -:1Ez- ý-C)oz--7 0 -9 Z
,;Y-)-IC7 -7.9
G("!.- /.- 0-ý; ;
71
31YONIIS3 IS03 (Vqn) V4nlNVHn IYNOUVW49INI
Ca // 2 I/v e C,- /, S'e- A Xe " - -3 ao'
Aae.4 P/
'S
7/ c e.1
:5;S---rwJ JQ -A (IVOr To ý5%4164) Do
7-7 'To Ataw
-so. OIL
x
0.- eerx- Jv eAr;p,.f7.mx dowe 4e-w--r
414 1Ace,4 #Wia .Ce
(Soff 1 -1 D,5ý05,6 / 44
0092 T 0 T00
/~ C)
o0 cc/ -Wow 0
0.
o;.q c)CE //, /0/
31V4ILS3 ISOD 'dJO:D CYSn) 'AnINVu lV1NOIlVNd31Nl
w PROJECT QUANTITIES
Cell Slopes Slope.
No,
1 Cell 2 North dike 2 Cell 2 North Dike 3 !Cell 2 West Dike 4 :Cell 2 East Dike 5 Cell 2 South Dike
u
Height feet L 12
1
3
iCell 2 Slope Totals
6 7 8 9
Cell 3 West Dike Cell 3 South Dike Cell 3 South Dike Cell 3 East Dike
2 16 39 6
Cell 3 Slope Totals
iTotal Material Requirements (CY)
NOTE:
Length EXISTING DIKE "A" feet AREA VOL (CY)
2,600 216.0 20,800 900 1.5 50 500 6.0 111
1,250 3,500
6,150
1,100 1,750 1,700 800
5,350
1.5 0.0
6.0 384.0
:2,281.5 54.0
69 0
21,031
244 24,889 143,650
1,600
WEDGE "B"VOL (CY)
13,867 33 74 46
1,167
15,187
163 16,593 95,767 1,067
AREA
144.0 1.0 4.0 1.0 9.0
4.0 256.0
1,521.0 36.0
170,383
191,414
RANDOM FILL "C" AREA IVOL(CY)!
62.5 6,019 7.5 250 1925 21
7.5 17.5
12.5 82.5 197.5 32.5
113,589
128,776
347 2,269
9,116
509 5,347 12,435
963
RANDOM FILL "D" AREA VOL (CY)
140.0 30.0 40.0 30.0 50.0
40.0 180.0 410.0 80.0
19,255
28,370
13,481 1,000 741
1,389 6,481
23,093
1,630 11,667 25,815 2,370
41,481
Id
(1,61,67
RIPRAP "E" AREA 'VOL (CY)
51.7 15.0 18.3 15.0 30.7
18.3 65.0 141.7 31.7
64,574
4,976 500 340 694
3,976
10,485
747 4,213 8,920 938
14,819
25,304
Values shown in the "Area" column are the CROSS SECTIONAL AREA for the component in SQUARE FEET. Values shown in the "Volume" column are the component's area x length converted to CUBIC YARDS.
CELL 2 RECLAMATION CAT 637 RESOURCE REQUIREMENTS
Volume Route- -- r -. -
Yds/Hr Equip hrsCell 2 Bridging Lift
Tailings Surface 23,000 5 296 100% 77.7 TOTAL 77.7
Cell 2 Lower Random fill
Tailings surface 110,700 5 296 67% 250.6
Tailings Surface 110,700 4 368 33% 99.3
Slope 1 13,900 5 296 100% 47.0
Slope 2 100 4 368 100% 0.3
Slope 3 100 5 296 100% 0.3
Slope 4 100 4 368 100% 0.3
Slope 5 1,200 5 296 100% 4.1 TOTAL 401.7
Cell 2 Upper Random Fill
Tailings surface 221,300 5 296 67% 500.9
Tailings Surface 221,300 4 368 33% 198.4
Slope 1 19,520 5 296 100% 65.9
Slope 2 1,300 4 368 100% 3.5
Slope 3 100 5 296 100% 0.3
Slope 4 1,800 4 368 100% 4.9
Slope 5 6,500 5 296 100% 22.0 TOTAL 796.0
Cell 2 Rock Armour use Highway Trucks
INTERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
/'���� ��- 0� � 4Z �Z�t�n �Co.i/ /� -
a .3
4 5
2sooo'
4 Zoo
so0
~i~4eZt 4I4 7s~ go i~lr 7A0s4 0.
11%'
1,8% o.SZ
4.2 (vO M'
/71/0 e-,
-7"
/ no.,
A 2.e~
9A,5 ,o'A 7.+3"-
~7 7c~ Aa.0' e,%e ?
5o 4fr-v Z. 27
I \
#4 L2zA-14 )
4JjjARW* e.ie
Fvc A- 7o~-0 .n
274~.Ac Soo ~b e%. 3 Z. o g £4 i70 O
epaW*E -guy .24 I3 20.~ .. ',
*A qL S~ 'oo
22'
Z 7I-
w m
0~ 0~4
081
NC4 C
(ez-C
Iwwl-'-'rlthe-ýrx '0"4" Ar-e-
INTERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
........ ............... .. pae ................. .. . . . . . . . . * et o
"y-oL-"w ex-r
4). LAd ien*
* -v-V4wo'A 4ovtoo%"O. gew 04F Basm r Bn~s'.j a~s me
C a d & -^ q a L- dh m0 0 0 -F*O i-s-
DIL WITH SINGL SHANKC
I I
I II. I
wy A :-0 0 - 01 I
111sa maaiv on am= w ww-m x is"
abcM W 4*A ~isomA4 Se AI&A 10 %;oug &-T LjrwW 06, lm /pA& t .11 A..A Amm6aa of
op: QL4,' ?*0acO.ataj Cog 'ZP4 A~ab din ,gU'v
'Fkcvhamvwftj-
RECLAMATION OF CELL 3
RECLAMATION OF CELL 3
Dewatering of Cell 3 Resource Description Units Cost/Unit Task Units Task Cosqt
Dewatering of Cell 3 Ihrs I $0.481 62,4001 $30,000
Total Dewatering of Cell 3 $30,000
Place Remainder of Bridging (Platform) Lift Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 1,582 $28,025 Cat 637 Scraper hrs $154.47 703 $108,593 Cat 825 Compactor hrs $75.09 176 $13,197 Cat D8N Dozer With Ripper hrs $74.64 176 $13,118 Cat D7 Dozer hrs $62.69 176 $11,017 Cat 651 Waterwagon hrs $79.92 176 $14,046 Cat 14G Motorgrader hrs $53.30 176 $9,368 Equipment Maintenance (Butler) hrs $10.56 1,582 $16,697
Total Place Remainder of Bridging (Platform) Lift $214,061
Place Lower Random Fill (12") Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 1,745 $30,913 Cat 637 Scraper hrs $154.47 775 $119,715 Cat 825 Compactor hrs $75.09 194 $14,549 Cat D8N Dozer With Ripper hrs $74.64 194 $14,481 Cat D7 Dozer hrs $62.69 194 $12,161 Cat 651 Waterwagon hrs $79.92 194 $15,504 Cat 14G Motorgrader hrs $53.30 194 $10,340 Equipment Maintenance (Butler) hrs $10.56 1,745 $18,417
Total Place Lower Random Fill (12") $236,080
Clay Layer Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators Cat 637 Scraper Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader Cat 980 Loader 5000 Gallon Water Truck Highway Trucks Truck Drivers Equipment Maintenance (Butler)
Total Place Clay Layer
hrs $154.47 0 $0 hrs $75.09 375 $28,158 hrs $74.64 350 $26,125 hrs $62.69 0 $0 hrs $79.92 350 $27,972 hrs $53.30 375 $19,988 hrs $70.32 350 $24,613 hrs $45.09 175 $7,891 hrs $40.00 2,800 $112,000 hrs $12.74 2,800 $35,674 hrs $10.56 4,775 $50,404
01/31/2001 - 2:29 PM - WM.RecPlanEst.Jan2001
$367,817
International Uranium (USA) Corp. White Mesa Mill
hrs $17.72 1.975 $34 9.q3
I of 2
RECLAMATION OF CELL 3
Upper Random Fill Resource Description
Equipment Operators Cat 637 Scraper Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader 5000 Gallon Water Truck Equipment Maintenance (Butler)
Total Place Upper Random Fill
Rock Armor. Resource Description
Units Cost/Unit Task Units Task Cost
$321,546
Units Cost/Unit Task Units Task CostEquipment Operators hrs $17.72 948 $16,796 Cat D7 Dozer hrs $62.69 316 $19,809 Cat 651 Waterwagon hrs $79.92 316 $25,254 Cat 14G Motorgrader hrs $53.30 316 $16,843 Rock Cost Delivered CY $3.66 76,110 $278,799 Equipment Maintenance (Butler) hrs $10.56 948 $10,007
Total Place Rock Armor $367,508
Quality Control Resource Description Units Cost/Unit Task Units Task Cost
Quality Contro LContractor
Total Quality Control
lhrs I $62.001 1,4061 $87,172j
$87,172
TOTAL RECLAMATION OF CELL 3 $1,624,1841
International Uranium (USA) Corp. White Mesa Mill
01131/2001 - 2:29 PM - WM.RecPlanEst.Jan2001
hrs $154.47 996 $153,853 hrs $75.09 249 $18,697 hrs $74.64 249 $18,586 hrs $62.69 249 $15,609 hrs $79.92 249 $19,900 hrs $53.30 249 $13,272 hrs $45.09 249 $11,228 hrs $10.56 2,490 $26,284
2 of 2
hrs $17.72 2,490 $44,117
I
COST ESTIMATE
23.25
E 0
Ln~
U, .6
I-7
Z-V, 2I .4 7-
- x-7 1). 9 w 17 I,130 *74y: o
INTERNATIONAL UIIANIUWM 1UZýAi j
COST ESTIMATE
CA C%4P-�..i. � -
--- - ---
... O4 y
.25s*Zz 41L za, _i
~~ c-I- oT6c-zdCeJ - 7-4,0 E-c
3,-235,+, 25Z -4z- . -
*?3-~157 Cy> ~ 3 (eOO C
55's 10071y
&E4C. -� ��JE�.7 5 dE (s�.c w�)
2q .5 1 4 C7 -.a.
