Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 1 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
Document Title: Annual Report 2018-19
Document No: PD-REP-002
Department: Procurement
Approval: Procurement Scrutiny Group
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 2 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
Table of Contents
Introduction ......................................................................................................................... 3
1 Summary of Regulated Procurements 2018/19 ........................................................... 3
2 Procurements not complying with NHS Ayrshire & Arran Procurement Strategy ......... 7
3 Community Benefits .................................................................................................... 7
3.1 AA1271 Development of Garden Pathways: Ayrshire Central hospital .................................. 8
3.2 AA1330 Principle Contractor for boiler house reconfiguration at University Hospital Ayr ...... 8
3.3 AA 1336 Upgrade of building, energy management systems, University Hospital
Crosshouse ..................................................................................................................................... 8
3.4 AA1307 Purchase of wood pellet fuel for biomass boilers...................................................... 8
4 Supported Businesses ................................................................................................ 8
5 Proposed Regulated Procurements 2019/20 and 2020/21 .......................................... 8
6 Reference Documents / Appendices ......................................................................... 11
7 Glossary of Terms ..................................................................................................... 13
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 3 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
Introduction
In compliance with the Procurement Reform (Scotland) Act 2014 (The Act) NHS Ayrshire & Arran (NHSA&A) publishes a list of regulated procurements planned for the next two years and this report details the award of business made from this list of procurements with detail of compliance with key duties stipulated within The Act.
A regulated procurement is any procurement for goods or services with an estimated value for the life of the contract of £50,000 or more and any such procurement for works with an estimated value for the life of the contract of £2,000,000 or more.
The professional management of procurement activity is an important factor contributing towards the efficient operation of NHS Ayrshire & Arran (NHSA&A) and the attainment of corporate objectives as identified within the Corporate Plan 13-16. It is vital to staff and patients that quality projects, supplies and services are delivered on time to NHSA&A within optimum commercial arrangements.
NHSA&A has a total non-pay spend of £102M of which approximately £58 M p.a. is expenditure with 3rd Party providers and as such can be influenced by procurement activity.
The Procurement Strategy positions procurement activity visibly within the organisation establishing Board level commitment to and involvement in the management of the Health Board’s procurement deliverables. It additionally sets out clear, measurable objectives and priorities for improvement which is closely monitored. Progress against strategic objectives is reported annually to NHSA&A, CMT by the Director of Finance who chairs monthly meetings of the Procurement Scrutiny Group. The strategy addresses key procurement issues over a 3 year time frame and is subject to annual review.
The strategy is pursued through the line management accountability structures with clear targets and timescales being established in relation to improvement in procurement activity undertaken at strategic and operational levels. These targets are reflected within the individual performance plans of appropriate Senior Managers.
Procurement Managers and Senior Managers with Designated Purchasing Authority (DPOs) have responsibility for procurement services and cover NHS A&A Corporate, Acute and Partnerships Divisions. Therefore the compliance and outcomes set-out in the Strategy document apply to all parts of the organisation and all procurement activity undertaken by NHSA&A.
The report owner is
Andrew Elliot NHS Ayrshire and Arran Head of Procurement, Ayrshire Central Hospital, Irvine KA12 8SS Tel 01294 323585 Mob 07795 044566
1 Summary of Regulated Procurements 2018/19
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 4 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
The following is a list of regulated procurements completed during the period April 2018 to March 2019.
Tender No.
Description
Complied with
Procurement Strategy
Community Benefit
AA1373 Provision of an Integrated Design Team In Relation To Alterations and Refurbishment of Ward
Yes No
AA1372 Integrated design team, integration of community health teams within one base at Three Towns Resource Centre Stevenston
Yes No
AA1371 West Kilbride Medical Practice Yes No
AA1370 Kilmaurs Medical Practice Yes No
AA1369 Replacement of reverse osmosis pipe work Central Decontamination Unit, ACH
Yes No
AA1368 Replacement of Ailsa generator Yes No
AA1367 Manikins for Resuscitation simulation training Yes No
AA1366 Provision of medical services in HMP Kilmarnock Yes No
AA1363 Pneumatic Tube System - UHA & UHC Yes No
AA1362 Uninterrupted power supply Yes No
AA1365 Leica Embedder Yes No
AA1364 Asbestos removal, Ward 4B, UHC, Crosshouse Yes No
AA1361 Cardiology information system Yes No
AA1360 Consultancy from The Consultation Institute Yes No
AA1359 CO2 incubator for microbiological investigations Yes No
AA1358 SHREWD Yes No
AA1357 MR compatible physiological monitor Yes No
AA1356 High Performance Liquid Chromatography - repair/upgrade Yes No
AA1355 Appointment of Investment Advisor Endowment Funds Yes No
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 5 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
AA1354 Brain Injury support Yes No
AA1353 Extension of contract - BBV / MSM Services Yes No
AA1352 Authorising Engineer Service - Lifts - passenger Service and Goods
Yes No
AA1351 Demolition of Kirklandside Hospital Yes No
AA1350 Principal Contractor for the replacement of steam boilers at Ayrshire Central Hospital.
