Project Infrastructure and Stakeholder Analysis of Husky Air Integrated Database SystemAS08
Project Team: Samir Negash, Ben Hall, James Manalel, Mariam Bhatti, Afreen Khalid
DS2
Table of Contents
Project Description 2-3MOV 2-3
Earned Value Analysis 4-5Excel Screenshots 4 Earned Value Analysis 5
Quality Management Analysis 5-6Team Philosophy 5Quality Based Metrics6Verification 6Validation 6
1
TEAM: DS2
TEAM MEMBERS
Name Phone Email address
1. Mariam Bhatti 571-451-5023 bhattim@vcu.edu
2. Afreen Khalid 703-786-5040 khalidas@vcu.edu
3. Samir Negash (Team Leader)
703-505-9712 negashsm@vcu.edu
4. James Manalel 703-531-9454 manalelj@vcu.edu
5. Ben Hall 804-335-6628 hallcb@vcu.edu
2
Team Bios:
Mariam Bhatti – I am an undergraduate student, junior level, studying at the school
business, with the hopes of graduating in May 2016 with a Bachelor in Information Systems.
With my future Information Systems degree I hope to work for national security for the
government. To achieve this dream of mine I am accepting an internship this summer to
increase my experience in the field of IS.
Afreen Khalid – I am currently a junior studying in the School of Business on the track to
graduating with Bachelors in Information Systems. I am the first in my family to graduate
from a University with a four-year degree. With my degree I plan to apply my knowledge in
creating network floor plans for companies.
Samir Negash - Hey guys I’m a senior majoring in information systems I hope to learn a lot
in the course and be efficient with the project. This is a skill that companies love and I want
to be proficient in it for future job opportunities.
Ben Hall - I am a senior IS major who recently switched over from Business Admin to
Information Systems and I’m excited to further gain knowledge in the area. I’m anticipating
another semester and hope to get a lot out of this class.
James Manalel - Howdy everyone, I am James and a senior in the Information Systems
Department. I currently work for UBS which is a wealth management firm. I am an IS major
but I want to get into the finance field and eventually own my own businesses. I believe this
course will help me better my project managing skills.
3
Team Strengths and Weaknesses
Mariam Bhatti – I am proficient in HTML5 language and am also familiar with Microsoft
Visio and building a network layout. I am a great team player and know how to cooperate
with others as well as contributing to the team effort. My weaknesses would include system
analysis since it is fairly knew to me, but hopefully after taking this course that will change.
Afreen Khalid – My strengths include knowledge of the Microsoft suite as well as basic
coding language. I am extremely interpersonal and know how to read people which will help
bring our team together and aid in the completion of upcoming tasks. A tend to nit pick at
certain aspects of things which delays the time I complete tasks.
James Manalel - I am proficient with Microsoft Office and have been a team leader before, I
am well organized and ready to take on any task during the project. One of my weaknesses is
that I tend to procrastinate, but I have been working on it and it should not be a problem.
Ben Hall – One of my weaknesses is that this is the first instance where I am actively
connecting the information systems world with the business world, so I may be
inexperienced in that sense. However, I am experienced in various technical software and
have the ability to organize and manage.
Samir Negash - A weakness I have is how to get those ideas to come together where
everyone is happy with the project. One of my strengths is the experience of being on
different teams here at VCU and making sure the task at hand is completed to the teams
satisfactions.
4
Roles and Responsibilities
Since all members of the group have similar skill attributes on both a technical and managerial
level, leadership duties will be rotated on a weekly basis. When not in a leadership role (project
manager), all other team members are on an equal level of hierarchy and have equal input and no
specific role. This means that the various roles such as business analyst, systems analyst,
infrastructure analyst are shared among those who are not the project manager for that particular
project.
Meeting Times
Meeting times are dependent on the type and difficulty of the assignment as well as the schedules
of the team members. If tasks are relatively simple, team members can communicate via text or
online via email and work on projects and contribute on their own time with interfaces such as
Google docs. Assignments that require in-person communication can be worked on in the hours
after class on Tuesdays and Thursdays.
Team Rules and Expectations
If for any reason a team member can not show up to team meeting, member must notify
team leader a day before designating meeting time.
Team members must come prepared to all meetings with necessary materials for
projects/assignments.
All members must fully contribute to assignments to reduce conflict.
If a member doesn’t agree with organization of project they must speak up to reduce
conflict and increase the group’s efficiency in completing tasks.
Members can switch between different roles if needed to increase productivity.
