demonstrating co2 storage in the otway basinin the otway basin mtg 4/sandeep.pdf · in the otway...

Post on 25-Jun-2020

12 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Demonstrating CO2 Storagein the Otway Basinin the Otway Basin

Communication and Public Perception

Melbourne April 17 2009Melbourne, April 17, 2009

Sandeep Sharma

Sandeep Sharma

Otway Project Teamwork Acknowledgements

• CO2CRC Colleagues

– P.Cook, B.Hooper, G.Morvell, J.Kaldi, D.Hilditch, J.Scarano, C.Peacock, D van Puyvelde, D.Smith, Lee-Anne, Roslyn, G Morvell, T.Steeper and others

– Subsurface team: T.Dance, L.Paterson, J.Xu, Y.Cinar, J.E.King, D.Sherlock, P vanRuth, R.Causebrook, B.Vakarelov, R.Daniel and others

– M&V team: C.Jenkins, A.Hennig, J.Undershultz, M.Urosovic, D.Etheridge, A.Kepic, g g pP.Wisman, U.Sacht, E.Perkins,D.Kirste, P.deCaritat, R.Leuning and others

• Government colleagues from DPI, ITR, EPA, AGO, DSE, Moyne Shire, SRW

• International Collaborators: LBNL, Schlumberger Reserach, ARC reviewers and other advisorsg

• CO2CRC Participant companies

– Special thanks to the CPPL companies

S G Off | |Supporting participants: Australian Greenhouse Office | Australian National University | | CANSYD | Meiji University | The Process Group | University of Queensland |LBNL ARC

Outline• The Otway Basin Project

– Project Goals and Concept

– Key Challenges

• Community consultation

– Process and activities

• Performance Scorecard

L L• Lessons Learnt

Confidential

CO2CRC Otway Project Goals • Contribute towards CO2CRC Vision and Mission.

– Demonstrate that CCS is technically feasible and environmentally safe. F ilit t h i t it i t h l i– Facilitate research into new monitoring technologies

– Offer opportunities for trial and experimentation thereby supporting education/training in greenhouse gas technologies.

S ifi ll d t t t th ti f ti f t k h ld th t• Specifically demonstrate to the satisfaction of stakeholders that – CO2 can be safely produced, transported and injected into the sub-surface– CO2 can be safely stored– Subsurface behaviour of the injected CO2 can be effectively modeled and

monitored– Storage Volume can be verified as far as possible

f CCS– Build public support for CCS as a mitigation mechanism

Confidential

Project Assets and Site

Source

Sink

Otway Basin Stratigraphy

500 M Dilywn

896 M Pebble Point

Multiple barriers to Aquifer. Injection point is > 1 km deeper

976 M Timboon

1089 M Top Paratte – Injection Horizon Stage 2

1977 M Warre C – Injection Horizon Stage 1

Multiple barriers

Otway Project Concept

Key Challenges – each a risk !• Regulatory

– No existing regulation for geo-sequestration.

• Site Characterisation– Limited dataq

– Overlaps between jurisdictions– Access

• Organisational/Operational

• Risk Assessment

• Monitoring– CRC not an operating entity– Lack of Operations Systems

• Liability ManagementWho would shoulder long term

– Imaging under gas cap – Existing wells

– Who would shoulder long term liability.

• Community / Public AcceptanceCommunity / Public Acceptance– No precedents – Mixed reports on CCS in the media

N d f l l d– Need for compulsory land acquisition

Community Consultation: Process Map

Phase 1Ph 2 Phase 3 Ph 5Ph 4Opportunity

DefinitionPhase 2Select

Alternatives

Phase 3Define(FEED)

Phase 5Operations &

Evaluation

Phase 4Execution

6/04 1/05 12/05 8/06 6/104/08

L d M tiLandowner Meetings Shire Presentation

2 Public Meetings

Social Research

4 Public Meetings

Shire Presentation

2 Public Meetings to date

Critical Social Research

Stakeholder Reference Group Formed

Brochures Leaflets Newsletters

Period

Brochures, LeafletsMail drops

Newsletters

Community Consultation • Formal program to engage with and brief the community early – starting Jan 05

– key landholders – Shire and neighbouring councils

th l l di– the local media• Informing via email and offering briefings to:

– local State Upper and Lower House MPs NGOs (eg WWF ACF)– NGOs (eg WWF, ACF)

– State and Federal ministers through their Departments• Invited Mayor and Planning Manager to CRC technical Symposium• Formal briefing to shire and publicFormal briefing to shire and public

