CATEGORY 2 TOTALS - MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total No Current Total
$25,144,000 $5,088 $18,118 $1,136,013 $561,654 $743,229 $458,307 $460,366 $659,458 $8,183 $715,334 $453,847 $21,550 $260,935 $207,811 $1,443,240 $11,879 $0 $914,209 $143,216 $6,288,650 $146,225 $254,314 $705,268 $427,212 $1,056,550 $490,312 $238,964 $947,117 $420,875 $2,509,908 $9,238 $32,979 $1,443,404 $198,028 $1,009,944 $24,479 $432,200 $72,158 $15,153 $9,543,040 $59,632,456 $34,488,456
A A - SUBSTRUCTURE: Foundations $1,538,631 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,538,631 $0
A10 Foundations $316,805 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $316,805 $0A20 Basement Construction $1,221,826 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,221,826 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$4,052,320 $0 $0 $901,889 $556,295 $591,633 $159,797 $234,541 $505,508 $0 $237,889 $0 $0 $0 $201,437 $1,401,729 $0 $0 $867,747 $133,483 $2,069,927 $138,647 $227,259 $361,110 $299,169 $823,584 $240,972 $0 $766,051 $408,444 $1,663,839 $0 $0 $1,043,099 $188,225 $945,948 $0 $432,200 $0 $0 $2,985,435 $22,438,177 $18,385,857
B10 Superstructure $24,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,800 $0B20 Exterior Enclosure $2,506,912 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,506,912 $0B30 Roofing $1,520,608 $0 $0 $901,889 $556,295 $591,633 $159,797 $234,541 $505,508 $0 $237,889 $0 $0 $0 $201,437 $1,401,729 $0 $0 $867,747 $133,483 $2,069,927 $138,647 $227,259 $361,110 $299,169 $823,584 $240,972 $0 $766,051 $408,444 $1,663,839 $0 $0 $1,043,099 $188,225 $945,948 $0 $432,200 $0 $0 $2,985,435 $19,906,465 $18,385,857
CC - INTERIORS: Interior Construction and Interior Finishes
$2,140,310 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,140,310 $0
C10 C10 - Interior Construction $1,146,626 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,146,626 $0C20 C20 - Stairs $449,482 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $449,482 $0C30 C30 - Interior Finishes $544,202 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $544,202 $0D D - COMPONENTS $16,680,939 $5,088 $18,118 $234,124 $5,359 $151,596 $298,510 $225,824 $153,950 $8,183 $477,445 $453,847 $21,550 $260,935 $6,375 $41,511 $11,879 $0 $46,462 $9,733 $4,218,724 $7,578 $27,055 $344,158 $128,042 $232,966 $249,339 $238,964 $181,067 $12,431 $846,069 $9,238 $32,979 $400,305 $9,803 $63,996 $24,479 $0 $72,158 $15,153 $6,557,605 $32,783,539 $16,102,600
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$3,954,447 $5,088 $18,118 $51,881 $5,359 $34,900 $143,152 $0 $39,062 $8,183 $221,715 $453,847 $21,550 $72,987 $6,375 $41,511 $11,879 $0 $46,462 $9,733 $138,510 $7,578 $27,055 $91,854 $8,042 $52,499 $15,061 $0 $59,195 $12,431 $644,754 $9,238 $32,979 $111,970 $9,803 $63,996 $24,479 $0 $72,158 $15,153 $227,212 $6,770,217 $2,815,770
D30 HVAC $4,014,946 $0 $0 $182,242 $0 $116,696 $155,358 $225,824 $114,888 $0 $255,731 $0 $0 $187,948 $0 $0 $0 $0 $0 $0 $2,666,251 $0 $0 $252,304 $120,000 $180,467 $234,279 $238,964 $121,872 $0 $181,136 $0 $0 $288,335 $0 $0 $0 $0 $0 $0 $4,185,498 $13,722,740 $9,707,794D50 Electrical (incl D51) $8,711,546 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,413,963 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,179 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,144,895 $12,290,582 $3,579,036
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$731,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $731,800 $0
G Sitework $731,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $731,800 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Category 2 - SUMMARY ALL
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$28,880 $0 $0 $76,110 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,952 $0 $0 $0 $0 $0 $0 $186,145 $0 $0 $7,490 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,131 $0 $0 $0 $0 $0 $0 $301,556 $615,264
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$9,100 $0 $0 $71,106 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $95,498 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $149,043 $324,746
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $9,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,100B30 Roofing $0 $0 $0 $71,106 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $95,498 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $149,043 $315,646
C C - INTERIORS: Interior Construction and Interior Finishes
$6,280 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,280
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $6,280 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,280C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $5,000 $0 $0 $5,004 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,952 $0 $0 $0 $0 $0 $0 $90,648 $0 $0 $7,490 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,131 $0 $0 $0 $0 $0 $0 $152,514 $275,738
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$0 $0 $0 $5,004 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,952 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,490 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,131 $0 $0 $0 $0 $0 $0 $11,040 $38,617
D30 HVAC $5,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $71,548 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $111,665 $188,213D50 Electrical (incl D51) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $29,809 $48,908
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$8,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,500
G Sitework $8,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,500
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE ZONE 02 - B108Size: 5,414 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$855,977 $0 $0 $0 $0 $5,180 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,162 $0 $0 $0 $0 $73,568 $0 $0 $0 $0 $7,793 $0 $0 $0 $142,068 $0 $0 $0 $0 $0 $9,499 $0 $0 $0 $0 $293,669 $1,393,917
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $142,068 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $142,068
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $142,068 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $142,068
C C - INTERIORS: Interior Construction and Interior Finishes
$54,964 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $54,964
C10 C10 - Interior Construction $4,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,500C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $50,464 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,464D D - COMPONENTS $796,063 $0 $0 $0 $0 $5,180 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,162 $0 $0 $0 $0 $73,568 $0 $0 $0 $0 $7,793 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,499 $0 $0 $0 $0 $293,669 $1,191,935
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$250,797 $0 $0 $0 $0 $5,180 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,162 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,793 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,499 $0 $0 $0 $0 $0 $279,432
D30 HVAC $253,522 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,733 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $198,724 $464,979D50 Electrical (incl D51) $291,744 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,835 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $94,946 $447,525
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$4,950 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,950
G Sitework $4,950 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,950
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 14 - B110Size: 17,262 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$2,091,410 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,648 $0 $0 $0 $0 $0 $0 $0 $0 $0 $680,946 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,062,750 $3,845,755
A A - SUBSTRUCTURE: Foundations $700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $700
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $700
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$338,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $415,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $649,164 $1,403,358
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $44,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $44,250B30 Roofing $294,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $415,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $649,164 $1,359,108
C C - INTERIORS: Interior Construction and Interior Finishes
$126,438 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $126,438
C10 C10 - Interior Construction $42,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $42,000C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $84,438 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $84,438D D - COMPONENTS $1,626,022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,648 $0 $0 $0 $0 $0 $0 $0 $0 $0 $265,001 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $413,587 $2,315,258
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$499,129 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,648 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,665 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,766 $542,208
D30 HVAC $335,628 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $152,796 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $238,468 $726,892D50 Electrical (incl D51) $791,265 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,540 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $155,352 $1,046,157
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F20Selective Building Demolition $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 24 - B111Size: 28,146 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$981,151 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $358,130 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $521,658 $1,875,943
A A - SUBSTRUCTURE: Foundations $4,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,500
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $4,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,500
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$183,340 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $212,217 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $331,206 $726,763
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $31,580 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,580B30 Roofing $151,760 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $212,217 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $331,206 $695,183
C C - INTERIORS: Interior Construction and Interior Finishes
$158,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,900
C10 C10 - Interior Construction $158,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,900C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $592,411 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $145,913 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $190,452 $943,780
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$168,211 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $201,329
D30 HVAC $244,084 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $497,681D50 Electrical (incl D51) $180,116 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $39,805 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,849 $244,770