A/4 C r- f 7,- V
rOA~ 6'r,*vt 4,74 A #7 f OrJ /a,d zczy a o~~eQ wc v iu'e* d#4o 4 'm
Q ZxZ %.5 z>( )IC)#4-')/ 7=
a AW67 )e' :5Zx Z X.5
-*0 -57/7504j3
* c�. Ar#�.o.r
.271-~
zz
-�
�274�728 c 7 --t
Vu
0~
CL E2
0.
LOC
LO
-z W
-4 -7
volvir.e Jae 4ý I --+ -- , I
407c, 1,4 c-v
aivyvlIS3 Isoo ilvcm) YVnINVHn 'IVNOIIWNPMfN,
z ZR
VOZýL_ ý5;5 -ff EER ýý;16 e- -- 4 .7 VZ 4
r- -\ OOL_ !sr.-Slr LYxwx rz. - i976-V I -6C] v
I', * rýax 171 T)? 4 L I
(v4 1,,t*2
is
q x "Iff-L I E
.Vjol.ý T a`4- l-"- r`J"-J _;`ý
.'/, -ý zz JýJ- Iss4k- C'_7 1ý61 ý;l
-2
LOY 61. -A Ls 6\
S, LS 169*
y s7tný AI)k 7,
t 0 VU IEEE
0
m Z = 0
CD CD 0 L
0 0 3
CL
d6- 4 -;, 0 Z, ,-
1- -2 Li X L 6ý1 "A )I
<-- `24am JI.J uvoowr,!j
Ldt!)
(Qj
INTERNATIONAL URANIUM (USA) CORP.iF COST ESTIMATE
0 0 C,L z
52, 7 5 -
1ý - V
42� �'- 4Z.Cax� .4z )e IZ xC2-
24/, £4'85-d
-4
7od /
I~~
I~ ~ C..e,--.4.. -5 ,Lhpe
o csc kclv4+Ers oQL
- z± ,
- (4.- V dI %A
2 /
//, (/�4?
uprocv' R~r,, -
0~
-Z 0
'K �
ý x 57
,35,25c) c,7
d -141x.
3-"OaD .4-f
LIZO,3 c- -712, a--,a A -3 Z7 -z- -7 Týzca//&Scy :t:-
16 .41 --,
wr> ) 4jo ýýý
" 7Ze
OOZ't
co i? ?(I rfA
CC/ /Z- cog / 0) P"Vlý
31YO41IS3 ISOO fwcm) wnlkrwwn -?VNr)llwww:)iwl
0
0
m z 0
CD 0
Ch
0 0 -3
5'
00YI611 1. C>10),Zgz0// coz,
w-lY vPrrx77 I -&w'wl ;'17"& 1wwvte
';ý-L4-Anj I
aos ý .0 / -- - --I-
gjlf'A MN ..lVNAL VMA1Uf~LM ~~J~.~~ COST ESTIMATE
6~A~7 ~ _____1 /9-, 750 £c/
75 Lc 11A,
0 0
-) .c
/~~"7,/~-3.5 rC7 5 /
EQj 47le LG1/
0. A- r5 -T A.]," 4
3-4
?:7T~3o~r
Pyl
P/,q /Zr-,n /,I1ý,e-,c IWI 4 Cc
'k 3.0 P go/
t /,;l /U,-ý ý71/4 - I - Cl.& 3
CELL 3 RECLAMATION CAT 637 RESOURCE REQUIREMENTS
Volume___________ 1 -- -
Route Yds/Hr Equip hrs
Cell 3 Bridging Lift
Tailings Surface 6 277 100% 7O3Z. TOTAL :703425
Cell 3 Lower Random Fill
Tailings surface 119,800 6 296 100% 404.7
Slope 6 410 6 296 100% 1.4
Slope 7 16,600 6 368 100% 45.1
Slope 8 95,800 6 296 100% 323.6
Slope 9 0 6 368 100% 0.0 TOTAL 774.9
Cell 3 Upper Random fill
Tailings surface 239,400 6 296 100% 808.8
Slope 6 2,200 6 296 100% 7.4
Slope 7 17,100 6 368 100% 46.5
Slope 8 38,300 6 296 100% 129.4
Slope 9 1,200 6 368 100% 3.3 TOTAL 995.3
Cell 3 Rock Armour use Highway Trucks
CELL 4A CLEANUP
CELL 4A CLEANUP
Dewatering of Cell 4A Resource Description Units
Dewatering of Cell 4A Ihrs $0.481 11500 $5,529
Total Dewatering of Cell 4A $5,529
Remove Fencing Resource Description Units Cost/Unit Task Units Task Cost
Cat 988 Loader hrs $104.70 40 $4,188 Equipment Operators hrs $17.72 40 $709 Equipment Maintenance (Butler) hrs $10.56 40 $422 Laborers hrs $10.35 160 $1,655
Total Remove Fencing $6,974
Remove Liner & Contaminated Material to Cell 3 Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 303 $5,368 Cat 769 Truck hrs $66.18 606 $40,104 Truck Driver hrs $12.74 606 $7,721 Cat 988 Loader hrs $104.70 303 $31,724 Equipment Maintenance (Butler) hrs $10.56 909 $9,595
Total Remove Liner & Contaminated Material to Cell 3 $94,512
Quality Control Resource Description Units Cost/Unit Task Units Task Cost
QuaiLy Control Contractor
Total Quality Control
TOTAL CELL 4A CLEANUP
I rs1 $62.001 3251 5ý20 ~1r
$20,150
1 $127,165
International Uranium (USA) Corp.
White Mesa Mill01/31/2001 - 2:29 PM - WM.RecPlanEst.Jan2001 1 of 1
I $62.001 3251
INTERNATIONAL URANIUM (USA) CORP. ' rIMAA TV - -
C, -430,ow 761-L+ '24?*% 31 ;- 2- P/fla IOW 05:5
c� 5 mi.g�, �9�cao.'r '
jo610viDe La.oLls
it�-
........ ...................... ....... ........ ca .b ..................... .5ih at ....... Of.......
AJIT4 kA'I4OWJA'L
* ~ ~ ~ ~ rca%,w ý40 Caw ;& R.. oL.'5.Yc1Ytw 1a3,
*~~~~~~~~~~~1 9,0jL-- V~7 MA 4p+~ Lh~h~~TS~ '~ Ar
(peep Tic"
s03 mum-r
RECLAMATION OF CELLI
RECLAMATION OF CELL I
Dewatering of Cell 1 Resource Description Cost/Unit Task Units Task Cost
Dewatering of Cell 1 Ihrs I $0481 62,4001 $30,00°°
Total Dewatering of Cell 1 $30,000
Crystal Removal
Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 2,695 $47,749 Cat 769 Truck hrs $66.18 2,157 $142,745 Truck Drivers hrs $12.74 2,157 $27,481 Cat 988 Loader hrs $104.70 539 $56,433 Cat D8N Dozer With Ripper hrs $74.64 539 $40,232 Cat 375 Excavator hrs $132.76 539 $71,556 Cat 651 Waterwagon hrs $79.92 539 $43,076 Cat 14G Motorgrader hrs $53.30 539 $28,729 Equipment Maintenance (Butler) hrs $10.56 4,852 $51,217
Total Crystal Removal $509,220
Contaminated Materials Removal Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 616 $10,914 Cat 637 Scraper hrs $154.47 308 $47,577 Cat D8N Dozer With Ripper hrs $74.64 77 $5,747 Cat 825C Compactor hrs $75.09 77 $5,782 Cat 651 Waterwagon hrs $79.92 77 $6,154 Cat 14G Motorgrader hrs $53.30 77 $4,104 Equipment Maintenance (Butler) hrs $10.56 616 $6,502
Total Contaminated Materials Removal $86,781
Topsoil Application
Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators Cat 637 Scraper Cat D8N Dozer With Ripper Cat 651 Waterwagon Cat 14G Motorgrader Equipment Maintenance (Butler)
Total Topsoil Application
hrs $154.47 120 $18,537 hrs $74.64 40 $2,986 hrs $79.92 40 $3,197 hrs $53.30 40 $2,132 hrs $10.56 240 $2,533
$33,637
01/31/2001 - 2:29 PM - WM.RecPlanEst.Jan2001International Uranium (USA) Corp.
