DEPARTMENT OF PLANNING AND INFRASTRUCTURE

OBLIGATIONS OF A BUILDING CONTRACTORUNDER THE

NORTHERN TERRITORYBUILDING ACT

MARCH 2009

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

PURPOSE

To provide registered Building Contractors with information about their obligations under the

Building Act.

This is not a substitute for a building contractor informing themself of the specific obligations through

reading the Act and developing appropriate procedures.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

CONTENTS• Background• Before Commencing Works

• Prescribed works• Registration requirements• Documentation (Contracts, Insurance & Building Permit)

• Construction of Works• Supervision• Inspections• Geographic application

• Completion of Works• Completion of works• Permit to occupy

• Regulators• Building Practitioners Board• Director building control

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BACKGROUND

• Governments response to community concerns

• The requirements commenced on 3 July 2006

• Measures protect consumers and builders

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORKS

1. Prescribed works

2. Registration requirements

3. Documentation• Contract requirements• Insurance• Building permit

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORKS – Prescribed works

Only a Registered Building Contractor can do prescribed building works

• New houses and new units in residential buildings to any

height;

• Verandahs, garages and carports built as part of a new

single dwelling and residential units;

• Extensions such as living areas and bedrooms and to

existing single houses and residential units over

$12,000;

• Retaining walls associated with the actual structure of a

single house or residential unit.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORKS – Prescribed works

NEW DWELLING ADDITIONSFENCE

SHED

NEWDWELLING

NEWCARPORT

NEW

VERANDAH

FENCE

SHED

EXISTINGDWELLING

NewGARAGE

VERANDAH

STUD BED Y

Ensuite

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORKS - Registration

Only registered building contractors can do prescribed building works.

Building Contractor Residential (Restricted) • Single dwellings, townhouses, duplexes and residential

units NOT more than two storeys.

Building Contractor Residential (Unrestricted)

• Single dwellings, townhouses, duplexes and residential units with no height restriction.

Your registration certificate shows your category

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORKS - Registration

• A person or a company can be a registered building contractor residential.

• The registered person must supervise all works and sign the relevant paperwork.

• Advertisements must include the registered person’s name.

• Registration certificates displayed in a conspicuous place in the principal place of business.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORK - Contracts

A written contract is required to build prescribed building works:

• A house;

• Verandahs, garages and carports built as part of new house;

• Extensions such as livings areas, bedrooms and garages to an existing house; or

• Retaining walls associated with the actual structure of a house;

AND

• Where the cost is above $12,000.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORK - Contracts

There must be a written contract which:• Is limited to a single building project• Identifies the building contractor & number• Specifies the works and value• Identifies work stages & progress payments• Identifies the amount of each progress payment• Stipulates a dispute resolution process• Limits any deposit to 5% of contracted price

Evidence must be provided in the Approved Form

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORK - Contracts

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORK - Insurance

• The current policy is HBCF provided by TIO

• An offence to undertake prescribed building work without HBCF policy for the project

• The TIO certificate to be presented to the building certifier

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORK - Insurance

Home Warranty Insurance (HWI)

• Anticipated in 2010

• Subject to competitive products being available

• Covers non-completion and non-compliance for a period of 6 years

• Consultation to follow

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORK – Building Permit

• Required for building works in all declared Building Control Areas.

• An offence to build:• Without a valid building permit; or • Not in accordance with the building permit.

• Certifier cannot issue a building permit unless there is evidence of:• A contract in the approved form;• An approved policy of insurance; and• Your registration.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BEFORE COMMENCING WORKS - Summary

Before you commence work ensure you:

• Are registered to perform the works;

• Have entered into a written contract with the owner of the property where the work will be undertaken if constructing a detached house;

• Have obtained the required insurance for the works (HBCF) at this stage; and

• Have a valid Building Permit.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

CONSTRUCTION OF WORKS

1. Supervision

2. Inspections

3. Geographic application of the Building Act

provisions

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

CONSTRUCTION OF WORKS - Supervision

• Only a registered building contractor or someone

who is being supervised by a registered building

contractor can undertake prescribed works.

