HANDLING CONCRETE
-
8/12/2019 CHAPTER 4 Concrete
2/43
CONTENTHANDLING CONCRETE
Identification of hazards
Concrete placing by direct discharge, excavator andcrane
Concrete pumping
Concrete curing
-
8/12/2019 CHAPTER 4 Concrete
3/43
INTRODUCTION Concretes versatility, durability,
and economy have made it theworlds most used constructionmaterial.
The U.S. uses about 180 millioncubic meters (240 million cubic
yards) of ready-mixed concreteeach year.
It is used in highways, streets,parking lots, parking garages,bridges, high-rise buildings,dams, homes, floors, sidewalks,driveways, and numerous otherapplications.
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=NTHgSVwN2cpRvM&tbnid=RbARZmAHNhEDwM:&ved=0CAUQjRw&url=http://commons.wikimedia.org/wiki/File:Bluemetal_coarse_granite_gravel_texture.jpg&ei=En2VUpTGLMe3rAee6oC4Dg&bvm=bv.57155469,d.bmk&psig=AFQjCNF5caw2jIq7k_-xKDNfDUZ8NiIjDA&ust=1385614988998141 -
8/12/2019 CHAPTER 4 Concrete
4/43
INTRODUCTION Concrete and cement are not the
same thing; cement is one of acomponent of concrete.
Cement, usually in powder form,acts as a binding agent whenmixed with water andaggregates.
This combination, or concretemix, will be poured and hardeninto the durable material withwhich we are all familiar.
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=NTHgSVwN2cpRvM&tbnid=RbARZmAHNhEDwM:&ved=0CAUQjRw&url=http://commons.wikimedia.org/wiki/File:Bluemetal_coarse_granite_gravel_texture.jpg&ei=En2VUpTGLMe3rAee6oC4Dg&bvm=bv.57155469,d.bmk&psig=AFQjCNF5caw2jIq7k_-xKDNfDUZ8NiIjDA&ust=1385614988998141http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=NTHgSVwN2cpRvM&tbnid=RbARZmAHNhEDwM:&ved=0CAUQjRw&url=http://commons.wikimedia.org/wiki/File:Bluemetal_coarse_granite_gravel_texture.jpg&ei=En2VUpTGLMe3rAee6oC4Dg&bvm=bv.57155469,d.bmk&psig=AFQjCNF5caw2jIq7k_-xKDNfDUZ8NiIjDA&ust=1385614988998141http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=l8YWrW9LyYImoM&tbnid=qAAphFNJ3NMPHM:&ved=0CAUQjRw&url=http://www.daviddarling.info/encyclopedia/A/AE_aggregate.html&ei=nH2VUruuL8asrAeKuIHQDg&bvm=bv.57155469,d.bmk&psig=AFQjCNFBvTmU67-6mqw_yCvil3jHJHEAPw&ust=1385615097365444http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=l8YWrW9LyYImoM&tbnid=qAAphFNJ3NMPHM:&ved=0CAUQjRw&url=http://www.daviddarling.info/encyclopedia/A/AE_aggregate.html&ei=nH2VUruuL8asrAeKuIHQDg&bvm=bv.57155469,d.bmk&psig=AFQjCNFBvTmU67-6mqw_yCvil3jHJHEAPw&ust=1385615097365444http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=NTHgSVwN2cpRvM&tbnid=RbARZmAHNhEDwM:&ved=0CAUQjRw&url=http://commons.wikimedia.org/wiki/File:Bluemetal_coarse_granite_gravel_texture.jpg&ei=En2VUpTGLMe3rAee6oC4Dg&bvm=bv.57155469,d.bmk&psig=AFQjCNF5caw2jIq7k_-xKDNfDUZ8NiIjDA&ust=1385614988998141 -
8/12/2019 CHAPTER 4 Concrete
5/43
INTRODUCTION Concrete is made up of three basic components:
water,
aggregate (rock, sand, or gravel) and Portland cement.
