CCC Commissioning
Django Manglunki, AB/OP
PS-SPS Days 18/1/2006
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 2
Outline
• Constraints and boundary limits
• Reminder of room and consoles layout
• Project status as of today
• Schedule/Resources for TI, PS complex, SPS, Cryogenics, LHC HWC
• Conclusions
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 3
Constraints and boundary limits• Restart of existing
accelerator chain and technical services
• TI operates 24/7
• LEIR early February
• LHC sector test mid-November
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 4
Room layout: 4 similar but not identical islets
~50 19”screens for controls, local fixed displays, administration and access on outer tables
4 large 46” screens for general purpose fixed displays
3 19”screens for laptops and mail/web on central tables
19” cabinet for rackable HW (access, intercom, beam inhibits, radiation alarms …)
5 IP-touch phones
1 colourprinter
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 5
Project status as of today• TS works finished except:
– Finishing paint (27/1)– Heating/AC (27/1?)– Blinds and lighting controls (20/1)– CCC Access control operational but administration needed
(cards distribution + EDH authorizations)
Picture January 16th 2006Simulation December 3rd 2004
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 6
Project status as of today (2)• CO works:
– Most hardware installed– Configuration in progress, TI islet will be delivered 19/1– Other islets to follow; end January 27th
• Video signals– Last HW delivery mid February– System operational end February
• Communications– All phones installed, operational– Server configuration started 13/1, finishing 27/1,
tests start with TI 30/1– SPS intercom February
• Fast analog signals– First HW batch delivered last week (11/1)– Observation of signals mid-April
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 7
Project status as of today (3)
• PS complex access– Configuration and test under way– Switch control from CSA on week-end
February 4-5 (LEIR starts February 6th!)– Radio protection alarms: Hardware being installed
• SPS Access– racks in 867 for configuration;move to CCC 20/1– Test access control from CCC 2nd fortnight March
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 8
Schedule/resources for TI
• CCC Cold checkout starts January 23rd
– Configure and test application programs– Configure and test room functions (lighting
and blinds controls…)– Configure and test communications (30-31/1)– Additional 2 TI technicians 8 hours/day
• Move in from MCR on February 1st
– 1 TI + 1 PS/PSB 24/7 until PS shifts start
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 9
Schedule/resources for PS complex• CCC Cold checkout starts February 13th
– Configure and test application programs– Configure and test communications– 2 PS/PSB technicians 8 hours/day– Until PS/PSB shifts start, access given by PSB
technician on TI shift• PS magnet tests start 20/2• PSB/PS closed 6/3
– PSB HW tests– Additional 2 PS/PSB tech 8 hours/day
• PS shifts start 20/3– 3 tech on shift 24/7– Only 1 TI tech
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 10
Schedule/resources for SPS• CCC Cold checkout starts March 6th
– Configure and test communications– Configure and test application programs– Test access control
• Give access only during working hours
– 2 SPS technicians 8 hours/day
• SPS shifts start 3/4 for HW tests– 2 tech on shift 24/7
• Request of SPS OP in February– for TI8/CNGS tests!
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 11
Schedule/resources for Cryogenics
• CCC Cold checkout starts March 6th in parallel with operations/tests from local control rooms– Configure and test application programs– Configure and test communications– 1 AT/ACR technician + 1 AB/CO 8 hours/day
• First operation from CCC expected in June
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 12
Schedule/resources for LHC HWC• CCC Cold checkout starts September 4th
– Test access control– Configure and test application programs– Configure and test communications– 3 LHC OP or EiC , 16 hours/day
• HWC gradually moves from FCR to CCC in October/November
• Sector test from CCC end November
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 13
Overall schedule January – April 2006
CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 14
Conclusion
• Good collaboration needed between all parts (AB/OP, AB/CO, TS/CSE, TS/EL, TS/CV, AT/ACR, TS/HDO, IT/CS…) for validation of CCC functionalities
• So far so good, February 1st is still the delivery date: 14 days to go!