– Public info packs distributed to 1200 households – Advertisements run in local papers– Public meeting with state regulators held on Feb 12,06 – others planned

• Social research in community perception

Initial Communication – 2005 • The CO2CRC

– CO2CRC is not-for-profit research organisation, funded by government, industry, and research bodies

– The Research Project is important for Victoria Australia and the WorldThe Research Project is important for Victoria, Australia and the World• The Potential Project

– Subject to all the necessary planning and environmental approvals– We will be using safe, proven technology and maintain the highest standards of HSE– Transparency about the Project at all times– Community consultation - we want to hear what you think and work with you

• Why Moyne ShireMoyne Shire as a world leader in energy innovation– Moyne Shire as a world leader in energy innovation.

– National and international profile for the region– Help Victoria to decrease it’s greenhouse gas emissions – Economic benefits to Victoria

• Communication Tools– Brochures, Videos. Mail drops, Web information

Social Research• Objectives

– Benchmark and track public perceptions of CO2 geo-sequestration – Identify existing and emerging issues and track these over time– Identify existing and emerging issues and track these over time– Provide input to the community consultation plan.

• Approach :F di i ith l li i i t th it– Focus group discussions with people living in country near the site

– Focus group discussions with people living in a close by city.– In-depth interviews with local landowners.

• Initial Results:– Contrast between above groups: education, knowledge of CCS– General desire to know more: facts not “spin”.– However, do not want it to be intrusive

Adapting the Strategy

• Formation of a Stakeholder Reference Group

L l L d d it t ti– Local Landowners and community representatives

– Independent chair from DSE

• Fundamental Tenet• Fundamental Tenet

– The community should hear of activities directly from us first

• Address concerns quickly

• Bring scientists to explain their work

• If unable to provide some data explain why

• Quarterly newsletter

Example - Informing Anticipated Activities N l Ph 1• Naylor Phase 1

• Late March – April : Logs to understand reservoir. 2 –3 trucks, a few people for 2 –3 days.

• Naylor Phase 2• Naylor Phase 2• New well : early 2007• Monitoring activity

– Sampling : 4 –6 months into injectionSampling : 4 6 months into injection – 1 seismic set every 2-3 years (2-3 weeks with a crew of 5-7 people)– Well logs 2 –3 times a year ( 2-3 days each time)

• Buttress Phase 1 • Late March – April : Well Test and Logs : Expected to be a few days

– Understand well depth : Truck mounted unit with depth gauge– Test : Vehicles and storage tanks to flow the well and test gas.g g

• Buttress Phase 2• Starting late in the year: Site civil works for plant , Plant assembly and

testing. Area needed : 1 ha • Plant Operations in 2007-8 for an initial period of up to 2 years

Options for proposed Plant and Gathering line

Around 20 landholders involved for Ops and M&V activities

Production Site: Processing Modules and Compressor StationCompressor Station

Process skidCompressor

After cooler

Buttress 1Buttress 1Production well

Pipeline Installation

Not all RosyMedia ReportsMedia Reports

• Warnambool Standard

• Feb 2007

Not all Rosy

Questions in ParliamentParliament

F b 2009• Feb 2009

Operational Challenges

• Boggy ground, windy, rain • Electric fences – everywhere!

More noise• Access issues: Dairy farms,

paddocks, fences

DELANEY CORNER

c h2 Gerrard &

paddocks, fences

0 1.5km

CurdievaleCalligans Road

das

Roa

d

Boggy Creek 1

Buttress 13

4 2

5 467

Gerrard & Andrea CouchAnth

ony

&

Kar

e n C

o uc

Peter &Angela Parsons

Peter &Angela Parsons

Mark Bushell

Bruce CouchRon Brumby

2 rard & Andrea Couch

X

XY

??

Dances Road

ces

Roa

d

Rad

ford

s R

oad

Curdievale- Port Campbell Rd

Sod

Naylor South 1

Naylor 1

689

10 1113

12

h

Mrs D. Dumesny

Gavin CouchJimBrumby

Mrs Francome

Wayne Jenkins

MalcolmCroft

X

Y?

Y

Y ?

Y Shot hole100mm dia 3m deep,

400 mg charge

Dan

c

T h e Gr e a

Curdie 1

Curdievale 1

3 deep,

CO2CRC Otway Project Score Cardy j1. Safely produce CO2 from Buttress, transport and inject in

Naylor fieldy2. Effectively and safely store and monitor CO2 in the sub-

surface to satisfaction of stakeholders.– Robust Site Characterisation– Observations vs Modelling results

3 Test/Develop technology and methodologies for3. Test/Develop technology and methodologies for monitoring

4. Build Community Confidence5. Safely abandon the site and facilities including necessary

restoration work.