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=NTHgSVwN2cpRvM&tbnid=RbARZmAHNhEDwM:&ved=0CAUQjRw&url=http://commons.wikimedia.org/wiki/File:Bluemetal_coarse_granite_gravel_texture.jpg&ei=En2VUpTGLMe3rAee6oC4Dg&bvm=bv.57155469,d.bmk&psig=AFQjCNF5caw2jIq7k_-xKDNfDUZ8NiIjDA&ust=1385614988998141http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=l8YWrW9LyYImoM&tbnid=qAAphFNJ3NMPHM:&ved=0CAUQjRw&url=http://www.daviddarling.info/encyclopedia/A/AE_aggregate.html&ei=nH2VUruuL8asrAeKuIHQDg&bvm=bv.57155469,d.bmk&psig=AFQjCNFBvTmU67-6mqw_yCvil3jHJHEAPw&ust=1385615097365444http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=l8YWrW9LyYImoM&tbnid=qAAphFNJ3NMPHM:&ved=0CAUQjRw&url=http://www.daviddarling.info/encyclopedia/A/AE_aggregate.html&ei=nH2VUruuL8asrAeKuIHQDg&bvm=bv.57155469,d.bmk&psig=AFQjCNFBvTmU67-6mqw_yCvil3jHJHEAPw&ust=1385615097365444http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=NTHgSVwN2cpRvM&tbnid=RbARZmAHNhEDwM:&ved=0CAUQjRw&url=http://commons.wikimedia.org/wiki/File:Bluemetal_coarse_granite_gravel_texture.jpg&ei=En2VUpTGLMe3rAee6oC4Dg&bvm=bv.57155469,d.bmk&psig=AFQjCNF5caw2jIq7k_-xKDNfDUZ8NiIjDA&ust=1385614988998141 -
8/12/2019 CHAPTER 4 Concrete
6/43
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=G5OFVboIeZNcXM&tbnid=p_l8u8Hd0dvKRM:&ved=0CAUQjRw&url=http://www.canberratimes.com.au/act-news/inspectors-look-into-rspcas-rabbit-holes-20130910-2tind.html&ei=kICVUsm8I8qOrgeW5oCYDg&psig=AFQjCNH6rwnWQ3fEDvnnOW2I1BVoLV8dLA&ust=1385615877823565http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=fmXvMnH-A-ziRM&tbnid=ZL0vpJnEYtKxDM:&ved=0CAUQjRw&url=http://www.cement.org/tech/cct_con_safety.asp&ei=T3-VUpbgGMe_rgfUoYGYDw&psig=AFQjCNEpeM_LJxzAuAApITQa_0NaF-YvaQ&ust=1385615560908221 -
8/12/2019 CHAPTER 4 Concrete
7/43
IDENTIFICATION OF HAZARD The current trend in construction-
related injuries is decreasing. Thistrend is most likely due to increasedawareness of the potential risks
surrounding construction jobsites. The concrete industry boasts one of
the lower jobsite-injury rates, but it isnot necessarily the concrete thatpresents the greatest risk.
An understanding of the potentialrisks of concrete construction andproper training is necessary forlimiting the number of concreteconstruction-related injuries.
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=G5OFVboIeZNcXM&tbnid=p_l8u8Hd0dvKRM:&ved=0CAUQjRw&url=http://www.canberratimes.com.au/act-news/inspectors-look-into-rspcas-rabbit-holes-20130910-2tind.html&ei=kICVUsm8I8qOrgeW5oCYDg&psig=AFQjCNH6rwnWQ3fEDvnnOW2I1BVoLV8dLA&ust=1385615877823565http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=G5OFVboIeZNcXM&tbnid=p_l8u8Hd0dvKRM:&ved=0CAUQjRw&url=http://www.canberratimes.com.au/act-news/inspectors-look-into-rspcas-rabbit-holes-20130910-2tind.html&ei=kICVUsm8I8qOrgeW5oCYDg&psig=AFQjCNH6rwnWQ3fEDvnnOW2I1BVoLV8dLA&ust=1385615877823565http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=fmXvMnH-A-ziRM&tbnid=ZL0vpJnEYtKxDM:&ved=0CAUQjRw&url=http://www.cement.org/tech/cct_con_safety.asp&ei=T3-VUpbgGMe_rgfUoYGYDw&psig=AFQjCNEpeM_LJxzAuAApITQa_0NaF-YvaQ&ust=1385615560908221 -
8/12/2019 CHAPTER 4 Concrete
8/43
IDENTIFICATION OF HAZARD Construction jobsites are full of hazards, and concrete
construction jobsites are no exception.
