dsm and resource planning jayant sathaye, amol phadke and ranjit bharvirkar energy analysis program...
Post on 28-Mar-2015
214 Views
Preview:
TRANSCRIPT
DSM and Resource Planning
Jayant Sathaye, Amol Phadke and Ranjit BharvirkarEnergy Analysis Program
Lawrence Berkeley National LaboratoryBerkeley, CA
Bob LiebermanRegulatory Assistance Project
Presented at the Forum of Indian Regulators
11 June 2009
Work supported by the US Departments of State and Energy
Lawrence Berkeley National Laboratory
• Managed by the University of California for the US Dept
of Energy
• Founded in 1931, about 4000 staff
• 12 Nobel Prizes – IPCC (2008) – Jayant Sathaye
• Utility programs – — Distribution loss reduction
— Demand-side management programs
— Load research and generation planning
—Transmission reliability
—Renewable energy
Regulatory Assistance Project (RAP)
• RAP is a non-profit organization providing technical and educational assistance to government officials on energy and environmental issues. RAP is funded by US Department of Energy, several foundations, and international agencies. We have worked in 40+ states and 16 nations.
• Bob Lieberman—Illinois utility regulator for the last five years. Term ended June 1st,
2009
—Ran Chicago-based NGO that developed and ran energy efficiency and demand response programs
—Implemented integrated resource planning in Illinois
Contents
I: Overview and Macro impacts
– Dr. Jayant Sathaye
II. Demand Side Power Purchase
-- Dr. Amol Phadke
III: ARR and Tariff Impact and Regulatory Treatment of
DSM
-- Dr. Amol Phadke
IV: Implementing DSM and Regulatory Perspective
-- Ranjit Bharvirkar
-- Bob Lieberman
V. Next Steps
Asia Pacific Partnership (APP)
1. 8 Participating Countries: Australia, Canada, China, India, Japan, Republic of
Korea and the United States
2. Eight task forces including one on power generation, transmission, distribution
and demand management
3. Goal: To develop, deploy and transfer cleaner, more efficient technologies and
to meet national pollution reduction, energy security and climate change
concerns consistent with the principles of the U.N. Framework Convention on
Climate Change (UNFCCC).
Assist partners to build human and institutional capacity to strengthen cooperative
efforts, and to seek opportunities to engage the private sector.
Electricity Demand Savings Potential (Percentage, 2030)
Country Residential Commercial TotalAustralia 12% 10% 11%Canada 12% 19% 15%China 25% 49% 33%India 38% 36% 38%Japan 18% 12% 15%Korea 15% 8% 10%United States 19% 13% 16%Average 22% 20% 21%
Memoranda of Understanding (MOU)
• Maharashtra MOU signed in December 2007—Maharashtra Electricity Regulatory Commission
• Former Chairman Dr. Pramod Deo
—California Energy Commission
• Commissioner Dr. Art Rosenfeld
—California Public Utilities Commission
• Commissioner Dian Grueneich
—Lawrence Berkeley National Laboratory
• Former Director Dr. Steve Chu (Current Energy Secretary)
• Similar MOUs signed with the Delhi Electricity
Regulatory Commission (Shri Berjinder Singh) and the
Forum of Regulators (Dr. Pramod Deo) in March 2009
Maharashtra and Delhi MOU Scope of Cooperation
• The Parties will endeavor to promote information exchanges and future joint research activities in the following areas:
— • Energy efficiency and Demand Side Management policies and programs
— • Regulatory policies for renewable energy development
— • Integrated Resource Planning
— • Electricity regulation and governance
— • Transmission pricing framework
— • Balancing market framework in Maharashtra
— • Market development through open access and consumer choice
Demand-side Management of Efficiency
Project Motivation
Reducing carbon emissions from electricity use –
DSM Programs (NAPCC, 11th Five Year Plan)
Electricity shortage accompanied by blackouts
and load shedding is common across India
In Maharashtra, electricity deficit was 4800 MW in
2008 or more than 25% of available capacity