Yes No
AA1349 Alternations to Haematology UHC Yes No
AA1348 Cooling Equipment Yes No
AA1347 Replacement of Existing Uninterruptible Power Supply (UPS) at Theatres, University Hospital Crosshouse
Yes No
AA1346 Proposed Alterations To Form Police Accommodation At Brooksby Medical & Resource Centre, Largs
Yes No
AA1345 Asbestos Demolition Surveys for Kirklandside Hospital Yes No
AA1344 Alteration and Upgrade of Ward 4B, University Hospital Crosshouse
Yes No
AA1343 Alteration and Upgrade of Ward1D/Clinic K, University Hospital Crosshouse
Yes No
AA1342 Sale of Standalane, Stewarton Yes No
AA1341 Hair Removal Service Yes No
AA1340 Asbestos demolition surveys - Kirklandside Yes No
AA1339 Purchase of 10 Care Home beds - 26 weeks Yes No
AA1338 Mechanical Contractor for replacement of internal water storage tanks at UHA and UHC
Yes No
AA1337 Electrical Contractor for UPS installation at UHA Yes No
AA1336 Upgrade of building, energy management systems, UHC Yes Yes
AA1335 Cardiac output monitor Yes No
AA1334 Proposed Alterations and Refurbishment of the A&E Facility at Arran War Memorial Hospital
Yes No
AA1333 Alterations and Refurbishment of Stevenson and Saltcoats Health Centres
Yes No
AA1331 Demolition of bed store ACH Yes No
AA1330 Principle Contractor for boiler house reconfiguration at University Hospital Ayr
Yes Yes
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 6 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
AA1329 Winter gritting and snow clearance - community sites Yes No
AA1328 Improvement works to entrance/drop off area at UHA Yes No
AA1327 Purchase of AK98 Dialysis Machine and 2 water treatment units
Yes No
AA1326 Paging System upgrade Yes No
AA1325 Provision of Estates Pre Planned Maintenance (PPM) Software
Yes No
AA1324 Integrated Design Team, alternations refurbishment - A&E/XRay - Arran
Yes No
AA1323 Integrated Design Team - alterations and refurb ward 4B, UHC
Yes No
AA1322 Principal Demolition Contractor for the Demolition of the Water Filtration Plant, UHC
Yes No
AA1321 Provision of CCTV System for UHC Yes No
AA1320 Magseed Yes No
AA1319 Consulting Engineers - Estates Emergency Manuals Yes No
AA1318 M&E Design Team for replacement of internal water storage tanks UHC/UHA
Yes No
AA1317 Provision of Feminine Hygiene Services Yes No
AA1316 Consulting Engineers - Estates Emergency Manuals Yes No
AA1315 Consultation Institute Yes No
AA1314 Provision of Integrated M&E led design team for the construction for installation of steam boilers and associated boiler house.
Yes Yes
AA1313 Fire Risk Assessments Yes No
AA1312 Integrated Design Team for the alterations & Refurbishment of Ward 1D UHC
Yes No
AA1310 Civil engineering works for demolition of bed store, ACH Yes No
AA1309 Renewal of service contract: Automatic Doors Yes No
AA1308 Reverse Osmosis Plant Maintenance, ward 2F UHC / Renal Unit UHA
Yes No
AA1307 Purchase of wood pellet fuel for biomass boilers Yes Yes
AA1306 Maintenance and repair of Standby Generators - renewal of 3 year contract
Yes No
AA1305 Provision of Primary Medical Services at Three towns medical practice
Yes No
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 7 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
AA1304 Healthcare and Forensic Medical Services for People in Custody
Yes No
AA1303 Asbestos Licensed Removal Works, Brunston House Yes No
AA1302 Water Treatment Services Yes No
AA1301 Ascribe A&E System Yes No
AA1300 Uninterrupted Power Supply / Insulated Power Supply Yes No
AA1299 Pilot CM2000 Call scheduling system Yes No
AA1298 Emergency lighting to common areas at UHC Yes No
AA1297 Endoscopy RO Plant Maintenance UHC / UHA Yes No
AA1296 Risk & Safety Management Web System Yes No
AA1295 Renewal of service contract - pneumatic tube system, UHA Yes No
AA1294 Proposed Police Accommodation at Brooksby MRC Yes No
AA1292 Diamante Database Yes No
AA1291 Analysis & reconciliation services: water Yes No
AA1290 Signpost Training for practice and out of hours reception staff in General Practice
Yes No
AA1289 Proposed alterations and extension of oral maxillofacial treatment room and telephonist's room UHC
Yes No
AA1288 Supply, installation and commissioning of a biomass CHP plant at UHC
Yes
Detail of regulated procurements called off from collaborative national contracts (frameworks) is contained in Appendix 1.