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$42,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $42,000
G Sitework $42,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $42,000
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MEDIC 03/ARSON/POLICE ZONE 6 - B112Size: 11,254 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$762,780 $0 $0 $0 $0 $7,634 $0 $0 $0 $0 $5,471 $0 $0 $0 $0 $0 $0 $0 $0 $0 $327,924 $0 $0 $0 $0 $65,624 $0 $0 $0 $0 $8,332 $0 $0 $0 $0 $0 $0 $0 $0 $0 $511,790 $1,689,557
A A - SUBSTRUCTURE: Foundations $118,126 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $118,126
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $118,126 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $118,126
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $282,956 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $441,608 $924,564
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $282,956 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $441,608 $924,564
C C - INTERIORS: Interior Construction and Interior Finishes
$55,550 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $55,550
C10 C10 - Interior Construction $4,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,500C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $51,050 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $51,050D D - COMPONENTS $386,404 $0 $0 $0 $0 $7,634 $0 $0 $0 $0 $5,471 $0 $0 $0 $0 $0 $0 $0 $0 $0 $44,969 $0 $0 $0 $0 $65,624 $0 $0 $0 $0 $8,332 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,183 $588,618
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$101,766 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,471 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,508 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,332 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,157 $132,235
D30 HVAC $34,150 $0 $0 $0 $0 $7,634 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,624 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $107,409D50 Electrical (incl D51) $250,488 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $38,461 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,026 $348,974
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$2,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,700
G Sitework $2,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,700
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 8 - B114Size: 20,874 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$1,063,271 $0 $0 $0 $0 $0 $99,873 $0 $0 $0 $246,631 $0 $0 $0 $0 $0 $0 $0 $0 $0 $66,523 $0 $0 $0 $0 $328,121 $150,608 $0 $0 $0 $13,314 $0 $0 $0 $0 $0 $0 $0 $0 $0 $545,430 $2,513,771
A A - SUBSTRUCTURE: Foundations $215,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $215,500
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $215,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $215,500
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$97,121 $0 $0 $0 $0 $0 $0 $0 $0 $0 $237,889 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $328,121 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $441,608 $1,104,739
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $97,121 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $97,121B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $237,889 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $328,121 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $441,608 $1,007,618
C C - INTERIORS: Interior Construction and Interior Finishes
$158,650 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,650
C10 C10 - Interior Construction $158,650 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,650C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $567,790 $0 $0 $0 $0 $0 $99,873 $0 $0 $0 $8,742 $0 $0 $0 $0 $0 $0 $0 $0 $0 $66,523 $0 $0 $0 $0 $0 $150,608 $0 $0 $0 $13,314 $0 $0 $0 $0 $0 $0 $0 $0 $0 $103,822 $1,010,672
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$221,707 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,742 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,399 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,314 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,229 $270,391
D30 HVAC $123,008 $0 $0 $0 $0 $0 $99,873 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,608 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $373,489D50 Electrical (incl D51) $223,075 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $56,124 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $87,593 $366,792
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$24,210 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,210
G Sitework $24,210 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,210
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE ZONE 04/FIREHOUSE 18 - B115Size: 15,868 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$610,392 $0 $10,871 $0 $0 $0 $0 $165,981 $9,191 $0 $0 $0 $12,930 $0 $0 $0 $0 $0 $10,932 $0 $108,011 $0 $243,492 $0 $0 $0 $0 $0 $13,928 $0 $0 $0 $19,788 $0 $0 $0 $0 $305,861 $16,978 $0 $168,573 $1,696,928
A A - SUBSTRUCTURE: Foundations $500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$41,030 $0 $0 $0 $0 $0 $0 $165,981 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $227,259 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $305,861 $0 $0 $0 $740,131
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $40,030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,030B30 Roofing $1,000 $0 $0 $0 $0 $0 $0 $165,981 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $227,259 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $305,861 $0 $0 $0 $700,101
C C - INTERIORS: Interior Construction and Interior Finishes
$27,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $27,200
C10 C10 - Interior Construction $23,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $23,600C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $3,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,600D D - COMPONENTS $397,482 $0 $10,871 $0 $0 $0 $0 $0 $9,191 $0 $0 $0 $12,930 $0 $0 $0 $0 $0 $10,932 $0 $108,011 $0 $16,233 $0 $0 $0 $0 $0 $13,928 $0 $0 $0 $19,788 $0 $0 $0 $0 $0 $16,978 $0 $168,573 $784,917
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$115,462 $0 $10,871 $0 $0 $0 $0 $0 $9,191 $0 $0 $0 $12,930 $0 $0 $0 $0 $0 $10,932 $0 $0 $0 $16,233 $0 $0 $0 $0 $0 $13,928 $0 $0 $0 $19,788 $0 $0 $0 $0 $0 $16,978 $0 $0 $226,313
D30 HVAC $144,622 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $398,219D50 Electrical (incl D51) $137,398 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,977 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,010 $160,385
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$144,180 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $144,180
G Sitework $144,180 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $144,180
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 03 - B117Size: 6,345 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$1,543,343 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,771 $0 $893,864 $0 $0 $0 $0 $242,733 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $1,248,131 $0 $0 $13,456 $0 $0 $0 $0 $0 $0 $378,833 $4,347,544
A A - SUBSTRUCTURE: Foundations $250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$126,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $893,864 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,248,131 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,267,995
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $126,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $126,000B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $893,864 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,248,131 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,141,995
CC - INTERIORS: Interior Construction and Interior Finishes
$107,098 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $107,098
C10 C10 - Interior Construction $15,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,000C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $92,098 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $92,098D D - COMPONENTS $1,041,773 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,771 $0 $0 $0 $0 $0 $0 $242,733 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,456 $0 $0 $0 $0 $0 $0 $378,833 $1,703,979
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$355,447 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,771 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,456 $0 $0 $0 $0 $0 $0 $0 $396,086
D30 HVAC $316,616 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $149,966 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $234,052 $700,635D50 Electrical (incl D51) $369,710 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $92,767 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $144,781 $607,258
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$18,472 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,472
G Sitework $18,472 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,472
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 04 - B118Size: 26,228 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$278,719 $0 $0 $5,267 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $252,237 $0 $0 $7,884 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $393,666 $953,650
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$85,390 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $161,815 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $252,545 $499,750
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $3,040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,040B30 Roofing $82,350 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $161,815 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $252,545 $496,710
C C - INTERIORS: Interior Construction and Interior Finishes
$500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500
C10 C10 - Interior Construction $500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $189,779 $0 $0 $5,267 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $90,422 $0 $0 $7,884 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $141,121 $450,350
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$3,950 $0 $0 $5,267 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,884 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $0 $32,978
D30 HVAC $90,572 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $271,713D50 Electrical (incl D51) $95,257 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,683 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,719 $145,659
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$3,050 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,050
G Sitework $3,050 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,050
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE ACCIDENT INVESTIGATION/SWAT - B119
Size: 5,565 SFTOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$302,305 $0 $0 $142,212 $0 $0 $55,485 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $177,649 $0 $22,470 $0 $0 $7,884 $0 $0 $83,671 $0 $0 $0 $0 $0 $0 $259,501 $0 $0 $0 $0 $0 $0 $35,069 $1,092,512
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$27,500 $0 $0 $136,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $177,649 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $249,890 $0 $0 $0 $0 $0 $0 $0 $591,984
