1
BOARD OF COMMISSIONERS TRAINING
U. S. Department of Housing and Urban Development
PROCUREMENT AND CONTRACTING OVERVIEW
April 2009
2
BOARD OF COMMISSIONERS TRAINING SERIES
I. The Commissioner’s RoleII. The Executive Director’s RoleIII. Program ManagementIV. Financial Operations and OversightV. Physical Facilities and Maintenance
VI. Procurement and Contracting OverviewVII. Preventing and Resolving Audit FindingsVIII. Performance Measures
PHAS, MASS, FASS, PASS, SEMAP
IX. Conducting an Effective Board MeetingX. Emergency and Disaster Preparedness
3
PROCUREMENT AND CONTRACTING TRAINING
I. The Key to Good Procurement ActionsII. Basic Procurement RequirementsIII. Roles and ResponsibilitiesIV. Procurement PlanningV. Resident Businesses and Section 3VI. Cost and Price AnalysisVII. Types of ProcurementVIII. Types of ContractsIX. Closeout
1. Appendix I – Summary of Procurement Methods Chart2. Appendix II - Glossary
4
I. The Key to Good Procurement Actions
• Common Sense• Sound business approach• Integrity and ethical standards• Planning • Internal management controls• Clear and detailed conditions, terms
and specifications• Open and free competition
5
Good Procurement Actions Cont’d.• Careful award• Confidentiality• Conformance with Federal, State and Local laws and
regulations• Adherence to the requirements of the HA’s
procurement policies, procedures and contract administration system
• Oversight• Consistent application and enforcement of standards
6
The Down Side of Poor Procurement• Cancelled and reissued actions• Poor or untimely service or delivery• Incomplete, inadequate or useless items• Inappropriate acquisition costs• Litigation • Audit findings and repayment $s• Waste and misuse of PHA resources, i.e.
time, personnel, and money
7
II. BASIC PROCUREMENT AND CONTRACTING REQUIREMENTS
Housing Authorities are required to develop and use procurement policies and procedures and contract administration systems
Procurement procedures must:• Conform to applicable Federal, State and local laws and
regulations• Provide for internal management controls• Cover all phases of procurement activity from plan
development through award to close out and oversight
8
II. BASIC PROCUREMENT AND CONTRACTING REQUIREMENTS
Federal Requirements • 24 CFR 85.36
• Provides regulations and administrative guidance
• Procurement Handbook 7460.8 Rev-1• PIH Procurement Policy
• PIH Notices• State and Local Law Interagency
Agreements
9
II. BASIC PROCUREMENT AND CONTRACTING REQUIREMENTS
Procurement and Contracting Policies• Board approved• Written and officially issued• Establish parameters for procurement and
contracting procedures• Designate the Contracting Officer• Establish levels of contracting authority
10
II. BASIC PROCUREMENT AND CONTRACTING REQUIREMENTS
• Establish detailed written guidance and operating instructions for implementing ALL procurement and contracting actions
• Incorporate the HA’s applicable internal management controls [IMC] and Standard Operating Procedures [SOP]
• Cover every phase of procurement process• Designations of levels of authority and approval• Contract Administration system• Procurement planning• Determining the procurement methodology• Public Notice• Selection• Award • Monitoring, oversight and evaluation of performance• Closeout
11
II. BASIC PROCUREMENT AND CONTRACTING REQUIREMENTS
CONTRACT ADMINISTRATION SYSTEM [CAS]
• Covers every phase of procurement and contracting activity - without exception
• Operational processes
• Authorizations and justifications
• Data/transaction entry and verification,
• Internal management controls and accountability
12
II. BASIC PROCUREMENT AND CONTRACTING REQUIREMENTS
• Records modifications and terminations
• Provides documentation and paper trail
• Provides for evaluation of contractor-supplier performance
• Tracks Dollars and Performance Time
• Documents closeouts
13
III. Roles and Responsibilities
The Board of Commissioners is responsible for:
• Developing, approving and officially issuing the HA’s procurement policies and procedures
• Appointing a contracting officer and establishing the levels of authority
• Monitoring the contracting officer’s performance, which must comply with 24 CFR Part 85.36
14
III. Roles and Responsibilities
The Executive Director is responsible for:• Carrying out the procurement policies and procedures
established by the Board
• Developing or revising as appropriate the procurement procedures and obtaining Board approval.
• Serving as the Contracting Officer when so designated and supervision of procurement and contracting by the HC
15
III. Roles and Responsibilities
The Contracting Officer’s duties are:• Implementing the procurement procedures• Exercising sound judgment in carrying out
procurement and contracting responsibilities • Ensuring that contractors receive impartial, fair
and equitable treatment;• Adherence to high standards of conduct and
avoiding conflicts of interest
16
III. Roles and Responsibilities
• Providing procurement assistance to HA staff
• Acquiring HA supplies, equipment and services
• Utilizing the advice of specialists in audit, law, engineering and other subjects, as appropriate;
• Analyzing bids and proposals
• Signing all contracts, modifications, purchase orders, intergovernmental purchasing agreements within authority level
17
III. Roles and Responsibilities
• Detecting and minimizing contract irregularities
• Reviewing and ratifying unauthorized actions upon receipt of adequate justification
• Recommending and instituting remedial action
• Operation of the Contract Administration System
• Supervision and oversight of all HA staff involvement in procurement and contracting.