2 Procurements not complying with NHS Ayrshire & Arran Procurement Strategy
The procurements are overseen by Procurement managers or DPOs and there is scrutiny of each proposed procurement before it is approved for going to competition.
All of the regulated procurements awarded over the period April 2018 to March 2019 complied with the NHS A&A procurement strategy requirements.
The strategy has since been reviewed and amended in April 2019 and will be published on the NHS A&A public web site.
3 Community Benefits
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 8 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
The summary table indicated procurements that were awarded with contractual requirements imposed on the successful bidder to provide community benefits as part of the delivery of the requirement.
In addition to this some key procurements awarded 2017/18 were fully implemented in 2018/19 and information on these is included in this section.
3.1 AA1271 Development of Garden Pathways: Ayrshire Central hospital
This project enhances the access to the boards green spaces and opportunities to increase exercise for patients, staff and visitors. Local community groups are involved with the maintenance and use of the greenspace developed.
3.2 AA1330 Principle Contractor for boiler house reconfiguration at University Hospital Ayr
To increase the boards renewable energy consumption and progress the transition away from using fossil fuels.
The plant was installed during the summer of 2018, and has been operating to great effect. The efficiency of the design has ensured that the maximum heat produced by the plant has been seamlessly integrated into the hospitals large heating system, and not conflicting against the fossil fuel based boilers already in situ. The gas heating is now acting as a resilience backup to the new biomass boiler plant cost.
3.3 AA 1336 Upgrade of building, energy management systems, University Hospital Crosshouse
The project will provide a tender document to upgrade the existing hospital plant controls using a ground up approach. This will make savings in energy and utility costs, by reducing energy use through increased control over existing plant equipment, increase the board’s renewable energy consumption and progress the transition away from using fossil fuels, and more efficient energy consumption.
3.4 AA1307 Purchase of wood pellet fuel for biomass boilers
New supplier established for biomass fuel pellets at UHC, UHA and Arran War Memorial Hospital. To increase the boards renewable energy consumption and progress the transition away from using fossil fuels
4 Supported Businesses
NHS Ayrshire and Arran are committed to facilitating the involvement of supported businesses in competition and the award of business through our procurement processes.
During 2018/19 work has been undertaken to provide business for the furniture workshop at Ailsa hospital.
The Head of Procurement visited Scotland’s Bravest Manufacturing Co at Erskine Hospital; the board are working with this supported business on opportunities to purchase print services and to explore the remanufacture of patient walking aids.
5 Proposed Regulated Procurements 2019/20 and 2020/21
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 9 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
The following is a list of regulated procurements likely to be undertaken during the next two financial years. Definitive start dates and go live dates are dependent on allocated capital and final approval to proceed.
This will be published on the NHS Ayrshire and Arran public Website.
http://www.nhsaaa.net/services-a-to-z/procurement/
Title Annual Budget or Budget Allocation
Start Date
Go Live date
Fire compartmentation surveys including remedials £ 100,000 tbc tbc
Stainless steel pipe work replacement programme £ 200,000 tbc tbc
Replace air conditioning main server room £ 40,000 tbc tbc
Upgrade nurse call system £ 75,000 tbc tbc
Biomass boiler flue alterations £ 60,000 tbc tbc
Domestic hot and cold pipe work £ 100,000 tbc tbc
Fire detection systems £ 25,000 tbc tbc
Main theatres upgrade (partial) £ 60,000 tbc tbc
Main theatres upgrade (partial) £ 60,000 tbc tbc
Urquhart ward fire compartmentation £ 175,000 tbc tbc
Air handling unit hydro pool £ 50,000 tbc tbc
Filtration plant hydro pool £ 25,000 tbc tbc
Replace hot water calorifiers with plate heat exchangers £ 100,000 tbc tbc
Upgrade electrical switch infrastructure £ 60,000 tbc tbc
Accessible walkways within roof spaces £ 30,000 tbc tbc
National forensic adolescent service for Scotland £ 5,500,000 tbc tbc
Water infrastructure phase 4 £ 400,000 tbc tbc