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $27,500 $0 $0 $136,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $177,649 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $249,890 $0 $0 $0 $0 $0 $0 $0 $591,984
CC - INTERIORS: Interior Construction and Interior Finishes
$350 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $350
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $350 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $350D D - COMPONENTS $246,980 $0 $0 $5,267 $0 $0 $55,485 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $22,470 $0 $0 $7,884 $0 $0 $83,671 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $35,069 $472,703
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$1,250 $0 $0 $5,267 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,884 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $0 $30,278
D30 HVAC $60,633 $0 $0 $0 $0 $0 $55,485 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $83,671 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $199,789D50 Electrical (incl D51) $185,097 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,470 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,069 $242,636
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$27,475 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $27,475
G Sitework $27,475 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $27,475
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 06 - B120Size: 6,353 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$914,002 $0 $0 $0 $80,389 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $136,604 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,327 $0 $0 $0 $0 $0 $0 $0 $0 $0 $213,197 $1,625,467
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$116,225 $0 $0 $0 $80,389 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $196,614
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $114,150 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,150B30 Roofing $2,075 $0 $0 $0 $80,389 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $82,464
C C - INTERIORS: Interior Construction and Interior Finishes
$258,660 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $258,660
C10 C10 - Interior Construction $258,660 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $258,660C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $507,717 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $136,604 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,327 $0 $0 $0 $0 $0 $0 $0 $0 $0 $213,197 $1,138,792
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$152,386 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,327 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $451,774
D30 HVAC $165,890 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $419,487D50 Electrical (incl D51) $189,441 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,496 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $47,594 $267,531
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$31,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,400
G Sitework $31,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,400
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 07 - B121Size: 8,622 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$368,245 $0 $7,247 $0 $102,898 $0 $0 $0 $0 $0 $0 $0 $8,620 $0 $0 $0 $0 $0 $0 $133,483 $90,192 $0 $10,822 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,192 $0 $188,225 $0 $0 $0 $0 $0 $140,763 $1,063,687
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$15,790 $0 $0 $0 $102,898 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $133,483 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $188,225 $0 $0 $0 $0 $0 $0 $440,396
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $15,790 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,790B30 Roofing $0 $0 $0 $0 $102,898 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $133,483 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $188,225 $0 $0 $0 $0 $0 $0 $424,606
C C - INTERIORS: Interior Construction and Interior Finishes
$16,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,900
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $16,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,900D D - COMPONENTS $328,455 $0 $7,247 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,620 $0 $0 $0 $0 $0 $0 $0 $90,192 $0 $10,822 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,192 $0 $0 $0 $0 $0 $0 $0 $140,763 $599,290
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$101,925 $0 $7,247 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,620 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,822 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,192 $0 $0 $0 $0 $0 $0 $0 $0 $141,806
D30 HVAC $123,160 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $304,301D50 Electrical (incl D51) $103,370 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,453 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,361 $153,184
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$7,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,100
G Sitework $7,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,100
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 10/MEDIC 5 - B122Size: 5,500 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$99,308 $0 $0 $140,105 $5,359 $0 $0 $124,203 $0 $0 $0 $0 $0 $0 $6,375 $0 $0 $0 $181,749 $0 $15,761 $0 $0 $0 $8,042 $0 $0 $85,344 $0 $0 $20,179 $0 $0 $255,657 $9,803 $0 $0 $0 $0 $0 $0 $951,885
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$0 $0 $0 $140,105 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $181,749 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $255,657 $0 $0 $0 $0 $0 $0 $0 $577,511
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $0 $0 $0 $140,105 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $181,749 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $255,657 $0 $0 $0 $0 $0 $0 $0 $577,511
C C - INTERIORS: Interior Construction and Interior Finishes
$24,508 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,508
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $24,508 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,508D D - COMPONENTS $55,700 $0 $0 $0 $5,359 $0 $0 $124,203 $0 $0 $0 $0 $0 $0 $6,375 $0 $0 $0 $0 $0 $15,761 $0 $0 $0 $8,042 $0 $0 $85,344 $0 $0 $20,179 $0 $0 $0 $9,803 $0 $0 $0 $0 $0 $0 $330,766
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$0 $0 $0 $0 $5,359 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,375 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,803 $0 $0 $0 $0 $0 $0 $29,579
D30 HVAC $0 $0 $0 $0 $0 $0 $0 $124,203 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $85,344 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $209,548D50 Electrical (incl D51) $55,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,761 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,179 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $91,639
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$19,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,100
G Sitework $19,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,100
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MEDIC 09/RESCUE 1 - B123Size: 4,456 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$918,101 $5,088 $0 $0 $0 $0 $159,797 $0 $0 $0 $0 $6,051 $0 $0 $0 $0 $0 $0 $0 $0 $96,470 $7,578 $0 $0 $0 $0 $240,972 $0 $0 $0 $0 $9,238 $0 $0 $0 $0 $0 $0 $0 $0 $150,561 $1,593,856
A A - SUBSTRUCTURE: Foundations $290,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $290,000
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $290,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $290,000
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$191,450 $0 $0 $0 $0 $0 $159,797 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $240,972 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $592,219
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $191,450 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $191,450B30 Roofing $0 $0 $0 $0 $0 $0 $159,797 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $240,972 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $400,769
C C - INTERIORS: Interior Construction and Interior Finishes
$12,740 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,740
C10 C10 - Interior Construction $10,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,100C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $2,640 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,640D D - COMPONENTS $416,411 $5,088 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,051 $0 $0 $0 $0 $0 $0 $0 $0 $96,470 $7,578 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,238 $0 $0 $0 $0 $0 $0 $0 $0 $150,561 $691,397
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$124,819 $5,088 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,051 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,578 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,238 $0 $0 $0 $0 $0 $0 $0 $0 $0 $152,774
D30 HVAC $166,794 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $347,935D50 Electrical (incl D51) $124,798 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,731 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,159 $190,688
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$7,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,500
G Sitework $7,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,500
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 13 - B125Size: 7,275 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$554,844 $0 $0 $0 $0 $0 $0 $0 $5,744 $0 $0 $0 $0 $0 $0 $113,507 $0 $0 $6,833 $0 $120,822 $0 $0 $0 $0 $0 $0 $0 $8,705 $0 $158,494 $0 $0 $0 $0 $0 $0 $0 $10,611 $0 $188,567 $1,168,128
A A - SUBSTRUCTURE: Foundations $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$1,925 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $113,507 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,494 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $273,927
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $1,925 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,925B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $113,507 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,494 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $272,002
C C - INTERIORS: Interior Construction and Interior Finishes
$77,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $77,000
C10 C10 - Interior Construction $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,000C20 C20 - Stairs $12,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,000C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $369,279 $0 $0 $0 $0 $0 $0 $0 $5,744 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,833 $0 $120,822 $0 $0 $0 $0 $0 $0 $0 $8,705 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,611 $0 $188,567 $710,561
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$93,120 $0 $0 $0 $0 $0 $0 $0 $5,744 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,833 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,705 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,611 $0 $0 $125,014
D30 HVAC $132,020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $385,617D50 Electrical (incl D51) $144,139 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $21,788 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $34,004 $199,930
