Centura Health Lawson 8.x Upgrade Project March 6, 2003 Presented by: Chris L’Archevesque & Paul Jensen. We extend the healing ministry of Christ by caring for those who are ill and by nurturing the health of the people in our communities. Centura Health Mission Statement. Prior to Upgrade - PowerPoint PPT Presentation

TRANSCRIPT

1111

Centura Health Centura Health Lawson 8.x Upgrade Lawson 8.x Upgrade

ProjectProjectMarch 6, 2003March 6, 2003

Presented by: Chris L’Archevesque & Paul Presented by: Chris L’Archevesque & Paul

JensenJensen

2222

We extend the healing ministry of Christ We extend the healing ministry of Christ by caring for those who are ill and by by caring for those who are ill and by nurturing the health of the people in our nurturing the health of the people in our communitiescommunities

Centura HealthMission Statement

3333

Centura HealthLawson Environment

Prior to Upgrade

Lawson 7.2.2 applications Lawson 7.3.3 environment Lawson 7.3.3 LID UNIX S70 (12k

trans/minute) Oracle Database (50Gb) Oracle 8.1.6 AIX 4.33.8

After Upgrade

Lawson 8.0.2 applications Lawson 7.3.3 environment Lawson 7.3.3 LID UNIX P660 (56k

trans/minute) Oracle Database (100Gb) Oracle 8.1.7 AIX 4.33.10

4444

 

Centura HealthProject Organization

• Project Sponsor

• Steering Committee

• Project Manager

• 3 Core Teams (Finance, MM, HR/Payroll)

• Lawson Project Manager

• Lawson Consultants

5555

Centura HealthLawson 8.x Project

Timeframe• Start Date: 10/25/01

• Differences Training: 11/28/01

• Application Exploration 12/20/01

• CRP 04/19/02

• System Test #1 08/23/02

• System Test #5 11/15/02

• Lawson 8.x Upgrade 01/13/03

6666

Task Hours Start EndCyclical 4 12:00 Fri 16:00 Fri

Verification tasks 1 16:00 Fri 17:00 FriSetup 1 17:00 Fri 18:00 Fri

Prejobs 1 18:00 Fri 19:00 FriUnloads 10 19:00 Fri 05:00 SatReorgs 4 05:00 Sat 09:00 SatLoads 17 09:00 Sat 02:00 Sun

Post jobs 4 02:00 Sun 06:00 SunPost Upgrade tasks 7 06:00 Sun 13:00 SunSystem Verification 7 13:00 Sun 20:00 Sun

56

Centura HealthLawson 8.x Conversion Weekend

7777

Centura HealthLawson 8.x Lessons Learned

Planning & Organization• Leadership commitment

• Evaluate hardware upgrades

• No Such thing as too much communication

• Evaluate Risk and re-visit it on a regular basis

• Huge user commitment that needs to be agreed upon upfront

8888

Centura HealthLawson 8.x Lessons Learned

(Cont.)Testing• If you have mods, evaluate need and

get rid of them

• Make sure your scripts are robust enough to test EVERYTHING

• Upgraded data

• Hand keyed data

• Interfaced data

• Verify that EVERYTHING is tested

• If at all possible: Your testing should be done on a different box

9999

Centura HealthLawson 8.x Lessons Learned

(Cont.)Testing (Cont.)

• I.T. should perform the System Upgrade process at least 3 times

• Stay on the same UIP from beginning to end

• All 3rd party reports (i.e. ReportSmith, Crystal, MS:Access) need to be converted and tested

• If you think you are finished testing, test again

10101010

Centura HealthLawson 8.x Lessons Learned

(Cont.)Implementation• Develop a detailed Cutover document

• Task list

• Screen prints

• 2 people teams

• Develop a Back out plan and make sure it works

• Arrange for Lawson support during implementation

11111111

Centura HealthLawson 8.x Lessons Learned

(Cont.)Post-Implementation support• You will have issues, count on it!

• Depending on your environment, you should have a plan for extended support

• Application of Lawson’s CTP’s (patches) should be coordinated within the I.T. dept.

12121212

Good Luck, You are going to need it!!!