18
IV. Procurement Planning
What -
• are the program requirements
• steps are taken to accomplish it
• is the timing of required actions
?
19
The Procurement Plan
A. Procurement Plan Requirements
• Written
• Approved by the Board
• Directly linked to the PHA Budget and PHA Plan
• Includes all procurement and contracting activity
• Periodically reviewed and modified as appropriate
• Evaluated and monitored by Board and ED
20
The Procurement Plan
B. Procurement Plan Scope and Timing• Identifies the item or scope of work required;• Is supported by documentation that includes: the
proposed use and description of item, requesting source, etc.,
• Considers time constraints • Type and size of job, market considerations, urgency of need
• Includes a cost estimate for each procurement action• Identifies the source and availability of funds
21
The Procurement Plan
• Sets the schedule and timeframe of all actions • Considers:
• local, state and interagency purchasing agreements• Consolidation vs. breakout and lease vs. purchase options
• Provides for special objectives and programs• Resident contracting, training and employment• Section 3• Multi-year requirements and projections
22
V. Resident Businesses and Section 3
Resident-owned businesses, training and employment• Direct HA training and employment of residents is not a
procurement action. • Issuing a contract to a resident owned and staffed company is
a procurement action• Special conditions for resident contracting must be included
in the HA’s policies and procedures.• An alternative procurement process which limits solicitation
to resident-owned businesses can be used• The resident-owned business must be ‘responsible’
23
V. Resident Businesses and Section 3
SECTION 3• The 1968 Act requirement that individuals or firms located in or owned
in substantial part by persons residing in the area of a HA project be used when possible.
• Provision for Section 3 actions must be included in the HA procurement plan
• All solicitations must advise contractors of this requirement
• Appropriate clauses must be included in all covered contracts
• Contractors and subcontractors must make good faith efforts to award contracts, purchase supplies or hire and train Section 3 eligible persons or companies
24
VI. Cost and Price Analysis
Cost And Price Analysis And Estimates Must Be:
• Independent and Confidential
• Performed as part of procurement planning for all actions including modifications and terminations
• In writing and retained in the HA records
25
VI. Cost and Price Analysis
A cost analysis is usually completed to:• Evaluate the proposals
• A review or comparison of components and the end price or value of the items to be obtained: wages, materials, time/hours, etc.
• received in response to a • IFBs when only one bid is received • RFPS
• Prepare for• negotiations• Contract modifications• Terminations
• PROFIT MUST be negotiated separately when a cost analysis is required
26
VI. Cost and Price Analysis
A Price Analysis is:• A review or comparison of the amount for which the item or service
can be obtained• Usually performed for small purchases and Invitation for Bids
[IFB]s• May be as simple as reviewing prior recent procurements for similar
items and factoring inflation or conducting a simple survey of suppliers.
• More complex analyses may be required for large purchases or contracts including estimated labor categories and hours required, materials needed and subcontractors required, etc.
• Must sufficient enough to properly evaluate offers and proposals
27
VII. Types Of Procurements
• Small Purchases• IFB • Competitive
• Qualifications – Based Proposals• Competitive Proposals
• Noncompetitive Proposals
28
VII. Types Of Procurements
• Small Purchases• The category covers a range of types of procurements and
materials - copy paper, plumbing supplies, computer software.• $100,000 or lower as set in local law and the HA’s Procurement
Policy. • Less formal than other types of procurement• At least 3 oral or written quotes
• Oral quotes – notes should be made during discussions and follow-up documentation obtained – fax, e-mail, etc., obtained from supplier or sent out as confirmation
• Documentation is required for all small purchases – paper trail for bookkeeping, budget development and audits
29
VII. Procurement
Small Purchases Continued• Factors to be considered in setting the small
purchase limit:• The size of the HC and the overall procurement budget• The level of experience of the CO[s] • The HC Board assessment of past CO performance• Local law where appropriate• The CO’s bonding level• Availability of HA Board and ED time for oversight
30
VII. PROCUREMENT
INVITATION FOR BID OR SEALED BID• Primarily used for construction contracts and major
purchases of equipment and supplies• Requires public notice of item/work to be obtained• IFBs issued should include:
• A detailed description of item to be purchased, specifications, schedule for delivery, all terms and conditions.
• Deductive alternatives may be included and must be used in the order listed
• Additive alternatives or pre-priced future work may not be included
• Sealed bids are submitted, Firm fixed-price contracts are awarded – negotiation with lowest bidder is not permissible.