These hazards can be dissected into categories for better
reference as they pertain to various projects. Types of hazard includes:-
Material Hazard
Machinery
Tools Height
Construction Practices
Jobsite Conditions
-
8/12/2019 CHAPTER 4 Concrete
9/43
IDENTIFICATION OF HAZARD(i) Material Hazards Cement comprises 7-15% of total concrete volume. As an alkaline material, wet cement is caustic, and can cause severe chemical burns to
exposed skin and eyes. Working with fresh concrete presents an obvious risk.
It is so important to always wear water-proof gloves, a long-sleeved shirt, full-lengthtrousers, and proper eye protection.
Water-proof boots must be high enough to keep concrete from flowing into if theworkers need to stand in wet concrete,
Wet concrete, mortar, cement, or cement mixtures must be washed immediately fromskin.
Flush eyes with clean water immediately after contact.
Indirect contact through clothing can be as serious as direct contact, so promptly rinseout wet concrete, mortar, cement or cement mixtures from clothing. And always seekimmediate medical attention if you have persistent or severe discomfort.
In addition to the caustic nature of cement, 95% of cement particles are smaller than 45m.compared to tobacco smoke of approximately 3 msuggesting that the danger ofinhalation is possible. Workers opening bags or sacks of cement and cement productsshould always wear a dust mask in addition to their regular safety attire.
-
8/12/2019 CHAPTER 4 Concrete
10/43
IDENTIFICATION OF HAZARD(ii) Machinery Hazard Rotating machinery is always a source of potential injury
on a jobsite.
Early-entry saws, concrete/masonry saws, cut-off saws, andpower trowels pose a threat to appendages when usedimproperly. In addition, any sustained or sudden noiseabove 85 decibels emanating from machinery can bedamaging to the ear.
Hydraulic jacks used in shoring, compressed air andhydraulic concrete pumps, belt conveyors, weldingequipment, post-tensioning jacks, demolition devices, andother equipment also create potential hazards on aconcrete construction site.
-
8/12/2019 CHAPTER 4 Concrete
11/43
IDENTIFICATION OF HAZARD(iii) Tools
Besides the mechanized saws and power trowels listed above,sharp-edged trowels, hammers, chisels, utility knives, etc. canbe dangerous if used carelessly or incorrectly.
Long-handled bull f loats, when used near utility wires, caneven be dangerous.
(iv)Height
The number-one leading cause of construction-relatedinjuries and fatalities is attributed to falls from height.
Sources of height associated with concrete constructioninclude but are not limited to scaffolding, ladders, bucket-trucks, catwalks, elevated or wall forms, and elevated f loors.
Owners, managers, contractors, and laborers should be awareof specific height sources on a project as they are virtuallyunavoidable in construction.
-
8/12/2019 CHAPTER 4 Concrete
12/43
IDENTIFICATION OF HAZARD(v) Construction Practices The use of cranes for lifting and placing concrete buckets, for tilt-up
concrete panels, and for lifting precast members present hazards to thefinishers and erectors.
Concrete pumping, hydro-demolition, or shotcreteing operationswhere high pressures are generated in hoses prompt safety concerns forthe nozzlemen.
Reinforcement construction can demand heavy materials, protrudingsteel, oxyacetylene torches or welding equipment, and height sources,each of which introduces a safety hazard either singularly or in any
combination. Post-tensioning operations impart stresses nearly equal to the yieldstrength of prestressing tendons which can be 250,000 psi. Suchforces are dangerous to jack-operators or on-looking personnel.