Maharashtra: Electricity shortage
04/10/23 Dr. Jayant Sathaye12
Shedule (MW)
Net Exch. (MW)
-55 -31 10413 1076 11456 1942 13431 48.72-55 -27 9928 1055 11562 1811 12794 48.7839 67 10032 1061 12044 1708 12801 48.7886 118 9897 1420 12374 1660 12977 48.89
110 144 9634 1822 12415 1635 13091 48.9463 94 9803 1759 12854 1684 13246 48.95-9 16 9480 2564 13513 1761 13805 49.14-9 11 8887 3487 13781 1769 14143 49.269 8 8769 3646 14006 1770 14185 49.09
-9 9 9205 3649 13655 1768 14622 49.14-9 9 9794 3719 12384 1772 15285 49.27-9 8 9745 4036 12783 1799 15580 49.12-9 13 9471 4535 13183 1790 15796 49.19
FREQ. (HZs)
TPCL MSEDCL Catered Demand
(MW)
Load Shed. (MW)
MSEDCL Demand
(MW)
TPCL+REL
Demand (MW)
State Demand (MW)
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
1 3 5 7 9 11 13 15 17 19 21 23
MW
Hour
Maharashtra State April 28th, 2008
Electricity Shortage
Demand Met
S
29% shortage
Maharashtra Project Motivation
Electricity shortage
Affects industrial production quantity and quality,
Lower production and sales lead to reduced sales tax payment
Government loses sales tax revenue
LBNL estimates sales tax loss of 20 cents/kWh
Shortage met partially by extensive use of inefficient diesel and
gasoline micro generators and hence high CO2 emissions
Savings potential
Energy savings potential of about 6,800 GWh/year
CO2 savings potential of 3-5 Mt CO2/year
India Power Supply Capacity and Peak DemandReference Scenario with Shortage
0
50000
100000
150000
200000
250000
2000 2002 2004 2006 2008 2010 2012 2014
Actual (2002-08) and ProjectedPeak Demand (MW)
Actual (2002-08) and ProjectedSupply Capacity (MW)
• Assuming that from 2009 onwards deficit is 10% and12,500 MW of new capacity
is constructed each year for three years• Total investment for the 11th Five Year Plan would be Rs. 250 thousand crores
India Power Supply Capacity and Peak DemandEfficiency Scenario with No Shortage
• Assuming that from 2007 onwards efficiency improvements (4300 MW/year) reduce deficit.
Potential exists to eliminate deficit. • Construction of new power plants is reduced to about 9400 MW/year• Total investment for efficiency and supply power plants is still the same as that in the reference
scenario – Rs. 250 thousand crores
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
200000
2000 2002 2004 2006 2008 2010 2012 2014
MW
Actual (2002-08) andProjected Peak Demand(MW)
Actual (2002-08) andProjected Supply Capacity(MW)
Efficiency Scenario with No Shortage: Efficiency Options
Energy Efficiency Measure
Investment (Rs./kW)
Daily Use (Hours/day)
Peak Demand Savings (MW)
2008
Electricity Savings (TWh)
2008
Variable speed drives in industry 4,700 11 948 3.8
Ag. Pump Rectification 9,400 8 655 1.9
Motor rewinding and downsizing 10,810 10 914 3.3
High efficiency agricultural pump sets
8,460 8 715 2.1
Improved high efficiency refrigerators
14,100 12 320 1.4
CFL and Electronic Ballasts 9,400 4 821 1.2
Total Energy Efficiency Savings (MW)
4,372 13.7
Supply Capacity Additions (MW) 46,624 9,772
Macro-economic Results
• Assuming identical investment in each of the two
scenarios for the 11th Plan – Rs. 250 thousand crores
• Annual average electricity savings of efficiency
scenario
— 41 TWh/year
• Assuming business use of saved electricity is 50% --
20 TWh/yr
—Total increase in business output
• Rs. 180 thousand crores/year
—Potential sales tax Rs. 12 thousand crores per year
• Assuming Rs. 6/kWh sales tax
Demand Side Power Purchase
Demand Side Power Purchase: Basics
Demand side Power Purchase is a bundled set of energy efficiency (EE) programs that are designed to deliver the energy and capacity equivalent of a power purchase on the supply side.– purchase “negawatts” and “negawatt-hours”
that are functionally equivalent to the kilowatts and kilowatt-hours procured
– Can resemble a conventional peaking power purchase by emphasizing efficiency measures (and demand response) that reduce electricity during periods of peak power consumption.
