application of ac dc in the connection of wind farms...offshore wind farm connections in operation...

Post on 02-Jun-2020

8 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Application of AC – DC in the connection of wind farms

G.J.Gerdes

Deutsche WindGuard GmbH

www.windguard.de

EU Round table

16th of May 2018

www.windguard.dewww.windguard.de

Outline

• AC/DC/AC Inverter in wind turbines

• HVDC and AC in German wind farm feeders

www.windguard.de

DC in Wind Turbines

2

www.windguard.dewww.windguard.de

Direct ConnectionDirect Connection

Grid coupling of wind turbines

Disadvantage:

• fluctuations in wind are directly transformed into power fluctuations

• this having an impact on mechanical loads (torque) and electrical power quality

• Low controllability

3

Gen

generatorGear box

rotor

grid

Grid frequency

inverter system

coupled

=Decoupled

Advantage:

• lower mechanical stress high controllability

• Improved electrical power quality

• Higher aerodynamic efficiency

Generating frequency

www.windguard.dewww.windguard.de

Downtime due to inverter failures in wind turbines

4Source: Elforsk

From research study “Investigation of converter failure in wind turbines”, Elforsk

www.windguard.de

• Technical availability calculated for 5 wind farms

– Covers: standstills due to technical failures of the wind turbines and repair

– Excludes: regular maintenance, external faults (grid, meteorology, owner stops)

5

Example of annual availability of selected wind farms

Year11 WTG Full

inverter5 WTG Full

inverter4 WTG

double fed IG5 WTG

double fed IG5WTG direct

coupling

2017 97.7% 99.6% 99.1% 97.7% 98.3%

2016 98.2% 96.7% 98.9% 99.1% 96.1%

2015 99.9% 99.3% 99.0% 97.2% 98.3%

2014 99.1% 96.0% 98.9% 97.7% 95.5%

Average 98.7% 97.9% 99.0% 97.9% 97.1%

Standstill 1.3% 2.1% 1.0% 2.1% 3.0%

www.windguard.de

Development of Offshore wind farm connection in Germany

6

www.windguard.dewww.windguard.de

Planning of offshore connections started in 2002: Total capacity planned from 2010 on

6,3 GW

6,8 GW

2,4 GW

9,5 GW

3

3

4

Total capacity: 25 GW

1

www.windguard.de

8

Ecological concerns

• Extension of areas:

– National park: along most of the coast line

– Shipping routes: the remaining coast line

• Compromise:

– Very few drillings underneath the national park area

– Limited number through shipping lines

Resulting in cables with high transport capacity

www.windguard.de

Target:

• to minimize the number of connecting cables

• To maximize the transport capacity of each cable

• To minimize the ecological impact (electromagnetic fields, heating of see ground, etc.)

First plans for connecting offshore wind farms

www.windguard.dewww.windguard.de

Available technology in 2004 for maximumtransport capacity of each cable

• 3-phase AC current:

– Three-conductor cable : 170kV, 200MW to 245kV, 250MW

– Single conductor cables: 420kV, 400MW

– Largest distance offhsore 120km

• DC current:

– Conventional HVDC (Thyristor): 800MW to 1 GW, 800kV (±400kV)

– Bipolar Transmission (Monopolar cable) ±600kV, 2500MW

– HVDC-IGBT up to 145kV, 250 - 300MW

• GIL:

– At that time realisation of 400kV at 2000MVA

– Higher capacities are theoretically possible

www.windguard.dewww.windguard.de

Technology and transmission distance

11

0 60 120 180 240

Co

st

Length of Line[km]