Precast plants with heavy table forms, consolidation equipment, andcuring rooms must follow safety procedures.
-
8/12/2019 CHAPTER 4 Concrete
13/43
IDENTIFICATION OF HAZARD(vi) Jobsite Conditions
The general condition of the jobsite can also be
hazardous. Cramped, confined projects or sections of a project
affect operations and safety.
Locations exposed to traffic, utility wires, excavations,
or hazardous materials can produce unsafe conditions. Even weather (ie: snow, ice, rain, standing water, heat)
can result directly in injury or combine with anotherrisk to inflict injury to workers.
-
8/12/2019 CHAPTER 4 Concrete
14/43
IDENTIFICATION OF HAZARD
Prevention
Personal
Protection
Equipment
Protection
Jobsite
Protection
-
8/12/2019 CHAPTER 4 Concrete
15/43
PreventionPersonal Protection
Hardhats and hearingprotection are always
necessary on a constructionsite when overhead hazardsand loud or sustained noiseis present.
When working with cement,
sand, or any other finematerial, the use of arespirator is necessary.
-
8/12/2019 CHAPTER 4 Concrete
16/43
PreventionEquipment Protection All equipment should be properly maintained and
equipped with manufacturer-recommended safety devices.
Disabling or removing safety devices is dangerous andshould be avoided. All unsafe or inoperable equipment should be marked as
such to prevent further use of the equipment. All workers should be trained and tested by the manager or
superintendent before operating any equipment (fromdrills to backhoes). Knowledge of the hazards associated with specific
equipment is the first line of defense against injury.
-
8/12/2019 CHAPTER 4 Concrete
17/43
PreventionJobsite Protection
Responsibility of the manager to provide a safe jobsite
for workers. The manager or superintendent should ensure that
potential hazards at the project site are identified andcorrected or, at minimum, made known to employees.
-
8/12/2019 CHAPTER 4 Concrete
18/43
-
8/12/2019 CHAPTER 4 Concrete
19/43
CONCRETE PLACING Normal concrete weighs
approximately 68kg@150 poundper cubic foot and should be
placed as near as possible to itsfinal position.
Excess handling can causesegregation of the course and fineaggregates.
Wetting up the concrete to ensurethat it can be raked or pushed intoa location far from where it isdischarged is not acceptable.
-
8/12/2019 CHAPTER 4 Concrete
20/43
CONCRETE PLACING Concrete is poured directly from the
chute of the ready mix truck,wheeled into place with a buggy, orpumped into place with a concreteboom pump.
Concrete is normally specified at a4-5" slump.
Industrial, commercial, and someresidential projects require aninspector on concrete pours whomonitors the concrete slump andtakes slump measurements at therequired intervals.
-
8/12/2019 CHAPTER 4 Concrete
21/43
CONCRETE PLACING The smooth delivery of concrete to the job-site is
critical.
Delays in the delivery of the concrete or during theplacement operation may cause problems that are timeconsuming and costly to resolve.
The field Technician, the Contractor, and the concrete
plant Technician are required to work together toensure the correct concrete is delivered on time and inthe necessary quantities.
-
8/12/2019 CHAPTER 4 Concrete
22/43
SITE PREPARATION FOR CONCRETE
PLACINGThe Technician is required to ensure that the site has beenadequately prepared for concrete placement. Such preparationsinclude that:1) Excavations have been dewatered
2) Forms have been checked for adequate bracing and properelevations and alignment3) Chamfer strips have been installed and are in good shape4) Trash and debris have been removed from all forms5) Reinforcement has been tied securely and checked forproper clearance and spacing6) The Contractor has adequate manpower and equipment tohandle the pour to include a sufficient number of vibratorsand backups.
-
8/12/2019 CHAPTER 4 Concrete
23/43
WEATHER CONDITIONS Weather conditions may influence everything from the timing and
method of concrete delivery and placement to postponing theoperation altogether.