– Can resemble a base-load power purchase emphasizing measures to reduce consumption during all hours of the day.
Will you Approve This Peak Load Power Purchase?
One year contract 500 MW during the four hours of evening peak over the year = 730 GWh
Mysterious Regular
Rs/Unit 1.2 5
Total Cost Rs Cr/ Year
88 Cr. 365 Cr.
What is this Mysterious Power Purchase?
• Saving 400 MW during the evening peak hours at the load end > 500 MW generation at the bus bar
• What does it take to saving 400 MW at the load end —Replacing ~ 88 lakh incandescent with CFLs —45 Watt saving/replacement ; 88 lackh
replacements ~ 400 MW saving
• How much does it cost — If the utility decides to give the CFLs at the price
of incandescent lamps, 100 Rs subsidy needed/bulb
—Total expenditure 88 Cr: less that one third of the expenditure of the supply side !
Comparing Supply and Demand Side Power Purchase
Cost of demand side power purchase per unit =
(Annualized incremental capital cost)/(saving per year )
CFL example = (88 Cr)/(730 GWh) = 1.2 Rs/Unit
One important different: Demand side power purchase appears happens at the consumer end (avoids losses)
Power purchase cost of 5 Rs/Unit translates to more than 8 Rs/Unit when it lands at the consumers doorstep due to lossess
Many Demand Side Power Purchase Options: Delhi Example
CFL T5 LPG WHNG
WHSolar WH
ACRefrigerat
ors
Peak power saving at bus bar (W)
49 29 2,647 2,647 2,647 233 13
Total Energy saving kWh/yr 79 46 529 529 529 565 133
Cost of Demand Side Power Purchase Rs/kWh
1.29 2.25 2.74 1.26 5.00 1.16 0.70
Demand Side Power Purchase: Merit Order Stack
Preliminary Estimate of the Saving Potential (MU) in 3 years (Residential)
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
0 200 400 600 800 1000 1200 1400 1600Cumulative Saving Potential in 3 years MU FY2008 to FY2011
Rs/
kWh
CCE Rs/kWh Avoided PP Rs/kWh
Refrigrtr(N)
AC(N) CFL(N)CFL(R)
NG WH(N)
T5(N)
LPG WH(N)
T5(R)
AC(R)
SolarWH(N+R
Avoided PP Cost
CCE
`
Average Tariff
Utility Benefit
Consumer Benefit
Least Cost Power Rationale: DERC Example
“ The Commission is keen to see that distribution licensees undertake DSM initiatives, not only because DSM initiatives provides an opportunity for conservation of power use but also because these initiatives when integrated with supply,
provides a least cost solution for distribution licensees to meet their power demand”
Advantages of Demand Side Power Purchase
• Cost-effective resource—Cheaper than a conventional power purchase
~ For e.g. Rs 350 Cr Savings/year for a 500 MW evening peak power purchase for the CFL example
• Additional option to reduce power needs—Large economic benefits of reducing load shortages
• Environmental benefits—Reduced local pollution —Reduced carbon emissions—Reduced resource requirements – land, water,
Session III: ARR and Tariff Impact of Demand Side Power purchase
ARR and Impact on Consumer
One line summary
If the demand side power purchase cheaper than the supply side, impacts on the consumer are going to be positive!
