coal creek culvert replacement pacific coast salmon coalition

Post on 18-Jan-2016

219 Views

Category:

Documents

2 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Coal Creek Culvert Replacement

Pacific Coast Salmon Coalition

Project Description Coal Creek is a tributary to the Dickey River. The Dickey River and

its’ tributaries provide abundant low-gradient habitat for spawning and rearing Coho, Steelhead and Cutthroat. The Dickey drainage is known as one of the top Coho smolt producers (measured by square kilometer of drainage) in Washington State. The Dickey confluences with the Quillayute River in the Quillayute Esturary.

The culvert on Coal Creek we will be addressing is under the 5000 line, a well used logging road. The current structure is a 96” CMP that is perched and undersized. The average stream width upstream is 14’ with a 20” outfall drop that plunges directly onto large rip rap, placed to protect the road, creating an obstacle to salmonid migrating upstream to access the habitat above the blocking culvert. Because the pipe is undersized at the inlet there is a whirlpool effect that is resulting in bank destabilization. There is approximately 6’ of road fill covering the CMP.

Location 47.98543°N 124.59863°W 8.2 Mile on 5000

Driving DirectionsFrom the stop light in Forks Drive on HWY 101 for 1.4 miles Turn left onto the La Push Rd. Drive 3

miles. Turn right onto Quillayute Rd. Drive 3.7

miles. Turn right onto Mina Smith Rd. Drive .07

miles. Turn left onto the 5000. Drive 3.8 miles

the culvert is directly under the road.

Map

Project Site

Map

Drainage

Current Conditions 96” or 8’ Corrugated Metal Pipe Under Sized Perched Degraded Pipe 2.9 Miles of inaccessible stream

Cost Estimate Total Cost of the Project is $260,472 Rayonier 35% match is $91,165 Request from SRF Board $169,307

Budget

Coal Creek Tributary Bridge Project - 5000 Road @ M.P. 9486 Exisiting Structure No.

90307 Future Structure No.

Bridge Fabrication60' steel portable bridge, Big R style 75,000$

Culvert Removal

1500 cys & pipe, w/ pumping

Backhoe operator for 4 days 5,200$ Laborer for 4 days 1,600$ 2 dump truck drivers for 4 days 6,800$

Bridge Installation

Crane operator for 10 days 18,000$ 3 laborer for 10 days 12,000$ materials piles & caps 32,000$ backwalls 12,000$

Instream LWD Installation

Placement 1,000$ LWD 15 pieces 2,000$

Planting

Erosion/Water Pollution Control 1,000$ Seeding and Regetation 1,000$

Backfill

2 dump trucks for 2 days 3,400$ 1 cat operator for 2 days 2,200$

Mob 8,000$

A&E 18,760$

Construction Engineering 12,000$

3 laborers and truck drivers for 2 days 5,100$

Subtotal 217,060$ 20% contingency 43,412$

Total 260,472$

Rayonier Match of 35% 91,165$ Request From SRFB 169,307$

RMAP Project Requirements Project is not solely mitigation. Project is not Mitigation Project is an expedited action ahead of the Department of

Natural Resources approved RMAP schedule. Project is currently scheduled for 2016

Expedited actions do not include RMAP projects that might be delayed beyond their originally scheduled completion date. It will be 4 years earlier

Project must provide a clear benefit to salmon recovery. It opens almost 3 miles of habitat

There will be harm to salmon recovery if the project is delayed (i.e., not completed earlier than the scheduled RMAP completion date). 3 miles of habitat, inaccessible

Large landowners must provide 35 percent match for fish passage projects and 50 percent for sediment reduction projects. Meets 35% criteria and is a fish passage blockage

Priority Listed in the North Pacific Coast Lead

Entity Strategy, Appendix B: 2011 Project List as a priority project.

Proposed Structure Big R style bridge 60’ long 16’ wide

Bridge Design

`

7/8" minus Crushed Rock

Finished SurfaceRoad Grade Filter Fabric between gravel and bridge16 foot minimum width

60 foot Steel Bridge, U-80 minimum loading @ 1/310 Maximum deflection

15" minimum clearance from finnished gravel surface to top of guard rail. Metal side wall, 4" min.

above fininshed gravel surface

Guard Rail

Reflective Delineator, all four

2% Minimum Bridge Slope

12" diameter steel piles with concrete or steel I beam caps

Galvanized Sheet Metal Endwalls, both ends

Slope road grade to drain away from bridge, 2% minimum slope, both ends

Bridge with two longitudinal halves, bolted together

Grade Skid-A 2" BY 2" Square Tubing welded to top of deck

2 feet

Grader Bumper, Treated Wooden 10" By 10" minimum, placed at finished grade, both ends

Use A588 weathering steel or approved Wasser Paint system on all structural members. Nonstructural members must be galvanized steel.

Bridge must be designed by a licensed structural engineer, licensed in the state of Washington and approved by RFR's representative prior to delivery.

Installation plans that deviate from these plans must be approved by RFR's representative prior to commencement.

Coal Creek Tributary - 5000 Mainline Road @ Mile Post 8.185 - RMAP No. CL 90307

Bridge Installation Sketch

Located in Section 26, Township 29 North, Range 15 West, W.M., Clallam County, Washington

Rayonier Forest Resources, April, 2009

Design

Permit HPA FPA

Site Photos

Downstream

Outfall Drop

Inside the Pipe

Species Coho Steelhead Cutthroat

Partners Rayonier (Property Owner) WDF&W Quileute Tribe (Post Project Monitoring)

Questions?

top related