appendix-i form i (i) basic information sn. item...
Post on 23-Jul-2020
0 Views
Preview:
TRANSCRIPT
APPENDIX-I
FORM – I
(I) Basic Information
SN. Item Details
Whether it is a violation case and application is
being submitted under Notification No. S.O.804(E)
dated 14.03.2017 ?
No
1 Name of the Project/s
Brief summary of project
Project Cost (in lacs)
Amendment in Environmental Clearance for
minor changes in plant configuration of
Modernisation-cum-expansion of Bhilai Steel
Plant (4.0 MTPA to 7.0 MTPA) along with Captive
Power Plant (72 MW) at Bhilai, Chhattisgarh by
M/s Steel Authority of India Ltd.
Annexure 1 -Brief summary of project
Estimated 2008 cost at Environmental Clearance
stage: Rs. 12,954.30 Crores. SAIL Board
approved revised cost : Rs. 17,265 Crores (Net
of CENVAT) including foreign exchange
component. The cost for the proposed minor
changes included in the above cost.
2 S. No. in the schedule
Project Sector
3(a) Metallurgical industries (ferrous &non-
ferrous);
Industrial Projects 1
3 Proposed capacity/area/length/tonnage to be
handled/command area/lease area/number or
wells to be drilled
Minor changes in plant configuration, without any
change in EC approved production capacity and
pollution load.
4 New/Expansion/Modernization
Proposal Number
MoEFCC file number(Previous EC)
Uploaded EC letter
Amendment
Will be generated Online by Portal
J-11011/28/2007-IA II (I) dated 31.03.2008.
Annexure 2 -Previous EC Letter (Along with
amendments dated 23.06.2011 & 23.07.2014
and EC Extension letter 05.07.2013)
5 Existing Capacity/Area etc. EC granted for Crude Steel production capacity
7.0 MTPA, Captive Power Plant (72 MW) &
Green Power (CDCP & TRT).
Total area under possession: 6286.75 ha.
Proposed modernisation-cum-expansion under
existing plant premises of 3284.75 ha.
6 Category of project i.e. 'A' or 'B' A
7 Does it attract the general condition? If yes,
please specify
No
8 Does it attract the specific condition? If yes,
please specify
No
9 Location of the project
The modernisation-cum-expansion project is
located inside the existing Bhilai Steel Plant
(BSP) plant boundary, which is located in Bhilai,
Chhattisgarh
Newai
Khursipar, Maroda, Bhilai, Morid, Dundera &
Purena, Joratarai, Sonth, Hingna, Boriya,
Villages :
to 578, 588 to 595, 596, 597, 580 to 589)
385, 384, 382, 381, 380, 379, 311, 318, 429, 554
to 762, 1128, 600 to 630, 490, 491, 387, 389,
to 376 379 to 387, 313 to 321, 529, 528, 599, 682
366,340 to 358,328 to336, 322 to 324, 305, 369
Village Newai : (446 to 500, 505 to 535,361 to
Village Dundera : (1 to 263 & 589 to 621);
Village Morid : (1);
Village Bhilai : (460 to 604);
Village Maroda : (16, 108, 174, 290 to 296);
Village Khursipar : (238 to 383 & 457 to 473);
368, 379, 233, 234, 235 to 240);
410, 416 to 424 to 440, 441 to 460, 461 to 680,
388, 384, 414, 415 , 411, 412, 398,390 to 405 to
376, 280, 379, 378, 377, 383, 382, 381, 380,
260, 251 to 266, 248, 247, 279, 282, 281, 375,
183, 184, 185, 277, 273, 272, 271, 270, 268, 269,
219, 205, 203, 201, 206, 191 to 200, 188, 178,
210, 211 ,212, 213, 214, 215, 216, 217 ,218,
TO 175, 222 , 225 ,226, 228 to 232, 656, 224,
108, TO 119, 151, 154, 156, 157, 159, 165
Village Boriya : (89, 93, 96, 97, 98, 102, to 105,
Village Hingna : (1 to 454 - complete village);
Village Sonth : (1 to 604 -complete village);
Village Joratarai : (1 to 424 & 460 to 473);
Village Purena : (1 to 201 & 275 to 323);
Villages & Khasra No. :
Annexure 3 Survey of India topo-sheet
Block (Polygon)
Durg and nearest Airport is Raipur.
Great Eastern Road (NH 6). Nearest town is
Chhattisgarh plains. Nearest National Highway is
Kharun and Tandula Sheonath river system in
Shape of the project land
Uploaded copy of survey of India Toposheet
Plot/Survey/Khasra No.
Town / Village
State of the project
District Durg, Chattisgarh between North latitude
21011' to 21 013' and East longitude 81022' to
81024'. The site lies on the watershed between
Details of State of the Project
SN. State Name District Name Tehsil Name
Chhattisgarh Durg Durg
10 Nearest railway station along with distance in
kms.
Major railway Station: Durg (~12kms)
11 Nearest Town/City/District Headquarters along
with distance in kms
Durg (~12kms from Plant main gate)
12 Village Panchayats, ZilaParishad, Muncipal
Corporation, Local body (Complete postal
address with telephone nos. to be given)
Municipal Corporation: Bhilai Nagar Nigam, Supela, Bhilai
13 Name of the Applicant Ms. Uma Katoch
14 Registered Address Environment Management Department, Ispat Bhavan, Bhilai Steel Plant, M/s Steel Authority of India Limited (SAIL) Bhilai, Dist. Durg, C.G. PIN- 490001
15 Name of the Company
Name of the Applicant
Designation (Owner/ Partner/ CEO)
Pin code
Telephone No.
Fax No.
Copy of documents in support of the
competence/authority of the person making this
application to make application on behalf of the
User Agency.
Bhilai Steel Plant-Steel Authority of India Limited (BSP-SAIL) Ms. Uma Katoch Dy. General Manager (Environmental Management Department),BSP (On Behalf of CEO, Bhilai Steel Plant), 490 001 bspenvironment@sail-bhilaisteel.com 09407981777(M); 0788 2853862(O) 0788 2222010 Annexure 4 -Authorisation Letter
16 Details of Alternative Sites examined, if any.
Location of these sites should be shown on a
toposheet.