Impact on ARR
Goal: meet 1000 MW of demand increase during the four peak hours in the evening
- Supply side power purchase- Sign a bilateral contract of 1000 MW for evening peak
delivery (1460 GWh delivered during the evening peak hours over the years)
- Addition to the ARR: 730 Cr
- Demand side option - Facilitate the replacement of 1.7 Cr incandescent by
providing Rs 100/bulb rebate to the consumer - Addition to ARR: 170 Cr
Impact on Tariff & Bills
• How is the increase in ARR typically is met—Tariff increase — Increase in government subsidy — Improvement in operations — Increase sales to high paying consumers
• If the increase in ARR is lower for demand side power purchase —Tariff increase can be mitigated —Need for government subsidy can be reduced
• If the Rs 730 Cr of power purchase cost on the supply side is used for demand side power purchase, more than three times the units can be purchased and could potentially eliminate shortages !
IV: Implementing Demand Side Power purchase
Barriers to Reducing Electricity Consumption: A Customer’s Perspective
• Lack of information about electricity savings
opportunities
• Lack of ability and/or technical assistance for
analyzing electricity consumption patterns
• Lack of financial resources to invest in electricity
savings options (e.g. technology, etc.)
• Lack of appropriate technological options to
reduce electricity consumption
What is a DSM Program?
Mechanism to influence customer’s CAPABILITY and WILLINGNESS to reduce electricity consumption
How to Influence Customer CAPABILITY to Reduce Electricity Consumption?
• Availability of tools to understand electricity consumption
patterns (e.g. plug-in power meters to measure appliance-
level electricity consumption, software to analyze and
identify electricity savings opportunities, etc.)
• Availability of technology to reduce electricity consumption
(e.g. high efficiency T-5 tube-light to replace inefficient T-
12)
— R&D for developing new technology
How to Influence Customer WILLINGNESS to Reduce Electricity Consumption?
• Awareness
—Marketing, promotion, education, etc.
• Technical assistance
—Audits, analysis, equipment installation, facilitating
financing of projects, etc.
• Financial incentives
—Rebates, loans at low interest rates, shared savings,
electricity pricing schemes, etc.
DSM Program Design - Principles
• Systematic road-map for overcoming barriers
faced by customers in their goal of reducing
electricity consumption (and bills)
—BOTH in short-term and long-term
• Must be cost-effective – i.e. program costs must
be lower than benefits from program
• Ensure customer satisfaction
Types of DSM Programs
• All three reduce energy consumption (kWh) and peak demand
(kW), however, emphasis differs
—Energy Efficiency – emphasis is on reducing overall energy
consumption and also peak demand over several years
—Peak Load Management– emphasis is on reducing peak demand
consistently over a season
—Demand Response – emphasis is on reducing peak demand for
short periods of time for a few days during the year
Energy Efficiency
• Permanent energy (kWh) reduction
—Permanent peak demand (kW) reduction
• Size of impact is predictable
• No reduction or shift in customer value, comfort, or output
• Not dispatchable by distribution company
• Examples – rebates on efficient appliances, energy savings
performance contracting, etc.
Energy Efficiency Programs:Level of Involvement of Distribution Company
Peak Load Management
• Overall energy consumption likely to stay same
—Focus is on changing customer load profile
• Size of impact fixed
• Fixed duration (4 - 6 hours daily) demand (kW) reduction
• Change/transfer in customer value, comfort, or output
• Not dispatchable by distribution company
• Examples – tariffs for agricultural pumps
Demand Response
• Overall energy consumption may vary based on customer load
curtailment strategy
—Focus is on changing customer load profile
• Size of impact may vary from event to event
• Small duration (15 min – 6 hours) demand (kW) reduction
• May involve a reduction in customer value, comfort, or output
• Dispatchable by distribution company
• Examples – “cycling” of air conditioners, critical peak pricing tariffs s
Characteristics of Successful DSM Initiatives
• Deeply committed senior management and program
staff – at both State Electricity Regulatory
Commission and distribution company (or
implementing agency)
• Clearly defined goals and objectives
• Data-driven, systematic, and comprehensive DSM
program planning processes
—“you can’t manage what you don’t measure”
• Stable program funding sources and levels
Best Practices – Planning
• Solicit stakeholder input
—Formal interview process or a collaborative planning process
involving key stakeholders
• Conduct market analyses around information gaps and
key issues in order to understand existing conditions
—Target resources toward the very largest markets, and those
that are least understood
• Establish baseline for tracking program expenditure
and impact
Best Practices – Program Design
• Seek to include programs with related and
complementary goals,
— for example, electricity conservation, water
conservation, and renewables (e.g. rooftop solar)
• Simplify participation in multiple programs
—Offer one “bundle” that may consist of energy
efficiency, measures from several different
organizations but is seamless to the customer
Best Practices – Program Design (cont.)