• Supervised = personal oversight having regard to

the persons skills and experience.

• All works must be completed according to the

building permit and as contracted.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

• Mandatory inspection stages for prescribed residential works

• There are 6 mandatory inspections stages

• Inspection stages are required to be specified in the building permit

CONSTRUCTION OF WORKS - Inspections

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

CONSTRUCTION OF WORKS - Inspections

For prescribed works the following are mandatory:

1.Pre pour stage Before pouring of footings, floor slabs or other in situ concrete building element

2.Frame stage Before covering the frame work for floors walls, roof or other building element

3.Block wall stage Before pouring any reinforced masonry or block walls

4.Fire separation Before covering walls, floors or ceilings, for the purpose of checking fire resistance levels

5.Wet area stage Before covering waterproofing in wet areas

6.Final stage After completion of the building work but prior to the issue of an occupancy permit

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

CONSTRUCTION OF WORKS - Inspections

The Building Contractor must:

• Notify the Building Certifier when each stage of the building work is completed and ready for inspection.

• Not continue with further work until the Building Certifier has approved the works to continue.

• Rectify any matters found to be non-compliant.

• Upon completion contact the Building Certifier and request a final inspection.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

CONSTRUCTION OF WORKS - Inspections

The Building Contractor should:

• Develop a process with the Building Certifier to arrange for inspections.

• Keep a record of the requests for inspections.

• Obtain a copy of the inspection certificate from the Building Certifier.

• Keep a copy for your records.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

GEOGRAPHIC APPLICATION OF THE BUILDING ACT

From 3 July 2006 the application of provisions of the Building Act has changed.

Government approved a two-tier system of certification.

Recognises the difficulties related to delivering full certification in areas distant from Darwin and Alice Springs where building certifiers are based.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

GEOGRAPHIC APPLICATION OF THE BUILDING ACT

TIER 1

Applies to:• Darwin (Greater Area) • Lake Bennett• Alice Springs (Greater Area)

Requires:• Full certification• Mandatory staged inspections• Permit to Occupy

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

GEOGRAPHIC APPLICATION OF THE BUILDING ACT

TIER 2• Applies to all other declared building areas.

• No requirement for mandatory inspections & occupancy permits for houses.

• Requires a builders declaration.

• Property owner can choose to pay for mandatory inspections and a permit to occupy under a contractual arrangement.

• Full certification, mandatory inspections and a permit to occupy are required for attached dwellings, flats and units.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

CONSTRUCTION OF WORKS - Summary

During construction of works you should:

• Build in accordance with the building permit

• Ensure adequate supervision

• Ensure the inspection process is followed

where required

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLETION OF WORKS

Builders Declaration• Required in all areas (Tier 1 and 2)

Permit to Occupy• Required in all Tier 1 areas

• Not required for houses in Tier 2 areas unless contracted

• Required for all other works in Tier 2

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLETION OF WORKS - Builders Declaration

Builders Declaration is:

• A statement that all works were completed in accordance with the building permit;

• Required to be issued within 14 days;

• In the approved form;

• Form must be fully completed and signed by the Building Contractor, or if a Company by the Director/Nominee.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLETION OF WORKS - Builders Declaration

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLETION OF WORKS - Builders Declaration

It is an offence to:

• Not provide the Declaration to the Building Certifier within 14 days

• Withhold the issue of the declaration on the basis of non-payment

• Make a false Declaration

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLETION OF WORKS - Permit to Occupy

• The Permit to Occupy is the final part in the building process and is issued by a Building Certifier.

• A Building Certifier requires:• Application to issue a Permit to Occupy;• The Builders Declaration; and• Any other documents / certificates nominated.

• If acting as the Owners-Agent, it is the Building Contractors responsibility to provide these documents.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLETION OF WORKS - Summary

At the completion of works you should:

• Sign the builders declaration

• Provide the Certifier with:

• Builders declaration within 14 days

• Any other documentation as required

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

WORK COMPETENTLY & PROFESSIONALY

At all times act within the level of competency required and in a professional manner.