Ideally, concrete is placed in temperatures between 50 and 90 F, when
there is no threat of rain, and when steps have been taken to protectthe concrete from excessive wind. In general, when the temperature is 35 F or below, the temperature of
the concrete is required to be between 50 and 80 F at the time ofplacing.
The Contractor may heat the water and/or aggregates used in theconcrete mix to achieve this range of temperatures; however, theheating is required to be done in accordance with the Specifications forcold-weather concrete.
The Technician is required to use a dial thermometer to check theconcrete temperature whenever the concrete is suspected to be nearthe Specifications limits.
-
8/12/2019 CHAPTER 4 Concrete
24/43
CONCRETE DELIVERY No concrete may be placed without a Technician on
the job and another Technician at the concrete plant.
Prior to the beginning of concrete delivery, thetechnician is required to contact the plant Technicianto double-check the following items:
1) The class of concrete to be used
2) The quantity of concrete needed for the pour3) The slump and air content requirements
4) The proposed starting time of delivery
5) The desired rate of delivery.
-
8/12/2019 CHAPTER 4 Concrete
25/43
CONCRETE DELIVERY Concrete is typically delivered to the job-site in mixer
trucks, agitator trucks, or in non-agitating equipment.
Mixer Trucks
-
8/12/2019 CHAPTER 4 Concrete
26/43
CONCRETE DELIVERY Mixer trucks are designed for
mixing concrete at or on theway to the job-site. For thisreason, mixer trucks always
have a water tank on boardand a measuring device thatis capable of controlling theamount of water that isadded to the mix.
Agitator trucks deliver ready-mixed concrete. Any water onthe truck is for cleaningpurposes only, not formixing.
Agitator truck
-
8/12/2019 CHAPTER 4 Concrete
27/43
Directplacement
Usingbuggy/wheelbarrow
BoomPump
-
8/12/2019 CHAPTER 4 Concrete
28/43
Placing the Ready-Mixed Concrete Access for the ready-mixed concrete truck should be provided as close
as possible to the required location in the structure. It may be possible to discharge concrete directly from the truck into
foundations and column bases, but for other components a means of
transporting the concrete from the truck discharge point to its requiredlocation in the frame will be required. The two methods of transporting concrete that are most applicable to
multi-storey frame construction are:1. Pumping. A truck-mounted (or occasionally static) concrete
pump is sited at round level with its delivery boom and/or hosesdeployed so that concrete can be pumped directly to where it isrequired in the frame.The input hopper of the pump is topped-up from truck-mixers.2. By skip.
A site crane hoists a skip from ground level (where it is filled withconcrete from a truck-mixer) to the required location in the frame.
-
8/12/2019 CHAPTER 4 Concrete
29/43
CONCRETE SKIPPING METHODLoad concrete intobucket
Using crane totransport theconcrete todesired place.
-
8/12/2019 CHAPTER 4 Concrete
30/43
-
8/12/2019 CHAPTER 4 Concrete
31/43
CONCRETE PUMPING(ii) The second main type of concrete pumpis either mounted on a truck and knownas a truck-mounted concrete pump orplaced on a trailer, and it is commonlyreferred to as a line pumpor trailer-
mounted concrete pump. This pump requires steel or flexibleconcrete placing hoses to be manuallyattached to the outlet of the machine. Those hoses are linked together andlead to wherever the concrete needs tobe placed
Line pumps normally pumpconcrete at lower volumes than boompumps and are used for smaller volumeconcrete placing applications such asswimming pools, sidewalks, and singlefamily home concrete slabs and mostground slabs.