• Efficiently deliver integrated programs to all end-
users regardless of their size
—Upstream Vs downstream incentives
—Larger customers, should be assigned a single point of
contact that represents all related programs
—Smaller customers should be offered a whole building
strategy that incorporate measures from multiple
programs.
Best Practices – Adapting to Changes
• Keep abreast of new developments in energy efficiency
technology
— Coordinate with BEE and FOR
• Network with peers; stay connected to developments in this field
— E.g. FOR/FOIR meetings, interactions with international
experts
• Foster close relationships with market actors; rely on them for
market intelligence
— E.g. attending conferences to exchange ideas
Best Practices - Staffing
• Clearly define responsibilities and clarify roles to minimize
confusion
— Streamlining/facilitating stakeholder interaction
• Reward high performing staff and contractors
— DSM is a new activity and in the initial phases staff will strong
motivation to explore this field
• Encourage and facilitate development of energy efficiency
expertise of staff
— DSM training workshop at NPTI – June 15-18, 2009
What can be learned from the US experience?
• Useful— Identification of the DSM value proposition and the
understanding that “saved” energy was cheaper and cleaner than energy consumed
—Evolving understanding that customer engagement and behavior are key drivers in achieving and sustaining cost-effective energy efficiency
—Broad experience (successes and failures) related to delivering, measuring and valuing energy efficiency
What can be learned from the US experience? Cont.
• Not so useful—Pattern of utility by utility DSM implementation an
accident of institutional history and politics—30 year focus on technology as the sole DSM driver
• the “no-behavior change” strategy
—Corollary to above:• 30 year refusal to engage with customers
– “revenue enhancement units”
Tales from the front:The Illinois experience with DSM
• For nearly 30 years, Illinois regulators and policymakers refused to implement DSM—Swimming in electricity
• Reserve margins as high as 40%
—Concern about raising rates—Utilities uninterested—Customers uninterested
The Illinois experience, cont.
• By 2005—Volatile energy prices—Concern about emissions—Shrinking reserve margins—No State control over generation (restructured)
Commission concerns
• Concern of raising rates to pay for DSM• Concern of political backlash• Concerns about lack of capacity to manage DSM
initiatives
Relearning
• “Its not as if we are not going to spend the money. The only question is:
What are we going to spend the money on?”
Four issues
• DSM increases rates in the short term—Energy efficiency was less expensive than purchased
energy
• Public Education/key messages—“helping customers”
• Commission staff and utility capacity—Training and capacity building
• Cost recovery
Need for Co-ordination
• Efficient tube light program is applicable in almost every state
• SERCs should explore coordinating programs
Role of Regulators
• Establish clear goals for DSM power purchase based on potential estimates
• Allocate resources from ARR for DSM power purchase
• Provide guidance/regulation to facilitate implementation of DSM power purchase
• Tariff options for promoting demand side power prucahse (can either viewed as pumped storage or peak power purchase)
Establish Clear Goals for Constructing Demand Side Power purchase
• In the initial period, the goal should be to get a few small demand side power purchase/programs started to gain experience
• In the long run, the achievable potential for cost effective power purchase should determine the goals set for utilities —California Loading Order: Buy all cost effective demand
side power purchase before any supply side options are considered
• Load research and technology assessment is critical for potential estimates and target setting—What kind appliances consumers are using and how,