White Mesa Mill
Units
hrs $17.72 240 $4,252
Page 1 of 4
RECLAMATION OF CELL1
Construct Channel Resource Description
Equipment Operators Cat 637 Scraper Cat 769 Truck Truck Drivers Cat 988 Loader Drilling & Blasting Contractor Cat 14G Motorgrader Cat D8N Dozer With Ripper Equipment Maintenance (Butler)
Total Construct Channel
Place Clay Liner Resource Description
Equipment Operators Cat 637 Scraper Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 980 Loader 5000 Gallon Water Truck Highway Trucks Truck Drivers Cat 14G Motorgrader Equipment Maintenance (Butler)
Units Cost/Unit Task Units Task Costt -
hrs $154.47 272 $42,016 hrs $66.18 450 $29,780 hrs $12.74 450 $5,733 hrs $104.70 150 $15,705 BCY $1.50 89,100 $133,650 hrs $53.30 218 $11,620 hrs. $74.64 218 $16,272 hrs $10.56 1,308 $13,807
$283,785
Units Cost/Unit Task Units Task Cost
Total Place Clay Liner
Place Lower Random Fill Resource Description
Equipment Operators Cat 637 Scraper Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader Equipment Maintenance (Butler)
VUnits Cost/Unit Task Units Task Cost
hrs $154.47 172 $26,569 hrs $75.09 86 $6,458 hrs $74.64 86 $6,419 hrs $62.69 86 $5,391 hrs $79.92 86 $6,873 hrs $53.30 86 $4,584
hs $17.72 602 $10666
hrs $10.56 602 $6,355
Total Place Lower Random Fill
01131/2001 - 2:29 PM - WM.RecPlanEst.Jan2001
$73,314
International Uranium (USA) Corp.
White Mesa Mill
hrs $154.47 0 $0 hrs $75.09 60 $4,505 hrs $74.64 60 $4,479 hrs $62.69 0 $0 hrs $79.92 60 $4,795 hrs $70.32 60 $4,219 hrs $45.09 30 $1,353 hrs $40.00 435 $17,400 hrs $12.74 435 $5,542 hrs $53.30 85 $4,531 hrs $10.56 1,580 $16,678
$69,792
hrs $17.72 858 $15,202
hrs $17.72 355 $6,290
hrs $17.72 602 $10.666
Page 2 of 4
RECLAMATION OF CELL1
Clay CapResource Description
Equipment Operators Cat 637 Scraper Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader Cat 980 Loader 5000 Gallon Water Truck Highway Trucks Truck Drivers Equipment Maintenance (Butler)
Units Cost/Unit Task Units Task Cost
hrs $154.47 0 $0 hrs $75.09 55 $4,130 hrs $74.64 55 $4,105 hrs $62.69 0 $0 hrs $79.92 55 $4,396 hrs $53.30 55 $2,932 hrs $70.32 55 $3,868 hrs $45.09 30 $1,353 hrs $40.00 440 $17,600 hrs $12.74 440 $5,606 hrs $10.56 305 $3,220
Total Place Clay Cap $52,612
Upper Random Fill
Resource Description
Equipment Operators Cat 637 Scraper Cat 825 Compactor Cat D8N Dozer With Ripper Cat D7 Dozer Cat 651 Waterwagon Cat 14G Motorgrader 5000 Gallon Water Truck Equipment Maintenance (Butler)
Total Place Upper Random Fill
Units Cost/Unit1 1 1
hrs $17.72 688 $12,190Task Units Task Cost
hrs $154.47 172 $26,569 hrs $75.09 86 $6,458 hrs $74.64 86 $6,419 hrs $62.69 86 $5,391 hrs $79.92 86 $6,873 hrs $53.30 86 $4,584 hrs $45.09 86 $3,878 hrs $10.56 688 $7,262
01/31/2001 - 2:29 PM - WM.RecPlanEst.Jan2001
$79,624
International Uranium (USA) Corp.
White Mesa Mill
hrs $17.72 305 $5,404
hrs $17.72 688 $12,190
Page 3 of 4
RECLAMATION OF CELL1
Rock Armor Resource Description Units Cost/Unit Task Units Task Cost
Equipment Operators hrs $17.72 90 $1,595 Cat D7 Dozer hrs $62.69 30 $1,881 Cat 651 Waterwagon hrs $79.92 30 $2,398 Cat 14G Motorgrader hrs $53.30 30 $1,599 Rock Cost Delivered CY $3.66 8,607 $31,528 Equipment Maintenance (Butler) hrs $10.56 90 $950
Total Place Rock Armor $39,950
Quality Control Resource Description Units Cost/Unit Task Units Task Cost
Q4uaity uontrol Contractor
Total Quality Control
Ihrs I $62.001
TOTAL RECLAMATION OF CELL I
01/31/2001 - 2:29 PM - WM.RecPlanEst.Jan2001
1 $1,308,31s5
International Uranium (USA) Corp.
White Mesa Mill
8001 $49,600
$49,600
Page 4 of 4
I~ I ,E ETSI I I le i W W G~S~n)22-142 100 SHEETSW
"..'22-144 200 SHEETS
'CN
*r
t'f
'k3
V 4V k
%A k (I - SI .
N~e. ~ tN
22-144 200 SHEETS
I I .1
elk
(I'
'4 .
I'
� r'
4 %'
�K) 1K
(' N�
.�-' \
V ) (4,
I
N '4
(3
- IA .19
tow~
fit I
V.0
V)
$1 'U
ti
IN,
II
- LS
tv
(r\ in r
-c
m I
m
c
M
fitAg
4sý
-D
INTERNATIONAL URANIUM (USA) CORP. COST ESTIMATE
A -A 4
goMI,, h ecic CC.o'j7-c-r see z
0 cc inur I0
4 C4 C4 5
W44.7ov -' r'wleo
ar~/t -IV,
PA
77
4
9
-n--3 --r C'Vllll.A(a
4;.
f- -Srs
7ý Cý/ -r
C) /A#$
31VVIIIS3 ISOO (Ysn) v4nlNyun IYNOIIYNU31NI
-3
I.
�
'�i t
417
JIi
A9
-eb 25 99 01i:38FP. 1
U.S. Silica Ccmpan:ý
I 107AMERICAN MINE SERI.
August 1~ 1998 C
Via Fax:
Attn: Msrk Kerr, KLG Associates, Inc.
Re: D6r1,2 itgAnd Blasting Lirne-tone, Will, Cre eir, Oklahoma
We are ; lease to subrnit the following prope: atlto providc all equipment, labor and materials for
the abov*: referenced projett &% follows-
Descripion.~
Drill and Blast Cubs
Seisn*Miconitoring
Unit PriCe
$8,000.00
$ l.351CY
S300,00IEA
Ent. Quantity
I
30,000 CY
z
General '."larifications: > L~ayoui and gradie control by others
>r!XCaV,' tion1 by others U 2xplofives storage on site
> Pripinj assuines two 10 hour drillingo ihift,- m-, day fiF 6day por week > If bon fin, is required add 1% 1> igit working lights by other > Piicirq. axwnes dry hole conditions, add. 1.5 per CY if wet bole conditioli are encounLered
> Pricing: is bawWv on a rninimum of 30,000 4! Y ahot during a 10 day period
If you havtc any questions or Aced additional nlbonration, Please feel free to contact me at
3033.499+770.
Sincerely,
C. B. .0,1260, Project Muanaer
0'p'9/'
118083 Hi-frway 93 * BOUL' £-EF. COLORADO B0303.SO4S 9 US5A TELEPHOW. 13W~] 4994770 - FAX: [3031) 4994'M
T>-F--
Calculation I Work Sheet ......