Not Applicable. Application is for amendment in Environmental Clearance
17 Whether part of Interlinked projects? Not Applicable
18 Whether separate application of Interlinked
project has been submitted?
Not Applicable
19 If Yes, MoEF file number
Date of submission
Not Applicable
20 If No, Reason Not Applicable
21 Whether the proposal involves Approval/
Clearance under: if yes, details of the same and
their status to be given
(i) Whether the proposal involves
approval/clearance under the Forest
(Conservation) Act,1980?
(ii) Whether the proposal involves
approval/clearance under the wildlife (Protection)
Act,1972?
(iii) Whether the proposal involves
approval/clearance under the C.R.Z notification,
2011?
No No No
22 Whether there is any Government Order/Policy
relevant / relating to the site?
No
23 Whether any Forest Land Involved?
Area of Forest land Involved (hectares)
No Not Applicable
24 Whether there is any litigation pending against
the project and/or land in which the project is
proposed to be set up?
No litigation is pending against the project and or land in which the project is proposed to be set up.
(II) ACTIVITY
1) Construction, operation or decommissioning of the Project involving actions, which will
cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
SN. Information/Checklist
confirmation
Yes/No Details there of (with approximate
1.1 Permanent or temporary change in
land use, land cover or topography
including increase in intensity of
land use (with respect to local land
use plan)
No
BSP is established since 1956. Since then there has been phases of expansion with increase intensity of land-use within the plant premises. The proposed minor changes in plant configuration of modernisation-cum-expansion is being executed within the existing integrated steel plant of BSP; hence, changes in land use and topography is not expected.
1.2 Clearance of existing land,
vegetation and buildings? No
Not required. As the proposed minor changes in plant configuration of modernisation-cum-expansion is being carried out within the existing Plant Boundary only.
1.3 Creation of new land uses?
No
The units envisaged under minor changes in plant configuration of modernisation-cum-expansion plan are within the existing BSP plant boundary. No new land use is envisaged.
1.4 Preconstruction investigations e.g.
bore houses, soil testing? Yes
All Necessary testing like soil testing has already been conducted. No further preconstruction investigations is required.
1.5 Construction works?
Yes
Remaining civil and structural work to facilitate the proposed minor changes in plant configuration of modernisation-cum-expansion plan. By complying the Construction and Demolition Waste Management Rules, 2016.
1.6 Demolition works? Yes
Some demolition work will be required during phasing out of some units, which will be limited within the existing BSP plant boundary.
1.7 Temporary sites used for
construction works or housing of
construction workers?
No Existing site within plant being used for construction work. As such no housing of construction workers is envisaged.
1.8 Above ground buildings, structures
or earthworks including linear
structures, cut and fill or
excavations and fill or excavations
Yes Remaining construction, earthworks and excavation under modernisation-cum-expansion plan will be carried out for a short period of time.
1.9 Underground works including
mining or tunneling? No
No mining/tunnelling is involved under the proposed minor changes in plant configuration of modernisation-cum-expansion plan. However some underground works limited to foundation/duct, etc. may be done within the
(a) Name of the Court
(b) Name of the Sub court
(c) Case No.
(d)Orders/directions of the court, if any and
relevance with the proposed project
quantities/rates, wherever possible) with
source of information data
SN. Information/Checklist
confirmation
Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
existing plant premises.
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing
processes? Yes Steel Production : BF-BOF Route along with Coke Oven & Sinter Plant, Captive Power Plant & Auxiliary facilities.
1.14 Facilities for storage of goods or
materials? Yes BSP being an existing plant, the storage facilities are already available. This will be further augmented if required.
1.15 Facilities for treatment or disposal of
solid waste or liquid effluents? Yes Solid wastes are recycled/sold/dumped. Individual shop-wise waste water treatment facilities provided.
1.16 Facilities for long term housing of
operational workers? No Existing facilities is adequate
1.17 New road, rail or sea traffic during
construction or operation?
No
The site is well connected with National Highway and Howrah – Mumbai Rail line (South East Central Rail Zone). The nearest major railway station is Durg, about 12km from the project site. Therefore, any construction for infrastructure is not required.
1.18 New road, rail, air water borne or
other transport infrastructure
including new or altered routes and
stations, ports, airports etc?
No No new infrastructure required for the proposed minor changes in plant configuration - the existing facilities will be used.
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No
Not Applicable
1.20 New or diverted transmission lines
or pipelines? No
The proposed new Electric transmission line envisaged in modernisation-cum-expansion plan has already been erected and as of now no new electric transmission line is required for the proposed minor changes in plant configuration.
1.21 Impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or
aquifers?
No
Not Applicable
1.22 Stream crossings? No Not Applicable
1.23 Abstraction or transfers of water
from ground or surface waters?
Yes
Total water requirement after Modernisation-cum-expansion of 7.0 MTPA plant is 15981m3/hr. Source: Chhattisgarh Water Resource Department through Tandula Canal to Maroda-II reservoir of BSP. For the proposed minor changes in plant configuration no additional water is required from that as specified above for Modernisation-cum-expansion of 7.0 MTPA plant. The water after plant use and required treatment is stored in Maroda-I (cooling pond for centralized re-circulating system of the plant) reservoir and is
SN. Information/Checklist
confirmation
Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
reused as re-circulating industrial water. While the makeup water and drinking water requirement is met from Maroda - II.
1.24 Changes in water bodies or the land
surface affecting drainage or
runoff?
No
No change in drainage pattern of the area is envisaged due to the proposed minor changes in plant configuration.
1.25 Transport of personnel or materials
for construction, operation or
decommissioning?
Yes
Through existing facilities only.
1.26 Longterm dismantling or
decommissioning or restoration
works? Yes
SP-I has already been phased out and dismantled. Moreover, SMS-I, RMP-I, BF-1, BF-2 (already phased out) & BF-3, BBM shall be phased out and decommissioned progressively.
1.27 Ongoing activity during
decommissioning which could have
an impact on the environment?
No
At present there is no decommissioning activity being carried out. However, after stabilisation of BF-8 and SMS-3, units like SMS-I, RMP-I, BF-1, BF-2 (already phased out), & BF-3, BBM shall be decommissioned and progressively phased out. However, all possible environmental impacts will be confined within the existing plant premises and appropriate control measure will be undertaken to minimise the impacts.