Confidential

Scorecard 4: Public Acceptance

Buttress Site: Production ell (B ttress 1) &

Public are interested• What

well (Buttress-1) & Surface Plant

Ai M it i Sit L Fl & Fl T

• Where• When• Impacts

– Noise

CRC-1 Site: Injection well (CRC-1)

Naylor-1 Site:Monitoring well (Naylor-1)

Air Monitoring Site: Lo-Flo & Flux TowerPipeline– Traffic– Water– Dairy Ops

Fire– Fire– General Safety– Compensation

Community Engagement: Site Emergency Response Plan (ERP) Test: Aug 26 08Response Plan (ERP) Test: Aug 26 08

• 10:30 am: Alarm raised – man down Call made to Operator by scientist regrading his colleague being unconsciousbeing unconscious.

• 10:39: Peter Dumesny (Operator) arrives. Confirms that he has informed the ERG. Gives CPRGives CPR

•10:55: The CERT and CFA arrive. The CERT team enters the room and attends to the patient.

11:00: Ambulance arrives and comes in through the site gate. Th t t h i b ht dThe stretcher is brought down

11:20: Patient moved into ambulance.

• 11:45 : Debriefing• 11:45 : Debriefing

Achievements Field Performance• Strong planning and systems• Approx. 125,000 manhours without incident

– CRC-1 and Naylor 1 completion

Site characterisation• Further reducing uncertainty

y p– Construction activities

• Approx 47,000 tonnes injected

Regulatory

Risk Assessment• QRA confirmed confidence in site

• Complex pathway • Compliance with Overlapping jurisdictions

Community• Landowner Matters : Compulsory Acquisition

M&V• Geophysics, Geochemistry and

Atmospheric ongoing

• Observations consistent with models• Landowner Matters : Compulsory Acquisition• Seismic Issues• Overall acceptance Financial Management

Lessons Learnt

• Do not under-estimate Landowner matters – This is their livelihood

Th i d i i ill k i– Their decisions will take time• Start early on Community consultation – shire, public meetings etc.• Involve Govt. representatives in public meetings

– Clear interfaces with Govt, Public, Media– A single Govt focal point is of great help.

• The M&V plan should be built early – basis for discussionsThe M&V plan should be built early basis for discussions– Explain in simple terms and share information

• There will be difficulties and you cannot please everyoneB i t t d t t– Be consistent, open and transparent

– Local support is essential

“What we have to learn to do, we learn by doing"we learn by doing"

Aristotle

Thank You

A knowledge continuum• Warrnambool respondents not aware of the project however those who partook in the research• Warrnambool respondents not aware of the project, however those who partook in the research,

whilst not opposed to the project as such, have several concerns they would like addressed• Nirranda we found much more heterogeneous knowledge bases and opinions

Untapped

Aware - but don’t know

details Informedde a s

Most Warrnambool residents (i.e. not

involved in the A minority of Nirranda

residents are advocates of

Apathetic Engaged Advocate Opposer

market research)residents are advocates of

the project, with a very small minority opposed

s sConcernedWarrnambool residents who

Most Nirranda residents are polarised between

engaged and apathetic, but with only a basic

knowledge of the project participated in the market research

knowledge of the project

CRC-1 I j ti SitInjection Site

42.9 M Core

Full Suite of Logs

• PEX-HALS, Caliper• CMR+• ECS (elemental capture spectroscopy)• FMI (image log)

S i S• Sonic Scanner • MDT: • 3D VSP

Otway helped identify Legislative ComplexitiesComplexities

Petroleum Act DPI

Well OpsEPA

SRW

Planning Act DSE/Shi– DSE/Shire

M&V

Social Research in 2006 • Overall attitude to the pilot varied

– Some advocates and others who are opposed – Most open to learning more.

• Overall attitude to geosequestration– The community in Nirranda, Warrnambool and surrounds are not yet

convinced that geosequestration is a viable mitigation option – Need more information before they can decide

• Moving forward with community engagement– Keen for further community consultation.y– Community meetings and quarterly newsletters preferred – CO2CRC to make information available and transparent to the community– Allow the community to initiate engagement rather than being too intrusive.y g g g

• Reaction to the communication messages– Need to be clear, concise and factual – residents do not want to hear ‘spin’

but facts.but facts.

top related