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$6,640 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,640
G Sitework $6,640 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,640
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 15 - B126Size: 6,160 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
` 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$696,002 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $201,070 $0 $0 $0 $0 $170,368 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $309,983 $0 $0 $0 $0 $265,892 $1,658,319
A A - SUBSTRUCTURE: Foundations $130,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $130,000
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $130,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $130,000
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$4,875 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $201,070 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $309,983 $0 $0 $0 $0 $0 $515,928
B10 Superstructure $500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500B20 Exterior Enclosure $375 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $375B30 Roofing $4,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $201,070 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $309,983 $0 $0 $0 $0 $0 $515,053
C C - INTERIORS: Interior Construction and Interior Finishes
$150 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $150 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150D D - COMPONENTS $560,977 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $170,368 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $265,892 $1,012,241
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$206,412 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $239,530
D30 HVAC $140,736 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $127,330 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $198,724 $466,790D50 Electrical (incl D51) $213,829 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,964 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $56,128 $305,921
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 17 - B128Size: 10,168 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$245,663 $0 $0 $0 $0 $5,453 $0 $56,456 $0 $0 $0 $0 $0 $0 $0 $15,567 $0 $0 $136,653 $0 $14,353 $0 $0 $0 $0 $8,203 $0 $85,344 $0 $0 $0 $0 $0 $0 $0 $23,999 $0 $0 $0 $0 $22,401 $614,092
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$9,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,081 $0 $0 $136,653 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,999 $0 $0 $0 $0 $0 $169,633
B10 Superstructure $7,550 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,550B20 Exterior Enclosure $2,350 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,350B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,081 $0 $0 $136,653 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,999 $0 $0 $0 $0 $0 $159,733
C C - INTERIORS: Interior Construction and Interior Finishes
$21,978 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $21,978
C10 C10 - Interior Construction $20,478 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,478C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $1,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500D D - COMPONENTS $207,785 $0 $0 $0 $0 $5,453 $0 $56,456 $0 $0 $0 $0 $0 $0 $0 $6,486 $0 $0 $0 $0 $14,353 $0 $0 $0 $0 $8,203 $0 $85,344 $0 $0 $0 $0 $0 $0 $0 $9,999 $0 $0 $0 $0 $22,401 $416,481
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$73,735 $0 $0 $0 $0 $5,453 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,486 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,203 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,999 $0 $0 $0 $0 $0 $103,877
D30 HVAC $55,776 $0 $0 $0 $0 $0 $0 $56,456 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $85,344 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $197,576D50 Electrical (incl D51) $78,274 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,353 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,401 $115,027
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$6,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,000
G Sitework $6,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,000
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 19 - B129Size: 4,058 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$395,266 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $90,806 $0 $0 $0 $0 $97,779 $0 $0 $0 $0 $0 $0 $0 $0 $0 $135,852 $0 $0 $0 $0 $0 $0 $0 $0 $0 $152,603 $878,253
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$97,320 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,806 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $126,795 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $314,921
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $9,120 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,120B30 Roofing $88,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,806 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $126,795 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $305,801
C C - INTERIORS: Interior Construction and Interior Finishes
$26,130 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $26,130
C10 C10 - Interior Construction $25,980 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,980C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $150 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150D D - COMPONENTS $235,656 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $97,779 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $152,603 $501,042
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$17,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $51,018
D30 HVAC $121,445 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $302,586D50 Electrical (incl D51) $96,311 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,966 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,161 $147,438
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$36,160 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $36,160
G Sitework $36,160 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $36,160
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 20/MEDIC 12 - B130Size: 5,645 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$603,133 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,771 $0 $93,400 $0 $0 $0 $0 $85,463 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $130,418 $0 $0 $13,456 $0 $0 $0 $0 $0 $0 $133,382 $1,086,436
A A - SUBSTRUCTURE: Foundations $1,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500
A10 Foundations $1,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$223,030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $93,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $130,418 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $446,848
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $151,030 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $151,030B30 Roofing $72,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $93,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $130,418 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $295,818
C C - INTERIORS: Interior Construction and Interior Finishes
$30,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,000
C10 C10 - Interior Construction $25,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,000C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $5,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000D D - COMPONENTS $299,083 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,771 $0 $0 $0 $0 $0 $0 $85,463 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,456 $0 $0 $0 $0 $0 $0 $133,382 $558,567
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$86,636 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,771 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,456 $0 $0 $0 $0 $0 $0 $0 $127,275
D30 HVAC $108,870 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $290,011D50 Electrical (incl D51) $103,577 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,724 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,980 $141,281
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$49,520 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $49,520
G Sitework $49,520 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $49,520
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MEDIC 08 - B131Size: 4,163 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$795,050 $0 $0 $17,908 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $96,559 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,699 $1,081,221
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$449,400 $0 $0 $17,908 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $467,308
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $439,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $439,400B30 Roofing $10,000 $0 $0 $17,908 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $27,908
C C - INTERIORS: Interior Construction and Interior Finishes
$6,050 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,050
C10 C10 - Interior Construction $1,050 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,050C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $5,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000D D - COMPONENTS $339,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $96,559 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,699 $607,863
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$107,275 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,903 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,456 $153,640
D30 HVAC $113,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $295,041D50 Electrical (incl D51) $118,425 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,916 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,840 $159,182
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 22 - B132Size: 4,500 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$780,399 $0 $0 $0 $0 $163,592 $4,439 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,280 $0 $0 $0 $346,196 $0 $0 $0 $0 $0 $6,694 $0 $0 $0 $0 $0 $0 $0 $0 $299,983 $8,160 $0 $0 $0 $209,101 $1,823,844
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$159,969 $0 $0 $0 $0 $163,592 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $212,217 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $299,983 $0 $0 $0 $0 $0 $835,762
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $34,969 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $34,969B30 Roofing $125,000 $0 $0 $0 $0 $163,592 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $212,217 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $299,983 $0 $0 $0 $0 $0 $800,793
C C - INTERIORS: Interior Construction and Interior Finishes
$68,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $68,100
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $68,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $68,100D D - COMPONENTS $547,210 $0 $0 $0 $0 $0 $4,439 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,280 $0 $0 $0 $133,979 $0 $0 $0 $0 $0 $6,694 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,160 $0 $0 $0 $209,101 $914,863
