APPLICABLE FROM JUNE 1st 2016
PARTICULAR CONDITIONS
I. Basement for signing Contract
- Civil Code No. 33/2005/QH dated 14th June 2005 of the XI National Assembly
- Law on Construction No. 50/2014/QH13 dated 18th June 2014 of the XIII National
Assembly;
- Decree No. 59/2015/ND-CP dated 18 June 2015 of the Government on construction
project management;
- Decree No. 46/2015/ND-CP dated 12 May 2015 of the Government on quality control
and maintenance of construction project;
- Decree No. 37/2015/ND-CP dated 22 April 2015 of the Government on the Contracts in
the construction activities;
- Circular No. 08/2010/TT-BXD dated 29 July 2010 of Ministry of Construction on
guiding the method on adjustment of price of construction contract;
- Law on Fire prevention and fighting No. 40/2013/QH13 dated 22 November 2013 of the
XIII National Assembly
- Bidding documents; and
- Other relevant legal documents.
This contract is made and signed on between the following Parties:
II. Contracting Parties
1. The Owner
Name of Company : Honda Vietnam Company Limited
Address : Phuc Thang Ward, Phuc Yen Town, Vinh Phuc Province
Representative by : Mr. Toshiyuki Takada
Title : General Manager of Purchasing Unit
Tel : 84-211- 3868888 Fax : 84-211-3868900
Bank Account No. : 2890211-000300
At : Agribank, Phuc Yen Branch
Account Name : Honda Vietnam Company Limited
-2-
APPLICABLE FROM JUNE 1st 2016
Tax code : 2500150543
And
2. The Contractor
Name of Company :
Address :
Representative by :
Title :
Tel : Fax :
Bank Account No. :
At :
Account Name :
Tax code :
The Parties hereby agree to sign the Contract for the implementation of the bidding package
“ " (hereinafter referred to as “Contract”) owned by Honda Vietnam Company Limited
with the terms and conditions as follows:
1. Location: Honda Vietnam - Phuc Thang - Phuc Yen - Vinh Phuc
2. Project Schedule
Date of Commencement : ……./……./ 2018
Date of Completion : ……./……./ 2018
3. Contract Price: (In words: , included VAT 10%) , including:
Contract Price before tax : VND
Value Added Tax (10%) : VND
Contract Price after tax : VND
-3-
APPLICABLE FROM JUNE 1st 2016
The above Contract Price is a lump sum contract price (hereinafter referred to as “Contract
Price”) including all relevant taxes and fees, including but not limited to Value Added Tax
(VAT), import tax, contractor taxes, and other taxes and fees as stipulated in Article 4 in
General Conditions of the Contract. These taxes and fees, if any, shall be calculated and paid
in full by the Contractor.
4. Payment of Contract Price
The Owner shall make each time of payment by transferring to the Contractor's bank account
in Vietnam dong.
The payment of total Contract Price shall be made on or after the completion of jobs (in whole
or in part), testing the quality that meets all the requirements of the Owner; and at least 25 days
before the payment due date, the Owner receives the original invoice issued by the Contractor
and other necessary documents according to the request of the Owner.
Payment times: Every month, payment shall be made by the Owner in 03 (three) occasions on
2nd, 12th, 23rd day of the month.
The payment process is as follows:
Payment 100% contract value after the Purchaser receives the followings documents:
+ Signed hand over minute.
+ Regular invoice issued by the Seller
+ Seller submits the valid Guarantee Bond with the amount equal to five percent (5%) of
total contract price which issued by the the Seller’s Bank for one year (01) of Guarantee period
from issue date.
+ Payment proposal documents with value of 100% of contract price (indicate name and no.
of Bank’s account).
+ Contract termination with signatures from both Parties.
5. Contract Documents
-4-
APPLICABLE FROM JUNE 1st 2016
The Contract documents include the following documents. In case of inconsistency and
discrepancy between the documents of the Contract, the documents shall be referred to by the
priority order as listed below:
1) EPC Contract (including particular conditions, general conditions and amendations,
supplements (if any))
2) Quotation dated (if any)
3) Drawings and specifications, both are prepared by the Contractor and to be approved by the
Owner, technical sheets upon request of the Owner agreed by competent agencies in case
required by law.
4) Bidding Submission and its amendments
5) Bidding invitation Dossier and its amendments
6) Others (if any)
6. Trial period:
7. The Defects Liability Period 12 monthThe Defects Liability Period applicable to all works included herewith shall be 12 month from the handover date of the Works to the Owner.Errors under warranty scope must be repaired, overcome by the Contractor in a reasonable time
after receiving of the warranty claim notice from the Owner. In any cases, the repairmen must be
started within 07 days after the Contractor receives of the warranty claim notice from the Owner.
8. Performance Guarantee of Contracts
- Guarantee value 5 % Contract price
- Time for submitting guarantee certificate: 07 days since the signing date of the Contract
9. Insurance
9.1 The Contractor shall be responsible for purchasing and maintaining necessary insurances
until the completion of the Job, namely:
1) Human accident insurance
2) Contractor’s all-risks insurance
All above types of insurance has its value of respectively limited amount which is
appropriate and relevant to job scope and construction conditions. This insurance shall
indicate the Owner's name as the insurance beneficiary
-5-
APPLICABLE FROM JUNE 1st 2016
9.2 The human accident insurance shall only cover all Contractor’s workers and staffs, the
Owner shall be responsible for buying and maintaining such kind of insurance for its staff.
10. Penalty for late implementation of Contract: calculated at the rate equivalent to 0.8 %
Contract Price for every day of delay but the total penalty should not exceed the maximum
penalty permitted by the laws.
11. Penalty for breaching quality and quantity of work of Contractor: penalty level
equivalent to 8 % Contract Price.
12. Penalty for late payment of Owner: Contractor is entitled to require the Owner to pay
interest on late payment in accordance with basic interest rate announced by the State Bank at
the time of payment corresponding to the period of late payment,
13. Governing Law
This Contract shall be governed and construed in accordance with the laws of Vietnam
14. Language
This Contract is made in Vietnamese and English, if a part or the whole of this Contract is
translated into Japanese, and in case of any discrepancy or difference in interpretation between
the Japanese and the Vietnamese or the English, the Vietnamese version shall be applied.
15. Validity of Contract
This Contract takes effect from the signing date and terminates its validity when the Project was
fully done by the Contractor under this Contract.
For and on behalf of
HONDA VIETNAM COMPANY
LIMITED
For and on behalf of
-6-
APPLICABLE FROM JUNE 1st 2016
CONTENTSARTICLE 1A. DEFINITIONS AND DESCRIPTIONS...........................................................................................11
ARTICLE 1B. GENERAL PRINCIPLES.................................................................................................................12
ARTICLE 1C. CONTENTS AND SCOPE OF WORKS.........................................................................................13
ARTICLE 1D. QUALITY AND TECHNICAL REQUIREMENTS.......................................................................14
ARTICLE 1E. ADDITIONAL PROVISION.............................................................................................................19
ARTICLE 2. CONSTRUCTION AREA, SITE........................................................................................................20
ARTICLE 3. COMMITMENTS..........................................................................................................................21
ARTICLE 3A. COORDINATION WITH PROJECTS CLOSELY RELATED..................................................22
ARTICLE 4. DETAILS OF CONTRACT PRICE, TAXES AND FEES...............................................................22
ARTICLE 5. SUBCONTRACTOR...........................................................................................................................23
ARTICLE 6. ASSIGNMENT OF RIGHTS AND OBLIGATIONS.......................................................................23
ARTICLE 7. PATENT AND OTHER INTELLECTUAL PROPERTY RIGHTS...............................................24
ARTICLE 8. PERFORMANCE BOND.....................................................................................................................24
ARTICLE 10. SUPERINTENDENT.........................................................................................................................26
ARTICLE 11. REPORT ON PERFORMANCE OF WORKS...............................................................................27
ARTICLE 12. OBJECTIONS OF INDIVIDUALS CONCERNED WITH WORKS...........................................27
ARTICLE 13. CONSTRUCTION MATERIALS, EQUIPMENT..........................................................................28
ARTICLE 14. FURNISHED MATERIALS OR LENT ARTICLES.....................................................................29
ARTICLE 15. SUPERVISION PARTY ’S ATTENDANCE, PREPARATION OF WORK RECORD............30
ARTICLE 16. AMBIGUITY OR DISCREPANCY IN DRAWINGS AND SPECIFICATIONS, CHANGES
IN CONDITIONS.........................................................................................................................................................31
ARTICLE 17. WORKS ARE NOT IN COMPLIANCE WITH DRAWINGS OR
SPECIFICATIONS.......................................................................................................................................................31
ARTICLE 18. PREVENTION OF DAMAGE..........................................................................................................33
ARTICLE 19. DISPUTE AND DAMAGE TO THIRD PARTY...........................................................................33
ARTICLE 20. GENERAL DAMAGE.......................................................................................................................34
ARTICLE 21. DAMAGE CAUSED BY FORCE MAJEURE................................................................................35
ARTICLE 21A. FORCE MAJEURE EVENTS.........................................................................................................35
ARTICLE 22. INSURANCE......................................................................................................................................36
ARTICLE 23. COMPLETION, INSPECTION........................................................................................................37
ARTICLE 24. CONDITIONS ON CHECK AND ACCEPTANCE AND HAND-OVER THE WORKS...........37
ARTICLE 25. PARTIAL DELIVERY......................................................................................................................38
ARTICLE 26. PARTIAL USE...................................................................................................................................39
ARTICLE 27. REQUEST FOR PAYMENT, PAYMENT, HAND-OVER OF PROJECT.................................40
ARTICLE 28. DEFECT LIABILITY........................................................................................................................41
ARTICLE 29. CHANGES IN WORKS, CHANGES IN TIME FOR COMPLETION........................................42
ARTICLE 30. ADJUSTMENT OF CONTRACT PRICE.......................................................................................43
-9-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 31. DELAY IN PERFORMANCE, LIQUIDATED DAMAGES AND CONTRACTUAL BREACH
PENALTY.....................................................................................................................................................................44
ARTICLE 32. OWNER’S RIGHTS TO SUSPEND PROJECT OR TERMINATE THE CONTRACT...........44
ARTICLE 33. NO CORRUPT / BRIBERY CONDUCT..........................................................................................45
ARTICLE 34. CONTRACTOR’S RIGHTS TO SUSPEND WORKS OR TERMINATE THE CONTRACT
.........................................................................................................................................................................................46
ARTICLE 35. MEASURES TO BE TAKEN UPON DELAY OF CONTRACT..................................................47
ARTICLE 36. WARRANTY OF THE WORKS.......................................................................................................48
ARTICLE 37. DAMAGE COMPENSATION...........................................................................................................50
ARTICLE 38. SETTLEMENT OF DISPUTE..........................................................................................................50
ARTICLE 39. FINALIZATION AND LIQUIDATION OF THE CONTRACT...................................................50
ARTICLE 40. NOTICE................................................................................................................................................51
ARTICLE 41. MISCELLANEOUS...........................................................................................................................51
-10-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 1A. DEFINITIONS AND DESCRIPTIONS
The words and terms used herein shall have the meaning as below (unless the context
requires another definition):
Owner shall mean Honda Vietnam Company Limited;
Contractor shall mean ;
EPC Contract means a contract for the engineering of, provision of technological equipment
to and construction of all works of an investment project
Supervision Party shall mean the Owner or the legal entity hired by the Owner for
implementing one or some professional works relating to the performance management of
this Contract;
Project or Works or Object of Contract is different names of the Project “ ”;
Job shall mean works including: the design, getting necessary approval/approving from
competent authorities for that design, providing technological equipments, performing
construction Works and procedures for the completion of the construction of Works, shall be
fulfilled by the Contractor in accordance with the requirements of the Contract and
reasonably satisfying the Owner’s requirements, for the final objective that is to provide the
Owner with a complete and safety work to efficiently run as described in Article 1C;
Contract shall mean all Contract Documents, as set forth in Articles 5 in Particular
conditions of this EPC Contract;
Project Standards shall mean technical specifications, economic-technical norms, orders for
fulfillment of works, standards, technical index, and index on natural conditions as mutually
agreed by the Parties;
Technical Indications (technical descriptions) shall mean technical norms, standards as set
forth for the Work and any amendment or supplement to such standards, technical norms to
meet fully the requirements of Laws; Technical Indications are the basis for the supervision,
construction and acceptance of the construction works. The approved technical indications
are a part of invitation for construction bidding, the basis for management, supervision and
acceptance for construction works.
