capitol hill ricin 2/2/04 – 2/9/04. incident description white powder – senator frist mailroom...
Post on 16-Dec-2015
213 Views
Preview:
TRANSCRIPT
Capitol Hill Ricin 2/2/04 – 2/9/04
Incident Description
White Powder – Senator Frist Mailroom –Found 2/2/04
Initial Assessment by Capitol Police HMRT
Field Tests – 5 of 6 Positive Lab Results on 2/3/04 -
Confirmed Ricin
Response Mobilization
HSAA Requested EPA Support EPA Activated ERT, USCG-AST,
ATSDR, ERRS, START Capitol Police Activated Marines-
CBIRF
Incident Command
ICS had Parallel Tracks - Investigations & Response
Limited Info Sharing from Investigations to Response
EPA Integrated Our Operations Into Capitol Police’s ICS Structure
Goal: Open Buildings asap
Initial Scope of Response
Initially Focused on Mail Collection- Bag, Document & Overpack
House Buildings Never Closed - Work @ Night
Develop Plan to Sample & Decontaminate Mailroom
Further Scope of Response
Implement Decontamination Plan
- Fumigation w/ Heat?- Washdown w/ Weak Bleach - Steam Vac Carpets
Dirksen Open On Schedule (2/9) USCG- PIAT & EPA-CIC Support to
Capitol Police’s PIO
Ongoing Work
Disposal of Wastes (PPE, decon water, rugs, etc.)
Treatment/Disposal of Mail EPA Costs: < $500K
Lessons Learned: Part 1
Increase in Capitol Police’s Hazmat Capabilities
- Good News: * Less Cross-Contamination * Improved ICS * Less Reliance on Others- Bad News: * Less Access to Sampling Data for EPA & CDC
Lessons Learned: Part 2
PFO – Offers Potential Help Efficacy Methods for Interior
Bldg Remediation Are Needed Criminal/Response Coordination:
Still a Work in Progress ERT Can Do Great Job as SSC Formalized Guidance on
Clearance Committees Would be Useful