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$181,885 $0 $0 $0 $0 $0 $4,439 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,280 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,694 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,160 $0 $0 $0 $0 $206,457
D30 HVAC $178,710 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $432,307D50 Electrical (incl D51) $186,615 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $34,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $54,539 $276,099
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$5,120 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,120
G Sitework $5,120 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,120
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 23 - B133Size: 9,880 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$550,110 $0 $0 $0 $0 $0 $0 $45,165 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $34,779 $0 $0 $0 $0 $0 $0 $68,275 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $54,279 $773,614
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$35,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,200
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $35,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,200B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
C C - INTERIORS: Interior Construction and Interior Finishes
$162,730 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $162,730
C10 C10 - Interior Construction $5,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,250C20 C20 - Stairs $154,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,800C30 C30 - Interior Finishes $2,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,680D D - COMPONENTS $342,580 $0 $0 $0 $0 $0 $0 $45,165 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $34,779 $0 $0 $0 $0 $0 $0 $68,275 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $54,279 $566,084
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$133,454 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,903 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,456 $179,819
D30 HVAC $87,050 $0 $0 $0 $0 $0 $0 $45,165 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $68,275 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,490D50 Electrical (incl D51) $122,076 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,875 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $38,823 $185,774
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$9,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,600
G Sitework $9,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,600
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 26 - B135Size: 7,033 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$556,164 $0 $0 $0 $0 $0 $0 $0 $8,042 $0 $0 $0 $0 $0 $201,437 $0 $0 $0 $9,566 $0 $140,891 $0 $0 $0 $0 $0 $0 $0 $12,187 $266,377 $0 $0 $0 $0 $0 $0 $0 $0 $14,856 $0 $219,888 $1,429,407
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $201,437 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $266,377 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $467,814
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $201,437 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $266,377 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $467,814
C C - INTERIORS: Interior Construction and Interior Finishes
$17,660 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,660
C10 C10 - Interior Construction $7,160 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,160C20 C20 - Stairs $900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900C30 C30 - Interior Finishes $9,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,600D D - COMPONENTS $535,504 $0 $0 $0 $0 $0 $0 $0 $8,042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,566 $0 $140,891 $0 $0 $0 $0 $0 $0 $0 $12,187 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,856 $0 $219,888 $940,933
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$194,579 $0 $0 $0 $0 $0 $0 $0 $8,042 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,566 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,187 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,856 $0 $0 $239,230
D30 HVAC $116,138 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $369,735D50 Electrical (incl D51) $224,787 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $41,856 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,325 $331,968
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$3,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000
G Sitework $3,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 27 - B136Size: 11,834 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$858,655 $0 $0 $0 $0 $175,589 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $370,958 $0 $0 $0 $0 $0 $0 $0 $0 $0 $232,760 $0 $0 $0 $0 $321,982 $0 $0 $0 $0 $223,459 $2,191,730
A A - SUBSTRUCTURE: Foundations $2,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,500
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $2,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,500
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$355,942 $0 $0 $0 $0 $175,589 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $227,779 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $321,982 $0 $0 $0 $0 $0 $1,081,293
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $351,260 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $351,260B30 Roofing $4,682 $0 $0 $0 $0 $175,589 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $227,779 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $321,982 $0 $0 $0 $0 $0 $730,033
C C - INTERIORS: Interior Construction and Interior Finishes
$14,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,250
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $14,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,250D D - COMPONENTS $483,763 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $143,179 $0 $0 $0 $0 $0 $0 $0 $0 $0 $232,760 $0 $0 $0 $0 $0 $0 $0 $0 $0 $223,459 $1,091,487
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$170,486 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $232,760 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,768 $442,366
D30 HVAC $136,746 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $390,343D50 Electrical (incl D51) $176,531 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $32,119 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,128 $258,778
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$2,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,200
G Sitework $2,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,200
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 28 - B137Size: 9,081 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$412,465 $0 $0 $0 $0 $0 $0 $0 $10,340 $0 $107,050 $0 $0 $0 $0 $0 $0 $0 $12,299 $0 $210,229 $0 $0 $0 $0 $0 $0 $0 $15,669 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,101 $0 $328,104 $1,115,256
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$57,890 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $89,131 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $139,106 $286,128
B10 Superstructure $12,850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,850B20 Exterior Enclosure $3,040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,040B30 Roofing $42,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $89,131 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $139,106 $270,238
C C - INTERIORS: Interior Construction and Interior Finishes
$158,190 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,190
C10 C10 - Interior Construction $63,890 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $63,890C20 C20 - Stairs $60,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,700C30 C30 - Interior Finishes $33,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $33,600D D - COMPONENTS $195,305 $0 $0 $0 $0 $0 $0 $0 $10,340 $0 $107,050 $0 $0 $0 $0 $0 $0 $0 $12,299 $0 $121,098 $0 $0 $0 $0 $0 $0 $0 $15,669 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,101 $0 $188,997 $669,859
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$0 $0 $0 $0 $0 $0 $0 $0 $10,340 $0 $107,050 $0 $0 $0 $0 $0 $0 $0 $12,299 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,669 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,101 $0 $0 $164,459
D30 HVAC $90,455 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $344,052D50 Electrical (incl D51) $104,850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $22,063 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $34,434 $161,348
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$1,080 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,080
G Sitework $1,080 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,080
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 30 - B138Size: 6,240 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$404,072 $0 $0 $103,762 $0 $0 $0 $0 $114,888 $0 $0 $0 $0 $10,650 $0 $0 $0 $0 $122,988 $0 $27,641 $0 $0 $13,404 $0 $0 $0 $0 $121,872 $0 $0 $0 $0 $189,340 $0 $0 $0 $0 $0 $0 $43,140 $1,151,757
A A - SUBSTRUCTURE: Foundations $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$102,840 $0 $0 $94,808 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $122,988 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $173,001 $0 $0 $0 $0 $0 $0 $0 $493,637
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $94,340 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $94,340B30 Roofing $8,500 $0 $0 $94,808 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $122,988 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $173,001 $0 $0 $0 $0 $0 $0 $0 $399,297
C C - INTERIORS: Interior Construction and Interior Finishes
$31,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,100
C10 C10 - Interior Construction $12,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,600C20 C20 - Stairs $10,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000C30 C30 - Interior Finishes $8,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,500D D - COMPONENTS $195,132 $0 $0 $8,954 $0 $0 $0 $0 $114,888 $0 $0 $0 $0 $10,650 $0 $0 $0 $0 $0 $0 $27,641 $0 $0 $13,404 $0 $0 $0 $0 $121,872 $0 $0 $0 $0 $16,339 $0 $0 $0 $0 $0 $0 $43,140 $552,020
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$94,713 $0 $0 $8,954 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,650 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,404 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,339 $0 $0 $0 $0 $0 $0 $0 $144,060
D30 HVAC $7,500 $0 $0 $0 $0 $0 $0 $0 $114,888 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $121,872 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $244,260D50 Electrical (incl D51) $92,919 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $27,641 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $43,140 $163,700
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 31 - B139Size: 7,815 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$328,793 $0 $0 $69,526 $0 $0 $0 $0 $0 $0 $0 $60,513 $0 $11,277 $0 $0 $0 $0 $0 $0 $143,331 $0 $0 $118,267 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,300 $0 $0 $0 $0 $0 $0 $223,696 $972,704
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$10,140 $0 $0 $69,526 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $104,075 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $183,741
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $9,340 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,340B30 Roofing $800 $0 $0 $69,526 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $104,075 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $174,401