1.28 Influx of people to an area in either
temporarily or permanently? Yes Temporarily for construction
1.29 Introduction of alien species? No Not Applicable
1.30 Loss of native species or genetic
diversity? No
Not Applicable
1.31 Any other actions? No Not Applicable
2) Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are nonrenewable or in short supply)
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
2.1 Land especially undeveloped or
agricultural land (ha) No
The proposed minor change in plant configuration of modernisation-cum-expansion plan is being carried out within the existing integrated steel plant premises.
2.2 Water (expected source & competing
users) unit: KLD
Yes
The total water requirement after modernisation-cum-expansion plan of 7.0 MTPA plant will not exceed 15981 m3/h (Same as per earlier EC). Source: Chhattisgarh Water Resource Department through Tandula Canal to Maroda-II reservoir of BSP.
2.3 Minerals (MT)
Yes
Annual requirement in tonnes are as follows: Iron ore fines: 7287000 MTPA Iron Ore lumps : 4378000 MTPA Limestone : 1847000 MTPA Dolomite: 1114700 MTPA
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
Quartzite: 104600 MTPA Coking Coal: 5697000 MTPA
2.4 Construction material – stone,
aggregates, sand / soil(expected
source – MT) Yes
The construction material required like Bricks, Stone Chips, Cement and Iron is being procured from local vendors. However major construction activities are already completed.
2.5 Forests and timber (source – MT) No Not Applicable
2.6 Energy including electricity and fuels
(source, competing users) Unit: fuel
(MT),energy (MW)
Yes
The total estimated power demand for 7.0 MTPA modernization-cum-expansion plant will be 468 MW. Only critical power and total process steam will be generated through the captive power plant. The balance power requirement will be met from outside sources. No additional power is required for the proposed minor changes in plant configuration.
The gas generated from Coke Ovens, BF and LD/BOF will be utilized inside the plant operation. The total generation of BF gas = 1380417 Nm3/hr ; BOF/LD gas = 71,529 Nm3/hr ; CO Gas = 189,195 Nm3/hr. The gas requirement for the proposed minor changes in plant configuration will be met from the gas being generated within the plant.
2.7 Any other natural resources (use
appropriate standard units) No
Not Applicable
3) Use, storage, transport, handling or production of substances or materials, which could
beharmful to human health or the environment or raise concerns about actual or perceived
risks to human health
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
3.1 Use of substances or materials,
which are hazardous (as per MSIHC
rules) to human health or the
environment (flora, fauna, and water
supplies
Yes Blast Furnace Gas (Major Constituents Carbon Monoxide): 1380417Nm3 /hr. Coke Oven Gas (Major Constituents Carbon monoxide, Hydrogen & Methane): 189195 Nm3 /hr BOF Gas (Major Constituents Carbon Monoxide): 71529 Nm3 /hr. Fuel Oil: 3231.097 liter / h. Propane: 507 Nm3/h Sulphuric Acid: 26768t/yr. Proper storage facility for aforesaid substances exists in the plant premises. Preventive measures for protection to human health and environment have already been envisaged and taken care off.
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
3.2 Changes in occurrence of disease or
affect disease vectors
(e.g. insect or water borne diseases)
No Not Applicable
3.3 Affect the welfare of people e.g. by
changing living conditions?
Yes Due to the undergoing modernization-cum-expansion project, the living conditions and welfare of people has improved by CSR schemes of BSP which are already being implemented and will be strengthened in near future.
3.4 Vulnerable groups of people who
could be affected by the project e.g.
hospital patients, children, the elderly
etc.
No Not Applicable
3.5 Any other causes No Not Applicable
4) Production of solid wastes during construction or operation or decommissioning
(MT/month)
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
4.1 Spoil, overburden or mine wastes Yes Spoil- Partly reused/ recycled and partly sold.
4.2 Municipal waste (domestic and or
commercial wastes)
No Not applicable. Township already exists and the waste generated is been managed by Bhilai Municipal Corporation, Supela.
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
Yes No additional Hazardous waste is being generated due to the proposed minor changes in plant configuration of the Modernisation-cum-expansion of Bhilai Steel Plant.
4.4 Other industrial process wastes Yes No additional solid waste is being generated due to the proposed minor changes in plant configuration of the Modernisation-cum-expansion of Bhilai Steel Plant. Note: Process wastes like Waste refractories, Dolo fines, Lime fines, Mill Scales and Cinder, will be 100% recycled/reused/sold.
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge from
effluent treatment
Yes No additional sewage sludge or ETP sludge is being generated due to the proposed minor changes in plant configuration of Modernisation-cum-expansion of Bhilai Steel Plant. ETP sludge generated is managed as per statutory requirement as applicable.
4.7 Construction or demolition wastes Yes Partly sold and partly will be utilised for land filling / suitably disposed off. As per the Construction and Demolition Waste Management Rules, 2016.
4.8 Redundant machinery or equipment Yes Will be sold / suitably disposed off.
4.9 Contaminated soils or other materials No Not Applicable
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes No Not Applicable. Top soil excavated during construction activities
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
were stacked separately and already used for re-laying on garden / green belt area.
5) Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
5.1 Emissions from combustion of fossil
fuels from stationary or mobile
sources
Yes During plant operation, PM, SO2 and NOx are the major emissions. The bulk raw materials and finished products are transported through Rail and conveyors. Raw-materials/ end products of smaller quantities are transported through road. No additional combustion of fossil fuels from stationary or mobile sources is envisaged due to the proposed minor changes in plant configuration of the Modernisation-cum-expansion project. However, post modernisation-cum-expansion, there will be reduction in PM, SOx and NOx emission levels due to phasing out of existing relatively polluting units, introducing better pollution control facilities in the existing unit and introducing new unit with environmentally sound pollution control measure meeting the latest norms.