-Project: Rec, Plan Revision 3.0 1? _ __ Date
7e~- e , ,, / (// i- - c / ,-e 6•- -•o ..c V Ca., -,7
f
•,o /( I•/...o
*~~~Ja C/( 43 .0e xof
(Is s•c ',c / ,fA. ,,
_______ ,'I-",o li•e.
six12 0/ 4e3
70-/j4
N
aC
Calculation,/ Worlý Sheet .....
lProiect: Rec. Plan Revision 3.0 by: __ Date*~
(3N
NY
N NS
'N- '4.2 )
N
N
V
Qý cl
C
0
C
0� d w
-U
U)
I
0
0
U
U
IL
K
________________________ -- - __________ - _______________________ - ________________________ - __________ - ________________________ - __________ - __________ - - __________-. 4 __________
e
'I'
A Tj
Calculation I Work Sheet
Project; Rec. Plan Revision 3.0 b-Date': 07.____
5-1•, 03• .,>
I/o r . 11, ý2• le•.<. m• 'I . / e /Z
Calculation I Work Sheet
~Proiect: Rec. Plan Revision 3.0 by: Date '41____
t~6c; &~- ~ -,1'( -5-7 e~- c- Ii
J~3/ - j
MISCELLANEOUS ITEMS
MISCELLANEOUS ITEMS
Equipment Mobilization
Resource Description Units Cost/Unit Task Units Task CostButler Machinery Mobilization jLS 1 $156,500.001 1 $156,500 Other Equipment Mobilization LS $2,500.00 1 $2,5001
Total Equipment Mobilization $159,000
Office Facilities Resource Description Units Cost/Unit Task Units Task Cost
Run New Powerline ILS I $15,000.00 1 $15,000 Utilities for Offices months $1,000.00 36 $36,000
Total Temporary Office Facilities $51,000
Wheel Wash Facility Resource Description Units Cost/Unit Task Units Task Cost
Laborers Ihrs $10.351 8,3201 $86,084 Construct Wheel Wash Facility LS $50,000.00 1 $50,000
Facility constructed in 2000 ($50,000) Total Wheel Wash Facility $86,084
MANAGEMENTISUPPORT Resource Description Units Cost/Unit Task Units Task Cost
manager/Engineer Radiation Safety Officer Secretary Clerk Environmental Technician Maintenance Foreman Chemist Security Safety Engineer Misc. Materials & Supplies Health Physics Costs
Total Management/Support
TOTAL MISCELLANEOUS ITEMS
01/31/2001 - 2:30 PM - WM.RecPlanEst. Jan2001
hrs $37.87 6,240 $236,309 hrs $15.55 6,240 $97,055 hrs $12.85 4,866 $62,522 hrs $20.29 4,866 $98,719 hrs $27.73 6,240 $173,012 hrs $22.65 2,080 $47,121 hrs $8.12 18,720 $151,913 hrs $20.29 4,160 $84,396 hrs $36.45 6,240 $227,448 hrs $64.81 2,080 $134,800
$1,617,120
$1,913,2041
International Uranium (USA) Corp. White Mesa Mill
hrs $48.69 6,240 $303,826
1 of 1
ROCK PRODUCTION COST
Assumptions:
Rock is obtained from gravel source north of Blanding, Utah. BLM Public pit Rock is processed by screening only, no crushing is required, 1.25 CY of feed for 1 CY of product Rock is produced and stockpiled at the site Site is 7 road miles from the mill; 6 miles of which is paved public highway Rock will be hauled in 22 CY bellydump trucks, contract haulers ($55.00/hr) Rock will be dumped in windrows on Tailings Cells by trucks, spread by grader, and compacted by D7 Dozer Trucks can average 30 MPH (1.75 rounds/hr)
Product Material Feed Required (CY) Reject Factor to Plant (CY)
146,000 25.0% 182,500Material fed to plant
Plant Throughput
(CY/hr) 122
Plant Operating
Hours 1,500
PRODUCTION OF RIPRAP
Resource DescriptionEquipment Operators Laborer Cat D8N Dozer With Ripper Cat 980 Loader Screening Plant w/conveyors* Contract Highway Trucks - Bellydumps** Equipment Maintenance (Butler)
Units Cost/Unit Task Units Task Cost
Total Production of RipRap
RIPRAP COST PER CUBIC YARD DELIVERED
* Cost Quoted from Mr. Terry Berg, Power Motive Corporation, Denver, Colorado Jan. 23, 2001 '$9,150 per month, 176 hours per month
** Cost quoted from Dennis Cosby, Cosby Trucking, Inc., Blanding, Utah, Jan 24, 2001
01/3112001 - 2:35 PM - WM.RecPlanEst.Jan2001International Uranium (USA) Corp.
White Mesa Mill
hrs $10.35 1,500 $15,520 hrs $74.64 365 $27,245 hrs $70.32 1,975 $138,888 hrs $52.00 1,500 $78,000 hrs $55.00 3,800 $209,000 hrs $10.56 2,340 $24,701
$534,813
$3.66
hrs 1 $17.72 2.340 $41.460
1Ofl
0 (D 5)
0 3
CD
N �N N
Nt,
I 4 Az�1'5�
0
9'i.
KqN
( NX t
I I
44*
'II
I
EQUIPMENT COSTS
WHITE MESA MILL RECLAMATION COST HOURLY EQUIPMENT COSTS 1999 DOLLARS
Actual equipment rates quoted from Butler Machinery 6 month rental period January 25, 2001
Units637E Scraper
D8R Dozer
D7R Dozer
825G Compactor
980 G Loader
988 F Loader 769D Haul Truck
375L Excavator
651 Water Wagon 5000 gal Water Truck 14H/Ripper Motor Grader 16H/Ripper Motor Grader
"4
RATE MTCE FUEL FUELQ TOTAL Mob/Demob Mob/Demob 0prating Hrs MONTHLY I HOURLY EXPENOABLES USAGE $102 COST per machine Totals per Month
ZL,Z1UU
11,400
9,600
10,500
10,550
16,000
9,750
20,500
10,500
6,000
8,200 11,750
121.04
64.77
54.55
59.66
59.94
90.91 55.40
116.48
59.66
34.09
46.59
66.76
2.15 1.20
1.00
1.15 1.20
1.55
1 60
2.00
1.90
0.80
1.10 1.25
24.0
8.5
7.0 14.0
9.0 12.0
9.0
14.0
180
10.0 5.5
8.5
24.48
8.67 7.14
14.28
9.18
12.24
9.18 14.28
18.36
10.20
5.61
8.67
$154.47
$74.64
$62.69
$75.09 $70.32
$104.70
$66.18
$132.76
$79.92 $45.09
$53.30 $76.68
Equipment Rental Rate Quoted by Power Motive, Denver, Colorado (01/23/2001) for PC400 Kamatsu Excavator with LaBounty MSD 70R Shear
PC-400 w Shear 22,950.00 130.40 18.94 14.0 14.28r $163.621
Small tools allocation - Demolition $1.25/mechanic labor hour for oxygen/acetylene, expendables
Total Equipment Mobilization
Butler Equipment Maintenance Cost
Crane Rental Rates 65 ton Hydraulic Crane 30 ton Hydraulic Crane
Maintenance Monthly Planned Cost per
Maintenance Operating Availability Operating Flat Rate Hours/month Factor Hour $31,100.00 3,168 0.93 $6
RATE MTCE FUEL FUEL TOTAL L MONTHLY I HOURLY EXPENDABLES USAGE $1.02 COST
8,000 45.45 2.05 15.0 15.30 $62.80 5,000 28.41 2.05 10.0 10.20 $40.66
Rental Rates updated from Crane Services, Inc. 01/2312001
01131/2001 - 2:30 PM - WM RecPilnEst Jan2001 International Urnium (USA) Corp. White Mass Mill
$11,400.00
$7,800.00
$6,800.00
$7,700.00
$7,700.00
$9,100.00 $7,800.00
$15,800.00
$8,500.00 $3,200.00
$5,900.00
$7,200.00
$45,600.00
$7,800.00
$6,800.00
$7,700.00
$7,700.00
$9,100.00 $31,200.00
$15,800.00
$8,500.00
$3,200.00
$5,900.00 $7,200.00
$156,500.00
704
176
176
176
176
176
704
176
176
176
176
176
3,168
$2,500.00
i $159,000.001
JANUARY 25, 2001
INTERNATIONAL URANIUM CORPORATION ATTN: HAROLD ROBERTS E-MAILED TO HRR91851@AOL.COM
DEAR HAROLD:
THANK YOU FOR THE INVITATION TO QUOTE INTERNATIONAL URANIUM CORPORATION (IRC) THE EQUIPMENT NEEDED FOR THEIR MINING PROJECT IN BLANDING, UTAH. BUTLER MACHINERY COMPANY (BUTLER) RESPECTFULLY SUBMITS OUR PROPOSAL FOR A MAINTAINED FLEET OF CATERPILLAR MACHINES.
LISTED ON ATTACHMENT A, YOU WILL FIND THE MODELS, QUANTITIES, MONTHLY RENTAL RATES, HOURS ALLOWED PER MONTH, EXCESS HOUR CHARGE, GUARANTEED NUMBER OF MONTHS RATES ARE BASED UPON, TOTAL FREIGHT CHARGES AND THE MAINTENANCE RATE PER HOUR FOR MATERIALS ONLY.
ALL RATES SHOWN ON ATTACHMENT A DO NOT INCLUDE ANY STATE, LOCAL, PROPERTY OR ANY OTHER TAXES THAT MAY BE APPLICABLE.