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=IoGdFL3EjTmOaM&tbnid=nGOJ36BvUv_mLM:&ved=0CAUQjRw&url=http://www.reedpumps.com/bseriesskidmounting.htm&ei=5LqWUrXtE8jyrQeU24DgDQ&bvm=bv.57155469,d.bmk&psig=AFQjCNGsFHl7ITaz3RfwUuEsqIkAjl1VCw&ust=1385696347091500http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=Qk4qB-pVC0mIVM&tbnid=BkF4Jgft90-PxM:&ved=0CAUQjRw&url=http://www.concreteconstruction.net/concrete-pumps/no-title.aspx&ei=o7qWUsDmC4iRrQeMjoGADw&bvm=bv.57155469,d.bmk&psig=AFQjCNFFKsouTIav2LjLFuu5cEa9nJkMFw&ust=1385696278730700 -
8/12/2019 CHAPTER 4 Concrete
32/43
CONCRETE PUMPING There are also skid mounted and rail mounted
concrete pumps, but these are uncommon and onlyused on specialized jobsites such as mines and
tunnels.
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=IoGdFL3EjTmOaM&tbnid=nGOJ36BvUv_mLM:&ved=0CAUQjRw&url=http://www.reedpumps.com/bseriesskidmounting.htm&ei=5LqWUrXtE8jyrQeU24DgDQ&bvm=bv.57155469,d.bmk&psig=AFQjCNGsFHl7ITaz3RfwUuEsqIkAjl1VCw&ust=1385696347091500http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=IoGdFL3EjTmOaM&tbnid=nGOJ36BvUv_mLM:&ved=0CAUQjRw&url=http://www.reedpumps.com/bseriesskidmounting.htm&ei=5LqWUrXtE8jyrQeU24DgDQ&bvm=bv.57155469,d.bmk&psig=AFQjCNGsFHl7ITaz3RfwUuEsqIkAjl1VCw&ust=1385696347091500http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=Qk4qB-pVC0mIVM&tbnid=BkF4Jgft90-PxM:&ved=0CAUQjRw&url=http://www.concreteconstruction.net/concrete-pumps/no-title.aspx&ei=o7qWUsDmC4iRrQeMjoGADw&bvm=bv.57155469,d.bmk&psig=AFQjCNFFKsouTIav2LjLFuu5cEa9nJkMFw&ust=1385696278730700 -
8/12/2019 CHAPTER 4 Concrete
33/43
SEGREGATION Segregation occurs when the coarse and fine aggregates used in the concrete separate and become unevenly distributed throughout the mix. The larger coarse aggregate sinks to the bottom while the fines rise to the top. Segregation always leads to an inferior quality of concrete.
For the most part, however, segregation may be prevented with the use of properplacement equipment and techniques. Concrete is required to be placed as close as possible to the location the concrete
occupies in the structure. The concrete should not be dumped in a central location and then spread to the
location required in the structure
-
8/12/2019 CHAPTER 4 Concrete
34/43
LAYERS When possible, concrete is required to be deposited in layers no
more than 24 in. thick. Care is required be taken, however, to place each successive layer
before the preceding layer has taken the initial set.
This initial set is usually 45 minutes to an hour, depending onthe temperature.
Too much time between the placement of layers usually resultsin a cold joint which is a weak line of separation between thelayers.
-
8/12/2019 CHAPTER 4 Concrete
35/43
DROPPING THE MIXED Dropping concrete from too great a heightcauses the finer particles in the mix to splashaway from the larger, heavier particles. Inaddition, the force of the mix striking thereinforcing steel may shift bars out of
position. The maximum drop height or allowable free fall
is 4- 5 ft. Hoppers with flexible chutes called tremies are
required to be used to funnel the mix down intotall, narrow forms. Workers may be stationedinside the forms to move the chutes around to
ensure an even distribution of the concrete. The hoppers may not rest on the reinforcing
steel and are required to be supported by theformwork.
Hopper
Chutes
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=vluixwPOxtzYjM&tbnid=08Cf8FryssilCM:&ved=0CAUQjRw&url=http://www.garbro.com/steel_drop_chutes.htm&ei=KrSWUr6-GcO4rgeckIGwDw&psig=AFQjCNEKsta0D_C4PUFyJwW1XlX7vq9Y5w&ust=1385694395288786 -
8/12/2019 CHAPTER 4 Concrete
36/43
COMPACTION Adequate compaction is essential to ensurethat the concrete performs satisfactorily inthe completed structure.