Design Dossier shall mean all drawings, calculations, technical descriptions and other
documents relating to the Work fulfilled by the Contractor and already approved by the
Owner and competent agencies (if any);
Party shall mean the Owner or the Contractor subjecting to the context;
Both Parties, the Parties shall mean the Owner and the Contractor subjecting to the context;
-11-
APPLICABLE FROM JUNE 1st 2016
Acceptance Minutes is the minutes which is issued under Article 24;
Day, Month shall mean calendar day and calendar month;
Working Day shall mean calendar day except for Sundays, public holidays under the
provisions of the laws of Vietnam;
Contractor’s Equipment shall mean all equipments and machineries, vehicles and other
equipment which are neccessary for Contractor to fulfill, complete the works under the
Contract and repair mistakes (if any);
Project Item shall mean a main work or a separate main work mentioned in the Contract (if
any);
Owner’s Equipment shall mean machineries, equipments which were provided to
Contractor by Owner to accomplish the Job;
Force Majeure is defined in Article 21A;
Laws shall mean all legal system of the Socialist Republic of Vietnam and its relevant
guiding documents;
Site shall mean the location where the Owner assigns the Contractor to carry out the Project
as well as any other location as mentioned in the Contract;
Change, adjustment shall mean the change, adjustment in the scope of work, Technical
Indication, and design drawings, Contract Price or Schedule for Implementation upon the
written consent by the Owner
ARTICLE 1B. GENERAL PRINCIPLES
(1) The Owner and the Contractor shall perform their respective obligations sincerely through
cooperation, good faith, and equality under the Contract, and the attached design drawings
and specifications , the on-site orientation records and the related written answers to the
queries (hereinafter collectively referred to as the “Design Documents”) and in accordance
with the laws of Viet Nam. The Contract comprises documents stipulated in Particular
conditions EPC Contract
(2) The enclosed document of the Contract may include the whole or a part of following
contents: Bidding documents, Bidding invitation dossiers, Bid winner announcement;
amendments, supplements in written; lists, charts; Performance Guarantee, Bank Guarantee
for Advance Payment and other bank guarantees (if any); minutes on contract negotiation;
other relevant documents.
-12-
APPLICABLE FROM JUNE 1st 2016
In case there is any contradiction between the EPC Contract and enclosed documents of the
Contract, the EPC Contract shall prevail.
(3) Any item of Project not mentioned in the Contract but necessary for the completion of the
projects, shall be done by the Contractor and shall be deemed to have been included in the
provisions of the Project and the Contract Price.
(4) The Contractor shall complete the Project and deliver the Project Items to the Owner in
accordance with the Contract, and the Owner shall then complete the payment of the
Contract Price to the Contractor.
(5) The Supervision Party shall be responsible for supervising, cooperating and supporting
for facilitating the performance of the Contract.
(6) Except for the necessary cases to fulfill the obligations or comply with the provisions of the
laws, the Parties must consider the details of this Contract to be confidential and be their
own The Contractor shall not disclose any details of the Project to any third party without
prior written consent of the Owner.
(7) When fulfilling the Contract, the Contractor and Owner shall have to comply with the current
laws of the Socialist Republic of Vietnam. Specifically, as follows:
(a) The Owner has to ensure the conditions for the commencement of the Project in
accordance with the provisions of the laws;
(b) The Contractor shall have to inform, pay all taxes, fees, charges and apply for all permits
under the provisions of the laws in relation to the Job. The Contractor is obligated to
compensate and bear all arising damages due to its failure to comply with the laws
instead of the Owner.
ARTICLE 1C. CONTENTS AND SCOPE OF WORKS
The Owner assigns the Contractor to carry out the Job in accordance with the provision of
law, including but not limited to the Job stipulated in specific document signed by both
Parties.
-13-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 1D. QUALITY AND TECHNICAL REQUIREMENTS
General requirements
The Contractor is obligated to fulfill in accordance with the design; ensure the solidity and
accuracy of construction structures and installed equipments under the construction norms of
Vietnam, the requirements of the Bidding Invitation Dossier and mutual agreement of the
Parties, namely:
(1) Requirements with regard to the construction design of the Work:
a. General requirements
The Contractor must be responsible for every operation and result of design activities
(including technical design, construction drawing design) of the Work and for the accuracy
of these works.
During the technical design and drawing design process, if the Contractor discovers any
mistake or difference between the requirements of the Owner, the Contractor shall inform the
Owner immediately before carrying out the technical design, drawings design and request the
Owner to clarify (if any)
At any moment when the Owner discovers mistake in the design dossier performed by the
Contractor, the Owner shall request the Contractor to make the adjustment to meet the
requirements of the Owner.
The Contractor shall have to ensure that the technical design, construction drawings design
and documents of the Contractor should be in accordance with:
+ The provisions of the laws of the Socialist Republic of Vietnam; and
+ The documents forming the Contract, including the necessary amendments and
supplements upon request of the Owner.
b. Norms and standards applied in the design
The technical design, construction drawings design of the Contractor must comply with
norms, technical standards and legal system of the Socialist Republic of Vietnam or the
Project Standards as agreed upon by the Parties.
c. Requirements with regard to the Design Dossier (or design drawings) of the Contractor
The Design Dossier of the Contractor must include description of the design, spreadsheets,
drawings, relevant construction survey documents, construction estimate and construction
-14-
APPLICABLE FROM JUNE 1st 2016
maintenance process (if any); technical documents as stipulated in the bidding invitation
dossier (or requiring dossier) of the Owner and satisfy the Owner’s requirements or suitable
to the Owner’s submission to competent authority for approval under the provisions of the
laws. Unless otherwise stipulated, the Design Dossier of the Contractor must be complied
with the provisions of laws and written in the language as stipulated in the Contract.
If, upon request of the Owner or under the provisions of the laws, the Design Dossier of the
Contractor is required to submit to the Owner for consideration and approval, such Design
Dossier shall be submitted together with the notice as mentioned below. Unless otherwise
stipulated in the Owner’s requests, the timing for consideration and approval shall not exceed
30 (thirty) days as from the date of the Owner’s receipt of the proper design dossier of the
Contractor. In the meantime, the Owner may inform the Contractor about which contents in
the Design Dossier of the Contractor are not suitable to the Contract. If a certain document in
the Design Dossier of the Contractor is not suitable to the Contract, the Contractor shall have
to amend, supplement and re-submit to the Owner for consideration and approval under this
sub-clause and the Contractor shall bear all relevant costs.
With regard to all works whose the design must be approved by the Owner and/or accepted
by competent agencies:
+ The construction of the Project shall only commence upon the approval of the Owner for
the Design Dossier of the Contractor and acceptance of competent agencies (if must be
accepted by competent agencies required by law);
+ The construction of the Project must be in accordance with the Design Dossier approved
by the Owner and acceptance of competent agencies (if must be accepted by competent
agencies required by law);
+ In case of change of the design, the construction of the Project shall only be implemented
upon the approval of the Owner for the amended Design Dossier and acceptance of
competent agencies (if must be accepted by competent agencies required by law).
Any agreement likewise or any consideration and approval (under this sub-clause or other)
shall not release the Contractor from its liabilities, obligations to the Job.
d. The Contractor is responsible for the design faults
-15-
APPLICABLE FROM JUNE 1st 2016
If the Owner discovers any fault, omission, inconsistence or impropriety in the Design
Dossier of the Contractor, the Contractor shall bear all costs to make the additional design or
remedy these faults as well as repair the errors with regard to the Project or parts of the
Project fulfilled by the Contractor, even in the case that the Owner has accepted or approved
the Design Dossier.