C C - INTERIORS: Interior Construction and Interior Finishes
$2,384 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,384
C10 C10 - Interior Construction $2,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,000C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $384 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $384D D - COMPONENTS $309,619 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,513 $0 $11,277 $0 $0 $0 $0 $0 $0 $143,331 $0 $0 $14,192 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,300 $0 $0 $0 $0 $0 $0 $223,696 $779,929
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$3,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,513 $0 $11,277 $0 $0 $0 $0 $0 $0 $0 $0 $0 $14,192 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,300 $0 $0 $0 $0 $0 $0 $0 $106,532
D30 HVAC $131,056 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $384,653D50 Electrical (incl D51) $175,313 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $44,297 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $69,134 $288,743
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$6,650 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,650
G Sitework $6,650 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,650
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 32 - B140Size: 12,525 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$595,718 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $136,728 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $213,390 $960,840
A A - SUBSTRUCTURE: Foundations $102,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $102,000
A10 Foundations $102,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $102,000A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$9,540 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,540
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $9,540 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,540B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
C C - INTERIORS: Interior Construction and Interior Finishes
$8,184 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,184
C10 C10 - Interior Construction $8,184 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,184C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $475,144 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $136,728 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $213,390 $840,266
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$148,879 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $181,997
D30 HVAC $143,997 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $397,594D50 Electrical (incl D51) $182,268 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,619 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $47,787 $260,675
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $850
G Sitework $850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $850
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 34 (ENGINE) - B141Size: 8,657 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$359,809 $0 $0 $105,342 $0 $0 $0 $0 $5,744 $0 $0 $121,026 $0 $0 $0 $0 $0 $0 $6,833 $0 $97,570 $0 $0 $157,690 $0 $0 $0 $0 $8,705 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,611 $0 $152,277 $1,025,609
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$108,896 $0 $0 $105,342 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $157,690 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $371,928
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $89,646 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $89,646B30 Roofing $19,250 $0 $0 $105,342 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $157,690 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $282,282
C C - INTERIORS: Interior Construction and Interior Finishes
$76,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $76,700
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $67,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $67,800C30 C30 - Interior Finishes $8,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,900D D - COMPONENTS $172,613 $0 $0 $0 $0 $0 $0 $0 $5,744 $0 $0 $121,026 $0 $0 $0 $0 $0 $0 $6,833 $0 $97,570 $0 $0 $0 $0 $0 $0 $0 $8,705 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,611 $0 $152,277 $575,380
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$350 $0 $0 $0 $0 $0 $0 $0 $5,744 $0 $0 $121,026 $0 $0 $0 $0 $0 $0 $6,833 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,705 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,611 $0 $0 $153,270
D30 HVAC $46,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,739 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $227,741D50 Electrical (incl D51) $125,663 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $26,831 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $41,875 $194,370
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$1,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,600
G Sitework $1,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,600
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 35 - B142Size: 7,585 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$714,041 $0 $0 $0 $173,641 $0 $0 $0 $0 $0 $8,921 $0 $0 $0 $0 $0 $0 $0 $0 $0 $176,069 $0 $0 $0 $0 $265,778 $0 $0 $0 $0 $13,585 $0 $0 $0 $0 $0 $0 $0 $0 $0 $274,791 $1,626,826
A A - SUBSTRUCTURE: Foundations $1,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,800
A10 Foundations $1,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,800A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$153,388 $0 $0 $0 $173,641 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $265,778 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $592,807
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $153,388 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $153,388B30 Roofing $0 $0 $0 $0 $173,641 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $265,778 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $439,419
C C - INTERIORS: Interior Construction and Interior Finishes
$28,008 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $28,008
C10 C10 - Interior Construction $28,008 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $28,008C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $523,445 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,921 $0 $0 $0 $0 $0 $0 $0 $0 $0 $176,069 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,585 $0 $0 $0 $0 $0 $0 $0 $0 $0 $274,791 $996,811
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$190,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,921 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,611 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,585 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,560 $240,622
D30 HVAC $120,485 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $127,330 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $198,724 $446,539D50 Electrical (incl D51) $212,015 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $38,128 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $59,507 $309,650
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$7,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,400
G Sitework $7,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,400
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 37 - B144Size: 10,780 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$261,761 $0 $0 $0 $0 $152,686 $0 $0 $0 $0 $5,947 $145,231 $0 $0 $0 $0 $0 $0 $0 $0 $164,082 $0 $0 $0 $0 $229,685 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $256,083 $1,224,533
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$27,750 $0 $0 $0 $0 $152,686 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $229,685 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $410,121
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $27,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $27,750B30 Roofing $0 $0 $0 $0 $0 $152,686 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $229,685 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $382,371
C C - INTERIORS: Interior Construction and Interior Finishes
$7,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,500
C10 C10 - Interior Construction $7,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,500C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $220,511 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $145,231 $0 $0 $0 $0 $0 $0 $0 $0 $164,082 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $256,083 $800,912
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$3,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $145,231 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $182,149
D30 HVAC $100,323 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $127,330 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $198,724 $426,377D50 Electrical (incl D51) $116,388 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $29,679 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $46,319 $192,386
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$6,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,000
G Sitework $6,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,000
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 38 - B145Size: 8,391 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$210,883 $0 $0 $81,114 $0 $0 $0 $0 $0 $0 $154,628 $0 $0 $0 $0 $0 $0 $0 $105,223 $0 $26,145 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,625 $0 $0 $148,012 $0 $0 $0 $0 $0 $0 $40,805 $866,434
A A - SUBSTRUCTURE: Foundations $32,760 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $32,760
A10 Foundations $32,760 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $32,760A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$6,080 $0 $0 $81,114 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $105,223 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $148,012 $0 $0 $0 $0 $0 $0 $0 $340,428
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $6,080 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,080B30 Roofing $0 $0 $0 $81,114 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $105,223 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $148,012 $0 $0 $0 $0 $0 $0 $0 $334,348
C C - INTERIORS: Interior Construction and Interior Finishes
$5,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $5,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $160,293 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,628 $0 $0 $0 $0 $0 $0 $0 $0 $0 $26,145 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,625 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,805 $481,495
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$77,078 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $110,196
D30 HVAC $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $148,681 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,568 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $239,249D50 Electrical (incl D51) $83,215 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $19,071 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $29,764 $132,051
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$6,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,750
G Sitework $6,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,750