RATES ARE BASED UPON ELECTRIC HOUR METER READINGS WHICH ARE ATTACHED TO THE DASH OF EACH MACHINE. RATES ARE BASED ON 176 HOURS OF USE EACH MONTH. EXCESS HOUR CHARGES, IF ANY, WILL BE CALCULATED AND INVOICED AT THE END OF THE PROJECT. THERE WOULD BE NO CREDIT ISSUED FOR ANY HOURS UNDER THE ALLOWED DURING THE TERM OF THIS PROPOSAL. IF IRC ELECTS TO DOUBLE SHIFT MACHINES, THEN BUTLER WOULD INVOICE THOSE HOURS AT THE END OF EACH MONTH. (TO FIGURE THE DOUBLE SHIFT RATES, TAKE THE EXCESS HOUR RATE
SHOWN ON ATTACHMENT A TIMES THE NUMBER OF HOURS).
RATES ARE BASED UPON A MINIMUM GUARANTEE OF 6 MONTHS AND A PACKAGE DEAL.
MAINTENANCE: THE MAINTENANCE RATES PER HOUR LISTED ON ATTACHMENT A INCLUDES THE MATERIAL PART ITEMS ONLY, SUCH AS AIR, OIL, AND FUEL FILTERS, LUBRICANT OILS, GREASE, ANTI-FREEZE, BATTERIES, FAN BELTS, LIGHTS AND MAKE-UP OILS. BUTLER WOULD INVOICE IRC ACTUAL HOURS USED ON MACHINES AT THE END OF EACH MONTH.
OUR MONTHLY MAINTENANCE CHARGE WOULD BE $31,100.00, WHICH INCLUDES OUR LABOR, SPECIALIZED LUBE TRUCKS, SUPPORT VEHICLES AND EQUIPMENT, SPECIALIZED TOOLING, SCHEDULED OIL SAMPLING, PARTS TRAILERS AND
INVENTORIES, MILEAGE AND TRAVEL EXPENSE. BUTLER WILL PROVIDE TWO (2) FULL-TIME MAINTENANCE TECHNICIANS ON SITE FIFTY (50) HOURS PER WEEK ON A SCHEDULE TO BE DETERMINED, MONDAY THROUGH FRIDAY. IRC WOULD HAVE TO SCHEDULE THE MACHINES AVAILABLE FOR A TIME FRAME YET TO BE DETERMINED ADEQUATE FOR BUTLER MAINTENANCE PERSONNEL TO PERFORM THE REQUIRED MAINTENANCE. BUTLER WOULD INVOICE IRC FOR THE MONTHLY MAINTENANCE CHARGE AT THE BEGINNING OF EACH MONTH.
REPAIRS:
BUTLER WOULD BE RESPONSIBLE FOR ALL REPAIRS INCLUDING PARTS AND LABOR ON OUR MACHINES OTHER THAN FAILURES CAUSED BY DAMAGES OR MIS-USE. REPAIRS INCLUDE ITEMS AS MINOR AS STARTERS, ALTERNATORS, WATER PUMPS, HYDRAULIC HOSES, ETC. TO THE MAJOR ITEMS SUCH AS ENGINES, TRANSMISSIONS, DIFFERENTIALS, BRAKES, HYDRAULIC PUMPS AND CYLINDERS, ETC. IF TIME PERMITS AND IRC REQUESTS BUTLER'S TECHNICIAN TO PERFORM REPAIRS OR MAINTENANCE ON THEIR MACHINES, OUR HOURLY CHARGE WOULD BE $63.00 PER HOUR FOR STANDARD TIME, $81.00 PER HOUR FOR OVERTIME AND $95.00 PER HOUR FOR SUNDAYS AND HOLIDAYS PLUS MATERIALS.
FREIGHT:
FREIGHT CHARGES INCLUDE BOTH DELIVERY AND RETURN, ASSEMBLY, AND DISASSEMBLY OF EQUIPMENT.
IRC'S RESPONSIBILITIES INCLUDE:
OPERATORS. PROVIDE THE OPERATORS AS NEEDED TO OPERATE MACHINES AS STATED IN CATERPILLAR'S OPERATING GUIDE. BUTLER WILL PROVIDE, AT NO EXPENSE TO IRC, QUALIFIED TRAINING INSTRUCTORS FOR THE PURPOSES OF TRAINING OPERATORS. THIS TRAINING WOULD TAKE PLACE ON THE JOBSITE AT THE INITIAL START UP OF THE JOB AND WOULD INCLUDE CLASSROOM, WALK AROUND, AND IN IRON DEMONSTRATIONS.
FUEL. SUPPLY AND FILL ALL FUEL FOR EQUIPMENT INCLUDING BUTLER'S SERVICE VEHICLES.
DAMAGES. THIS INCLUDES GLASS BREAKAGE, BENT HANDRAILS, STEP LADDERS, FENDERS, ETC. BUTLER'S NORMAL POLICY FOR REPAIRING DAMAGES TO RENTAL MACHINES IS TO REPAIR THEM WHEN THE RENTAL PERIOD IS COMPLETED, HOWEVER, IF THE DAMAGED ITEM IS OF A SAFETY CONCERN, WE WOULD REPAIR THE DAMAGES AS SOON AS POSSIBLE AFTER THEY OCCURRED. AN ITEMIZED LIST OF THE PARTS AND LABOR REQUIRED WOULD BE PROVIDED TO IRC PRIOR TO STARTING THE REPAIR, AND INVOICED AT CURRENT LIST PRICES PLUS FREIGHT UPON COMPLETION.
UNDERCARRIAGE AND TIRES: IRC WOULD BE RESPONSIBLE FOR ALL TIRE WEAR INCLUDING TIRE DAMAGES ON THE MACHINES WITH AN ASTERISK LISTED ON ATTACHMENT A. EQUIPMENT WOULD HAVE TO BE RETURNED WITH SAME BRAND AND MODEL TIRES AS WHEN DELIVERED, OR PRORATED ACCORDINGLY BY PERCENTAGE OF TIRE WEAR AND CONDITION AT TERMINATION OF RENTAL PERIOD.
UPON DELIVERY OF MACHINES, A REPRESENTATIVE OF BUTLER, A
REPRESENTATIVE OF IRC AND A REPRESENTATIVE FROM AN INDEPENDENT TIRE DEALER OR MANUFACTURER WOULD JOINTLY VERIFY IN WRITING THE CONDITION, PERCENTAGE OF WEAR, AND TIRE VALUE. UPON TERMINATION OF RENTAL, WE WOULD AGAIN HAVE THE REPRESENTATIVES MENTIONED ABOVE DETERMINE THE CONDITION, PERCENTAGE OF WEAR, AND TIRE VALUES. ANY DIFFERENCES NOTED, WOULD THEN BE CHARGED OR CREDITED TO IRC INCLUDING BOTH MATERIALS AND LABOR.
UNDERCARRIAGE WEAR ON ALL TRACK TYPE MACHINES WOULD BE BUTLER'S EXPENSE.
GROUND ENGAGING TOOLS:
IRC WOULD BE RESPONSIBLE FOR ALL PARTS RELATING TO GROUND ENGAGING TOOLS (G.E.T.), I.E. CUTTING EDGES, RIPPER TIPS AND PROTECTORS, BUCKET TIPS AND ADAPTERS, EDGES BETWEEN ADAPTERS, WEAR PLATES ON BOTTOM OF BUCKETS AND ALL MOUNTING HARDWARE. BUTLER WOULD INSTALL THESE ITEMS ON AN AS NEEDED BASIS AT THE CURRENT CATERPILLAR LIST PRICE PLUS FREIGHT AT NO ADDITIONAL LABOR COSTS. ALL MACHINES WOULD BE DELIVERED WITH NEW G.E.T. ITEMS AND ARE TO BE RETURNED WITH NEW.
WE WISH TO THANK IRC AND YOU FOR GIVING US THE OPPORTUNITY TO PRESENT OUR PROPOSAL AND FOR ALL THE CONSIDERATION WE RECEIVE.
SINCERELY YOURS,
BUTLER MACHINERY COMPANY
JOEL NIKLE
RENTAL FLEET MANAGER
JN:jw
ENCLOSURE
CC: OSCAR SWENSON, RENTAL FLEET MARKETING MANAGER
a ATTAMIIIENT AINTERNATIONAL URANIUM CORPORATION
EQUIPMENT NEEDED FOR JOB IN BLANDING, UTAH JANUARY 25, 2001
MINIMUM GUARANTEED TOTAL**
MONTHLY HOURS EXCESS NUMBER OF FREIGHT MAINTENANCE RENTAL ALLOWED HOUR MONTHS RATE CHARGES RATE
MODEL QTy RATE PER MONTH CHARGE BASED UPON TO & FROM PER HOUR
"*637E 4 $22,500 176 EA. $70 EA. 6 EA. $11,400 EA. $2.15 EA.
D9R/RIPPER 1 14,000 176 45 6 9,100 1.50
D8RIRIPPER 1 11,400 176 36 6 7,800 1.20
D7R/RIPPER 1 9,600 176 30 6 6,800 1.00
825G 1 10,500 176 32 6 7,700 1.15
980G 1 10,550 176 34 6 7,700 1.20
"*988F 1 16,000 176 51 6 9,100 1.55
"*769D 4 9,750 EA. 176 EA. 30 EA. 6 EA. 7,800 EA. 1.60 EA.
