Year End Budget Carry Forward
Functionalities in Project System
in Integration to IM Module
Applies to:
This article is applicable to carry forward of commitment and budgets in Investment Management and Project System modules (year end functionalities) when used in ECC 6 version.
Summary
This article explains you how to carry out the year end functionality like approval year carryforward and budget carryforward for IM program and its measures (projects).
Author: Raghavendra Praveen Phanibhatla
Company: Tata Consultancy Services Ltd, Hyderabad
Created on: 30 October 2010
Author Bio
Raghavendra Praveen has been associated with Tata Consultancy Services as PS consultant. He has expertise in Supply chain management, Project system and Investment management modules. Presently he is working in logistics department. He has around four years of domain expertise in power, cement sectors and three and half years in handling SCM and Project System projects.
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 2
Table of Contents
Purpose ............................................................................................................................................................... 3
Integration ........................................................................................................................................................... 3
Pre-Requisite ...................................................................................................................................................... 3
Steps ............................................................................................................................................................... 4
Opening of new approval year through IM27 .................................................................................................. 4
Period opening through MMPV ....................................................................................................................... 4
Commitment carry forward of projects through CJCF .................................................................................... 5
Budget carry forward of project through CJCO ............................................................................................... 6
Fiscal year budget carry forward of IM programs through IMCAOV ............................................................... 7
Budget & measure carry forward of IM programs through IM27_repeat ........................................................ 7
Original budgeting and supplement budgeting of measure/ projects in two IM programs .............................. 8
Closing the old approval year through IM27_close ....................................................................................... 10
Disclaimer and Liability Notice .......................................................................................................................... 11
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 3
Abbreviations Used TC = Transaction Code IM = Investment Management WBS = Work Breakdown Structure Measure = Project or WBS or any order Fiscal year = Financial year Approval year = Approval period (year) of the IM program Node = End position ID in a IM program hierarchy
Purpose
Purpose of this document is to give overview on how to carryout fiscal year change on IM program and its measure, also how to carryout yearend process like budget and commitment carryforward.
Integration
Year End functionality is integrated with following components/ objects
1. IM program and position ID.
2. Projects, WBS elements
3. Actuals and commitment values on WBS element/ Project
Pre-Requisite
o Create an IM program with approval year ex: 2010 (TC -> IM01) o Create IM position ID under IM program at level 1 (TC-> IM11) o Create further IM positions under main position ID (TC-> IM22) o Create a Project Definition (TC -> CJ06) o Create a main WBS element (summary WBS element) under project definition (TC-> CJ01) o Create complete WBS under top level WBS element (TC-> CJ02) o Assign the IM end position ID to the top level WBS element (TC-> CJ02) o Assign budget to IM position, end node (TC-> IM30) o Distribute the budget from IM end node to WBS element (TC-> IM52) o Post actuals & commitments on WBS element
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 4
Steps
Opening of new approval year through IM27
Open the new approval year for the IM program to be carried forward. Choose the options Copy program structure and copy forward measure/ appropriate request.
Period opening through MMPV
Open the MM period of new fiscal year using MMPV transaction (for budget carryforward).
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 5
Commitment carry forward of projects through CJCF
Carry forward the commitment values on project (WBS elements). It will transfer the values of open purchase orders and requisitions if any.
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 6
Budget carry forward of project through CJCO
Carry forward the unused budget value on project (WBS elements). You will get a system notification to carry forward the IM program budget values using IMCAOV (across years). You can carry forward IM position budget once all IM measures budget has been carried forward.
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 7
Fiscal year budget carry forward of IM programs through IMCAOV
Carry forward the IM program budget.
Budget & measure carry forward of IM programs through IM27_repeat
You can carry out this transaction as many times as possible in order to make IM measures’ budget synchronous with IM program budget. Choose the option carry forward budget values.
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 8
Original budgeting and supplement budgeting of measure/ projects in two IM programs
Carry forwarded budget will be seen as Forward budget in newly opened IM approval year/ fiscal year as shown below.
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 9
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 10
Closing the old approval year through IM27_close
Before closing the approval year, the measures will be shown as current measures in old approval year and carried forward measures in new approval year. Thus accepts the budget from both the approval years (supplement from new IM approval year program).
If you want to remove the link between IM measure (ex: project) and old approval year then carry out closing approval year task.
Year End Budget Carry Forward Functionalities in Project System in Integration to IM Module
SAP COMMUNITY NETWORK SDN - sdn.sap.com | BPX - bpx.sap.com | BOC - boc.sap.com | UAC - uac.sap.com
© 2010 SAP AG 11
Disclaimer and Liability Notice
This document may discuss sample coding or other information that does not include SAP official interfaces and therefore is not supported by SAP. Changes made based on this information are not supported and can be overwritten during an upgrade.
SAP will not be held liable for any damages caused by using or misusing the information, code or methods suggested in this document, and anyone using these methods does so at his/her own risk.
SAP offers no guarantees and assumes no responsibility or liability of any type with respect to the content of this technical article or code sample, including any liability resulting from incompatibility between the content within this document and the materials and services offered by SAP. You agree that you will not hold, or seek to hold, SAP responsible or liable with respect to the content of this document.
top related