5.2 Emissions from production
processes
Yes No additional pollutant emission is envisaged due to the proposed minor changes in plant configuration of the Modernisation-cum-expansion project. Emitted quantity from production processes - stationary sources (Kg/hr): 1. Stack Emissions:
As Envisaged at EC Stage
PM = 731 kg/hr
SO2 = 795 kg/hr
NOx = 864 kg/hr
Total Pollution Load after Minor Changes in
Plant Configuration
SPM = 661 kg/hr
SO2 = 788.5 kg/hr
NOx = 847 kg/hr
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
Resultant decrease due to Minor Changes
in Plant Configuration
SPM = 70.27 kg/hr
SO2 = 6.48 kg/hr
NOx = 17.17 kg/hr
Provision has been envisaged to keep fugitive emission from process under control. Also work zone emission will be kept below 3 mg/m3 for new BF-8 and SMS-3 and below 4 mg/m3 for all existing BFs and SMS-2
5.3 Emissions from materials handling
including storage or transport
Yes No additional fugitive emissions are envisaged from material handling / storage areas and transportation activities due to the proposed minor changes in plant configuration. The emission quantities from material handling / storage will be kept within the applicable norms by adopting suitable mitigation measures.
5.4 Emissions from construction
activities including plant and
equipment
Yes Presently, most of the construction activities associated with the modernization-cum-expansion project is nearing completion. Further, no additional fugitive emissions are envisaged from material handling / storage areas and transportation activities due to the proposed minor changes in plant configuration.
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
Yes There may be some dust emission from construction activities. However, these emissions will last for a very short period and it will be temporary & restricted within the plant boundary. The impact will be reversible, marginal, and temporary in nature. There will not be any odour generation.
5.6 Emissions from incineration of waste No Not Applicable
5.7 Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
No Not Applicable
5.8 Emissions from any other sources No Not Applicable
6) Generation of Noise and Vibration, and Emissions of Light and Heat:
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
6.1 From operation of equipment e.g.
engines, ventilation plant, crushers
Yes The noise generation sources from the units will be kept below 85 dB(A) at 1m from source and all other existing units of the plant will be kept below 90 dB(A) at 1m from source.
6.2 From industrial or similar processes Yes The noise level generated will be kept within the
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
applicable statutory norms by implementing various mitigation measures.
6.3 From construction or demolition Yes The noise level generated will be kept within the applicable statutory norms by implementing various mitigation measures.
6.4 From blasting or piling Yes The noise level generated will be kept within the applicable statutory norms by implementing various mitigation measures.
6.5 From construction or operational
traffic
Yes The noise level generated will be kept within the applicable statutory norms by implementing various mitigation measures.
6.6 From lighting or cooling systems No Not Applicable
6.7 From any other sources No Not Applicable
7) Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea:
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
7.1 From handling, storage, use or
spillage of hazardous materials
No All hazardous chemicals & waste handled/disposed as per applicable statutory rules & norms. All precautionary measures are being/shall be taken to minimize any such risks.
7.2 From discharge of sewage or other
effluents to water or the land
(expected mode and place of
discharge)
No Domestic sewage is being treated through 30 MLD sewage treatment plant (STP) and treated waste water is recycled for process application. From the present plant operation, all the effluent is being treated & mostly recycled and partly discharged. Moreover, water conservation schemes are being implemented to achieve zero discharge from plant outlets.
7.3 By deposition of pollutants emitted to
air into the land or into water
No Ambient Air Quality Norms and waste water quality discharge limits are being maintained and thus contamination of land and water bodies is not envisaged.
7.4 From any other sources No Not Applicable as there is no major industries in the area.
7.5 Is there a risk of long term build up of
pollutants in the environment from
these sources?
No Not Applicable
8) Risk of accidents during construction or operation of the Project, which could affect human
health or the environment
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous substances
Yes All the suitable preventive measures / emergency planning are already in place. Both onsite and offsite Disaster management plan exists and are being properly followed.
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
8.2 From any other causes No Not Applicable
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g. floods,
earthquakes, landslides, cloudburst
etc)?
No Not Applicable. As the proposed project falls under Seismic Zone II (as per the seismic zoning map published by Bureau of Indian Standard). This zone is referred to as Low Damage Risk Zone.
9) Factors which should be considered (such as consequential development) which couldlead
to environmental effects or the potential for cumulative impacts with other existing or
planned activities in the locality
SN. Information/Checklist confirmation Yes/No Details there of (with approximate
quantities/rates, wherever possible) with
source of information data
9.1 Lead to development of supporting,
utilities, ancillary development or
development stimulated by the
project which could have impact on
the environment e.g.:
Supporting infrastructure (roads,
power supply, waste or waste
water treatment, etc.)
housing development
extractive industries
supply industries
Other
Yes Undergoing Modernisation and Expansion project has already resulted in considerable growth of service sector and has also generated new industrial and business opportunities in the area. Bhilai Steel plant has always acted as an active nucleus for new industries and business activities. Further, more growth in the region is expected. However, this development will not have any adverse impact on environment.
9.2 Lead to afteruse of the site, which
could have an impact on the
environment
No No adverse impact on environment.
9.3 Set a precedent for later
developments
Yes Small supportive industries may be developed as a consequence.
9.4 Have cumulative effects due to
proximity to other existing or planned
projects with similar effects
No There is no similar industry within 15km radius of the project site.
(III)ENVIRONMENTAL SENSITIVITY
SN
.
Areas Name/Identity Aerial distance (within 15km.)
Proposed project location
boundary
1 Areas protected under international conventions,
national or local legislation for their ecological,
landscape, cultural or other related value
None No such area comes under 15 km of the project.
2 Areas which are important or sensitive for
ecological reasons Wetlands, watercourses or
other water bodies, coastal zone, biospheres,
mountains, forests
None Not Applicable
SN
.
Areas Name/Identity Aerial distance (within 15km.)
Proposed project location
boundary
3 Areas used by protected, important or sensitive
species of flora or fauna for breeding, nesting,
foraging, resting, over wintering, migration
None Not Applicable
4 Inland, coastal, marine or underground waters None No such area comes under 15 km of the project.
5 State, National boundaries None No National / State boundary within 15km aerial distance.
6 Routes or facilities used by the public for access
to recreation or other tourist, pilgrim areas
None Not Applicable
7 Defence installations None No such area comes under the 15 km of the project.
8 Densely populated or builtup area Bhilai Durg
Bhilai City (~5km) Durg (~12 km)
9 Areas occupied by sensitive manmade land
uses (hospitals, schools, places of worship,
community facilities)
Yes All the amenities are available at Bhilai. Hospitals, places of worship and schools exist within 15 km radius area.
