Decentralized Wastewater Workshop

Greenville, South Carolina

July 30, 2009

Land Disposal of Treated WastewaterTreatment & Disposal Options Overview

2

Secondary TreatmentTreatment Method Options

3

Tertiary TreatmentTreatment Method Options

4

Secondary Treatment OptionsOrenco AdVantex Recirculating Packed-Bed Media Filter

5

Secondary Treatment OptionsAqueonics Multi-Stage Trickling Filter

6

Secondary Treatment OptionsAquapoint Bioclere Modified Trickling Filter

7

Secondary Treatment OptionsPuraflo Peat Fiber Biofilter

8

Secondary Treatment OptionsRecirculating Sand Filter (RSF)

9

Secondary Treatment OptionsExtended-Air Activated Sludge Plant

10

Secondary Treatment OptionsClearstream ATU

11

Secondary Treatment OptionsSBR

12

Secondary Treatment OptionsPuraflo PuraMax MBBR

13

How to Select the Right SystemDecision Process Overview

14

Individual Lot Conventional Drain FieldSystem Summary

Std. Septic Tank & Stone Drain Tile FieldDrain field requires cleared land w/ <

10% slope.3,000 sq ft active drain field + 50%

repair areaApprox. Unit Cost = $4,000 - $5,000 per

lot.

15

Individual Lot Drip IrrigationSystem Schematic

16

Individual Lot Drip IrrigationSystem Summary

Std. Septic Tank + Secondary & Tertiary Treatment.

Subsurface drip field requires un-cleared land w/ < 33% slope.

2,000 sq ft drip field + no repair area.Approx. Unit Cost = $25,000 - $28,000 per lot.Requires 110-volt power supply + telephone line.Requires routine maintenance @ approx. $600/yr.

17

Individual Lot Drip IrrigationSystem Cost(City of Austin, TX)

18

Estimated drip irrigation system costs, installed, including controls and alarm, (not including pretreatment unit(s)),

$15,000

Energy costs (using 0.193 KWH/day energy use), $0.47/month

O&M, with a maintenance contract of $540/year (est. 18 hrs. @ $15/hour * 2.0, including taxes, overhead, and profit),

$45/month

Equipment repair/replacement costs, estimated at $50/year,

$4.17/month

20-year NPW (not including design & permitting costs), $20,934.68

Individual Lot Repair SolutionCamden County, NCAdVantex Pre-Treatment & Sand Mound Disposal over Sand Line Trench

19

Communal Drain FieldSystem Overview100-Lot Subdivision, Avg. 3-BR, in UpstatePrimary Treatment0.4 GPD/Sq Ft LTARRequires 6.9 acres of Active Drain Field plus

additional 3.4 acres for 50% Repair AreaHOA Ownership (excluding Collection

System)Permitting by DHEC-Bureau of

Environmental Health (up to 50,000 GPD +/-)Approx. Unit Cost = $5,000 - $6,000 per lot

20

Communal Drain FieldCottageville Elem School

21

Communal Drip IrrigationSystem Overview

100-Lot Subdivision, Avg. 3-BR, in UpstatePrimary & AdVantex Secondary Treatment0.2 GPD/Sq Ft LTARRequires 4.1 acres of Subsurface Drip Field &

No Repair AreaRequires Routine O&MRequires Utility OwnershipPermitting by DHEC-Bureau of WaterApprox. Unit Cost = $18,000 - $20,000 per lot

22

Ralph Chandler Middle SchoolSurface-Drip Irrigation SystemDecision Process

23

School Surface-Drip IrrigationSystem Overview

New Ralph Chandler Middle School at Fork Shoals

- Orenco Recirculating Media Filter Treatment

- 6-Acre GeoFlow Surface-Drip Irrigation Disposal- 0.1 – 0.2 GPD/Sq Ft LTAR- 250,000 Gal (2 weeks) Treated Effluent Storage- 15,900 GPD Design Flow- 4 Groundwater Monitoring Wells- $1.6 Million Construction Cost- Contract Operator – All Seasons Environmental Laboratories- Orenco Vendor Oversight Operations Contract - AQWA

24

School Surface-Drip IrrigationEQ Tank, Recirc Pumps, & Treated Effluent Storage

25

School Surface-Drip IrrigationAdVantex Treatment Pods

26

School Surface-Drip IrrigationIrrigation Pumps & Disc Filter

27

School Surface-Drip IrrigationSurface-Drip Irrigation Field

28

Wrap-Up ….

What Makes a DecentralizedSystem Successful?Suitability of Site & Sustainable Loading Rate.Proper Application of Treatment & Disposal

Methods Selected.Good Design.Good Installation.Good O&M.