what is the demand side power purchase potential and what is the cost
Allocate Resources for Demand Side Power purchase
• Public benefits charge: small surcharge on tariff to create a fund for DSM Power purchase —Stable funding mechanisms - allows utilities and ESCOs
to expand in the area of DSM Power purchase —5 paise/kWh charge 75 Cr of DSM funds in Delhi
• Recovery through ARR/power procurement accounts —Treat as a an expense (same as the cost of power
purcahse)—Amortize over the life the saving measure
Next Steps For Regulators
• Allocate staff/consultants — Dedicated one or two staff or consultants to begin with at the
SERC
• Work with FOR to develop and issue a standard set of guidelines on to facilitate demand side power purchase
• Allocate resources for demand side power purchase — Firm approval of resources for utilities to create a DSM cell,
hire DSM consultants (if needed), conduct load research, and prepare programs
— Conditional approval for funding for the first year (final approval provided after programs are submitted)
• Develop a roadmap for demand side power purchase via a stakeholder process — Conduct/facilitate a potential study — Goals and strategy by sector — Role played various stakeholders — Co-ordination with other programs
Questions for Discussion
Please check this website for
LBNL India and related publications
http://ies.lbl.gov
Thank you
Jayant Sathaye
Other Slides
Efficiency Programs
• Two types of efficiency programs
• Standards and labels –
—Bureau of Energy Efficiency
• DSM through financial and other incentives --
—Regulatory and utility incentives
• MERC, DERC and FOR
Comparative Growth in the Power Sector
0%
2%
4%
6%
8%
10%
12%
Sixth Plan (1980-84) Seventh Plan (1985-89) Eighth Plan (1992-96) Ninth Plan (1997-2001) Tenth Plan (2002-07)
GDP Power Capacity Per Capita Electricity Consumption
Construction Cost Estimates
Plant TypePlanned Capacity Addition
(11th Plan)Cost
Estimates
MW Rs crore/MW
Coal and natural gas 58644 4.51
Large hydro 16553 4.86
Small hydro 1400 5.50
Wind power 12600 4.50
Nuclear power 3380 6.58
Overall 92577 4.66
Energy Supply with Deficit Reference Scenario -- Annual Capacity and Deficit Year Actual
and Projected Capacity (MW)
10th Plan: Actual Capacity Additions (MW)
11th Plan: Actual and Estimated Capacity Additions (MW)
Actual and Projected Capacity Deficit (%)
Actual and Projected Capacity Deficit (MW)
Investment for Projected Capacity @ $ 992 / kW(Million US $)
(Col. 1) (Col. 2) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7)
2002 105,046 2,831 12.2 12,816
2003 107,877 4,807 11.2 12,082
2004 112,684 5,742 11.7 13,184
2005 118,426 5,861 12.3 14,566
2006 124,287 8,042 13.8 17,152
2007 132,329 10,732 16.6 21,967 10,648
2008 143,061 5,204 11.9 17,024 5,163
2009 148,265 12,506 10 14,827 12,408
2010 160,771 12,506 10 16,077 12,408
2011 173,276 12,506 10 17,328 12,408
2012 185,782 10 18,578
Total 27,283 53,453 53,036
Planned Additional Capacity
44,185 92,577
Supply with Efficiency Scenario - 2: Characteristics of Efficiency measures, and Efficiency Savings and Supply Capacity
Energy Efficiency Measure
Investment (Rs./kW)
Daily Use (Hours/day)
Peak Demand Savings (MW) 2008
Annual Electricity Savings (TWh) 2008
Variable speed drives in industry 4,700 11 948 3.8
Ag. Pump Rectification 9,400 8 655 1.9
Motor rewinding and downsizing 10,810 10 914 3.3
High efficiency agricultural pump sets
8,460 8 715 2.1
Improved high efficiency refrigerators
14,100 12 320 1.4
CFL and Electronic Ballasts 9,400 4 821 1.2
Total Energy Efficiency Savings (MW)
4,372 13.7
Supply Capacity Additions (MW) 9,772
India Multipliers and Direct Coefficients
Direct Employment Employment Multiplier Output Multiplier coefficient Agriculture 17.52 1.39 1.59 Mining 13.97 1.00 5.47 Manufacturing 2.22 5.1 2.21 Electricity 0.59 5.24 2.98 Construction 2.98 5.03 2.05 Trade 4.52 1.71 1.83 Transport 2.16 3.18 2.08 service 4.00 2.10 1.54
top related