Demolitions including associated works tbc tbc tbc
ENT operating microscopes, main theatre £ 210,000 tbc tbc
Gynaecology laparoscopic stack system-in theatre 10 £ 90,000 tbc tbc
Demolitions including associated works £ 200,000 tbc tbc
Cardiology refurbishment ward 1D/clinic K £1,950,000 tbc tbc
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 10 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
Discharge lounge £ 200,000 tbc tbc
Chemotherapy including aseptic £ 665,000 tbc tbc
CDU equipment upgrade £ 200,000 tbc tbc
Sexual assault forensic centre £ 301,000 tbc tbc
RESUSCITAIRE for laboratories, wards and maternity theatre
£ 84,000 tbc tbc
Upper GI endoscopes for endoscopy unit £ 67,000 tbc tbc
Operating table and transfer trolley for theatres tbc tbc tbc
Tissue identifcation system for pathology department, laboratories
tbc tbc tbc
YAG / SLT laser system for Eye OPD tbc tbc tbc
Surgical tourniquets for theatres tbc tbc tbc
Cell Saver for Theatres tbc tbc tbc
Insufflator for general surgery tbc tbc tbc
Embedding system to embed patient samples in parafin wax, laboratories
tbc tbc tbc
Transcutaneous monitoring system for paediatric ward tbc tbc tbc
Photodynamic treatment system for dermatology department tbc tbc tbc
Centrifuge system for laboratories tbc tbc tbc
Pelvic floor rehabilitation system for women's health physiotherapy
tbc tbc tbc
Endoscopy stacking system for endoscopy suite £ 60,000 tbc tbc
Ultrasound scanner £ 60,000 tbc tbc
Colonoscope for endoscopy suite £ 48,000 tbc tbc
Endoscope for endoscopy suite £ 43,200 tbc tbc
Endoscope for endoscopy suite £ 43,000 tbc tbc
Gastroscope for endoscopy suite £ 43,000 tbc tbc
Narrow band imaging and slim intubation scope for endoscopy suite
£ 43,000 tbc tbc
Coverslipper and transfer sytem for pathology, histology laboratories
£ 40,000 tbc tbc
Video laryngoscope for emergency department £ 30,000 tbc tbc
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 11 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
Wide channel scope for endoscopy suite £ 38,400 tbc tbc
Duodenoscope for endoscopy suite £ 32,000 tbc tbc
Ultrasound scanners £ 1,180,000 tbc tbc
Static x-ray fluoroscopy £ 500,000 tbc tbc
Gamma camera £ 475,000 tbc tbc
Static x-ray system for room 6 £ 200,000 tbc tbc
Siemens mammo room £ 200,000 tbc tbc
C-Arm X-ray system £ 160,000 tbc tbc
Static x-ray system £ 75,000 tbc tbc
Infusion devices £ 1,100,000 tbc tbc
Telemetry systems CCU £ 300,000 tbc tbc
Anaesthetic machines £ 300,000 tbc tbc
Diathermy £ 100,000 tbc tbc
Endoscopes £ 500,000 tbc tbc
Slit lamps £ 100,000 tbc tbc
In addition to this, information on planned participation in collaborative National contracts (Frameworks) is attached in Appendix 2.
6 Reference Documents / Appendices
Procurement Reform (Scotland) Act 2014 Procurement Strategy Procurement Operating Procedures
Appendix 1 – Regulated Procurements April 2018 to March 2019 Called off from Frameworks.
Appendix 1.xlsx
Appendix 2 – Planned regulated Procurements April 2019 to March 2021Local Tenders and National Frameworks
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 12 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
Appendix 2.xlsx
Annual Report
Document No: PD-REP-002 Revision:1.01 Date Issued: 04/06/19
Page 13 of 13
Uncontrolled if printed: Status of document should be checked, prior to use. Valid only for date printed. Last printed 18-Jun-19
7 Glossary of Terms
CMT Corporate Management Team
UHA University Hospital Ayr
UHC University Hospital Crosshouse
AMU Ayrshire Maternity Unit
ACH Ayrshire Central Hospital
Framework Agreement In the context of this document a contract establishing a supplier or suppliers with agreed terms and conditions for the supply of goods services or works established for one or more health board who will call off as required.
Ranked Framework A ranked framework establishes several suppliers on agreed terms and conditions with rates however the 1st ranked supplier will be the supplier who gets the work if they are able to carry it out. If they cannot then it will be offered to the 2nd ranked, then 3rd etc.
Term Contract An arrangement put in place for a fixed period of time. These are sometimes referred to as 'period contracts'.
CHP Plant Combined heat and power plant
M&E Mechanical and Electrical
COSHH Control of Substances Hazardous to Health
BEMS Building Energy Management System
NSS NHS NSS is the common name for the common Services Agency for the Scottish Health Service Including providing a procurement and program management service for NHSScotland. Offering expertise and guidance
HDU High Dependency Unit
ICU Intensive Care Unit
DSU Day Surgery Unit
SLT Speech and Language Therapy
top related