Black SeaRegional Transmission Planning Project- renewables integration -By Predrag MikšaEKC - Electricity Coordinating Center

Simferopol, June 2011

Black Sea Transmission Project

TASK#3 – Renewables data collection

Renewables Generation expansion plans Wind Small hydro Other Estimated connection to grid Market approach (feed in tariff

and price,…) Rules of engagement

Each country to prepare country report, Model integrator to prepare regional overview and regional report

Black Sea Transmission Project

ARMENIA

Renewables development plan Small hydro Biomass? Solar? Geothermal? Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

ARMENIA

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

ARMENIA

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

ARMENIA

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.

Black Sea Transmission Project

BULGARIA

Renewables development plan Small hydro Biomass Solar Geothermal Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

BULGARIA

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

BULGARIA

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

BULGARIA

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.

Black Sea Transmission Project

GEORGIA

Renewables development plan Small hydro Biomass Solar Geothermal Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

GEORGIA

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

GEORGIA

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

GEORGIA

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.

Black Sea Transmission Project

MOLDOVA

Renewables development plan Small hydro Biomass Solar Geothermal Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

MOLDOVA

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

MOLDOVA

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

MOLDOVA

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.

Black Sea Transmission Project

ROMANIA

Renewables development plan Small hydro Biomass Solar Geothermal Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

ROMANIA

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

ROMANIA

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

ROMANIA

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.

Black Sea Transmission Project

RUSSIA

Renewables development plan Small hydro Biomass Solar Geothermal Tidal Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

RUSSIA

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

RUSSIA

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

RUSSIA

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.

Black Sea Transmission Project

TURKEY

Renewables development plan Small hydro Biomass Solar Geothermal Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

TURKEY

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

TURKEY

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

TURKEY

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.

Black Sea Transmission Project

UKRAINE

Renewables development plan Small hydro Biomass Solar Geothermal Wind

Few sentences with basic data (estimated posible capacities, present level of usage, development plans etc...)

Maps with RES locations, wind measurements etc...

Black Sea Transmission Project

UKRAINE

Connection of renewables to transmission gridDescription of present networkConnection strategy?Network development plan

Development that does not depend on RES

Development required by RESConnection procedure? (rough

description or algorithm)Studies and analyses (done so

far, conclusions etc...)

Black Sea Transmission Project

UKRAINE

Renewables tariffs Stipulation system? Present level of RES tariffs Future plans?

Analyses results and renewables balancing and control System reserves (analyses results so

far) Power plants that are used Operational difficulties?

results and conclusions based on calculations done by EKC

Black Sea Transmission Project

UKRAINE

Remarks and comments Critical overview by TSO on realization

of plans and how realistic they really are. Also, expected problems that can occur because large renewables penetration in transmission networks (points of network that need strengthening) based on your experience and expertise.

References list of documents (official ones),

studies etc that are used for this survey, no mater if they are public or not.