10 Areas containing important, high quality or
scarce resources.(ground water resources,
surfaceresources,forestry,agriculture,fisheries,to
urism,minerals)
None Not Applicable
11 Areas already subjected to pollution or
environmental damage.(those where existing
legal environmental standards are exceeded)
None Not Applicable
12 Areas susceptible to natural hazard which could
cause the project to present environmental
problems (earthquakes, subsidence, landslides,
erosion, flooding or extreme or adverse climatic
conditions) similar effects
None Not Applicable
(IV)PROPOSED TERMS OF REFERENCE FOR EIA STUDIES – Minor changes in plant configuration
without any change in EC approved production capacity and pollution load.
The aforesaid application and documents furnished here with are true to my knowledge:
V Name of Applicant Ms. Uma Katoch
Designation Dy. General Manager (Environmental Management Department),BSP
Name of Company
(Applicant Name should not be given here)
Bhilai Steel Plant (BSP), Steel Authority of India Limited (SAIL)
Address Room No. 548, Environment Management Department,
(V)UNDERTAKING
1 Uploaded Proposed TOR File N.A. 2 Uploaded scanned copy of covering letter Uploaded with application 3 Uploaded PreFeasibility report (PFR) Uploaded with application
Ispat Bhavan, Bhilai Steel Plant, M/s Steel Authority of India Limited (SAIL) Bhilai, Dist. Durg, C.G. PIN- 490001
Brief Summary of the Project (Amendment in EC) Annexure 1
Page 1 of 2
Brief Summary of the project (Amendment in EC)
Reference for Modernization-cum-Expansion M/s. Bhilai Steel Plant (BSP), Steel Authority of India Limited (SAIL) proposes for amendments in Environmental
Clearance accorded vide lr.no. J-11011/28/2007-IA II (I) dated 31.03.2008 for modernization cum expansion of 4.0 MTPA to 7.0 MTPA Modernization-Cum-Expansion Plan of Bhilai Steel Plant along with captive power plant. BSP is presently based on Blast Furnace-Twin Hearth Furnace (BF-THF) and BF- Basic Oxygen Furnace (BF-BOF) routes for production of iron and steel. Under the ongoing modernization-cum-expansion plan the crude steel production capacity is envisaged to be 7.0 MTPA within the existing premises of BSP.
Reasons for Amendments The present project was accorded environmental clearance for 4.0 MTPA to 7.0 MTPA Modernization-Cum-
Expansion Plan of Bhilai Steel Plant along with captive power plant vide lr.no. J-11011/28/2007-IA II (I) dated 31.03.2008 with amendments dated 23.06.2011 and 23.07.2014. The EC validity was extended up to 30.03.2018 by MoEFCC vide letter dtd 05.07.2013. Consent to Establish was accorded by Chhattisgarh Environment Conservation Board (CECB) vide lr. no. 12981/TS/CECB/2009 dated 01.06.2009. The targeted Crude steel production capacity of the Integrated Steel Plant is 7.0 million TPA. The ore transportation will be done through Indian Railways (95-97%) and Roads (3-5%). During execution of the project after detailed design engineering certain changes are envisaged in the configuration of the plant from the Environmental Clearance conditions, without any change in crude steel production. Further, certain changes in the product mix are envisaged without any change in finished steel production capacity. Moreover, there will be a decrease in overall pollution load from that envisaged during the EC 2008. Amendment Requested The proposed amendments are as follows:
The hot metal, crude steel and finished steel production will be same as envisaged in EC 2008, i.e 7.5 MTPA, 7.0 MTPA and 6.3 MTPA, respectively.
Table 1: Configuration as per EC (accorded in 2008) and Proposed Changes (Note: Only those units
where changes have been proposed are shown in this table)
SN. Units 7.0 MTPA Expansion EC Accorded Valid until
31.03. 2018
Amendment Requested/ Changes Proposed
Change in Capacity
1 Sinter Plant Complex a. Sinter Plant-3 M/c 2 1x 320 m2 (new) Change in grate area1x360 m2
(new)
Total Sinter Production 9.235 MTPA 9.235 MTPA No Change 2 Coke Oven Complex A Coke Oven Battery 1 to 11
Battery No. 1, 7 & 8 to be phased out
At any time, three batteries will not be in operation (will always be under cold repair / rebuilding cycle). Total Coke production will be same as per accorded EC.
Total Capacity 3.94 MTPA 3.94 MTPA No Change
3 Rolling Mills
a. Universal Beam Mill 1.0 MTPA Now not coming -1.00 MTPA
b. Rail & Structural Mill (RSM) with new Universal Rail Mill (URM)
1.70 MTPA 2.20 MTPA +0.50 MTPA
Brief Summary of the Project (Amendment in EC) Annexure 1
Page 2 of 2
SN. Units 7.0 MTPA Expansion EC Accorded Valid until
31.03. 2018
Amendment Requested/ Changes Proposed
Change in Capacity
c. Plate Mill 1.42 MTPA 1.65 MTPA +0.23 MTPA
d. Merchant Mill 0.60 MTPA 0.85 MTPA +0.25 MTPA
e. Wire Rod Mill 0.68 MTPA 0.70 MTPA +0.02 MTPA
f. Bar and Rod Mill 0.90 MTPA 0.90 MTPA -
Total Capacity 6.30 MTPA 6.30 MTPA No Change
4 Power Blowing Station
a. 4 PBS I
Existing 3x12 MW Turbo-generators to be upgraded to 1 x 12 MW + 2 x 15 MW
Turb-generators not up-graded, 3 x 12 MW (Existing)
b. PBS II 2 x 170 TPH BF gas fired boiler 1 x 15 MW turbo-generator.