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE-COMMERCIAL VEHICLE INSPECTION - B146
Size: 5,392 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$602,119 $0 $0 $24,229 $0 $7,634 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,081 $0 $0 $0 $0 $124,193 $0 $0 $70,960 $0 $11,484 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,999 $0 $0 $0 $0 $193,827 $1,057,527
A A - SUBSTRUCTURE: Foundations $7,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,200
A10 Foundations $7,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,200A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$47,240 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $300,837
B10 Superstructure $3,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,900B20 Exterior Enclosure $900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900B30 Roofing $42,440 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,034 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $154,563 $296,037
C C - INTERIORS: Interior Construction and Interior Finishes
$114,208 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,208
C10 C10 - Interior Construction $57,930 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $57,930C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $56,278 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $56,278D D - COMPONENTS $302,196 $0 $0 $24,229 $0 $7,634 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,081 $0 $0 $0 $0 $25,158 $0 $0 $70,960 $0 $11,484 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,999 $0 $0 $0 $0 $39,264 $504,006
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$42,251 $0 $0 $0 $0 $7,634 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,081 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,484 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,999 $0 $0 $0 $0 $0 $84,449
D30 HVAC $25,180 $0 $0 $24,229 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,960 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $120,369D50 Electrical (incl D51) $234,765 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,158 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $39,264 $299,188
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$131,275 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $131,275
G Sitework $131,275 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $131,275
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MEDIC 04 - B150Size: 7,113 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$1,220,851 $0 $0 $7,374 $0 $0 $0 $0 $229,776 $0 $0 $121,026 $0 $196,719 $0 $0 $0 $0 $0 $0 $31,321 $0 $0 $11,038 $0 $0 $0 $0 $348,205 $0 $0 $0 $0 $301,790 $0 $0 $0 $0 $0 $0 $48,883 $2,516,984
A A - SUBSTRUCTURE: Foundations $171,545 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $171,545
A10 Foundations $171,545 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $171,545A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$273,005 $0 $0 $0 $0 $0 $0 $0 $229,776 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $348,205 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $850,986
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $268,245 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $268,245B30 Roofing $4,760 $0 $0 $0 $0 $0 $0 $0 $229,776 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $348,205 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $582,741
C C - INTERIORS: Interior Construction and Interior Finishes
$88,554 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $88,554
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $88,554 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $88,554C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $650,330 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $121,026 $0 $196,719 $0 $0 $0 $0 $0 $0 $31,321 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $301,790 $0 $0 $0 $0 $0 $0 $48,883 $1,368,482
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$0 $0 $0 $7,374 $0 $0 $0 $0 $0 $0 $0 $121,026 $0 $8,771 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,038 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,456 $0 $0 $0 $0 $0 $0 $0 $161,665
D30 HVAC $750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $187,948 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $288,335 $0 $0 $0 $0 $0 $0 $0 $477,033D50 Electrical (incl D51) $649,580 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,321 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $48,883 $729,784
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$37,417 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $37,417
G Sitework $37,417 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $37,417
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MEDIC HEADQUARTERS - B153Size: 44,277 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$73,656 $0 $0 $0 $0 $0 $138,713 $0 $0 $0 $107,050 $0 $0 $0 $0 $0 $6,600 $0 $143,486 $0 $39,614 $0 $0 $0 $0 $0 $8,367 $0 $0 $0 $90,568 $0 $0 $0 $0 $0 $16,319 $0 $0 $0 $61,825 $686,197
A A - SUBSTRUCTURE: Foundations $35,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,000
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $35,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,000
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $143,486 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $143,486
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $143,486 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $143,486
C C - INTERIORS: Interior Construction and Interior Finishes
$1,556 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,556
C10 C10 - Interior Construction $1,456 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,456C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100D D - COMPONENTS $33,250 $0 $0 $0 $0 $0 $138,713 $0 $0 $0 $107,050 $0 $0 $0 $0 $0 $6,600 $0 $0 $0 $39,614 $0 $0 $0 $0 $0 $8,367 $0 $0 $0 $90,568 $0 $0 $0 $0 $0 $16,319 $0 $0 $0 $61,825 $502,306
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$4,000 $0 $0 $0 $0 $0 $138,713 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,367 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,319 $0 $0 $0 $0 $173,999
D30 HVAC $11,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $107,050 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,568 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $208,618D50 Electrical (incl D51) $18,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $39,614 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $61,825 $119,689
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$3,850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,850
G Sitework $3,850 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,850
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 29 - B225Size: 11,450 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$55,623 $0 $0 $118,668 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $146,430 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $216,539 $0 $0 $0 $0 $0 $0 $129,170 $666,430
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$0 $0 $0 $118,668 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $216,539 $0 $0 $0 $0 $0 $0 $0 $335,208
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $0 $0 $0 $118,668 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $216,539 $0 $0 $0 $0 $0 $0 $0 $335,208
C C - INTERIORS: Interior Construction and Interior Finishes
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $39,623 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $146,430 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $129,170 $315,223
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
D30 HVAC $1,125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $134,404 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,402 $245,931D50 Electrical (incl D51) $38,498 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,768 $69,292
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000
G Sitework $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MEDIC 02 - B364Size: 3,423 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$86,854 $0 $0 $52,671 $0 $0 $0 $68,560 $0 $8,183 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,733 $9,620 $0 $0 $39,422 $0 $0 $0 $0 $0 $12,431 $0 $0 $0 $0 $0 $0 $0 $126,339 $0 $15,153 $15,015 $443,982
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$0 $0 $0 $0 $0 $0 $0 $68,560 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $126,339 $0 $0 $0 $194,899
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $0 $0 $0 $0 $0 $0 $0 $68,560 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $126,339 $0 $0 $0 $194,899
C C - INTERIORS: Interior Construction and Interior Finishes
$33,538 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $33,538
C10 C10 - Interior Construction $10,130 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,130C20 C20 - Stairs $23,408 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $23,408C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $52,310 $0 $0 $52,671 $0 $0 $0 $0 $0 $8,183 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,733 $9,620 $0 $0 $39,422 $0 $0 $0 $0 $0 $12,431 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,153 $15,015 $214,539
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$500 $0 $0 $0 $0 $0 $0 $0 $0 $8,183 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,733 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,431 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,153 $0 $46,000
D30 HVAC $8,860 $0 $0 $52,671 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $39,422 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,954D50 Electrical (incl D51) $42,950 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,620 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,015 $67,585
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$1,006 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,006
G Sitework $1,006 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,006
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
FIREHOUSE 34 (TRUCK) - B366Size: 2,684 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$104,927 $0 $0 $0 $0 $116,423 $0 $0 $275,732 $0 $0 $0 $0 $0 $0 $8,756 $0 $0 $0 $0 $28,649 $0 $0 $0 $0 $125,917 $0 $0 $417,846 $0 $0 $0 $0 $0 $0 $13,499 $0 $0 $0 $0 $44,713 $1,136,462
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$1,190 $0 $0 $0 $0 $0 $0 $0 $275,732 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $417,846 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $694,767
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $180 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $180B30 Roofing $1,010 $0 $0 $0 $0 $0 $0 $0 $275,732 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $417,846 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $694,587
C C - INTERIORS: Interior Construction and Interior Finishes
$1,012 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,012
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $1,012 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,012D D - COMPONENTS $99,725 $0 $0 $0 $0 $116,423 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,756 $0 $0 $0 $0 $28,649 $0 $0 $0 $0 $125,917 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,499 $0 $0 $0 $0 $44,713 $437,682