(2) Requirements relating to the provision and installation of the equipments
a. In case of necessity and upon request of the Owner or in accordance with regulations of laws,
materials, equipments, technologies must be tested before their delivery to the Site (The
testing organization appointed by the Owner, all incurred costs borne by the Contractor) so as
to ensure the technical requirements, quality specifications, kind of goods, origin in
accordance with this Contract.
b. The Contractor must be responsible about the stability, safety of all equipments during the
construction, completion of the Works, during the maintenance and after-sales period (The
Contractor shall be responsible about the technical matters, human resources such as experts,
technicians for supporting the Owner during the operation, incident remedies, and
maintenance) with a period of months as from the expiry of warranty.
c. The machineries, equipments in the installed technological chain must be new ones, and their
type should be as described in the Contract and in accordance with technical standards and
requirements accepted by the Owner (under the specification standards) and must have the
certificate of origin (CO) of the manufacturing country and the Certificate of Quality issued
by the producer.
d. The equipments delivered to the Site must have the Certificate of inspection issued by the
inspection agency on the origin, type of goods, quantity meeting requirements as stipulated in
the Contract and the bidding dossier (or requiring dossier), bidding application dossier (or
proposal dossier), commitments, documents clarifying the bidding dossier;
e. The installed technological equipments to the Site must have clear, legitimate origin, and
suitable to the provisions of this Contract and already inspected;
-16-
APPLICABLE FROM JUNE 1st 2016
f. The installed technological equipments to the Site must have capacity and technical
specifications suitable to the Design Dossier approved by the Owner;
g. The installation of the equipments, machineries should be as exact as possible so as to
normally put machineries into operation, prolong the life expectancy of the machineries. The
installation of machineries must be performed under the design and drawings and comply
with provisions set forth in the guide book on installation and operation, equipment record. If
there is lack of any technical requirement in the design and the guide book on installation and
operation, the current Vietnam’s standards shall be applied;
h. The installed equipments which fail to meet technical requirements (not in accordance with
the design, improper to the manufacturer’s guide book on installation and operation, not
satisfactory with provisions of the applied technical specifications, etc) shall be rejected for
acceptance and must be removed out of the Site;
i. The Contractor shall have to prepare the Site under the equipment installation section,
technicians, workers for operation, workers for repairing equipments, necessary power,
materials for the purpose of testing;
j. During the testing, the Contractor shall have to allocate sufficiently technicians and workers
on the site for timely settlement of arising incidents and mistakes;
k. The Contractor is responsible for following up, guiding the installation in accordance with
the technical requirements, the design, the technical description of the manufacturer, and is
obligated to test, with concerned parties, the equipment in accordance with the design power,
helping the Owner to exactly determine the quality of the installed equipments;
l. The Contractor is responsible for checking itself and completing the installation of
equipments, preparing in full the dossier for acceptance (minutes, as-built map, Works diary,
etc); the installation of equipments is performed in accordance with technique and the testing
is satisfactory with design requirement.
(3) Requirements with regard to the construction of the Project
-17-
APPLICABLE FROM JUNE 1st 2016
a. The Contractor shall have to ensure the performance under technical standards, regulations as
agreed by the Parties and current provisions of the laws;
b. To ensure that the Project shall be put into operation perfectly under request of the bidding
invitation dossier (or requiring dossier), the bidding application dossier (or proposal dossier),
commitments of the Contractor; documents clarifying the bidding dossier;
c. The Contractor must have the plan to carry out the construction, gather the equipments,
materials; allocate equipments and materials in the Site so as not to adversely affect the
surrounding activities; construction implementation method must be suitable to technological
requirements, be proper to supply progress for equipment, to construction progress and actual
conditions at the Site;
d. The Contractor make the general contract implementation progress and detailed contract
implementation progress on a monthly basis submitted to the Owner for approval as a basis
to implement the Contract. To have the measures for ensuring labour safety, environmental
hygiene, fire and explosion prevention, security during the construction;
e. Based on the construction and acceptance standards, the Design Dossier approved by the
Owner, the Contractor shall have process and plan for inspecting the Project’s quality,
ensuring the performance in accordance with the provisions of the laws;
f. The Contractor shall have to construct, complete the Project and repair any error found in the
Project in accordance with the design dossier approved by the Owner and comply with
current construction processes and norms issued by the State as well as be suitable to the
conditions of the Project and conform to the instruction of the Owner (or the Engineer);
g. During the installation and construction of equipments, it is required to strictly comply with
requirements of the design dossier approved by the Owner and instructions of the
manufacturer;
h. During the performance of the Contract, any damage or loss arises in relation to the Site,
staff, materials, equipments, the Contractor shall repair, compensate by its own costs;
-18-
APPLICABLE FROM JUNE 1st 2016
i. The Contractor is responsible for implementing of the Project with technical requirements
and in accordance with the completion time of the Work as stipulated in the Contract;
j. After the construction of the Project, the Contractor is responsible for the training, operation
guidance the Owner. The Contractor is obligated to provide the documents for guiding the
operation, operation process and documents for maintenance guidance of the Project;
k. After the pilot operation in Trial period, if the Project operate well and meets requirements,
the Owner shall accept the Works for putting into operation, use;
l. After the acceptance of the Works, the Contractor shall continue to continuously supervise
the operation of the Works in time for monitoring after acceptance of works and have reports
on the operation efficiency of the Works to the Owner;
m. Contractor shall ensure the efficient operation of the whole Project that meeting
requirements of the Owner under the Contract.
ARTICLE 1E. ADDITIONAL PROVISION
The Contractor commits itself to construct the Project:
(1) with all due skill, care and diligence, in a good, professional and workmanlike manner in
accordance with accepted international practices and standards in the Construction
industry and such other practices, standards, regulations, and codes as may be specified
by the Owner;
(2) in strict compliance with all applicable governmental, local and other competent
authorities' laws and regulations, practices, standards, norms and codes presently in effect
and becoming effective in the Socialist Republic of Vietnam during the performance of
the Project.
(3) apply for rights, approvals, permits and technical innovation rights and other activities
rights and ask for opinions from issuing authorities, necessary approvals and permits with
regards to methods, processes, and systems incorporated into the Project.
-19-
APPLICABLE FROM JUNE 1st 2016
(4) at its own costs, be responsible for obtaining all necessary licenses, permits, consents and
all necessary import, export licenses for customs clearance of Contractor’s personnel and
of any materials and equipment in respect of execution of the Project or any parts thereof
as from time to time required by the laws and regulations of Vietnam
In addition, the Contractor must always give priority to the issues related to Contracts, support
and protect the legitimate interests of the Owner in transactions with third parties.
ARTICLE 2. CONSTRUCTION AREA, SITE
The Owner are responsible to ensure and prepare for construction site and such other places
which are necessary for the construction work and are mentioned in the Design Documents
(hereinafter referred to as "Construction Area" ) on or before the date required to use this
construction area for construction works (or on or before the date specified in the Design
Documents). The staff of the Contractors involved in the construction must comply with all
rules and regulations applied by the Owner at a time.
The Contractor shall at all times during the construction of the Project, keep the Construction
Area clean and free from all hazards, accumulations of waste materials and rubbish and
debris, radioactive and other toxic substance as may be occasioned during the construction of
the Project caused by the Contractor’s employees and shall also keep all residential camps
and the Site of the Project in a sanitary condition as directed by the Owner.
After completion of the Project, and prior to the hand-over of the same, the Contractor shall
remove, store or dispose as may be directed by the Owner, from the Construction Area and
other areas where he operated, all buildings, rubbish, scraps, unused materials, storage tanks,
temporary power distribution lines, the Construction Equipment and all other temporary
facilities except those facilities being within the cost of the Project and having been provided
under the Contract which the Owner deems necessary for his future use, fill and dress all
holes and cavities made for his convenience, and leave all areas in good order and condition,
all as required by the Owner.
The Contractor acknowledges that the Owner may have other contractors or activities being
performed adjacent to, or associated with the Project, its operations, or the development of
this project, and, therefore, the Contractor has a duty to cooperate and coordinate with the
-20-
APPLICABLE FROM JUNE 1st 2016
Owner and its third party contractors regarding interfaces between the Project under this
Contract and other work associated with the project and adjacent activities or operations in
order to minimize disruptions, conflicts, and promote a safe construction environment. All
necessary operations for the execution and completion of the Project and the remedy for any
defects therein shall, so far as compliance with requirements of the Contract permits, be
carried on so as not to interfere unnecessarily or improperly with:
• Public construction or
• The access to, use and occupation of the public or private roads and footpaths to or of
properties whether in the possession of the Owner or to any other person.
The Contractor shall save harmless and indemnify the Owner in respect of all claims,
proceedings, damages, costs, charges and expenses whatsoever arising out of, or in relation
to, any such matters insofar as the Contractor is responsible therefore.
ARTICLE 3. COMMITMENTS
3.1 The Contractor hereby commits and warrants to the Owner that:
3.1.1 The Contractor is entitled to implement all the duties required by this Contract. At all
times during the term of this Contract, The Contractor holds, or is expressly authorized to
use, all patents, copyright or trademark rights, licenses, franchises and other intellectual
property necessary for the Project. The Contractor shall, at its sole cost and expense, keep
in full force and effect all professional and business permits, licenses and approvals
affecting the Contractor’s ability to perform the Project and otherwise necessary and
appropriate to enable the Contractor to perform this Contract.
3.1.2 The Contractor is financially solvent, able to pay its due debts and has sufficient working
capital and other resources to complete its obligations under this Contract.
3.2 The Contractor has made these commitments and warranties to the Owner and
acknowledges that the Owner is relying to a material extent on said representations and
warranties in entering into this Contract. The Contractor accepts the relationship of trust
and confidence established by this Contract and shall exercise its best skill and judgment
and shall cooperate with the Owner to further the interests of the Owner. The Contractor
-21-
APPLICABLE FROM JUNE 1st 2016
shall perform the Project under this Contract in accordance with the professional standard
and quality which prevails among reputable, well-qualified, internationally recognized,
licensed design/build general contracting, architectural and engineering firms performing
services of the nature and in the locations similar to the Project under the Contract. All
Project shall be performed by well-qualified, efficient, properly-trained and adequately
supervised Subcontractors, and employees of the Contractor in accordance with the
foregoing professional standards in condition that assignment to Subcontractor accepted
by the Owner.
ARTICLE 3A. COORDINATION WITH PROJECTS CLOSELY RELATED
The Owner, or the Supervision Party if so empowered by the Owner under the agreement for
supervisory services with the owner, shall coordinate the Project under the Contract and any
other works ordered by the Owner and performed by a third party contractor, if the respective
works are closely related to each other and such coordination is deemed necessary. The
Contractor shall follow and cooperate in such coordination to facilitate the performance of
the Project by the third party contractor.