5
If a member has a problem with the work of another team member then they must consult
the team before talking to the professor.
Groups will make decisions by voting with a majority rule.
CODE OF ETHICS
All members must respect the work of each individual within the group and must always
contribute work during each project. Work must be reliable and content must be applicable to
project/assignments. All individuals must show integrity and respect towards all members.
Contributions must be on equal levels with all members. Lastly, individual work must be honest
and reputable.
6
AGREEMENT
All members of Team DS2 agree to the requirements of the team charter by the signatures below.
Print name Signature DateSamir Negash Samir Negash 9/1/15
Print name Signature Date
Afreen Khalid Afreen Khalid 9/1/15
Print name Signature Date
Ben Hall Ben Hall 9/1/15 P
rint name Signature Date
James Manalel James Manalel 9/1/15 Print name Signature Date
Mariam Bhatti Mariam Bhatti 9/1/15
Project Name: Project Infrastructure and Stakeholder Analysis of Husky Air Integrated Database System
7
Project Team: Mariam Bhatti, Afreen Khalid, James Manalel, Samir Negash, Ben Hall
Project Description:
Husky Air is a non-profit organization that provides free transportation by aircrafts to patients in hospitals, health care agencies, and organ banks. Husky Air has been in the process of transitions from their old way of storing data in file folders. They have a hard time with record keeping of information of the pilots. DS2 have been hired as an IT consultant to Husky Air to help them solve their problem and effectively organize their data. DS2 plans on helping Husky Air implement a new integrated database system that will help securely store all pilots’ information and to easily notify end-users (Husky Air) about all details of flight, date/time, distance, destination, patient, pilot, and availabilities. The use of this computer-based system the company will be able to keep track of all their patients and pilot angels’ information which include: names, addresses, contact information, locations, education, certifications, and their total hours of flying. DS2 has many knowledgeable and qualified individuals to assist Husky Air with this new database system that will ultimately help them save them time, money, and improve productivity.
Measurable Organizational Value:
The Desired Area of Impact:
This table shows the desired areas of impact before starting the new installations. The objectives of this IT project include increasing customer satisfaction, reducing cost/time for pilots/patients, as well as increasing market shares and branding between Husky Air, investors, and donators.
Desired Areas of Impact
Desired Value of New System
Metrics Time-Frame
Strategic -Increase shares in the market-Branding of marketing and expansion
-Increase the availability of private pilots by 19-20% and see an increase by 12% annually-Increase numbers of investors and donators by 10% per year
-20% 1st year-10-12% per year-10-15% per year
Operational
-Eliminate slow processing time and improve speed of transactions
-Decrease the process time by 50%-Increase numbers of volunteered pilots by 20% each year
-20% first year-30% Second year-50% over 5 years-Increase the amount of pilots by 20% per year
8
-Increase flexibility for the pilots
Customer -Improve waiting time for patients to ensure more satisfied customers
-Increase the customer satisfaction by 50%
-50% over 5 years
Social -More recognized public appearance of private pilot angel services to promote partnerships and sponsorships
-Increase amount of investment and donations by 20% per year
-20% per year
Financial -Reduce the pilot's cost and time-Increase the amount of aircrafts and equipment
-Decrease fuel expense and planes -Maintenance by 15% per year-Increase investments and market shares by $200,000 for Husky Air to gain more aircrafts in case of emergency
-15% per year-$200k over 3 years
Desired Value to the Organization:
Our mission is to improve overall efficiency of operations for Husky Air Pilot Angels. We plan to do this by creating a project to develop a system that delivers valuable and relevant information to Husky Air. The system will allow the Husky Air Pilot Angels organization to analyze existing data, as well as facilitate the collection of future data. We feel that doing away with the old pen and paper transactions and moving to a digital database will significantly reduce the time it takes to process a transaction. The system we will be using will support rapidly updated information on the availability of pilots and aircrafts. This will reduce confusion between the pilots and the organization. A solid system will be beneficial to the patients in need of Pilot Angels’ services. The reduction in transaction time will allow pilots to take off quicker for time-sensitive flights.
9
Metrics:
Our system will reduce the time it takes to contact a volunteer pilot by a whopping 70%. Our hopes are that this will encourage more pilots to volunteer. We estimate that pilot availability will increase by 19-20% and will also increase by 12% (annually). Worker productivity will increase by 50% due to the readily available information provided by the system. Overall, the operation is expected to be a total of 60% more efficient, which will promote growth and expansion for the entire organization.