2 x 150 TPH BF gas fired boiler 1 x 25 MW turbo-generator
Total Power Generation (MW) & Steam Generation (TPH)
1390 TPH Steam 72 MW
1350 TPH Steam 76 MW
-40 TPH Steam +4 MW
5 TRT Power Generation Capacity not specified
14 MW Green power from TRT indicated
6 CDCP Power Generation Capacity not specified
4MW Green power (from CDCP indicated
7 Blast Furnace BF 6 with CDI Modernisation Volume from
1719 m3 to 2000 m3 Modernisation not undertaken Volume - 1719 m3
Total Hot metal Production 7.5 MTPA 7.5 MTPA No Change
The assessment of change in production capacity, resource requirements and pollution load due to the proposed amendment shows that:
No change in hot metal, crude steel and finished steel production as envisaged at EC stage.
No change in sinter and coke production as envisaged at EC stage.
Decrease in overall pollution load from that envisaged during the EC stage
No change in raw water requirement as envisaged at EC stage
No change in power requirement as envisaged at EC stage
No change in fuel gas requirement as envisaged at EC stage
No change in land area requirement as envisaged at EC stage
No change in water requirement as envisaged at EC stage
No change in solid waste generation and its management as envisaged at EC stage
"T
/hF. No. J-11011/28/2007- IA II (I)
Government.of IndiaMinistry of Environment and Forests
(I.A.Division)Paryavaran Bhawan
CGO Complex, Lodhi RoadNew Delhi - 110 003
E-mail: pb.rastogi@>.nic.inTelefax: 011: 24367668
I- ~~- 3" ~ "'~~ 7> * -~ ~'C-" .~o,=- - ~.-=- "
Dated 31 sfMarch, 2008To, /
viAls Steel Authority of India Ltd.Bhilai Steel PlantBhilai - 490 001, DurgChhatishgarh
E-mail: emdsail~rediffmail.com/sailbsp~sancharnet.in Imeenakshi kakkar~vahoo.com I meenakshi.kakkar@sailex.com
Fax No.: 0788-2222890 I 2223491
Subject: Modernization-cum-expansion of Bhilai Steel Plant (4.00 MTPA to 7.00 MTPA)alongwith Captive Power Plant (72 MW) at Bhilai, Chhattisgarh by MIs SteelAuthority of India Ltd. - Environmental clearance reg.
I
1
Sir, . - - - ,. - -This has reference to your fetfgr no.--I5GM(EnMD)/EIA&EMP/1624dated 2th December,
2006 alongwith Application Form, Questionnaire, Executive Summary, Pre-feasibility Report andEIA/EMP Report subsequent clarifications furnishe9 by you vide your letter dated 14thMarch,2007, 20th March, 2007, 29th June, 2007, 8th December, 2007 "and 15th March, 2007 forenvironmental clearance on the above mentioned project.
2.0 The Ministry of Environment and Forests has examined the application. It is noted thatMIs Steel Authority of India Ltd. have proposed for the Modernization-cum-expansion of BhilaiSteel Plant (4.00 MTPA to 7.0 MTPA) alongwith Captive Power Plant (72 MW) at Bhilai,Chattishgarh and will involve modernization, modification, upgradation, addition, deletion etc. inthe existing plant. Total existing land is 6286.75 ha and no additional land will be required forthe expansion of project. No national parks, sanctuaries, biosphere reserves, monuments,heritage sites are located within 7 km. of the site. Details of existing, proposed and totalcapacities of various plants after expansion will be as follows:
- --- - -
I
1
S. Name of units I Existing Proposed Total CapacityN. Products Capacity Capacity (7.0 MTPA)
(4.0 MTPA) (3.0 MTPA)1 CokeOvenComplex 3.303MTPA 3.94MTPA 3.94MTPA2 SinterPlantComplex 8.374MTPA 9.235MTPA 9.235MTPA3 Blast Furnace Complex . 4.71 MTPA 7.5 MTPA 7.5 MTPA4 Steel Melting Shop-1 2.5 MTPA - -5 Steel Melting Shop-2 1.5 MTPA 3.0 MTPA 3.0 MTPA6 Steel Melting Shop-3 - 4.0 MTPA 4.0 MTPA7 Blooming & Billet Mill 2.149 MTPA - -8 Plate Mill 0.95 MTPA 1.42 MTPA 1.42 MTPA
Page 1Annexure 2
'"2
3.0 SPM, S02, NOx levels in the ambient air will decrease due to phasing out of the existingpolluting units, better pollution control due to use of environment-friendly technologies andinstallation of efficient air pollution control system. ESP, Bag filters, Gas cleaning plant (GCP),ventury scrubber, dust suppression system will be provided to control gaseous emissions anddust. Recovery type of the coke oven batteries with HPLA, smokeless charging cars etc. will beprovided to control emissions. Total water requirement from Maroda-II reservoir and Tandulacanal after expansion will be 15,981 m3/h and agreement is signed with the IrrigationDepartment for 13,576 m3/h and have applied for the 'Permission' for the drawl of additionalwater. Treated wastewater will be recycled and reused and 'zero' discharge will be adopted.Almost 98% solid waste will be utilized in the plant itself and 2% will be dumped within the
~ ~..~ .~_.. <Pf..emlses<""--o~~-~:;;~.~-,,,-,=..,..i ._'~-'. .-:"",C~~":-;"~ ""~-..~.~ ""=-~"'~~ ~~. ~.. ",.c; =
4.0. Public Hearing I Public Consultation meeting was held on 28th September, 2007. Totalcost of the proj~ct will be Rs. 12,954.30 Crores.
5.0. The Ministry of Environment and Forests hereby accords environmental clearance to theabove project under the provisions of EIA Notification, 2006 as amended subsequently subjectto strict compliance of the following specific and general conditions:
A.
~ iii)
SPECIFIC CONDITIONS:
i) Efforts shall be made to reduce RSPM levels in the ambient air and a time boundaction plan should be submitted. On-line stack monitoring facilities for all the stacksshall be provided and sufficient air pollution control devices shall be provided to keepthe emission levels below 100 mg/Nm3. Data on ambient air quality and stackemission should be regularly submitted ~othis Ministry including its Regional Officeat .Bhopal, CPCB and CE~B once in six months.