ARTICLE 4. DETAILS OF CONTRACT PRICE, TAXES AND FEES
4.1 Details of the Contract Price
The Contractor shall submit a detailed quotation of the Contract Price (hereinafter referred
to as the “Detailed Quotation”) to the Owner or the supervision party for approval, promptly
after signing the Contract based on approved bid price and a progress schedule.
The Contractor shall be deemed to have satisfied itself as to the correctness and sufficiency
of the rates, prices and other cost details provided in the Contract which shall cover all its
obligations under the Contract and all matters and things required for the proper
performance, completion and guarantee of the Project.
4.2 Taxes and Fees
The Contractor shall be solely responsible and liable for, and shall at its own costs and
expenses pay and cause to be paid any and all applicable taxes, levies, fees, duties, levies,
-22-
APPLICABLE FROM JUNE 1st 2016
charges, port fees, port charges, port tariffs social security premiums, fees, licenses, fines,
penalties of whatsoever nature assessed or levied or imposed on all Equipment and
Materials, Contractor’s facilities, Temporary Project and other special tools, instruments and
apparatus imported for the Project or against the Contractor, its affiliates, its subcontractors,
its employees and its agents by the competent authorities of the Socialist Republic of
Vietnam or of any other applicable authority on account of or in relation to or in connection
with the performance of this Contract, including but not limited to withholding tax, value
added tax, corporation income tax, import duties, personal income tax, special consuming
tax, …in strict compliance with all laws, rules, regulations of the Socialist Republic of
Vietnam.
All taxes, levies, duties, customs fees and the like levied outside the Socialist Republic of
Vietnam in connection with the execution of this Contract will be at the Contractor’s
account.
The Contractor shall be responsible for and indemnify, keep indemnified and hold the
Owner harmless from and against any and all liabilities, proceedings, actions, demands,
suits, damages, losses, costs, charges, fines, penalties and claims of whatsoever nature
resulting from the Contractor’s failure to pay such taxes, levies and duties herein above and
to comply with this clause.
ARTICLE 5. SUBCONTRACTOR
The Contractor shall not entrust or subcontract the whole or a major part of the Project or
such a portion of the Project which stands or functions as an independent structure to any
third party without the prior written consent of the Owner.
No subcontract agreement shall release the Contractor from its obligations to the Owner
hereunder. The Contractor shall be responsible to the Owner for all the works and faults of
subcontractor. The Contractor is all the times responsible for the Project, and that the
performance thereof conforms in all respects to the requirement of this Contract, regardless of
any failure of any subcontractor to perform or any disagreement between any subcontractors
or between any subcontractor and Contractor.
-23-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 6. ASSIGNMENT OF RIGHTS AND OBLIGATIONS
(1) Neither party to the Contract shall assign or delegate to any third party the whole or part of
its rights and obligations arising from the Contract without the written consent of the other
party.
(2) Neither party to the Contract shall assign, lend, mortgage or give as security the Object of
Contract, any of the approved construction materials thereof for the construction of the
Object of Contract (including products located at the suppliers’ plants, facilities or the like;
hereinafter the same) and building equipment to any third party without the written consent
of the other party.
ARTICLE 7. PATENT AND OTHER INTELLECTUAL PROPERTY RIGHTS
The Contractor shall be liable for the consequence of using any construction materials,
building equipment or construction methods which may be subject to any intellectual
property right of a third party, which is protected under the relevant laws of Vietnam,
including, but not limited to, patent, utility model, design and trademark (hereinafter referred
to as the “Patent and Other Rights”)., However, that the Owner shall bear the costs and
expenses incurred and to be paid for the Contractor’s use of such construction materials,
building equipment or construction methods in the case where the Owner specifies them
without expressly indicating in the Design Documents that they are subject to the Patent and
Other Rights and where the Contractor was not aware of the existence of such Patent and
Other Rights.
The Intellectual property rights to the design drawings implemented by the Contractor based
on requirements, the cost of the Owner will belong to the Owner.
ARTICLE 8. PERFORMANCE BOND
(1) The Contractor shall have to guarantee in order to ensure the fulfillment of the Contract’s
obligations which is issued by a reputable credit organization accepted by the Owner with
guarantee level and submitting performance bond time for the Owner stipulated in Particular
conditions of the Contract.
-24-
APPLICABLE FROM JUNE 1st 2016
(2) The Contractor shall have to ensure that the performance bond is valid and effective until
the Contractor has finished the construction and completed and checked for acceptance of
the Project by the Owner;
(3) The Contractor shall not be permitted to get back the contract performance guarantee in case
of refusal of performing the Contract after the contract takes effect and other violations as
prescribed in this Contract..
ARTICLE 9. SUPERVISION
(1) Basing on the hiring and authorization Contract of the Owner, the Supervision Party shall
carry out the following duties, in addition to those specifically stipulated in the Contract :
a. Make arrangements with the Contractor, and if necessary, prepare explanatory drawings
and the like, and deliver them to the Contractor in order to correctly inform the
Contractor of the design intent ;
b. Deliver to the Contractor detailed drawings and other drawings prepared in accordance
with the Design Documents at necessary times for the Contractor to smoothly proceed
with the Project in accordance with the progress schedule ;
c. Review plans for construction submitted by the Contractor and advise, if necessary, the
Contractor thereon;
d. Review the working drawings, such as full-size drawings and shop drawings, and models
made by the Contractor according to the Design Documents to verify if they are in
compliance with the Design Documents and approve them;
e. Give instructions regarding construction, inspect and observe the construction of the
Project, and inspect, study and approve construction materials, building equipment and
samples of finishing works, as provided in the Design Documents ;
f. Confirm that the Project are in compliance with the Contract, including the design
drawings, explanatory drawings, detailed drawings and working drawings (hereinafter
collectively referred to as the “Drawings”) and the specifications ;
g. Check from the technical points of view, applications for progress or final payments
submitted by the Contractor ;
h. Check from the technical points of view, documents regarding changes in the Project,
time for completion of the Project or the Contract Price ;
-25-
APPLICABLE FROM JUNE 1st 2016
i. Confirm the completion of the Project and attend the acceptance, delivery of the Object
of Contract ;
j. Examine the conformity of the capacity of the construction contractor with the bid
quotation dossier and the construction contract, including: human resources, construction
equipment, specialized construction laboratory and the quality control system of the
construction contractor;
k. Supervise the implementation of the regulations on environmental protection for the
construction work according to the legislations on environmental protection; supervise
the safety measures for the adjacent works and the construction monitoring;
l. Supervise the labor safety control according to the provisions in the standards and
regulations in the contract and the legislations on labor safety;
(2) If the Owner empowers the Supervision Party to carry out the duties other than those
stipulated in paragraph (1) of this Article, the Owner shall inform the Contractor thereof in
writing.
(3) The Supervision Party shall promptly respond to requests by the Contractor for instructions,
inspections, tests, attendance, confirmations, examinations, approvals, opinions or
consultations, which are based on this Contract.
(4) Unless otherwise provided in the Contract, all notices and negotiations between the Parties
hereto regarding the Project shall be made through and in the presence of the Supervision
Party
(5) If, upon approval of the Owner, the Supervision Party appoints a representative for the
execution of all or part of his duties or appoints a resident supervisor at the Site, the
Supervision Party shall inform the Contractor in writing of his or their names and duties.
(6) Unless otherwise provided, all the instructions, confirmations or approvals given by the
Supervision Party to the Contractor shall be in writing. The Supervision Party is not entitled
to reduce any obligations of the Contractor under the Contract.
ARTICLE 10. SUPERINTENDENT
-26-
APPLICABLE FROM JUNE 1st 2016
(1) The Contractor shall assign tasks and authorize some particular individuals upon approval of
the Owner, these individuals possibly are: a Superintendent, a Supervisory Engineer or Chief
Engineer, who is in charge of technical control of the Project, and a Special Engineer under
laws of Vietnam and the Contractor shall inform the Owner of their names in writing.
(2) The Superintendent shall be responsible for the overall management of the Site; provided
that he shall report to the Supervisor the matters which are important to the operation of the
Site, such as maintenance of order, safety and sanitation, accident prevention, working hours
and so forth.
(3) The Superintendent shall be authorized to exercise all of the Contractor’s rights granted
under the Contract, except for those provided below :
a. To change the Contract Price ;
b. To change the time for completion of the Project ;
c. To request or receive any payment of the Contract Price;
d. To receive letters issued pursuant to paragraph (1) of Article 12 hereof ; and
e. To suspend the Project, terminate the Contract and claim for damages.
(4) Notwithstanding paragraph (3) of this Article, if the Contractor wishes to exercise any of his
authorities by himself rather than to delegate them to the Superintendent, the Contractor
shall inform the Owner to that effect in writing.
(5) One person may be appointed concurrently as the Superintendent, the Supervisory
Engineering or Chief Engineer, and the Special Engineer.
ARTICLE 11. REPORT ON PERFORMANCE OF WORKS
The Contractor shall report to the Supervision Party on the performance of the Project in
accordance with the Deign Documents, wherever the Design Documents so require.
ARTICLE 12. OBJECTIONS OF INDIVIDUALS CONCERNED WITH WORKS
(1) If any of the Contractor’s Superintendent, Supervisory Engineer or Chief Engineer, Special
Engineer or other employees, or subcontractors or their laborers, is deemed extremely
deficient in their performance or management of the Project, based upon the opinion of the
-27-
APPLICABLE FROM JUNE 1st 2016
Supervision Party the Owner may send a document clearly stating the reason for requiring
the Contractor to take necessary rectification measures.
(2) If the Contractor deems any measures taken by the Supervision Party’s representative or
resident supervisor at the Site to be improper or unreasonable, he may send a document
clearly stating the reason for requiring the Supervision Party to take necessary rectification
measures
(3) If any measures taken by the Supervision Party is deemed extremely improper or
unreasonable, the Contractor may make an objection to the Owner.
ARTICLE 13. CONSTRUCTION MATERIALS, EQUIPMENT
(1) All Equipment and Materials for incorporation in Project must be supplied with any and all
quality assurance documentation or other certification documents in respect of the
Equipment and Materials in accordance with international standards application for
construction industry or other standard accepted by the Owner or required by law.
(2) According to the requirements of the specifications, all supplies, equipment and other items
provided for the project must be in new condition, unused, generation of new products and
innovations in design and materials unless the contract stipulates otherwise
(3) The Contractor shall provide proper security measures to ensure that all Equipments and
Materials are protected against theft, fire, vandalism and other hazards.