Time-Frame:
The Database for the Husky Air non-profit organization should be completed within a one month period. This will allow the database to be created, have all the tables, entities, scripts, and codes written and implemented. The database will be placed on a small LAN located inside of the organization. The setup of Local Area Network and configuration of routers will take around one week. After the LAN and desktops have been established, a single testing day will be conducted to ensure connections and proper configurations are in place. Then we will be able to train employees over the next three weeks on how to access, edit, delete, and move all information onto the database as well as any basic computer or network training. This will enable them to add their older handwritten and manual files to the new database as well as any new files and information. The time frame is approximately one month for the completion of the project.
Summary of the MOV:
The goal of this project is to allow Husky Air to have a secure and working database system that will grant the non-profit organization reduced costs, increase processing speeds of transactions and missions, as well as increase customer satisfaction. The new system would not only increase productivity and decrease paperwork, but also increase the efficiency of Husky Air and their mission of providing air transportation to and from hospitals.
A Comparison of Alternatives:
DS2 team members are assigned to discover the best alternatives to minimize the overhead cost. There are three alternatives:
Maintain the status quo
Purchase a software package
Build a custom system and training
First Option:
10
With the constant advancements in technology it would be beneficial to create a Software package that will be more efficient and effective than using paper files. Changes in software should decrease number of workers, as well as time and effort applied to specific tasks while reducing potential errors. Internet service will be a great factor to connect the workstations and link our new software package with Husky Air. We will also need to pay for training sessions so that our employee scan adapt to the changes being implemented. Estimated additional charges and fees are as follows:
Second Option:
Is to create a system that enhances all the requirements· Pilots· Passengers· Planes used· Distance/Destination of flights· Date/Time of flights. With the implementation of this new and improved software, it will maintain same benefits as the old system but with an increased reliability over the traditional paper system. An improvement to the software is that It will eliminate losing files and file redundancy while increasing costs. Estimated additional charges and fees are as follows:
Custom System (Server, PCs)
$4525
ISP $125
Installation $255
Training session $350
Total $5220
Total Benefits of Ownership:
11
Software $ 4000
ISP $ 100
Installation $ 300
Training Session
$ 620
Total $ 5220
Objectives:
· Increasing high-value work
· Improving accuracy and efficiency (cost savings)
· Improved decision making
· Improving customer service
· Maintain the status quo (i.e., ‘do nothing’);
· Purchase a software package; or
· Build a custom system.
Option 1: Maintain the Status Quo Option one is the cheapest option of the three. It requires no work, installation costs, and no training costs.
Option 2: Purchasing Software Package There are many benefits of purchasing a software package, one being that everything you need will be bundled into the package. This means that there will be no need to find different vendors for different parts of the system. Not only will the work of employees using the system be of higher quality, it will also be more organized due to a software package. The information that you will collect with the system will be sufficiently more accurate. Another benefit is that your ability to reply to calls will be allot more efficient. In addition to all of these benefits and more, your employees will not have to train as long to learn to use the system as they would with accustom system which means they will be accustomed to the new system faster in exchange being able to assist customers with their needs better. Lastly, due to the accuracy of the information you will be able to make better decisions.
Option 3: Custom Built System One of the benefits of building a custom system is that the system will contain everything that you would need. It won’t have any extra features that your company will not use. Since there will not be any unnecessary features your employees will not have to learn to use the full comprehensive system. This is beneficial because it will decrease the amount of time needed to train them. The employees will also be able to deliver concise work because there wouldn’t be any distractions from unneeded features. Your employees will also be more accurate and efficient in their work productivity along with the similarity of new system. This system will eliminate use of paper, and the ongoing costs of having to replace paper used to keep pilot and patient information in the file folders.
Recommendation:
Based on our evaluation of the three alternatives, we strongly suggest building a custom system. We believe this will give Husky Air the best benefit rather than maintaining the old system or
12
purchased a software package. We also believe that long term costs will be noticeably lower than if you were to keep your old system or buy a package. The short term costs that you will incur with the building of a custom system are estimated to be $4,525 for a server and PCs, approximately $4,000 for software package that we will have to develop. These estimated numbers add up to be around $10,475. Our custom system will cost less upfront, and we believe that the benefits and positive results will show over a long term use of the system. This system will be sleeker, and more personalized to the specific tasks that Husky Air will need to accomplish. This in turn will reduce the time needed to train employees and volunteers on how to operate the system. We believe the benefits of a custom built system are more significant than the costs in terms of your ability to meet the demand of your patients and volunteers. As theDS2’s consulting co. technical team, we highly recommend that you spend the available funding wisely by obtaining a custom built system.