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$8,100 $0 $0 $0 $0 $7,362 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,756 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,499 $0 $0 $0 $0 $0 $48,791
D30 HVAC $500 $0 $0 $0 $0 $109,062 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $114,842 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $224,404D50 Electrical (incl D51) $91,125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $28,649 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $44,713 $164,487
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$3,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000
G Sitework $3,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MEDIC 06 - B373Size: 8,099 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$178,835 $0 $0 $105,342 $0 $99,765 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $46,688 $138,647 $0 $141,921 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $72,865 $799,068
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$25,970 $0 $0 $0 $0 $99,765 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $138,647 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $264,382
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $24,770 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,770B30 Roofing $1,200 $0 $0 $0 $0 $99,765 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $138,647 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $239,612
C C - INTERIORS: Interior Construction and Interior Finishes
$5,594 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,594
C10 C10 - Interior Construction $5,594 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,594C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $147,271 $0 $0 $105,342 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $46,688 $0 $0 $141,921 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $72,865 $529,091
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$4,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,947 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,074 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,057 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,040 $37,868
D30 HVAC $5,480 $0 $0 $105,342 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $141,921 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $252,743D50 Electrical (incl D51) $137,041 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $39,614 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $61,825 $238,480
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE ZONE 01 - B379Size: 11,187 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$1,096,875 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,096,875
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$7,175 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,175
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $7,175 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,175B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
C C - INTERIORS: Interior Construction and Interior Finishes
$2,450 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,450
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $2,450 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,450D D - COMPONENTS $1,087,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,087,250
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$1,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000
D30 HVAC $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D50 Electrical (incl D51) $1,086,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,086,250
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE HEADQUARTERS - B400Size: 80,000 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$444,455 $0 $0 $0 $199,366 $9,270 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,026 $0 $0 $0 $0 $200,899 $0 $0 $0 $299,169 $13,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,999 $0 $0 $0 $0 $258,341 $1,453,470
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$110,174 $0 $0 $0 $199,366 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $299,169 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $608,709
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $108,878 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $108,878B30 Roofing $1,296 $0 $0 $0 $199,366 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $299,169 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $499,831
C C - INTERIORS: Interior Construction and Interior Finishes
$121,506 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $121,506
C10 C10 - Interior Construction $121,506 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $121,506C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $212,775 $0 $0 $0 $0 $9,270 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,026 $0 $0 $0 $0 $200,899 $0 $0 $0 $0 $13,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,999 $0 $0 $0 $0 $258,341 $723,255
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$4,400 $0 $0 $0 $0 $9,270 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,026 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,945 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,999 $0 $0 $0 $0 $0 $55,641
D30 HVAC $39,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $162,699 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $198,724 $400,673D50 Electrical (incl D51) $169,125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $38,199 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $59,617 $266,941
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE ZONE 5 - B402Size: 11,046 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$171,448 $0 $0 $71,633 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $145,722 $0 $0 $107,229 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $227,428 $739,336
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$20,785 $0 $0 $66,366 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,345 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $186,495
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $1,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500B30 Roofing $19,285 $0 $0 $66,366 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $99,345 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $184,995
C C - INTERIORS: Interior Construction and Interior Finishes
$20,040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,040
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $20,040 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,040C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $130,623 $0 $0 $5,267 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $145,722 $0 $0 $7,884 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $227,428 $532,801
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$1,350 $0 $0 $5,267 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,265 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,884 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,611 $0 $0 $0 $0 $0 $0 $0 $30,378
D30 HVAC $17,940 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $113,182 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $176,643 $307,765D50 Electrical (incl D51) $111,333 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $32,540 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,785 $194,658
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
G Sitework $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
POLICE ZONE 3 - B405Size: 9,270 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$9,225 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,415 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,208 $12,848
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B30 Roofing $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
C C - INTERIORS: Interior Construction and Interior Finishes
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
C10 C10 - Interior Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0D D - COMPONENTS $8,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,415 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,208 $12,323
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
D30 HVAC $875 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,415 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,208 $4,498D50 Electrical (incl D51) $7,825 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7,825
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$525 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $525
G Sitework $525 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $525
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
RIVER SAFETY BOAT HOUSE - B621Size: 3,520 SF
TOTAL
MAINTENANCE 40 YEARS MAIN COMPONENTS LIFE-CYCLE INVESTMENT REQUIRED
Current 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 Total
$958,420 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $396,421 $0 $0 $0 $120,000 $0 $0 $0 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $618,693 $2,114,539
A A - SUBSTRUCTURE: Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
A10 Foundations $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0A20 Basement Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
BB - BUILDING SHELL: Building Frame, Structure, Concrete Stairs, Exterior Walls, Roofing
$321,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $273,335 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $426,593 $1,021,428
B10 Superstructure $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0B20 Exterior Enclosure $4,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,000B30 Roofing $317,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $273,335 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $426,593 $1,017,428
C C - INTERIORS: Interior Construction and Interior Finishes
$2,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,000
C10 C10 - Interior Construction $1,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500C20 C20 - Stairs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0C30 C30 - Interior Finishes $500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500D D - COMPONENTS $585,400 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $123,086 $0 $0 $0 $120,000 $0 $0 $0 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $192,099 $1,041,591
D20 Plumbing: Plumbing, Hot water, Drainage. (incl D21)
$6,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,326 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,903 $0 $0 $0 $0 $0 $0 $0 $0 $0 $12,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,456 $53,115
D30 HVAC $8,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $120,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $128,500D50 Electrical (incl D51) $570,150 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $113,182 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $176,643 $859,975
G
G - BUILDING SITEWORK: Landscaping, Paving, Curbing, Parking, Exterior Retaining Wall, Site Amenities and Topography
$49,520 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $49,520
G Sitework $49,520 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $49,520
F F - Special Construction & Demolition
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
F10 Special Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0F20 Selective Building Demolition $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
MUNICIPAL COURTS BUILDING - B902Size: 44,646 SF
TOTAL