(4) The Contractor shall use only such construction materials and building equipment that have
passed the inspection by the Supervision Party if such inspection is required in the Design
Documents, or that have passed the test, if such test is required in the Design Documents, as
the case may be.
(5) The direct cost of any inspection or test mentioned in paragraph (1) of this Article shall be
borne by the Contractor ; however, that the cost for those inspections or tests which are not
specified in the Design Documents and other exceptional costs shall be borne by the Owner.
(6) The Contractor shall remove from the Site any construction materials and building
equipment which have been rejected in any inspection or test and is responsible for handling
construction materials and equipment outside the radius of 30 kilometers from Owner’s
-28-
APPLICABLE FROM JUNE 1st 2016
address as the commitments in the Contract and ensuring the implementation in accordance
with the provisions of law
During the construction, the Contractor is obligated to keep the working site clean and safe
without any danger, unused materials, rubbish, scraps and etc which are unable to
recycle/reuse according to the process of the Owner (hereinafter referred to as “Waste”).
The Contractor shall be responsible for collecting and handling Waste arising during
implementing this Contract with the Owner.
The Contractor commits to treat Waste pursuant to the content of this Contract and the
current laws and regulations, and shall be responsible for any consequence, cost relating to
Waste treatment.
The Contractor shall take any necessary measure to guarantee that Owner is exempted from
all responsibilities regarding Waste treatment and shall compensate for Owner if Owner
bears any damage arising from Waste treatment.
(7) The quality of construction materials and building equipment shall be in accordance with the
Design Documents. If the quality is not specified in the Design Documents, such
construction materials or building equipment shall be of medium quality.
(8) No construction materials or building equipment delivered to the Site shall be removed from
the Site without the approval of the Supervision Party
(9) If any construction equipment is deemed to be improper for whatever reason, the
Supervision Party shall have right to require the Contractor to replace it.
(10) Unless the contract stipulates otherwise, the ownership of the equipment and materials
provided by the Contractor for the implementation of the Project will be transferred to the
investor when it is shipped to the construction area.. This transfer of title shall not be
construed to mean an acceptance of the Equipment and Materials and to release the
Contractor from his responsibility for the Project upon which payments have been made.
The Contractor shall continue to be responsible for the quantity, quality and performance of
-29-
APPLICABLE FROM JUNE 1st 2016
such Equipment and Materials, and for their compliance with the specifications, in
accordance with the Contract.
ARTICLE 14. FURNISHED MATERIALS OR LENT ARTICLES
(1) Construction materials and building equipment furnished by the Owner (hereinafter referred
to as the “Furnished Materials”) or articles lent by the Owner (hereinafter referred to as the
“Lent Articles”) shall be required to have passed the inspections or tests of the Supervision
Party
(2) If the Contractor has any objection to the results of the inspections or tests mentioned in
paragraph (1) of this Article, he may require re-inspection or re-test thereof.
(3) If, after receipt of the Furnished Materials or the Lent Articles, the Contractor considers that
they are unsuitable or improper for use in the Project for any reason such as latent defect
being discovered, which was is not apparent at the time of the inspection or test mentioned in
paragraph (1) or (2) of this Article, the Contractor shall forthwith inform the Supervision
Party to that effect and request the instructions.
(4) The Furnished Materials and Lent Articles shall be delivered in accordance with the
requirements of the progress schedule, and unless otherwise specified in the Design
Documents, they shall be delivered to the Site.
(5) The Contractor shall carefully manage the custody and use of the Furnished Materials and
the Lent Articles.
(6) Unless otherwise provided in the Design Documents, the Contractor shall abide by the
instructions of the Supervisor in the use of the Furnished Materials and disposal of surplus
Furnished Materials (except surplus Furnished Materials paid for by the Contractor).
(7) The place to which the Contractor shall return the surplus Furnished Materials (except those
paid for by the Contractor) and the Lent Articles which are no longer required, shall be the
Site, unless otherwise specified in the Design Documents.
-30-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 15. SUPERVISION PARTY ’S ATTENDANCE, PREPARATION OF WORK
RECORD
(1) Before the Contractor undertakes such works that require the Supervision Party’s
attendance according to the Design Documents, the Contractor shall give notice to the
Supervisor to that effect.
(2) If so instructed by the Supervision Party, the Contractor may perform the said works
without the Supervision Party ’s attendance, notwithstanding the provisions of paragraph
(1) of this Article. In such a case, the Contractor keeps proper records, including
photographs of the work and submits them to the Supervision Party
ARTICLE 16. AMBIGUITY OR DISCREPANCY IN DRAWINGS AND
SPECIFICATIONS, CHANGES IN CONDITIONS
(1) If any of the following events occurs, the Contractor shall forthwith give written notice
thereof to the Supervision Party
a. If the Contractor discovers any ambiguity in the Drawings or the specifications, any
discrepancy between the Drawings and the specifications, or any error or omission in the
Drawings or the specifications ;
b. If the Contractor recognizes that the construction works comply with Drawings, the
specifications or instructions of the Supervision Party is not appropriate
c. If the Contractor encounters at the Site any physical, geological or underground water
conditions, any obstructions to the execution of the Project or other conditions, and such
conditions or obstructions are different from those indicated in the Design Documents ;
or
d. If the Contractor encounters at the Site any obstruction to the execution of the Project
which was not foreseeable.
-31-
APPLICABLE FROM JUNE 1st 2016
(2) The Supervision Party shall, upon receipt of the notification mentioned in paragraph (1) of
this Article, or upon discovery by himself of the facts enumerated in paragraph (1) of this
Article, promptly give instructions to the Contractor in writing.
(3) If, due to the circumstances mentioned in paragraph (2) of this Article, it becomes necessary
to make changes in the Project, extend the time for completion of the Project or adjust the
Contract Price, the matter shall be agreed upon by negotiation between the Owner,
Supervision Party and Contractor.
ARTICLE 17. WORKS ARE NOT IN COMPLIANCE WITH DRAWINGS OR
SPECIFICATIONS
(1) Any part of the Project which shall be found not to be in compliance with the Drawings or
the specifications shall be promptly and properly re-executed by the Contractor at his own
expense in accordance with the instructions of the Supervision Party. In such case, the
Contractor may not request any extension of the time for completion of the Project.
(2) If the Supervision Party has reasonable doubts whether any part of the Project complies with
the Drawings or the specifications, he may, by notice to the Contractor stating the reasons
therefore, and after obtaining the written consent of the Owner, uncover such part as is
necessary for examination.
(3) If the part uncovered and examined in accordance with paragraph (2) of this Article is found
not to comply with the Drawings or the specifications, the expenses for uncovering and
examination shall be borne by the Contractor. If, however, the said part is found to comply
with the Drawings and the specifications, the expenses incurred for the uncovering,
examination and reinstatement shall be borne by the Owner, and the Contractor may, by
expressly stating the reasons therefore, claim to the Owner an extension of the time for
completion of the Project as appropriate.
(4) The Contractor shall not be responsible for any part of works not in compliance with the
Drawing or the specifications which result from any of the following causes :
a. Due to instructions of the Supervision Party;
-32-
APPLICABLE FROM JUNE 1st 2016
b. Due to the nature of the Furnished Materials, the Lent Articles, specified construction
materials or building equipment, or due to specified construction methods ;
c. Due to construction materials or building equipment which passed the inspections or tests
as provided in paragraphs (1) or (2) of Article 13 hereof ; or
d. Otherwise attributable to the Owner or the Supervisor.
(5) Notwithstanding the provisions of paragraph (4) of this Article, if the Contractor willfully or
with gross negligence fails to perform the Works in accordance with the Drawings and the
specifications, or if the Contractor has knowingly neglected to give advance notice to the
Supervisor of its inappropriateness, then the Contractor shall not be relieved from the
responsibility for such works. Provided, however, that the Contractor shall not be responsible if
the Supervisor fails to give proper instructions although the Contractor gives advance notice of
its inappropriateness.
ARTICLE 18. PREVENTION OF DAMAGE
(1) The Contractor shall, at his own expense, take necessary measures in accordance with the
Design Documents and relevant laws, ordinances and regulations as are necessary to prevent
damage to the Object of Contract, construction materials and building equipment, adjacent
structures or a third party, until the completion and delivery of the Project.
(2) The expenses for measures taken for or in connection with the protection of structures
adjacent to the Object of Contract shall be borne by the Owner upon agreement between the
Owner, Supervision Party and Contractor that it is beyond the scope of measures to be taken
pursuant to paragraph (1) of this Article and neither fair nor justifiable to include such
expenses on the Contract Price.
(3) The Contractor shall take such measures as he deems necessary and expedient for the
prevention of accident, after consultation with the Supervision Party; However, that the
Contractor may notify to the Supervision Party thereof after taking such measures in case of
emergency.
(4) Whenever the Owner or the Supervision Party deems necessary and requests the Contractor
to take appropriate measures for the prevention of accidents, the Contractor shall promptly
comply therewith.
-33-
APPLICABLE FROM JUNE 1st 2016
(5) The costs and expenses for the measures taken pursuant to paragraphs (3) and (4) of this
Article shall be borne by the Contractor.
ARTICLE 19. DISPUTE AND DAMAGE TO THIRD PARTY
(1) If any damage is caused to a third party by the performance of the Project, the Contractor
shall compensate for such damage. However, the Owner shall compensate for such damage
if the damage has arisen from causes attributable to the Owner
(2) Notwithstanding the provisions of paragraph (1) of this Article, the Owner shall compensate
for damage caused to a third party due to reasons beyond the control of the Contractor even
if he exercises due care and attention in performing the Project. Such reasons include, but
are not limited to, noise, vibration, ground settlement and interruption of ground water.
(3) In any of the cases mentioned in paragraphs (1) and (2) of this Article, or in the event of any
disputes with a third party in connection with the performance of the Project, the Contractor
shall settle the matter. However, that the Owner shall assist and cooperate with the
Contractor to settle in the capacity that the Owner deems appropriate if it is difficult for the
Contractor alone to settle the matter and the Contractor requests the Owner in writing for
supporting to settle.
(4) The Owner shall settle any dispute with a third party or the matter of damage to a third party
caused by obstruction of sunshine or radio waves, or by wind arising from the Object of
Contract or by any other reason attributable to the Owner, with the assistance of the
Contractor, if necessary. In this case, the Owner shall compensate the said third party for the
damage caused
(5) In any of the cases mentioned in paragraphs (1) to (4) of this Article, the Contractor may, by
expressly stating the reasons therefore, claim to the Owner an extension of the time for
completion of the Project as appropriate.