Resources Required:
Personnel Average Cost Description
IT Project Manager
$8,000/month To regulate the flow of the project. To keep tasks on schedule and to provide leadership to the group.
Network Administrator
$5,500/month To create, maintain, and administer Husky Air's computer network.
Database Developers
$9,650/month To design the database, and to show/teach the users how to input new and old information.
Programming Specialist
$5,500/month To create specific applications that will further the goals for the project.
Technology Average Cost Quantity
13
Smart Phones $30 per phone + 45 for services/ with contract
Quantity: 15 for current faculty
Server $850 1 SQL sever with license
Routers $200/each 3 to ensure quality connectivity
High speed internet access
$70/ month 1 contract with Comcast
Computers $1,079 4 fully equipped with workstations
Facilities Average Costs
Office space $2,400/month
Utilities $700/month (includes water and electricity)
Furniture $5,00
Office equipment $1000/month
Stakeholder Analysis:
Stakeholders Interests Influence Role Objective Strategy
President/ CEO
+1 5 Authorize payments for
projects
Increase number of charitable
flights
Hire DS2
Pilots 0 2 Responsible for transporation of patients, organs,
and medical personnels
Deliver customers and supplies safely and efficiently
Make sure aircraft is in
good condition and meets all regulations, as well as getting
14
patients to hospital safely
Passengers +1 4 Patients, their families,
caregivers, other medical
personnels
Arrive at hospital
Knowlegable of flying safety procedures
Shareholders +1 3 Project sponsors Provide available funds for Husky Air
Owns parts of company through
investing in stocks
Flight Coordinator
-1 2 Schedules and coordinates all
Pilot Angel flights
Operate the new system with speed and efficiency
Uses a manual system but will
have to get accustomed to
new system
Systems Analysts
+1 3 Involved in the design,
development, and delivery of the new Pilot
Angels system
Strategize to make a user
friendly system for employees and customers
Make it user friendly so that
it will be easy to adapt to
Airports 0 3 Landing/Takeoff point for pilots
and their passengers/cargo
Receive planes in a safe
enviornment
Have a runway available for landing and
take-off
DS2 +1 5 Develop new integrated
database system
Provide/maintain a user-friendly
database system that meets the Husky Air’s requirements
Conduct interviews, document
analysis and other techniques
to determine
15
user requirements
Deliverable Structure Chart
16
Use Case Diagram:
17
Scope Change Process:
18
Scope Change Request Form
Requestor Name:__________________________ Request Date:____________________Request Title:_____________________________ Request Number:_________________
Request Description:
Justification:
Possible Alternatives:
Recommendations:
Authorized By: _________________________ Date: __________________________
Potential Impacts: Alternative 1: Alternative 2: Alternative 3:
19
Scope
Schedule
Resources Required
Cost
Date of Request
Request #
Requested By
Subject Manager On Duty
Response Date
Approval
R-001
R-002
R-003
R-004
R-005
R-006
Project Approval
Received Date: _______________________Received By: _________________________
Project Summary Report (Original):
20
21
Work Breakdown Structure (Original):
22
Project Summary Report (Revised):
Work Breakdown Structure (Revised)
23
Report:
Our team managed to reduce the project schedule by 9%, which helped reduce the project budget by 15%. We were able to accomplish this by cutting host/client server installations and having the network administrators handle the installations. We also issued a scope change request and threw out some features that were not absolutely required. Effectively, we would save approximately $3,620 by making these cuts.
Project Risk Analysis and Plan Report:
Phases Initialize and Conceptualize
Project Plan and Charter
Execute and Control
Close Out Evaluation
Risk Budget Changes Scope Changes
Alignment Problems
Client Project Conflicts
Random software maintenance
checks
Layer 5 Impact
Unkown-unkown Known-unknown
Known-unknown
Known-unknown
Known-unknown
Type of Risk
Unknown-
unknown
-Budget cuts from the client could end up changing the project as a whole including
its potential outcomes.
-Stay on budget and do not change
anything in
Known-
unknown
-The project could have
too many/little objectives, changes in the plan, or
time involved for the scope.
Known-
unknown
-The devices, systems,
network, and applications have trouble aligning with the current systems.
-This will end up
Known-
unknown
-Even though the Business
Case and Project Chart
are on the same page as
the Client, there could be
potential conflicts with
any changes/expe
Known-
unknown
-Set maintenance periods will be put in place, but there
is always the possibility of
random downtime and required
system maintenance.