31
VII. PROCUREMENT
IFB or SEALED BID OPENING• Sealed Bids are received and handled in strictest
confidentiality • Bids are opened in public at the announced time and place• Names of bidders and bid price information is read out • loud and made part of the permanent record• [no other information is made public at this time]
• Any issues raised are taken under advisement and no determinations are made at this time. Information on decisions reached must made available to all bidders.
32
VII. PROCUREMENT
• IFB Contract Issuance• Contract issuance is the next step in the IFB
procurement process• Firm fixed-price contracts are awarded• Negotiations with lowest bidder is not
permissible• Contracts will be discussed in more detail in VIII
33
VII. PROCUREMENT RFP – REQUEST FOR PROPOSAL
Qualifications-Based Proposals• Used only for A/E• Price is not used as a selection
factor but is negotiated at a later date.
• Bidder must be responsible
Competitive Proposals• Used for procuring
professional and consulting services, including A/E• Ex. Architects, lawyers,
accountants, master plumber
• Price is used as one of the selection factors
• Bidder must be responsible
TWO TYPES
34
VII. PROCUREMENTRFP – REQUEST FOR PROPOSAL
• For all competitive proposals, the HA must• Establish an evaluation committee to review the technical factors• A cost analysis must be conducted by the procurement staff before
negotiations. The results are confidential!• Profit must be negotiated separately
• Proposals are time and date stamped at the time of receipt. Late proposals must be marked accordingly at the time of receipt and rejected as required by HA policy.
• Proposals are not opened publicly. No information is made public prior to final decisions for award.
35
VII. PROCUREMENTCOMPETITIVE PROPOSALS
PERMISSIBLE ACTIVITIES• The HA may
• Hold a pre-bid conference• Make an award based on initial proposals• Request and receive best and final offers • Conduct negotiations
36
VII. PROCUREMENT NONCOMPETITIVE PROPOSALS
Allowed in the following circumstances:• Emergency situations• Procurement under other methods is not feasible• Numerous solicitation efforts have not been successful and
competition is determined to be inadequate• Written justification exists and meets procurement policy• Cost analysis data existed prior to the solicitation• HUD approval is obtained under the original ACC. An
approval is not required under a new ACC.
37
VII. PROCUREMENT
RECOMMENDED PROCEDURES FOR ALL PROCUREMENTS
• No withdrawals or corrections are allowed after bid opening unless obvious error – clear and convincing documentation of intended price and error.
• All bids/offers and qualifications of potential contractors/suppliers are reviewed for• Responsiveness – meets all solicitation terms• Price/cost analysis – within guidelines• Responsibility – capacity to fulfill contract
38
VIII. Contracts
• Contract – a legal document that outlines • The terms and conditions that guide the performance of
the parties• Pricing and payment arrangements• Established time limits and delivery schedule• Limits, options, incentives and penalties• Clauses and terms required by Federal, State and local
law and HA policies• Provisions for special events and requirements
39
VIII. CONTRACTS
• The Contract must: • Be complete – in general if a provision is not in the
contract the supplier/contractor cannot be required to provide the service/product • Modifications of contracts if and when possible are costly and
time consuming and must be mutually agreeable• Exceptions exist contact your legal counsel
• Include all solicitation provisions• Provide guidance and criteria for monitoring,
evaluation of performance, product acceptance/rejection, payment and termination
40
VIII. CONTRACTS
• Two basic types of contracts:• Fixed Price – the contractor must deliver the
product or perform the service for the price and other conditions agreed upon.• This is the preferred contract type• Minimizes HA risk and provides maximum incentive for the
contractor to carryout the work effectively and in a timely manner
• The only contract type permitted with a sealed bid procurement
41
VIII. CONTRACTS
Cost Reimbursement Contract• The contractor agrees to make best efforts to complete
contract statement of work within estimated agreed upon amount, however, if work is not completed and funds are expended the contractor has no obligation for further performance unless the contract is modified.
• This type of contract:• must be justified prior to issuance• is used in situations where some aspect of the specifications is
not known or complete, e.g.. labor hours
42
VIII. CONTRACTS
Prohibited Contract Types:Cost plus a percentage of cost
• Requires HA to pay costs to be incurred in future plus [a commission on those costs] that can not be determined at the time of contract award
• There is no incentive for the contractor for controlling costs or carrying out the contact with “best efforts”
43
VIII. CONTRACTS
Prohibited Contract Types Continued: Percentage of construction cost
• Cost is determined by applying a percentage of actual construction costs as a fee to the total construction cost. Similar to process used in A/E costing.
• There is no incentive for timely, cost effective work and frequently has the result of encouraging the contractor to conduct an overly expensive construction job.
44
IX. CLOSEOUT
Closeout is the last stage of procurement and CAS • Receipt of product - delivery• Review and inspection• Acceptance • Determination that all contract terms have been fulfilled and no
incentives or penalty clauses should be implemented• Process of acceptance and fulfillment of contract terms, issue order
for payment• Payment• Paper work and final documentation completion
• Evaluation