ARTICLE 20. GENERAL DAMAGE
-34-
APPLICABLE FROM JUNE 1st 2016
(1) The Contractor shall be liable for any loss or damage which has been caused to the Object of
Contract, construction materials, building equipment, the Furnished Materials or the Lent
Articles, and any loss or damage in general which has been caused in connection with the
performance of the Project, if such loss or damage occurs prior to the delivery of the Project
and no request for extension and extension of the time for completion of the Project shall be
allowed therefore.
(2) The loss or damage mentioned in paragraph (1) of this Article shall belong to the Owner, the
Owner and the Contractor may, by expressly stating the reasons therefore, claim to the
Owner an extension of the time for completion of the Project if having occurrence as
follows :
a. When the Contractor has been unable to commence the Project by the date of
commencement due to the Owner’s cause, or when the Owner has postponed or
suspended the Project ;
b. When the Contractor has had to suspend the Project due to delay of the delivery of the
Furnished Materials or the Lent Articles :
c. When the Contractor has not commenced, or has suspended the Project due to delay of
advance or partial payments ; or
d. When there exists any other cause which is attributable to the Owner or the Supervision
Party.
ARTICLE 21. DAMAGE CAUSED BY FORCE MAJEURE
(1) If any of the executed works, temporary works, construction materials and building
equipment already delivered to the Site (including the Furnished Materials paid for by the
Contractor) or construction equipment suffers any loss or damage due to Force Majeure
events (hereinafter referred to as “Force Majeure”), the Contractor shall notify the Owner of
the details of such loss or damage promptly after its occurrence in writing in the earliest
possibly.
(2) The Owner shall bear the costs and expenses caused by the loss or damage mentioned in
paragraph (1) of this Article where the Owner, Supervision Party and Contractor agree that
such loss or damage is serious and that the Contractor has exercised due care and attention to
appropriately prevent.
-35-
APPLICABLE FROM JUNE 1st 2016
(3) If such loss or damage is covered by fire insurance, contractors’ all risk insurance or
otherwise, any amount recovered shall be deducted from the amount to be borne by the
Owner as provided for in paragraph (2) of this Article.
ARTICLE 21A. FORCE MAJEURE EVENTS
(1) Force majeure events are the occurred events with objective characters which are beyond the
control of the parties concerned such as: earthquake, storm, flood, cyclone, tsunami,
landline, fire, war or risk of potential war, etc. and other unforeseen disasters, policy changes
or prohibition of the competent authority of Vietnam, etc.
The unfulfilled obligation of a party due to the occurrence of the force majeure events shall
not be the basement for the termination of the Contract of other party. However, the party
suffering such force majeure event shall be obliged to:
+ Implementing the appropriate measures to avert and to replace promptly and quickly in
order to limit the maximum impact caused by force majeure events.
+ Notifying promptly other party in writing of such force majeure events within seven
(07) days from the date of occurrence of the force majeure event, in which shall specify
the obligations, the works of which are or shall be prevented.
(2) In case of force majeure events, the terms of Contract performance shall be extended
equivalent to the time of occurring such force majeure event in which the suffering party is
not able to conduct its obligations under the Contract.
ARTICLE 22. INSURANCE
(1).From the Effective Date and until the expiry of the work warranty, the Contractor shall at
its own cost effect and maintain all the necessary insurance policies acceptable to the
Owner or requested by the Owner and in compliance with applicable laws and
regulations of the Socialist Republic of Vietnam and the Contractor’s country for its
equipment, facilities, professions activities and personnel as maybe supplied hereunder
for the performance and provision of the Project including but not limited to
-36-
APPLICABLE FROM JUNE 1st 2016
Comprehensive General Liability (Third Party) insurance, Workman's Compensation,
Contractor’s all risk insurance, Automobile Liability insurance, Professional Liability
Insurance. The same shall apply to any other insurance prescribed in the Design
Documents.
(2).The Contractor shall ensure that the insurance policy shall include the Owner as the
beneficiary in the insurance coverage of risks and liabilities assumed by the Contractor
under this Contract. In any case, the Contractor shall be liable for the full amount of the
actual loss and/or cost of repair and replacement including the excess of Contractor’s
and/or Owner’s insurance coverage and include any deductible specified in Contractor’s
and/or Owner’s insurance coverage in case of the loss is not covered , unless otherwise
provided in the Contract.
(3).The Contractor shall submit original certificates of insurance as required above to the
Owner and shall provide evidence that such insurances are current and in force. If the
Contractor takes out and maintains any insurance other than those provided for in
paragraph (1) of this Article on the Object of Contract, construction materials, building
equipment and so forth, the Contractor shall promptly notify the Owner thereof right after
insurance claim takes effect.
ARTICLE 23. COMPLETION, INSPECTION
(1) Upon completion of the Project, the Contractor shall confirm that the Project are in
accordance with the Design Documents and request the final inspection of the Supervision
Party, and the Supervision Party shall promptly comply with the request and inspect the
Project in the presence of the Contractor.
(2) If any part of the Project does not pass the inspection, the Contractor shall repair or rectify
the works by the time for completion of the Project or within such other time as may be
designated by the Supervision Party, and shall have the works re-inspected by the
Supervision Party
(3) In compliance with the Supervision Party’s instructions, the Contractor shall remove the
temporary construction facilities, clean up the Construction Area and take such other
measures as appropriate by the time for completion of the Project or within such other time
as may be designated by the. Supervision Party
-37-
APPLICABLE FROM JUNE 1st 2016
(4) If, without justifiable reason, the Contractor delays in taking any measures mentioned in
paragraph (3) of this Article, the spite of the Owner’s notices to do so, the Owner may take such
measures in lieu of the Contractor and charge the expenses therefor to the Contractor.
ARTICLE 24. CONDITIONS ON CHECK AND ACCEPTANCE AND HAND-OVER THE
WORKS
(1) Conditions on check and acceptance:
a. The check and acceptance shall comply with the legal regulations on construction
quality management.
b. The Owner shall conduct the check and acceptance for each work, each section, each
stage and each Work Item and check and acceptance to commission of works. In
particular, there must be check and acceptance of each section of concealed works, and
there must be drawings of completed works prior to subsequent jobs being carried out
which shall conceal the acceptance object.
c. The Owner shall only conduct the check and acceptance when the object of the check
and acceptance has been completed and there is a complete file as required by
regulations.
d. Works shall be accept and use when ensuring that it meet the design and quality
requirements, quality , and achieve the prescribed standards.
(2) Conditions on handing-over the works for putting into operation:
a. Satisfying the requirements on principles, contents and hand over process of completed
works and put into using in accordance with the laws on construction.
b. Ensuring safety during operation and exploitation when works are commissioned.
c. Council of check and acceptance, hand-over must be established for the check and
acceptance and hand-over the Project, the members of such Council shall comply with
the regulations of the laws on check and acceptance, hand-over the Project.
-38-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 25. PARTIAL DELIVERY
(1) If any part of the Object of Contract is delivered to the Owner prior to the completion of the
Project (such delivery hereinafter referred to as the “Partial Delivery” and the subject of
Partial Delivery hereinafter referred to as the “Delivery Part”), the Partial Delivery shall be in
accordance with the EPC contract and the Design Documents. If the EPC contract and the
Design Documents do not mention about the Partial Delivery, the Owner shall obtain the
Contractor’s written consent to the Partial Delivery after the relevant part undergoes a
technical examination by the Supervision Party regarding the Partial Delivery and after
consulting with the Contractor in respect to fixing the value of the Delivery Part (hereinafter
referred to as the “Value of the Delivery Part”).
(2) Upon completion of the Delivery Part, the Contractor shall confirm that the Delivery Part is
in accordance with the Design Documents and request the Supervision Party to make
inspection thereof, and the Supervision Party shall promptly comply with the request and
inspect the Delivery Part in the presence of the Contractor.
(3) If the Delivery Part does not pass the inspection provided in paragraph (2) of this Article, the
Contractor shall make repair or rectification of the Delivery Part within such time as may be
designated by the Supervision Party and shall request the Supervision Party to re-inspect the
Delivery Part
(4) Upon passing the inspection or re-inspection as provided in paragraphs (2) or (3) of this
Article, the Owner may take delivery of the Delivery Part upon payment of the Value of the
Delivery Part.
(5) The Owner, or the Supervision Party if held responsible for the procedures stipulated herein
under the agreement for supervisory services with the Owner, shall be responsible for the
legal procedure required relevant to the Partial Use. The Owner shall bear and for the
necessary costs and expenses for such procedures.
ARTICLE 26. PARTIAL USE
-39-
APPLICABLE FROM JUNE 1st 2016
(1) If the Owner uses any part of the Object of Contract during the performance of the Project
(such use hereinafter referred to as the “Partial Use”), the Partial Use shall be in accordance
with the EPC contract and the Design Documents. If the EPC contract and the Design
Documents do not provide for the Partial Use, the Owner shall obtain the Contractor’s
written consent to the Partial Use after the relevant part undergoes a technical examination
by the Supervision Party regarding the Partial Use and after consulting with the Contractor
in respect of any necessary change in the time for completion of the Project and of the
Contract Price.
(2) In the case of the Partial Use, the Owner shall comply with the instructions of the Contractor.
(3) If any loss or damage is caused to the Contractor due to any conduct of the Owner in
violation of the instructions as provided in paragraph (2) of this Article, the Owner shall
compensate for such loss or damage.
(4) The Owner, or the Supervision Party if held responsible for the procedures stipulated herein
under the agreement for supervisory services with the Owner, shall be responsible for the
legal procedure required relevant to the Partial Use. The Owner shall bear the necessary
costs and expenses for such procedures.
ARTICLE 27. REQUEST FOR PAYMENT, PAYMENT, HAND-OVER OF PROJECT
(1) Unless otherwise provided in the Contract, after the Project have passed the acceptance
mentioned in paragraph (1) Article 24 hereof, the Contractor shall hand-over the Object of
Contract to the Owner, and at the same time the Owner shall make the full and final payment
of the Contract Price to the Contractor in accordance with the Contract.