Under-compacted concrete will have reducedstrength and / or durability, and may be of
unacceptable appearance. Appropriate compaction equipment must
therefore be available when it is required andconcrete-placing personnel should be trainedto use it correctly
The poker vibrator is likely to be mostappropriate compaction device for in-situ
reinforced concrete frames. Beam vibrators or hand tamping can be used
to compact and finish the top surfaces ofslabs, but a poker vibrator will still berequired to ensure that adequate compactionis achieved through the full thickness and atthe edges.
Poker vibrator
BeamVibrator
-
8/12/2019 CHAPTER 4 Concrete
37/43
COMPACTION Although the procedure is a simple operation, vibrating concrete is often conducted incorrectly.
Some points that ensure a good job include:
1) Vibrating is required to be done immediately as the concrete is placed
2) Vibrators are required to be inserted and withdrawn vertically and should not be dragged through theconcrete
3) Vibrators are required to be inserted and withdrawn within 5 seconds. Over-vibrating forces the fineraggregates to the top and drives the larger aggregates toward the bottom.
4) When concrete is poured in layers, the head of the vibrator is required to penetrate through the top layer andpartially through the layer underneath.
5) The workers are required to avoid contacting the reinforcing steel with the vibrator so that the bond betweenthe steel and the concrete is not broken
6) The workers are required to avoid contacting the form walls with the vibrator as that may loosen the formsand may also cause honeycombing of the concrete surface
7) The Contractor is required to have a backup vibrator on hand for larger pours in case of equipment problems
-
8/12/2019 CHAPTER 4 Concrete
38/43
CONCRETE SPREADING The purpose of
spreading fresh
concrete is to placeconcrete as close aspossible to finish levelto facilitate straightedging/ screeding theconcrete.
-
8/12/2019 CHAPTER 4 Concrete
39/43
CONCRETE SPREADING Short handled, square
ended shovels arerecommended forspreading concrete.
A come-along (a tool thatlooks like a hoe and has along straight edged blade)can also be used.
Any spreader used should
be rigid enough to pushand pull wet concrete
without bending.
-
8/12/2019 CHAPTER 4 Concrete
40/43
-
8/12/2019 CHAPTER 4 Concrete
41/43
CONCRETE CURING Once the concrete is in place, the concrete is allowed
to cure a certain amount of time to achieve the fullstrength.
During the curing period, the concrete is not to beplaced under stress.
The typical curing period of the concrete is 96 hours
after the initial set. The use of certain materials, such as fly ash or
Portland-pozzolan cement in the concrete, increasesthe curing period to 120 hours.
-
8/12/2019 CHAPTER 4 Concrete
42/43
CURING The Specifications describe two methods of curing concrete.(1) Protective covering curing method. This method requires covering the surfaces to be cured with canvas,
straw, burlap, sand, or other approved material and keeping theconcrete wet with water throughout the curing period.
The water prevents the concrete from drying out too quickly.
Surfaces that require a Class Two rubbing finish are required to havethe protective covering temporarily removed to allow the rubbing tocontinue.
The covering is required to be restored as soon as possible.
-
8/12/2019 CHAPTER 4 Concrete
43/43
CURING
(2) The use of a membrane forming curing compound.
The curing compound may be applied after the concrete surface has receivedthe specified finishing treatment. Up until then, the concrete is required to be protected by the protective
covering method or, in the case of vertical surfaces, simply by leaving theforms in place.
Curing compound is applied at a minimum rate of one gallon for every 150 ft2of concrete surface. The application is done in two stages.
The first coat is applied immediately after stripping the forms or uponacceptance of the concrete finish.
The surface is required to be wetted with water and coated with thecompound as soon as the water film disappears.
The second application is required to begin after the first has set andaccording to the manufacturers directions.