Competent:

• Having the necessary skills and knowledge to do something successfully

Professional Manner:

• What is reasonably expected.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

THINGS TO CONSIDER

• What processes / procedures do you have that

demonstrate compliance with your obligations?

• Do you use the approved / prescribed forms?

• Do your contracts meet the requirements of the Act?

• Your process for inspections where required?

• How do you supervise the construction of works?

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

END OF SESSION

20 MIN BREAK

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

REGULATORS

Building Practitioners Board

Director Building Control

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

BUILDING PRACTITIONERS BOARD• Statutory body made up of industry & legal

representatives

• Function is to:

• Register practitioners

• Establish policies/codes/requirements & standards for industry

• Monitor compliance

• Discipline practitioners

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

YOUR OBLIGATIONS TO THE BOARD

• Keep your registration current

• Renew your registration on time

• Work within your registration category

• Notify Board of change in contact, address details or

circumstances

• Keep records of what works you have performed

• Keep records of any training / seminars / courses that you

may have attended

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

DIRECTOR OF BUILDING CONTROL

• Investigates complaints against practitioners

• Audits work and/or conduct

• Takes disciplinary proceedings to the Board

• Prosecutes breaches of the Building Act & Regulations.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLAINTS

Grounds for complaint against a practitioner:

• Has committed an offence against the Building Act or the Building Regulations; and/or

• Has carried out work in a negligent or incompetent manner; and/or

• Is otherwise guilty of professional misconduct.

Must be in writing and contain sufficient particulars.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLAINTS

If complaint is investigated:

• You will be provided with a copy of complaint; and

• Requested to provide a written response.

Based on the response the complaint is either:

• Dismissed; or

• Proceed to formal investigation.

If you don’t respond the matter will proceed to a formal investigation.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLAINTS

During a formal investigation you are obliged to:

• Answer questions;

• Provide information; and/or

• Produce documents.

There are penalties for failing to comply and for providing false or misleading information:

• Disciplinary action by the Board; and/or

• Prosecution before the Courts.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

COMPLAINTS

At completion of the investigation the Director is obliged to determine what further action if any is to be taken:

• Dismiss the complaint; or• Refer the matter for inquiry by the Building

Practitioners Board; and/or• Refer the matter to the Courts.

Whatever the outcome the Director will notify you and the complainant in writing.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

AUDITS• An audit is a process of information gathering to:

• Ascertain compliance;

• Appraise and improve operational methods and performance; and

• Develop and implement educational programmes.

• An audit can be about work, conduct or both.

• May be conducted as a result of:

• A complaint;

• Industry wide program; or

• As directed by Practitioners Board.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

AUDITS

You are obliged to comply with all reasonable requests of an Auditor including:

• Answer questions;

• Produce information; and

• Provide documents.

There are penalties for failing to comply and for providing false or misleading information:

• Disciplinary action by the Board; and/or

• Prosecution before the Courts.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

AUDITSOn completion of an Audit you will be notified in writing what action the Director proposes to take:

• No action;

• Remedial plan;

• Prosecution for breaches of the Act;

• Referral to the Board for disciplinary proceedings.

Following the completion of the industry wide audit:

• Results will be evaluated;

• Areas for further education and awareness identified.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

UPCOMING AUDIT

• Audits commence late March;

• Random selection of practitioners;

• If selected you will be notified in writing at least 21 days prior;

• Will comprise of:

– assessment of administrative processes;

– examination of documentation associated with building works; and

– use of prescribed forms.

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

SUMMARY

You have obligations to:

• Clients

• Building Act

• Building Practitioners Board

• Director of Building Control

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

QUESTIONS

DEPARTMENT OF PLANNING AND INFRASTRUCTURE

For further information contact Building Advisory Services, Department of Planning and Infrastructure Monday to Friday 8.00am - 4.00pm.

Telephone: 08-899 98985Fax: 08-899 98967

Ground Floor, Cavenagh House38 Cavenagh St DARWIN CITY

http://www.dpi.nt.gov.au/lands/building

CONTACT INFORMATION

top related