COSTING FOR CIVIL ENGINEERING PROJECTS

UNIVERSITI MALAYSIA SARAWAK

Faculty Of Engineering

KNS 3333 CONSTRUCTION TECHNOLOGY

COSTING FOR CIVIL ENGINEERING PROJECTS

Cost

RateCost Estimating

Methods

Quantity

Cost

What is Cost ?

An estimate how much money will be neededor price to be charged for something.

(Oxford Advanced Learner’s Dictionary)

Why Cost (Control) Is Important?

Inception Design

Preliminary cost

estimate

Comparative cost estimate

Alternative materials

Form of construction

Tender Construction

Planned profits achieved ?

Feedback for future cost estimating available ?

What corrective action to be

taken ? Within economic limit of expenditure ?

Pre-contract Stage Post contract Stage

Quantity Rate AmountX

How Costing Is Done?

=

Quantity?

What is Quantity ?

The measurement of something by statinghow much of it there is.

(Oxford Advanced Learner’s Dictionary)

How quantity is read?

Quantity is shown as a figure and a unit of measurement behind it.

800 M

Unit of measurementQuantity

Quantity

Area (M2)

Weight (Kg or Ton)

Length (M)Volume

(M3)

OthersHours or

Day

Unit of measurement

Rate

What is Rate?

A fixed charge, payment or value.

(Oxford Advanced Learner’s Dictionary)

What is Rate?

Price per unit of measurement.

RM 250.00/M3

Per unit of measurement

Currency

How rate is read?

Price of item

Material CostWastagesPlant Cost

Labour CostProfit & Overheads

Rate Build Up

Example Of Market Rate

Description Unit Rate (RM)

Excavation (pit) M3 10.00

Concrete Grade 15 M3 240.00

Concrete Grade 20 M3 255.00

Concrete Grade 25 M3 270.00

Formwork M2 28.00

Reinforcement Kg 3.20

Rate will differ from one project to another due to various factors such as size, nature of work, location, market conditions, etc.

Cost Estimating Methods

Notes On Costing For Civil Engineering Projects

Involve large amount of uncertainty owing to

nature of ground conditions, temporary works, etc.

Notes On Costing For Civil Engineering Projects

Bill of quantities comprise large quantities of comparatively few items.

Quantities usually approximate and

remeasurement required when work is actually carried out.

Different method of measurement is used for civil engineering works (CESMM).

Notes On Costing For Civil Engineering Projects

Costing can be carried out by breaking

down works into smaller cost items and price the quantities against a rate.

Notes On Costing For Civil Engineering Projects

Costing similar to building works but more

towards method of construction rather than material cost.

Cost Estimating Methods

Unit Method

Standard Unit Of Accommodation

Appropriate Cost Per UnitXEstimated

Cost=

MidLow High

Cost Estimating Methods

Superficial Method

Area Of FloorsCost Per

Square MetreXEstimated Cost

=

MidLow High

Cost Estimating Methods

Approximate Quantities

Items Of Major Cost Importance Measured Only

Unit RateXEstimated Cost

=

MidLow High

Build up on basis from cost database price book or priced BQ

from previous project

Cost Estimating Methods

Bill Of Quantities

Measured Quantities

Unit RateXEstimated Cost

=

MidLow High

Build up on basis from cost database price book or priced BQ

from previous project

Pre-Tender Estimate to include other items like

Preliminaries, Provisional Sums, Prime Cost Sums,

Contingency, etc.

Cost Estimating Methods

Type of information provided

Quality of relevant available pricing information

Experience

Skills

Degree Of Accuracy