24
regards to the scope..
taking more time to
appropriately convert.
ctations.
Triple Constraint
Budget Scope Schedule Quality Schedule
Source of Risk
Internal Internal Internal Internal Internal
Resources Organization People and Process
Technology People, Product,
Process and Technology
Technology, and Other
Part I: Earned Value Analysis:
25
Earned Value Analysis Report:
Our earned value analysis shows the project will exceed the actual budget of $12,000. The actual cost at phase 4 totaled to be $9,050, and total of earned value at phase 4 is $7,235. The Estimate at Completion (EAC) for typical is $15,010 and for atypical is $13,815. These variances show that the project will exceed the original budget of $12,000, and based on the EAC for atypical of $13,815, we are still exceeding the project’s original budget. The SPI is less than a value of 1, which means that the project will also go over schedule and activity plans. This requires immediate actions from the third-party company, Bug Busters in order to find out why we are over budget and schedule.
Part II. Quality Management Plan:
DS2’s Objective Statement:
26
DS2 is fully committed to client satisfaction. Our underlying priority is to exceed client expectations, most efficiently. Once the project is deployed, our team will provide reliable maintenance, providing solutions for all bugs and errors. When bug removal is complete, we bring in an outside tester to check for any potential faults. Using this method, we guarantee the Superior Satisfaction of every client!
Quality Based Metrics:
Type Metric Description
Process Metrics
Employee Defect Design Defect
The number of defects caused by human error
The number of defects found in the product design
Product Metrics
User Found Defects Customer Response
Time
The number of defects found by the Husky Air employees
Average amount of time to respond to customer requests
Project Metrics
Phase completion time Early Task
Completion
Average amount of time to complete a phase
Number of tasks completed ahead of schedule
Verification Activities:
Verify that all processes related to the system regarding requirements, products, and deliverables, within the process-related activities, are up to the standards of the company and achieve what the initial project was set out to accomplish. Once the process has been verified, the validation of the product can begin.
Upon system completion the team will place this pseudo-finished system through three reviews. We will conduct a Technical Review of the Process, Management Review, and a Business Review.
1. The Technical Review will be conducted through walkthroughs and/or inspections to verify that the system has met all the Technical requirements of the project. Ensure they meet the standards and needs of the company.
2. The Management Review will tell us how the project is progressing in comparison to the baseline plan, and whether or not any changes need to be made to the project course. The
27
manager will verify expectations are met with the system's creation and the project status is met with the expected status with any and all problems are taken care of.
3. The Business Review will verify that project is within scope and that all deliverables are completed exceptionally.
Validation Activities:
Validating a project helps achieve excellent work result; every project must be tested to validate the performance, user loads, software interface and reliability for the work:· Unit testing; verifying detailed utilities work accurately and the software conforms to buyer’s requirement and expectations.· Functional testing: sending demands and detecting the output to observe how the system and software responds.· Integration: confirm the system and software is performing as required, functions great to any logically related works of the project all the way through the process.· System testing: verify that the new installations did not generate or deposit any bugs or viruses that could cause system failure or shutdown and also making sure the software is user friendly and doesn’t give individual users difficulties.· To finish, a total check to ensure everything performs accurately and the completion meets end user/clients expectations.
28
Part 1. Implementation & Project Closure Plan
Conversion Strategy: The phased operation method of processing new information into a system is more effective because there is less room for error compared to the direct cutover and parallel. Solving easing into the next step of the operation helps prevent system failure. Direct cutover has the highest failure risk because there is no proper link between each step.
Closure Checklist:
1 All outstanding tasks outlined on the WBS have been completed2 Outstanding issues have been documented and resolved3 Goals of Project Charter were met4 Feedback from stakeholders have been received and documented5 End users have been trained
6Measures for project success have been assessed and communicated
7 Project team have been evaluated and relieved from duty8 Project costs have been paid and accounted by Fianance9 Post-project evaluation completed
Project Evaluation: Systematic way of assessing ongoing and completed projects. Helps with determining levels of completion as well as the success rate of the project. Important in figuring out the effectiveness, efficiency, impact, sustainability and overall achievement of project.
Part 2. The Change management Plan
4. List of change sponsor(s), target(s), and agent(s): Pilots, Customers, Passengers, Shareholders/Stakeholders5. A change assessment: Mandatory software updates6. A change strategy: Using phased implementation7. A process for tracking change management plan: Implementing an ERP solution to the project