375L 1 20,500 176 59 6 15,800 2.00
10,000 GALLON 1 10,500 176 32 6 8,500 1.90 WATER WAGON
5,000 GALLON 1 6,000 176 19 6 3,200 0.80 WATER WAGON
14H/RIPPER 1 8,200 176 26 6 5,900 1.10
16H/RIPPER 1 11,750 176 36 6 7,200 1.25
* PLUS TIRE WEAR
INCLUDES ASSEMBLY AND DISASSEMBLY
637 SCRAPER EFFICIENCY
NOMINAL CAPACITY
2/25/99 - 10:13 AM - WmrSc298.xlw
International Uranium (USA) Corp. White Mesa Mill
31
HAUL TRAVEL FIXED EFFICIENCY MINUTES TRIPS/ YARDS/
ROUTE TIME TIME PER TRIP HOUR HOUR
1 3.90 1.20 85% 6.0 10.0 310
2 3.25 1.20 85% 5.2 11.5 355
3 4.30 1.20 85% 6.5 9.3 287
4 3.10 1.20 85% 5.1 11.9 368
5 4.15 1.20 85% 6.3 9.5 296
6 4.50 1.20 85% 6.7 8.9 277
7 3.75 1.20 85% 5.8 10.3 319
1 Of 1
CAT 637 SCR-APER
TRAVEL TIMES FOR CAT 637 SCRAPERS
BASED ON PROJECTED HAUL ROUTES
Hiaul Distlince Distance. RollIng Gae Ae See Time
segment Feet MMeter I Riistance MPH
la 200 67 7.5 0.0 9.1 0.25
lb 500 167 5.0 0.0 12.6 0.45
Ic 200 67 3.0 2.5 9.1 0.25
Id 1400 467 3.0 0.0 18.7 0.85
le 250 83 3.0 0.0 9.5 0.30
if 250 83 3.0 0.0 11.4 0.25
Ig 1400 467 3.0 0.0 21.2 0.75
1h 200 67 3.0 (2.5) 11.4 0.20
ii 400 133 5.0 0.0 13.0 0.35
lj 200 67 7.5 0.0 9.1 0.25 3.90
2a 200 67 7.5 0.0 9.1 0.25
2b 2150 717 3.0 (0.5) 22.2 1.10
2c 250 83 5.0 0.0 9.5 0.30
2d 250 83 5.0 0.0 11.4 0.25
2e 2250 750 3.0 +0.5 23.2 1.10
2f 200 67 7.5 0.0 9.1 0.25 3.25
3a 250 83 7.5 0.0 8.1 0.35
3b 3300 1100 3.0 -0.5 23.4 1.60
3c 250 83 5.0 0.0 9.5 0.30
3d 250 83 5.0 0.0 11.4 0.25
3e 3300 1100 3.0 +0.5 25.0 1.50
3f 250 83 7.5 0.0 9.5 0.30 4.30
4a 350 117 7.5 -3.5 11.4 0.35
4b 1450 483 3.0 0.0 19.4 0.85
4c 250 83 5.0 0.0 9.5 0.30
4d 250 83 5.0 0.0 11.4 0.25
4e 1700 567 3.0 0.0 22.7 0.85
4f 500 167 7.5 +3.5 11.4 0.50 3.10
2/25/99 - 10:27 AM - Wmrec298.xlw
International Uranium (USA) Corp. White Mesa MillI OF 2
CAT 637 SCRAPER
Haul, Distance Distance Rolling Grade jAve Speed Time Segment Feet Meters Risistance % : MPH Min
5a 1400 467 7.5 -2.75 15.9 1.00 5b 1350 450 3.0 0.0 19.2 0.80 5c 250 83 5.0 0.0 9.5 0.30 5d 250 83 5.0 0.0 11.4 0.25 5e 2250 750 3.0 0.0 23.2 1.10 5f 700 233 7.5 +5.5 11.4 0.70
_ __ _ 1 4.15
6a 600 200 7.5 0.0 11.4 0.60 6b 900 300 3.0 -3.3 20.5 0.50 6c 1450 483 3.0 0.0 19.4 0.85 6d 400 133 5.0 0.0 11.4 0.40 6e 400 133 5.0 0.0 11.4 0.40 6f 1450 483 3.0 0.0 22.0 0.75 6g 900 300 3.0 +3.3 17.0 0.60 6h 450 150 7.5 0.0 12.8 0.40
4.50
7a 750 250 7.5 -1.5 12.2 0.70 7b 1600 533 3.0 0.0 20.2 0.90 7c 350 117 5.0 0.0 11.4 0.35 7d 350 117 5.0 0.0 11.4 0.35 7e 1600 533 3.0 0.0 22.7 0.80 7f 750 250 7.5 +1.5 13.1 0.65
I I I 1 11 3.75
2/25/9 - 10:27 AM - Wrrec298.xlw2International Uranium (USA) Corp.
White Mesa Mill2 OF 2
769C TRUCK EFFICIENCY
NOMINAL CAPACITY
2/25/9 - 10:10 AM -Wmrec298.xlwIntemrational Uranium (USA) Corp.
White Mesa Mill
25
1 Of I
CAT 769 TRUCKS
TRAVEL TIMES FOR CAT 769C TRUCKS
BASED ON PROJECTED HAUL ROUTES
Haul Distance. Distance Rolling Grade Ave Speed Time
Segment L Feel Meteris jRisistance % V" 4Mm
I a 200 67 7.5 0.0 7.6 0.30
I b 500 167 5.0 0.0 12.6 0.45
I c 200 67 3.0 2.5 9.1 0.25
i d 1400 467 3.0 0.0 18.7 0.85
le 250 83 3.0 0.0 9.5 0.30
1 f 250 83 3.0 0.0 11.4 0.25
I g 1400 467 3.0 0.0 22.7 0.70
1 h 200 67 3.0 (2.5) 11.4 0.20
i i 400 133 5.0 0.0 13.0 0.35
lj 200 67 7.5 0.0 9.1 0.25
3.90
2a 200 67 7.5 0.0 7.6 0.30
2b 2150 717 3.0 (0.5) 24.4 1.00
2c 250 83 5.0 0.0 9.5 0.30
2d 250 83 5.0 0.0 11.4 0.25
2e 2250 750 3.0 +0.5 26.9 0.95
2f 200 67 7.5 0.0 9.1 0.25
1 3.05
3a 250 83 7.5 0.0 8.1 0.35
3b 3300 1100 3.0 -0.5 25.0 1.50
3c 250 83 5.0 0.0 9.5 0.30
3d 250 83 5.0 0.0 11.4 0.25
3e 3300 1100 3.0 +0.5 28.8 1.30
3f 250 83 7.5 0.0 9.5 0.30 4.00
4a 350 117 7.5 -3.5 11.4 0.35
4b 1450 483 3.0 0.0 19.4 0.85
4c 250 83 5.0 0.0 9.5 0.30
4d 250 83 5.0 0.0 11.4 0.25
4e 1700 567 3.0 0.0 22.7 0.85
4f 500 167 7.5 +3.5 11.4 0.50 3.10
2/25M99 - 10:21 AM - VWnwe,2.xlw1
International Uranium (USA) Corp. White Mesa Mil1 of 2
CAT 769 TRUCKS
Haul Distance Distance Rolling Grade Ave Speed Time
Segmento Feet Meters Risistance _ _% MPH Min
5a 1400 467 7.5 -2.75 15.9 1.00
5b 1350 450 3.0 0.0 19.2 0.80
5c 250 83 5.0 0.0 9.5 0.30
5d 250 83 5.0 0.0 11.4 0.25
5e 2250 750 3.0 0.0 23.2 1.10
5f 700 233 7.5 +5.5 11.4 0.70
4.15
6a 600 200 7.5 0.0 11.4 0.60
6b 900 300 3.0 -3.3 20.5 0.50
6c 1450 483 3.0 0.0 19.4 0.85
6d 400 133 5.0 0.0 11.4 0.40
6e 400 133 5.0 0.0 11.4 0.40
6f 1450 483 3.0 0.0 22.0 0.75
6g 900 300 3.0 +3.3 17.0 0.60
6h 450 150 7.5 0.0 12.8 0.40 4.50
7a 750 250 7.5 -1.5 12.2 0.70
7b 1600 533 3.0 0.0 20.2 0.90
7c 350 117 5.0 0.0 11.4 0.35
7d 350 117 5.0 0.0 11.4 0.35
7e 1600 533 3.0 0.0 22.7 0.80
7f 750 250 7.5 +1.5 13.1 0.65 3.75
2/25M9 - 10:21 AM - VWmrec2982.xow
Intemational Uranium (USA) Corp. White Mesa Mill
2 of 2
0 'hib
aN I"
N A
ci'3
V*
6 U)
� Cu � o o U)
'4..