(2) Both Parties may reach an agreement that the Contractor should request the partial payment
of the Contract Price before the date of completion of the Project under the EPC contract. If
the partial payment is conducted based on the rate of work progress, the Contractor may
request the payment of nine tenth (9/10) of the value of the performed work, the approved
construction materials, equipments inspected by the Supervision Party.
(3) If the Owner accepts that the Contractor shall receive the payment under the schedule as
mentioned in the paragraph (2) of this Article, the amount must be approved by the
-40-
APPLICABLE FROM JUNE 1st 2016
Supervision Party and the Contractor shall send the request for payment to the Owner at the
date as set forth in the EPC contract.
(4) If the Contractor has been paid in advance, the amount based on the schedule as mentioned
in the paragraph (2) of this Article will be calculated under the following method: :
(Contract Price – Payment amount in advance)
A = B x Contract Price
A= Payment amount per request
B= Payment amount based on the schedule mentioned in the paragraph (2).
(5) Payment Volume: When completing the total volume as in the Contract, the Parties shall
conduct: the acceptance, finalization and liquidation of the Contract, the Owner has to pay
in full under the signed Contract after the acceptance of the Project.
The Contractor shall warrant the work as regulated and agreed by the Parties.
(6) Payment dossier: The Contractor shall submit three (03) payment dossiers to the Owner at
the time specified in Article 4 – Particular Conditions in the forms accepted by the Owner.
The payment dossier must include the following documents:
a. The Contractor's request for payment which must have the following details:
value of the volume completed under the Contract, value of the additional job
volume (if any), deduction of advances and the value requested to be paid in the
period following the clearing of these amounts, certified by representatives of the
Owner and the Contractor
b. A written record of takeover test of volumes completed in the payment period
with certification by representatives of the Owner or the Supervision Party (if
any) and the Contractor. This written record serves as written certification of the
completion of Project, Project Items or job volumes within the scope of works or
jobs to be performed under the Contract requiring no certification of detailed
completed volumes:
c. A calculation table of the values of additional volumes (if any) outside the signed
Contract, certified by representatives of the Owner or the Supervision Party (if
any) and the Contractor:
d. Other documents as agreed upon by the Parties which are accepted by the Owner.
-41-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 28. DEFECT LIABILITY
(1) If any defect is found in the Object of Contract, the Owner may demand repair thereof by the
Contractor, specifying a reasonable period for the repair, or claim damages against the
Contractor either in lieu of, or in addition to such repair. However, that if the defect is not
serious and excessive expense would be incurred for the repairment, the Owner shall
consider and decide whether the Contractor needs to repair.
(2) The risks and defects repair costs shall be borne by the Contractor if and at the work volume
which is attributed to:
a) The equipments, materials and workmanship are not suitable to the Contract.
b) The Contractor does not follow other obligations.
(3) The period of overcome defect liability under paragraph (1) of this Article shall be one (1)
year with the wood construction, two (2) years with the stone, metal, concrete or other
similar material constructions, or other sustainable constructions or other underground
constructions from the date of hand-over mentioned in paragraph (4) of Article 26 or
paragraph (1) of Article 27 hereof; however, that if such defects have been willful caused by,
or due to gross negligence on the part of the Contractor, the said one (1)- year period shall be
extended to the five (05)- year one and the two(02)-year period shall be extended to the ten
(10)- year one.
(4) The Contractor shall not be liable for defects in the building equipment, interior decorations,
furniture or other similar items, unless the Supervision Party demands the Contractor to
repair or replace such defects immediately upon inspection at the time of delivery of the
Object of Contract. However, that the Contractor shall be liable for latent defects in such
items for one (1) year from the date of delivery of the Object of Contract.
(5) Notwithstanding the provisions of paragraph (1) of this Article, if the Owner finds any defect
in the Object of Contract at the time of hand-over thereof, the Owner may not demand repair
or damages unless a written notice identifying the defect was given to the Contractor without
delay. Provided, however, that the foregoing sentence shall not apply, if the Contractor was
aware of the existence of the defect.
-42-
APPLICABLE FROM JUNE 1st 2016
(6) If the Object of Contract has been destroyed or damaged due to the defect mentioned in
paragraph (1) of this Article, the Owner may not exercise the rights stated in the said
paragraph (1) unless they are exercised within the periods prescribed in this Contract and in
no case later than six (6) months from the date of the said destruction or damage.
(7) The provisions of paragraphs (1) through (5) of this Article shall not apply to any defect in,
or destruction or damage to, the Object of Contract which has been caused by any of the
causes stated in paragraph (4) of Article 17 hereof. However, that the foregoing sentence
shall not be applied, if the matter falls under paragraph (5) of Article 17 hereof.
ARTICLE 29. CHANGES IN WORKS, CHANGES IN TIME FOR COMPLETION
(1) The Owner may, when necessary, order additional or extra works or changes in the Project.
(2) The Owner may, when necessary, order the Contractor to change the time for completion of
the Project.
(3) If any loss or damage has been caused to the Contractor by virtue of either of paragraphs (1)
or (2) of this Article, the Contractor may claim compensation to the Owner for the said loss
or damage.
(4) In addition to the Contractor’s rights provided elsewhere in the Contract, the Contractor may,
be expressly stating the reason therefor, claim to the Owner an extension of the time for
completion of the Project as appropriate, under such circumstances as are justifiable to the
Contractor, which include, but are not limited to, addition or change in the Project, Force
Majeure, coordination of the Project with related works.
ARTICLE 30. ADJUSTMENT OF CONTRACT PRICE
(1) Either party may, by expressly stating the reason therefor, demand an adjustment of the
Contract Price as necessary due to any of the following cases;
a. If the project is ordered for additional or extra work, or the Project is changed;
-43-
APPLICABLE FROM JUNE 1st 2016
b. If the time for completion of the Project is changed;
c. If additional or extra cost is incurred by coordination in accordance with the provision of
Article 3 hereof;
d. If items, quantities, times for delivery, places of delivery, or places of return of the
Furnished Materials or the Lent Articles are changed;
e. If, during the term of the Contract, the Contract Price is found to have become obviously
inappropriate due to enactment, revision or abrogation of the laws, ordinances and
regulations; drastic changes in economic conditions or other unforeseeable causes;
f. If, in a long-term contract, the part of the Contract Price for the work which shall be
executed after one (1) year from the date of entering into the Contract is found to have
become inappropriate due to enactment, revision or abrogation of the laws, ordinances
and regulations, or changes in the commodity prices, wages and the like ; or
g. If, in the case of resuming the work which has been suspended or has suffered from
damage by force majeure, the Contract Price is deemed to have become obviously
inappropriate.
(2) In adjusting the Contract Price, the amount of adjustment for decreased or omitted portions
of the Project shall be determined based on the unit prices stated in the Detailed Statements
approved by the Owner or the Supervision Party, and for increased portions based on the
current market prices, unless otherwise agreed upon by the Parties hereto.
(3) The Contract Price must only be adjusted if the Parties agree to do so based on the request of
the Owner to the Contractor on additional/extra work.
ARTICLE 31. DELAY IN PERFORMANCE, LIQUIDATED DAMAGES AND
CONTRACTUAL BREACH PENALTY
(1) If the Contractor fails to deliver the Object of Contract within the time for completion of the
Project or within such other time as extended in accordance with the Contract due to causes
attributable to the Contractor, the Owner may, for each calendar day of delay, demand all
-44-
APPLICABLE FROM JUNE 1st 2016
actual liquidated damages due to the delay from the Contractor and suffer penalty for delay
performing Contract.
(2) If the Contractor violates the quantity and quality as stipulated in the Contract as well as in
the current provisions, the Contractor must remedy these quantity and quality breaches. The
costs for remedying and arising damages shall be borne by the Contractor. In addition, the
Contractor must be liable for the payment of a penalty for breaching quality and quantity
regulated in Particular conditions of the Contract.
(3) If the Owner is in arrears of the final payment of the Contract Price pursuant to the
Contract’s provisions, the Contractor may demand penalty for delay payment according to
penalty level stipulated in Particular conditions of the Contract.
(4) If the Owner has delayed advance or partial payments, the provisions of paragraph (3) of this
Article shall apply.
ARTICLE 32. OWNER’S RIGHTS TO SUSPEND PROJECT OR TERMINATE THE
CONTRACT
(1) The Owner may suspend the Project or terminate the Contract in any of the following cases
by notifying the Contractor to this effect in writing and in such cases. The Owner is not
responsible for the Contractor’s damages and losses due to such suspension or termination.
a. If the Contractor fails, without justifiable reason, to commence the Project after the date
of commencement;
b. If the progress of the Project is extremely behind schedule and it is deemed unlikely that
the Contractor will complete the Project within the time for completion of the Project or
within a reasonable time thereafter ;
c. If the Contractor is in serious breach of the obligations of the Contract;
d. If the Contractor is deprived of or loses his Contractor’s license granted under the
provisions of the laws;
e. If it is deemed that the Contractor is unlikely to proceed with the Project due to reasons,
such as suspension of payment by the Contractor, which include, but are not limited to,
-45-
APPLICABLE FROM JUNE 1st 2016
dishonoring any draft, promissory note or cheque issued by the Contractor due to
shortage of funds, or
f. If the Contractor proposes to terminate the Contract for any reasons other than those
provided in paragraph (4) of Article 33 hereof.
(2) The Owner may require the Contractor to resume the work suspended under the provisions
of paragraphs (1) of this Article by notifying in writing to the Contractor
(3) If the work suspended pursuant to paragraph (1) of this Article is recommenced,
the Contractor may, by expressly stating the reasons therefor, claim to the Owner
an extension of the time for completion of the Project as appropriate.
ARTICLE 33. NO CORRUPT / BRIBERY CONDUCT
Should the Contractor, and where applicable, the Contractor’s agents or sub-contractors
including any director/employee or any other person acting or purporting to act on behalf of the
Contractor pay or offer to pay, give or offer to give any money or make any gift of whatsoever
nature, whether by way of commission, gratuity or otherwise or lending or offering to lend any
money, or giving or offering to give any other valuable consideration to any person in the
employ of the Purchaser and/or civil servant/Public officials and/or any other third party
including but not limit the individual/organization/agencies have right to make decision or affect
to the implementation of contract/ transaction between two parties then the Purchaser shall be
entitled to summarily cancel or terminate the Contract, without payment to the Contractor of any
damages whatsoever including consequential damages, loss of business and/or profits resulting
from such termination or cancellation
ARTICLE 34. CONTRACTOR’S RIGHTS TO SUSPEND WORKS OR TERMINATE
THE CONTRACT
(1) The Contractor may suspend the Project in any of the following cases if the breaches is not
corrected within a reasonable period since the Contractor sent a written notice hereof to the
Owner :
a. If the Owner has delayed in making advance or partial payments ;
-46-
APPLICABLE FROM JUNE 1st 2016
b. If the Owner declines the Contractor’s request for negotiation under paragraph (3) of
Article 16 hereof without justifiable reason ;
c. If the performance of the Project is impossible because the Owner fails to make the
Construction Area mentioned in Article 2 hereof available to the Contractor for the
execution of the Project, or because of Force Majeure or other justifiable reasons ; or
d. If the Project are extremely delayed due to causes attributable to the Owner, other than
the causes mentioned in sub-paragraphs a. to c. above.
