Audi Proving Ground Neustadt

Facts Project DescriptionRehabilitation of oval test track

Length of oval track: 4,600 mWidth of bituminous pavement: 11.5 mMax. inclination in curves: 49 °

Partly additional hard shoulder and dam top road

Milling of Asphalt in parabolic curves, 78,000 m²transitions and straightsLaying of new binder and wearing course by bridgepaver in parabolic curve and byconventional paver in straight sections.

Rehabilitation of drainage system 1,100 mRoad marking and reconstruction of guardrails

City/Country

Neustadt an der Donau / Germany

Client

Audi AG Abt.I/PG 432, Ingolstadt

Contract Value

€ 7,42 Mio.

Construction Period

02/2015 - 05/2015 (3 Months)

.