(4
(�3
U, CD
"NZ4
a�I
U
4-, C U) E E 0I
I I
01/23/2001 14:45 435-678-2621 BCLDSRBTN AE 6
1261 SOUTH MAIN * BLANDING, UT 84511 Phone (435) 678-3311 -0- Fax (435) 678-2621
1-800-887-4174
A aR
To: 4A- A&Pr I a ao-
G~ t- W W Wg-S S
cc
ReUiew fJ9iease O~Ccxmt UJPkase Reply 0P1&=eRec~ycle
Notm: I 4C -tr qf-, Pei cas F-0. a. '15'A~~3itot1 CAZý W.&A- L.&A
`1 e-T. mL
1t.%. L
T2~eLLLaE& AULL APPCIAALLE
I
I �o'�-�
B C L DISTRIBUTING PAGE Ell
qw- i&W -. "
Notes: a/4/Je.
C6*C cec
"Gs4
s-zrccc
'9/ 9S /wof
/A 8.'s4 ASO 70 Srxe 04 (S.VAcV Real -vo01~c)
of o
Comments:
4',-
Call to:
Date:
Subject: (641
Constwcflon Equipment Co.
SCREEN-IT 4 X 10
Height 13'6" Width: 10'00 Length: 39'
?
TRANSPORT Fifth Wheel Pull Spring Suspension, air brakes Lights, oil filled hubs
HOPPER 5.5 cu. yard charging hopper Height to load 12'3" Side Loading width 12'0"
ENGINE 4 cylinder Deutz; 46 HP - Air Cooled 65 gallon fuel tank
OPTIONS 4 individual jacking legs Shredder Grizzly dump Stacking Conveyors Ball decks
SCREEN 4 x 10; 2 Deck Screen Hydraulic drive 5/8" Throw Rubber Spring Suspension
CONVEYORS 36" wide feed conveyor 36" wide under screen conveyor 24" side discharge conveyor 24" rear discharge conveyor
A
Diesel Hydraulic-Self Contained Portable and Easy to Set Up
High ProductionScreens Sand and Gravel
Conveyors Can Load Directly Into Truck
I
*Construction Equipment Co. 18650 S.W. Pacific Hwy Tualatin, OR 97062
503-692-9000 Fax 503-692-6220
Area Dealer
POWER MOTIVE 5000 VASQUEZ BLVD.
DENVER, CO 30216 PHONE: (303) 355-5900
FAX: (303) 388-932S
SCREEN Highly Portable
IT - Series - All Hydraulic Setup
IIProduces Three Different Products
SCREENS COMPOST 120-140 YARDS PER HOUR
SCREENS GRAVEL UP TO 600 TONS PER HOUR
SCREENS:
-I
LOG YARD WASTE, COMPOST, BARK, TOP SOIL,
SAND & GRAVEL, TRASH, C & D, STUMPS, CONCRETE,
ROCK AND MANY RECYCLE MATERIALS Patent 45234564
U
Construction Equipment Co. P.O. Box 1271 Lake Grove, Oregon 97035 503-635-4427 Fax 503-635-7819
Ame Dealer
|I
-ýt av,- -7
ALL HYDRAULIC FOLD AND SETUP
i :" "'" • '-. . .. ..... . . . * .. a---... ..¶ -". ..
Travel position of the SCREEN IT in which feed
conveyor and hopper hydraulically slide back
and lower down to transportation height, while
hopper wings told in.
Hydraulic jacking legs are standard for cantelever style blocking, but four (4) individual jacking legs can be an option.
Side and rear discharge conveyors hydraulically told out to the height of 14'.
Feed conveyor moves up and forward hydraulically, while the hopper wing walls extend for operation.
Feed conveyor hydraulically moves back and down for transport
The charging hopper folds out to the width of 14' while in its working position.
A 48' wide variable feed conveyor with 20"
rubber lagged head pulley feeds a 5 x 12 2 Deck screen.
Control panel and hydraulic controls are all located in turnkey area. Powered by a Deutz 4 cylinder, 70 HP diesel engine.
Actuator switch to control speed of feed conveyor is located on the catwalk platform along with kill switch. Actuator switch also located at control panel.
.ne SCREEN IT has an optional 14 foot long The optional grizzly dumps to the rear of the
by 8 foot wide hydraulic dumping grizzly. An plant
operator controlled remote dumping system is
also available.
SSCREENING,
Topsoil To 250 yds./hr. Sand & Gravel To 600 Tons/hr.
41 ) -A 8T-4- _ 37'-o DIA. REF.
HYDRAULIC DRIVE
TRANSPORT13'6* 11'110
43' 0V 38,600
Fifth wheel pull Spring suspension, air brakes Lights, oil filled hubs Transport speed 65 mph
ENGINE 4 cylinder Deutz 70 HP - Air Cooled 65 gallon fuel tank 110 gallon hydraulic tank
OPTIONS 4 individual jacking legs Shredder Grizzly Dump Stacking conveyors 79 HP Turbo Diesel (Water Cooled) 98 HP Turbo Diesel (Air Cooled)
HOPPER 14.5 cu. yard charging hopper Height to load 13' 6" Width at rear 14' - Working position Width at rear 8' - Travel position
SCREEN 5 x 12, 2 Deck with step deck
Hydraulic drive with 3/8l to 5/18 throw Rubber spring suspension
CONVEYORS 48" wide feed conveyor 23' 1 W long 42" wide under screen conveyor
30" side discharge conveyor 18' 4" long
30" rear discharge conveyor 18' 4" long
Height Width:
Length: Weight
7.,W, "/
CD 0 0
0 0 3 3 CD C,)
as
z 0
ý, Kk)
F
pa ,7"
l 4j1it
'I.
A
I
S~505 Md~rry Roatl SE SAlbuquerque, NM 87105-0817
(505) 877-1100 Al Fax: (505) 877-6900
.jOLD TO:
INTERNATIONAL URANIUM CORPORAT INDEPENDENCE PLAZA, SUITE 950 1050 17th STREET, ATTN: AP DENVER, CO 80265
CUSTOMER'S ORDER NO.
BL2843
INVOICE
NOV 2 2 REC'J
INVOICE NUMBER DATE OF INVOICE
26508 ovember 20, 2000
SALESPERSON
GILBERT EAVES JOB SITE
BLANDING, UTAH BLANDING, UT
Job: BB-1345
TERMO)UE UPON RECEIPT
Customer INT01 1
11/21/2000 i12120/2000
11ir
r 65 Ton Crane - Bare Rental 5147 1.00 Months
Total Invoice:
% PER MONTH FINANCE CHARGE WILL BE ADDED TO ALL AMO /HICH IS A ANNUAL % RATE OF 18 %. CUSTOMER AGREES TO P
COLLECTIONS, INCLUDING ATTORNEYS FEES.
To2 •......... Date..2. . Approved-AZ , . Cc•-es 'u - -
$8,000.00
qNTS OVER 30 DAY Y ALL COSTS OF
%AII^ r .- i V.1l-.' - 4I11inn Pinkl - .fgoaftmar (Pnli - Parmanant
$8,000.00
$8,000.00
E UNIT PRICETAL
4.
Boi
Mil
Iro
Ca
Ce
E
Ir
L
LABOR COSTS
Spe
International Uranium (USA) Corp Vhite Mesa Mill
I of 2
01/3112001 -230 PM - WM.RecPlanEst.Jan2001
eay Cnrtn 2000 Estimated Labor Rates- 13.97% 21.28%
Heavy Construction
Labor Burden Company
(FICA, SUI, Benefits (medical.
Labor Classification Base Rate Mandated Fringe FUI, etc. life insure, etc) Fringe Costs Labor Cost/HR
-e akr $96 $8.76 $2.74 no added cost $11.50 $31.10
iler Makers $96
Wrights$20.82 $4.2 $2.91 $0.1 $7.34 $28.16
nworkers $21.17 $7.21 $2.96 no added cost $10.17 $31.34
irpenters $1.51 $2.30 $3.81 $14.62
ement Masons $1.61 $2.45 $4.06 $15.58
$14.52 $2.71 $2.03 $0.38 $5.12 $19.64
lectricians
onworkers - Reinforcing $11.0$1.54
$2.34 $3.88 $14.88
aborers (including pipelayers) $7.65 $1.60 $1.07 $0.03 $2.70 $10.35
$1.76 $2.68 $4.44 $17.04
Pipefitters $26
POWER EQUIPMENT OPERATORS $1.40 $2.13 $3.53 $13.53
Backhoes $00
$1.46 $2.22 $3.68 $14.11
Cranes
Dozers$1.83
$2.79 $4.62 $17.7;
Graders $12.67$4.47
$17.
Loaders$11.26
$1.57 $2.40 $3.97 $15.2
Scrapers $10.00 $1.40 $2.13 $3.53 $13.5
Scrapers
Tractors$9.42
$1.3 $2.0 $3.32 $12.
TRUCK DRIVERS $9.42
$1.32 $2.00 $3.32 $12.
Note: base rates do not Include FICA, worker comp, unemployment, or company benefits which Increase the cost per hour
Updated from General Decision UT980009 - Modification 0 - 2/13/98, Current Update UT000009, 4 pages, 11/1012000
2
4
3
3
53
74
74
LABOR COSTS
Nonsoecified Wages
Survey Crew Member
Sample Crew Member
Mechanic (Demolition)
Manager/Engineer
Radiation Safety Officer
Secretary
Clerk
Engineer
Environmental Technician
Safety Engineer
Maintenance Foreman
Security Personnel
Chemist
Base Rate Mandated Fringe
$9.85
$9.85
$10.25
$36.00
$28.00
$11.50
$9.50
$28.00
$15.00
$15.00
$20.50
$6.00
$16.75
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Labor Burden (FICA, SUI,
FUI, etc.
