AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
Company / Owner
Marine Contractor
Main Contractors - JV
2
OUTLINE:.1Introduction
.2Resources
.3Progress Percentage◦Construction Status
.4Financial Summary
.5Variation Orders
AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
3
The project consists mainly of the detailed design and construction of LPG Jetty which includes:
•Access Trestle & Loading Platform
•2 No. Berthing Dolphins & 4 No. Mooring Dolphins & Catwalks
•Marine Loading Arms (x2)
•LPG and vapour return lines & Cathodic Protection System
•Fire fighting system & Electrical power supply and lighting
•Contractual project dates: 24-Feb-14 24-Oct-14
•Computed Completion Date :21-feb-15
1 .Introduction
AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
4
2 .ResourcesAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
Manpower 1-Nov-2014 1-Jan-2015Staff 51 54
Direct Labor 41 64Equipment Quantity Rented/
OwnedBarge 1 Owned
Flexi float barge 1 OwnedTug Boat 1 1 OwnedTug Boat 2 1 Rented
Speed Boat 1 RentedVibro Hammer 1 Owned
Diesel Hammer 1 OwnedCrawler Crane 1 OwnedMobile Crane 3 Rented
Air-Compressor 4 OwnedWelding Machine
20 Owned
Truck Mounted Crane
1 Owned
5
3. Progress Percentage
AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
Status Expected Completion DateTrestle 100% CompletePlatform 100% CompleteLoading Arm 100% CompletePile Static Load Test 100% CompletePipe Line 80% 31-Jan-15Mooring Dolphins 80% 25-Jan-15Berthing Dolphins 75% 31-Jan-15Catwalks 75% 5-Feb-15Abutement & Access 50% 28-Jan-15Electrical 30% 10-Feb-15Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15Commissioning 4-Feb to 18-Feb-15
Construction
6
3.1 Construction of Pipe LinesAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
Front View
10” FF Pipe4” Vapour Pipe
6” LPG Pipe2.5” Water
Pipe
U-Channel Pipe Support
Concrete Pipe Support
Pipe 13-Jan-15FireFighting 80%Vapour 80%LPG 80%Water 80%
7
4 .Financial Summary
AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
Invoice No.
Description
Initial Amount (JOD)
Agreed Amount (JOD)
Issue Date
Due Date
Settlement Date
Overdue
Period (days)
Status
001Advance payment
10%1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-
14 8-Jun-14 94 Closed
002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14
48 Closed
003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed
004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed
005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14
35 Closed
006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14
9 Closed
007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14
Closed
008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14
30-Nov-14
Closed
009 IPC-8 1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open
010 IPC-9 1,366,814.24 1,212,026.19 2-Jan-15 27-Feb-15 Not Yet Open
Issued 14-Jan-2015
8
.1Steel Water Tank to feed the fire fighting system•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%
.2Firefighting Pumps Room•Issued on 17th 2014 (40,700.0) JD, Progress : 95%
.3LPG and Vapour Return Tie-In to Existing Networks•Issued on 17th 2014 (64,509.61) JD, Progress : 100%
.4Design, Supply and Installation of Main Power cable•Issued on Dec. 24th (18,246.99) JD, Progress : 80%
.5Design, Supply and Installation of a Standby Power Generator•Issued on Dec. 24th (18,198.69) JD, Progress : 80%
5 .Variation Orders (Issued by Employer/CM)
AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN
9
General Layout
General Layout
Trestle Modules
Pipe Lines on Trestle
Mooring Dolphins
13
Firefighting Tank + Pump Room
14
Static Load Test
15
Loading Arm PrecommissioningLoading Arm Construction
16
Firefighting Monitor Towers
17
Abutment
18
Tie in at Loading Arm
19
Tie in Point
20
Cable Trays onshore + Trestle
21