(2) The Contractor shall recommence the suspended work when the causes mentioned in
paragraph (1) of this Article have been resolved.
(3) If the suspended work is recommended pursuant to paragraph (2) of this Article, the
Contractor may, by expressly stating the reasons therefor, claim to the Owner an extension
of the time for completion of the Project, as appropriate.
(4) The Contractor may terminate the Contract by notifying the Owner in writing to this effect,
in any of the following cases :
a. If the Project are delayed or suspended due to the reasons stipulated in paragraph (1) of
this Article in the aggregate for more than one forth (1/4) of the term of the Project, or
for more than two (2) months ;
b. If the Contract Price has been reduced by two-thirds (2/3) or more because the Project
have been substantially reduced or omitted by the Owner ; or
c. If the Owner breaches the Contract and it is deemed that the performance of the Contract
is impossible due to the said breach ; or
d. If it is deemed that the Owner is unable to pay the Contract Price due to reasons such as
suspension of payment, which include, but are not limited to, dishonoring any draft,
promissory note or cheque issued by the Owner due to shortage of funds (hereinafter
referred to as the “Events,”) the Contractor may suspend the Project or terminate the
Contract by notifying the Owner in writing to this effect. If the Project is suspended due
to the Events, and the Events are resolved, then paragraphs (2) and (3) of this Article
shall apply.
(5) In each of the cases mentioned in paragraphs (1) or (4) of this Article, the Contractor may
claim damages to the Owner therefor.
-47-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 35. MEASURES TO BE TAKEN UPON DELAY OF CONTRACT
(1) In the case of Delay of the Contract, accounts shall be settled by negotiation between the
Owner, Supervision Party and Contractor, on the condition that all of the executed works
and the approved construction materials and building equipment (including the Furnished
Materials paid for by the Contractor) are to be taken over by the Owner.
(2) In the case where the Owner terminates the Contract, the Contractor shall refund to the
Owner the sum overpaid, if any, as a result of the settlement of accounts.
(3) In the case of Delay of the Contract, each of the parties shall remove its belongings from the
Site and take other necessary measures including cleaning-up of the Site, in such manner and
within such period of time as may be agreed upon between the Owner, or the Supervision
Party
(4) If either party, without justifiable reason, delays in taking the measures stated in paragraph
(3) of this Article, despite having been given written notice by the other party, the other party
may take the measures in lieu of the delaying party and charge the expenses thereof to the
delaying party.
ARTICLE 36. WARRANTY OF THE WORKS
(1) The Contractor shall be responsible for the warranty of the construction after handing-over to
the Owner. Warranty contents include the remedy, repair or replace of the equipments having
faults, defects or when the work does not use normally due to the Contractor’s faults.
(2) The Contractor shall be fully responsible for making good by repair, fixing, correction or
replacement with all possible speed at his own expense any inaccuracy, miscalculation, error,
omission, defect in or damage of the Project which may appear or occur during the Warranty
Period and/or which may be deemed by the Owner as latent inaccuracy, miscalculation, error,
omission or defect and/or which arises either from:
-48-
APPLICABLE FROM JUNE 1st 2016
a. any defective, inaccurate or incorrect engineering or design; or
b. any defective, inaccurate or incorrect information or data;
c. any act, miscalculation or omission o is done by the Contractor during the said
Warranty Period and/or before delivery of the Final Documents; or
All costs incurred in performing such corrective Project shall be at the Contractor’s account.
It is understood that no exclusion or limit of liability will apply in case of gross negligence or
willful misconduct of the Contractor.
(3) The remedy of these defects must be conducted in time for repairing warranted errors
stipulated in Particular Conditions. If such time limit expires, the Contractor does not
commence this remedy, the Owner is entitled to appoint another contractor (third party) to
remedy these defects. The Contractor will be liable for all costs for such remedy for paying
the third party. The Contractor shall pay the third party within 10 days after receiving the
Owner’s notice on such payment. In case that the said time limit for payment expires, the
Contractor fails to pay such costs, the Owner shall proceed in accordance with the Article 37
hereof so as to request the payment from the Contractor.
(4) The period of warranty is stipulated in the Article 28 of this Contract.
(5) Guarantees for the maintenance of the Project:
(a) The Contractor is responsible for paying a deposit for guaranteeing the maintenance of
the Project equivalent to 5% of the Contract Price into the bank account of the Owner within
seven (07) days after receiving the Acceptance Minutes of the Project. (For the sake of
clarity, it is understood and agreed by and between the parties that the said warranty value
shall in no way affect, nor is it intended as a limitation of, the Seller’s liability with respect to
its warranty obligation, and that under no circumstance shall it be interpreted or construed
as a limitation on the Seller’s liability with respect to its warranty obligation)
(b) The Contractor shall only be refunded the maintenance money after the expiry of the
warranty period and their maintenance work’s completion has been confirmed by the Owner.
(c) Maintenance money can be replaced by the bank’s guarantee letter of similar amount or
-49-
APPLICABLE FROM JUNE 1st 2016
be deducted by the Owner in the last payment.
(6) The Contractor ensures to execute the Project under the requirement of the Contract with due
diligence and high devotement and the application of high standard in terms of qualification,
skills, acknowledgement recognized by worldwide well-known construction companies in
the construction similar to the Project.
(7) The Contractor commits, agrees and ensures that all Project Items shall:
a. Follow the requirements of the Contract.
b. Being constructed under the designs, drawings and technical standards stipulated in the
Contract and proper and sufficient practices in construction.
c. Being of first-class quality in details and defect-free in design, construction and
installation; materials or workmanship; under the standards as stipulated in the
Contract
d. Being assembled and installed under the specifications and instructions of agents and
manufacturers.
(8) The Contractor ensures that the total quality management will be conducted in all stages
from production, construction to completion of the Project.
ARTICLE 37. DAMAGE COMPENSATION
In case a party fails to perform the contractual obligations or improperly performs the
contractual obligations, after performing the obligations or applying remedies, it shall also
pay compensations for other damage, if any, caused to the other party at the level equivalent
to the level of damage caused to the other party.
If a party violates the contract due to the fault of a third party, the violating party shall take
responsibility for the violation to the other party. The dispute between the violating party
and the third party shall be settled in accordance with law.
ARTICLE 38. SETTLEMENT OF DISPUTE
-50-
APPLICABLE FROM JUNE 1st 2016
Any disputes, conflicts arising out of or in connection with the Contract, shall firstly be
settled between the Parties through negotiation and conciliation based on goodwill,
cooperation. In failure to reach an agreement for settlement of such dispute, it shall be
settled by the Vietnam International Arbitration Centre at the Vietnam Chamber of
Commerce and Industry in accordance with its Rules of Arbitration (The arbitration tribunal
shall include three (03) arbitrators. Each Party will choose one arbitrator and the third one
shall be appointed by such arbitrators chosen by the Parties. The place of settlement shall be
in Hanoi
ARTICLE 39. FINALIZATION AND LIQUIDATION OF THE CONTRACT
(1) Finalization of the Contract
Within 10 days after receiving the Acceptance Minutes and the confirmation of the Owner
about the completion of all the works in accordance with the Contract, the Contractor shall
submit to the Owner 03 finalization dossiers of the Contract attached with the detailed
explanatory documents in the form approved by the Owner about the value of all duly
performed works under the Contract and the amount that the Contractor considers as at due
date in accordance with the Contract or other agreements, including the following
documents:
(a) The Acceptance Minutes of all completed works under the scope of the Contract;
(b) The sheet on finalization value of the EPC contract, in which it clearly states the
amount which has been paid and the remaining value which the Owner is responsible
for paying to the Contractor;
(c) Completion dossier, construction diary of the Project;
(d) Other documents as agreed in the Contract.
If the Owner does not agree or is of view that the Contractor has not provided sufficient
grounds for confirming a certain part of the finalization dossier of the Contract, the
Contractor shall further supplement information upon reasonable request from the Owner
and amend the finalization dossier as mutually agreed by the Parties. The Contractor shall
prepare and submit the finalization dossier of the Contract to the Owner as agreed.
(2) Contract Liquidation
The Parties shall liquidate the Contract within seven (07) days from the date on which they
shall have fulfilled their obligations under the signed Contract, except for the guarantee
obligation.
-51-
APPLICABLE FROM JUNE 1st 2016
ARTICLE 40. NOTICE
Any terms and conditions of the Contract state that any requirement, proposal or issuance,
acceptance of any problem should be informed from one party to another by one of the
following ways:
(a) In writing and sent by hand-delivered (under the acknowledgement for receipt), by
post service, by fax or email;
(b) Sent or delivered to the right address so as to be communicated with the recipient.
In case the recipient informs about his/her another address (the new one), the information
must be transferred to this new one. If not, any information or request must be transferred to
the address as first above-written in the Contract.
ARTICLE 41. MISCELLANEOUS
Any matter which is not provided for in the Contract shall be agreed upon through
negotiation by and between the Owner, the Supervision Party and the Contractor, if
necessary.
This Contract as well as all documents, information relating to the Contract shall be
managed by the Parties in accordance with the State’s current regulations on strict
confidence.
The Parties commit themselves to duly implement all terms and conditions as agreed upon
in the Contract.
The Contract is made into 06 original versions (03 versions in English and 03 versions in
Vietnamese) of the same legal validity, The Owner keeps 04 versions (02 versions of each
language), The Contractor keeps 02 versions (01 versions of each language). In case that
there is any conflict on the contents between the English version and Vietnamese one, the
Vietnamese version shall prevail.
This Contract takes full force and effect from the signing date.