$1.38
$1.38
$1.43
$5.03
$3.91
$1.61
$1.33
$3.91
$2.10
$2.10
$2.86
$0.84
$2.34
Company Benefits (medical,
life insure, etc)
$2.10
$2.10
$2.18
$7.66
$5.96
$2.45
$2.02
$5.96
$3.19
$3.19
$4.36
$1.28
$3.56
Fringe Costs Labor Cost/HR
$3.47
$3.47
$3.61
$12.69
$9.87
$4.05
$3.35
$9.87
$5.29
$5.29
$7.23
$2.12
$5.90
$13.32
$13.32
$13.86
$48.69
$37.87
$15.55
$12.85
$37.87
$20.29
$20.29
$27.73
$8.12
$22.65
01131/2001 - 2:30 PM - WM.RecPlanEst.Jan2001International Uranium (USA) Corp,
White Mesa Mill2 OF2
U
+J.
rt W.1
,a a cc
c~hocat vi1
l.a
"A
0
N 0 0 C
I 1
0-M TIl
C
�C I
� * V..
U-.
C 0 0 C 10
pJ.
111111110on I@ 0Z 'isfto
r.
WI P I-I
3 n IAS IA.
i '1
0 0 0 0 �0
If S
I '1 Si I�a
I 0
�0 0 0 C w
I.
I.A 3.IO R RL~rk. 6214 ?67 2730 P. WV25
FOR OE
ISMN jUam
KANE PIDTIR SAN JUA S"N AMT
SEVIERCO tlN? ees):
DAOGET?
GRAND
D01L01292 04/01/1996
19.60 8.76
CARP2834D 10/ol/1s98
MILLWRICWS Rates rge MIL MRZ BT~20.A2 4.28
'IRCON0027G 0'7/01/2000Riat es FririusatRONWOriCBRS
Struxctural 21.17 7.23
SIflT20O-a 03/01/l9aa
CARPINTERS CEMM MAS ELRCTrciCANs
Rinforcing LABORERB (inc luding -pipalayers)
PZPEYZTT2R8 POMM ZGUPHENT OPMRTORS; backb~oes Cranes Dozer-s Grad~ers Loaders SCIMP~zS Tzackhoes Tractors TRUCK( DkXVERS
Rates
11.52 14.52
21100
7.65 12.60
10.00D
12.67 11.26 10.00
10.42 9.42
Fringeg
2.71
1.00
------------- 0 -------- --------------newibed for craft performing operation to which weldixW is Juaiclental. ------------------------ a --------------------------------------
Unlisted classifications needed for work not Jnc4uded witbin
Iryl kye; 1w WAGE L HOLR RMION 6
UTOOOO09 - a 11/20/2000
.1 N-;4 2ZM1 07;M14 767 2730B F.S4'SwAGE & HaR REGION 6
the scope of the classification listed nay be added after
award only an provide in the labor standards COtrc clauses
('29 CPR 5. S(a)(1) (V)) .
In the listing aboive, the *5TT' dusiEVi~tiOn meAns that ra~tes
listed under tbat ident~ifir 40 not reflect cloctively
bargained wage an fri~nge benefit rateD. Othe* debifl~atiLO"r
Indicate unions whose TatabS have beanl determinefld ro be
prevailing.
"NAm DMRTWMWTICV APIEALS MýSsa
1-.) Ha.s there bean an initial decisioninteR t) This5 Can~
* an existing published wage deiter-mi~ti~ * a survey underly~i1 a weA0 dotew n~ation
& Wage and Hlour Divisln -letter sertmrhg foxth a
position on a wage determJ~l~inton w~U"~IC
*a confoyffanlew (additional ciasasfioatiofl and rate)
On wurvey related matters, initial contact, ici~luding requesuts
for sumUD8Xiev of gurveys. 5hould ho with the Wiage and iHouX
Regional OfficS for the area in which the surve.y was conuducted
because those Regional offices have reopmoiabilley for the
-BaS~con survey p-gr~ r. the mepfSS this initial
contact is not sat isfactory, then the process described in 3.)
sand 3-) should be followed.
with roqard to any other matter not yet ripe toZr the formnal
process depcribed here. initial contact should Of with ths Branch
of r-wtrcticon wage Dcter¶4nat ~lon. wfrite to:
'Branch of Construction Wage DetermiunationsU wage "n Hlour Division U. S. napaxtment a~ ULbor 200 ConrntitUti.On AVenuO.W.N Washington, D. C. 20210
2.) It the answer to the questi.on in 1.) in yes'j, then an
interested party, (thorse affected by the acrion)ican request
review and, reconidej&ration fron' the Wage and NITor Administrator
(See 29 CMR Part 1.8 and 25 Cya part 7). Wri1te 0Q
wage and Hlour AdminlatratorZ. u.s. Department of Labor 201) Con tit1ZtiOZ kvon1J0, N.;:W. Washington, D. C. 20210
The request sboul,4 be aaccompanied by a full ata'cUUwflt ot the
intexested party#* pomitian and by any informaifttnQ (waimt Paywent
C.
C, p.
) �. *
co~
uToo0009 - 3 11/10/2000
data, project deacri~ptio?1, area practi.ce material. etc.) t~hat the - requestor considers relevant. Z1 the issuem.
3.) If the decision of the Administrator is ziet favorable, am interested party may appeal direc~tly to the Admn1isrrative Review '-lard (fozmerly the Wage Appeals Board) - Write to:
Administrative Review Board: a. a. Department Of XLabor
Washinqgo=, D. C. 20210
4.) All decisions by the Acministrotive Rsvisw MMP OF GMIRMI MJCIBacaI
Oil
UT000009 -
i~oard are final.
3-11/310/2000
TOT3FL P. as
JAN--24-2004 fir(; M WAUE L HOUR MMIUN 6 214 767 Z?30 P.05/W
LONG TERM CARE CALCULATION
Long Term Care Calculation
Base Amount (Starting in Dec. 1978) $250,000 CPI-U December, 1978 67.7 CPI-U December 2000 174.0
Adjusted Long Term Care = $250,000 x (CPI-U most recent / CPI-U Dec., 1978)
Adjusted Long Term Care $642,541
01/31/2001 - 2:30 PM - WM.RecPlanEst.Jan2001International Uranium (USA) Corp.
White Mesa Mill1 of 1
Series Id: CUUROOOOSAOCUUSOOOOSAO
Not Seasonally Adjusted Area: U.S. city average Item: All items Base Period: 1982-84=100
[iulýug ýep FCt [ýov Ann HaM HaM ýýjkr[ian b [1ýiar Fpr ýay I Jun cl Avg F I ýWUP-74[MMOFNUM[M912M 130.4Mp2-7MMMMO-7Fff8 -7 p -2.6
P9-11r-P--6P4875O1ff52"5 "6 MM[ff72P-74P7WmFTT6T1 135.2 [M7-2 "UPT8.-IFT8-.6-V39.-3p9.-5pV.-7l]4O.21140-Spq"RTI-ýý[r4-l-8pT-O-R4l--gFr4uTF-rTg-2-R2FI-4 MMff4Tl-"T-6pT4-URT4-21144.-41"T.Tp4Tff43-.TI 53M. "5. FT44T.FT41-.7-ff T5--T "IýF6.-2[r4-6.-7FT7--ýl[r47-.-4ffT7.-I[rT8.-OP8;.;4p;.;O"9-.-4p9.-5[r4-9--7[T4-9.-7FIT8--.2-FI T7. -2 [ 1 -49-.3 V"P"M"l FMM -51.5 F=
PTIFMM. P3--5Fr52.TF' RWV54-4R-54--9[B-57W6 1[F5-66[!-56-7"7 T 5-7-3 " 7-8 V5 8-3 p -5 -8-6 "8 1 m -9 F B 5-8 V5 7 -9
"Wfr6-l-.6[r6-l.-9[l6-2.-2F6-2.-5[r6T.-81163.OF3.-2[M.4F6T6-"4.-OF6-4.-0[16-3- 6-3-.O-FT62--.3 "9-9V647-3V64-5F5-OF66.-2[ff6--2F6.-2lT6-6-7P7-1"7 V68-2"-83"8 3FF66-6-1 165.4 W7-8 7WF8-8"9 V7l-2V71-3rl-5[F7'2--472-8R72-TV73-7r4-Op4-lF7-4--OFr72 2 PFM(R)F-ý R: REVISED
Bureau ofLabor Statistics Ribson s(a-)b1s.koi
- LS Data: cu http://l46.142.4.24/servlet/Survey ... tjrunsession id=9803 686790683 22715
of 2 0 1/24/2001 1:34 PM
Hollic
Data Home Page
BLS Home Pag
top related