....
ii) As proposed, electrostatic precipitator (ESP) shall be provided to sinter plant, steelmelting shop (SMS), blast furnace (BF) and Power plant to control gaseousemissions to 100 mg/Nm3. Two-stage Gas cleaning plant (GCP) and venturyscrubbers shall also be provided to BF-8, SMS-II & III, RMP-III and bag filter to RMP-II to control fugitive emissions. Dust suppression system shall be provided to controldust from coal and iron storage area. Dust extraction system shall be provided incoal crushing and screening, cooler discharge area, product separation area etc. tocontrol fugitive emissions.
All the standards prescribed for the coke oven plants shall be followed as per thelatest guidelines. Proper and full utilization of coke oven gases in power plant usingheat recovery steam generators shall be ensured and no fuel gases shall bedischarged into the air.
L-.
9 Rail & Structural Mill 0.75 MTPA 1.70 MTPA 1.70 MTPA10 Merchant Mill 0.5 MTPA 0.6 MTPA 0.6 MTPA11 Bar & Rod Mill - 0.9 MTPA 0.9 MTPA12 Universal Beam Mill . - - 1.0 MTPA13 Wire Rods 0.42 MTPA 0.54 MTPA 0.68 MTPA14 Lime & Dolo Plant 0.38 MTPA 1.58 MTPA 1.58 MTPA15 QxygeQ F?lDt 3 x 550TPD 3x 550 TPD, 3x 550 TPD, 1x
1x 650 TPD, 650 TPD, 2x2x 1250 TPD 1250 TPD
16 Power & Blowing Station 900 TPH steam, 1390 TPH steam 1390 TPH steam36MW 72MW 72MW
Page 2Annexure 2
/~{fIIJ
"- ~ ~
B.
3
iv) Gaseous emission levels including secondary fugitive emissions from blast furnaceand sinter plant shall be controlled within the latest permissible limits issued by theMinistry and regularly monitored. Guidelines / Code of Practice issued by the CPCBshall be followed.
v) Total water requirement from Maroda-II reservoir and Tandula canal after expansionshall not exceed 15,981 m3/h.Treated wastewater shall be recycled and reused forcooling in BF shel!, BF gas, valve of hot air blast and the skids in reheating furnaces.The treated effluent shall also be used in GCP for gas cleaning at BF, steel making,slag granulation plant (SGP), boiler make up water etc. Effluent from coke oven shall
~< ~be treated in B08cplan~and reusetJ"'for ~COKEfquenching~'JA..1I°th6'"treated~stewater.shall be recycled and reused in the process, dust suppression and green beltdevelopment. 'Zero' effluent discharge shall be strictly followed and no wastewatershall be discharged outside the premises. Treated effluent may be discharged onlyin emergency in water recovery system.
vi) Prior 'Permission' for the drawl of additional water from the concerned departmentshall be obtained.
vii) Continuous monitoring of Total Organic Compounds (TOC) shall be done at theoutlet of effluent treatment plant (BOD plant).
viii) As proposed, coal and coke fines shall be recycled and reused in the process. Ironore, fluxes, mill scale etc. shall be recycled to sinter plant to produce sinter. All theblast furnace (BF) slag shall be granulated and provided to cement manufacturers forfurther utilization. All the BOF slag shall be reused in the blast furnace, sinter plant.SMS slag shall~a!so be -properly utilized. All the-other" solid waste including brokenrefractory mass shall be properly disposed off in environment-friendly manner or in asuitably designed landfill as per CPCB guidelines to prevent leaching to the sub-soiland underground aquifer within the premises and efforts shall be made to makefurther utilization. Waste oil shall be sold to authorized recyclers.
ix) All the fly ash shall be utilized as per Fly Ash Notification, 1999 subsequentlyamendment in 2003.
x) A time bound action plan shall be submitted to reduce solid waste, its properutilization and disposal.
xi) As proposed, green belt shall be developed in 33 % area within and around the plantpremises as per the CPCB guidelines in consultation with OFO.
xii) All the recommendations made in the Charter on Corporate Responsibility forEnvironment Protection (CREP) for the Steel plants shall be implemented.
GENERAL CONDITIONS:
I. The project authorities must strictly adhere to the stipulations made by theChhattisgarh Environment Conservation Board (CECB) and the State Government.
ii. No further expansion or modifications in the plant should be carried out without priorapproval of the Ministry of Environment and Forests.
~-~~,-""~--""'-.
~~~'fft~~~~ant~ Th..r..'~ ~ ';HI~"'.. -, '"A" .- - . . ...
Page 3Annexure 2
...L ~.4
iii. The gaseous emissions from various process units shall conform to the load/massbased standards notified by this Ministry on 19th May, 1993 and standardsprescribed from time to time. The State Board may specify more stringent standardsfor the relevant parameters keeping in view the nature of the industry and its sizeand location. At no time the emission level shall go beyond the prescribedstandards. The interlocking facilities shall be provided so that process can be9~tomatically stopped in case emission level exce~ds the limit.
In-plant control measures for checking fugitive emissions from all the vulnerablesources like spillage/raw materials/coal handlings etc. shall be provided. Further,specific measures like provision of dust suppression system consisting of watersprinkling, suction hoods, fans and bag filters etc. shall be installed at materialtransfer points and other raw material handling areas. Centralized de-dusting systemi.e. collection of fugitive emissions through suction hood and subsequent treatmentthrough bag filter or any other device and finally emitted through a stack ofappropriately designed height conforming to the standards. Fugitive emissions shallbe regularly monitored and records maintained.
iv.
At least, four ambient air quality-monitoring stations should be established in thedownward direction as well as where maximum ground level concentration of SPM,S02 and NOx are anticipated in consultation with the CECB. Data on ambient airquality and stack emission should be regularly submitted to this Ministry including its
=-<'- ~- -. _1l~gio!}.~1Office atBh()p§1 afld the CECB/CPCB once in six months.- ~ ..,,".~ --'-=-~--~-~. .:-:- ::?"---~'" ~'#.~.., ""~~-"'"' S'"'" -- ..:-, - = 0<""'.
vi. Industrial wastewater shall be properly collected, treated so as to conform to thestandards prescribed under GSR 422 (E) dated 19thMay, 1993 and 31stDecember,1993 or as amended form time to time. The treated wastewater shall be utilized forplantation purpose.
