Dulles Connector Sound WallPARDON OUR DUST MEETING July 25, 2013 – 7:00 PM to 9:00 PM

McLean High School1633 Davidson Rd, McLean, VA 22101

Project website:http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp

2

WELCOME!

• John C. Muse District Environmental Manager

• Chan B. Basnayake Area Construction Engineer

http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp

3

Tonight's Objective:• Introduction of the Construction

Team• Present Project Scope of Work• Construction Elements

–Sequence of Construction–Lane Closures –Night Work

• Questions and Answers

http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp

4

Project Team• Virginia Department of Transportation

• Contractor: Lane Construction Corporation

http://www.virginiadot.org/projects/northernvirginia/dulles_connector_sound_walls.asp

5

Tonight's Objective:

• Introduction of the Construction Team

• Present Project Scope of Work• Lane Closures

6

Construction Team & Contact Information

VDOT Construction Management Team:• Chan B. Basnayake, PE, PMP – Area Construction Engineer

– (703) 259-2947 chan.basnayake@vdot.virginia.gov• Giles Njumbe P.E. – Construction Manager

– (703) 259- 3250giles.njumbe@vdot.virginia.gov• Divakar R. Reddy – Office Engineer

– (571) 329-0187 divakar.reddy@vdot.virginia.gov• Abdul Razak – Project Inspector

– (571) 722-2201 abdul.razak@vdot.virginia.gov• John P. Godwin– Sr. Inspector (Structural)

– (571) 898-5227 john.godwin@vdot.virginia.gov

VDOT Field office : 8245 Boone Blvd, Suite 530, Tysons Corner, VATel: (703) 847-1710Hours of Operation:Mon-Fri – (7:00 AM to 3:30 PM)

7

Construction Team & Contact Information continued

VDOT Design Team:• Lee Ann Hall, P.E. – Assistant Section Mgr. L&D

– (703) 259-2746 LeeAnn.Hall@vdot.virginia.gov• Hamid R. Misaghian, P.E.– L & D Consultant Mgr.

– (703) 259-1795 H.Misaghian@vdot.virginia.gov• Brad Stimpson, P.E.– Design Consultant McCormick & Taylor

Contractor: Lane Construction Corp.:• Jan Sherman– Assistant District Manager

– (703) 222-5670 jasherman@laneconstruct.com• Jim A Ballentine– Project Manager

– (571) 358-5390 jaballentine@laneconstruct.com• Will Haynie – Superintendent

– (703) 371-0648 ewhaynie@laneconstruct.com

8

Project Location

9

Project Timeline

• Contract Executed: May 21, 2013

• Notice to Proceed Date: June 5, 2013

• Start of Construction: June 14, 2013

• Substantial Completion: November 21, 2014

• Final Completion: May 29, 2015

10

Project Information

END NB Sound Wall

BEGIN SB Sound Wall

BEGIN NB Sound Wall

END SB Sound Wall

11

Allowable Lane Closure:

•Single lane closures on NB and SB Dulles Connector Road are

allowed from 9:30 PM to 5:00 AM, with the exception of Friday

night and Saturday night when these closures are permitted from

10:00 PM to 6:00 AM.

•Shoulder closures during the day are permitted from 10:00 AM to

3:00 PM (NB), and 10:00 AM to 2:00 PM (SB).

•Total closure of the roadway for a maximum duration of 20

minutes is permitted from 12:00 AM to 5:00 AM.

12

Tonight's Objective:

• Construction Elements–Sequence of Construction–Night Work

Construction : SequenceConstruction Phases:• Phase-1 (Southbound), Chain Bridge Road to I-66.• Phase-2 (Northbound), I-66 to Chain Bridge Road.

• Work on each Phase is divided into three segments. Clearing & Grubbing shall be confined to those areas required for access to and physical placement of the new sound barrier wall, erosion control devices and temporary safety fence. To the extent possible, all other existing vegetation shall remain.

13

Phase 1: Southbound

Aug 15, 2013 to Mar 26, 2014

• Section 1 – Sta. 10+00 to Magarity Road

• Section 2 – Magarity Road to Pimmit Run

• Section 3 – Pimmit Run to Sta. (107+15.16)

14

Phase 1: SouthboundTypical Section-A

15

Phase 1: SouthboundTypical Section-B

16

Phase 1: SouthboundTypical Section-C

17

Phase 1: SouthboundTypical Section-D

18

Phase 1: SouthboundTypical Section-E

19

Phase 1: SouthboundTypical Section-F

20

Phase 1: SouthboundTypical Section-G

21

Phase 2: Northbound

Mar 27, 2014 to Oct 20, 2014

• Section 1 – Sta. 118+65.72 to Pimmit Run

• Section 2 – Pimmit Run to Magarity Road

• Section 3 – Magarity Road to Sta. (11+48.59)

22

Phase 1: NorthboundTypical Section-H

23

Phase 1: NorthboundTypical Section-I

24

Phase 1: NorthboundTypical Section-J

25

Phase 1: NorthboundTypical Section-K

26

Phase 1: NorthboundTypical Section-L

27

Phase 1: NorthboundTypical Section-M

28

29

Night Work

Sensitive work such as• Caissons, Posts & Panel on an as needed

basis.

30

Project Schedule

31

Project Schedule- continued

32

Project Schedule- continued

33

Question & Answer Session