HVAC

HVDC

www.windguard.dewww.windguard.de

Offshore wind farm connections in operation or construction – North Sea

15

ConnectionCommissioning

date

Cabel

length

Offshore

Cabel

length

Onshore

Cabel

length

total

Technology CapacityVoltage

Level

DC

platform

Supplier

Alpha Ventus 2009 60 km 6 km 66 km HVAC 62 MW 110 kV AC

Riffgat 2014 50 km 30 km 80 km HVAC 113 MW 155 kV AC

Nordergründe 2017 28 km 4 km 32 km HVAC 111 MW 155 kV AC

BorWin1 2012 125 km 75 km 200 km HVDC 400 MW ±150 kV ABB

BorWin2 2015 125 km 75 km 200 km HVDC 800 MW ±300 kV Siemens

BorWin3 u. constr. 2019 130 km 30 km 160 km HVDC 900 MW ±320 kV Siemens

DolWin1 2015 75 km 90 km 165 km HVDC 800 MW ±320 kV ABB

DolWin2 2017 45 km 90 km 135 km HVDC 916 MW ±320 kV ABB

DolWin3 u. constr. 2018 80 km 80 km 160 km HVDC 900 MW ±320 kV Alstom

HelWin1 2015 85 km 45 km 130 km HVDC 576 MW ±250 kV Siemens

HelWin2 2015 85 km 45 km 130 km HVDC 690 MW ±320 kV Siemens

SylWin1 2015 160 km 45 km 205 km HVDC 864 MW ±320 kV Siemens

HelWin2 2015 85 km 45 km 130 km HVDC 690 MW ±320 kV Siemens

Total 1 133 km 660 km 1 793 km 7 822 MW only DC 7 536 MW

www.windguard.dewww.windguard.de 16

Source: TenneT

HVDC offshore wind farm connections in the North Sea

www.windguard.dewww.windguard.de

Offshore development in Germany until 2025

17

5.4 GW

0.8 GW

1.5 GW

0.02 GW

1.5 GW

1.6 GW

OWT (feeding in)

Installed OWT (no feed-in)

Construction in Progress

Final Investment Decision

Grid Connection Capacityassigned

Acceptance of Bid

Available in Tender 2018

Expected Development

by 2020 (7.7 GW)

Expected Development

by 2025 (10.8 GW)

Until 2030: 15GW, tender starting 2021

www.windguard.dewww.windguard.de

Development of offshore transmission and wind farm capacities

• Transmission capacity:

– 2020 7.8 GW

– 2021 to 2030 15.0 GW

• Offshore wind farm capacities:

– Today 5.4 GW

– 2020 7.8 GW

– 2025 10.8 GW

– From 2021 on 700-900 MW/year

– 2030 15.0 GW

18

www.windguard.dewww.windguard.de

Grid connection and offshore wind farm capacities

19Source: Stiftung Offshore Windenergie

www.windguard.de

Towards an offshore meshed grid

20

www.windguard.dewww.windguard.de

Development of a meshed offshore grid (MOG) in the North Sea

• Several studies have been conducted by the EU, showing the overall benefit for the participating countries

• Purpose of a MOG is

– the transport of offshore wind power to land

– the connection of markets and thus

– more electricity trading and levelling of electricity market prices in the EU

• A project to accelerate the development of a MOG is currently running: PROMOTION

21

www.windguard.dewww.windguard.de

Example of a meshed offshore grid

22Source: PROMOTION

www.windguard.dewww.windguard.de

Example of meshing offshore grid connections

23

Kriegers Flak combined grid solution

Source:Energienet, Tennet

Thank you

Gerhard Gerdes

g.gerdes@windguard.de

04451 9515 110

www.windguard.dewww.windguard.de

www.windguard.de 26

Personal DC Experience, long time ago

• Stand alone system, 1983

• consumption approx. 10000kwh/a

• Electricity supply: wind turbine, photovoltaics, Back-up CHP-unit

• Storage: Lead acid Batteries and later Hydrogen

• Battery Storage: 170kWh

• System tension: DC, 208 VDC

Experience:

Huge switches

Huge auxiliary drives (pumps etc.)

Even ohmic loads were difficult

Sine wave (and even trapeze) inverters were very expensive

top related