.~
IIII'
Ii
~
xi.
l-",,"
v.
vii. The overall noise levels in and around the plant area shall be kept well within thestandards (85 dBA) by providing noise control measures including acoustic hoods,silencers, enclosures etc. on all sources of noise generation. The ambient noiselevels shall conform to the standards prescribed under EPA Rules, 1989 viz. 75 dBA(daytime) and 70 dBA (nighttime).
viii. Occupational health surveillance of the workers shall be done on a regular basis andrecords maintained as per the Factories Act.
ix. The company shall develop surface water harvesting structures to harvest the rainwater for utilization in the lean season besides recharging the ground water table.
x. The project proponent shall also comply with all the environmental protectionmeasures and safeguards recommended in the EIA / EMP report. Further, thecompany must undertake socio-economic development activities in the surroundingvillages like community development programmes, educational programmes,drinking water supply and health care etc.
As proposed, Project authorities shall earmark Rs. 736.50 Crores & Rs. 110.50Crores towards capital cost and recurring cost/annum for environmental pollutioncontrol measures to implement the conditions stipulated by the Ministry ofEnvironment and Forests as well as the State Government. An implementationschedule for implementing ~II the conditions stipulated herein shall be submitted tothe Ministry's Regional Office at Bhopal. The funds so provided should not bediverted for any other purpose. .
Page 4Annexure 2
(' xii.
.
I, xiii.
R===~ ~ ~ ~~, ~ ~~<>
I~
u
xiv.
-- ---5
The Regional Office of this Ministry at Bhopal/CPCB/CECB will monitor the stipulatedconditions. A six monthly compliance report and the monitored data along withstatistical interpretation shall be submitted to them regularly.
The Project Proponent shall inform the public that the project has been accordedenvironmental clearance by the Ministry and copies of the clearance letter areavailable with the CECB and may also be seen at Website of the Ministry ofEnvironment and Forests at http:/envfor.nic.in. This shall be advertised within sevendays from the date of issue of the clearance letter, at least in two local newspapersthat are widely circulated in the region of which one shall be in the vernacularfanglfage of the'"lctca1itrconc~rned1mCFa'?-cbPY'bf-'1'n'e'-sa~IibUld"CbetTorwardecrto=the Regional office.
Project authorities shall inform the Regional Office as well as the Ministry, the date offinancial closure and final approval of the project by the concerned authorities andthe date of commencing the land development work.
6.0. The Ministry may revoke or suspend the clearance, if implementation of any of the aboveconditions is not satisfactory.
7.0. The Ministry reserves the right to stipulate additional conditions if found necessary. TheCompany in a time bound manner shall implement these conditions.
8.0. The above conditions shall be enforced, inter-alia under the provisions of the Water(Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act,1981, the Environment (Protection) Act, 1986, Hazardous Wastes (Management and Handling)Rules, 2003 and,the Public (Insurance) liability Act, 1991 along'with their amendments and rules.--
Copy to:
~(Dr. P. B. Rastogi)
Director
1. Secretary, Department of Environment, Govt. of Chhattisgarh, Chhattisgarh.2. The Chairman, Central Pollution Control Board, Parivesh Bhavan, CBD-cum-Office
Complex, East Arjun Nagar, Delhi-110032.3. The Chairman, Chhattisgarh Environment Conservation Board, Nanak Niwas, Civil
lines, Raipur, Chhattisgarh.4. The Chief Conservator of Forests (Eastern), Regional Office (WZ), E-3/240, Arera
Colony, Bhopal- 462016, M.P.5. Adviser (lA-II), Ministry of Environment and Forests, Paryavaran Bhavan, CGO
Complex, New Delhi.6. Monitoring Cell, Ministry of Environment & Forests, New Delhi.7. Guard file.8. Record file.
~~(Dr. P. B. Rastogi)
Director
~ fc!;m'Ii"t~ ~ ~ "[31T~ <t'f There's a little bit of SAIL in everybody's life
Page 5Annexure 2
F. No. J-1101 1128120A7- lA lt (l) - partGovernment of lndia
Ministry of Environment and Forests(1.A. Division)
paryavaran BhawanCGO Complex, Lodhi Road
New Delhi - 110 003' E-mail: ms.industry-mef@nic.in
Tele/fax: 011 * 2436 3973. Dated: 23d June,2011
To,M/s SteelAuthority of lndia LimitedBhilai Steel Plant, Bhilai- 490 001, DurgChhattisgarh
E-mail: sailbsn@sancharn&.in
Sub: Modernization-cum-expansion of Bhilai Steel Plant (4.0 MTPA to 7.0 MTPA) atongwith Captive Power Planl (72 MW) at Bhilai in Chhattisgarh by M/s Steel Authorityof lndia Limited (SAIL) - regarding amendment in Environmental Clearance
This is in continuation of this Ministry's letter of even no. dated 31.03.2008 andsubsequent communications dated 23.03.2011 and 28.05.2011 informing the Ministry towithdraw 2x125A TPD Oxygen Plant from the list of units for rrrlhich environmental clearancewas accorded vide Ministry's letter of even no. dated 31.03.2008.
2. The proposal for amendment of environmental clearance was placed before theExpertAppraisal Committee-1 (lndustry) in its 24th meeting held during 19t6 - 20th May,2A1i.The Committee noted that as per the BOO contract for installation of 2x1250 TPD 02 plant,the responsibility to get statuary approvals lie with Mls PRRXnIR lndia Limited. The land forthe installation of the Oz plant has been leased to M/s PRAXAIR lndia Limited with in theboundary of the steel plant. The Committee decided that M/s SAIL would withdraw theOxygen Plant from the list of units mentioned in the environmental clearance of even no.dated 31.03.2008 and take measures for risk management due to the Oxygen Plant.
3. ln view of the above, the Ministry's has taken note of your request vide letter no.DGM(EnMD)|B-101111409 dated 20.05.2011 regarding withdrawal of Oxygen Plant from thelist of units as mentioned in the Environmental clearance accorded on 31't March, 2008. Asthe Oxygen plant will be set up within the premises of Steel Plant, measure for risk mitigationshall be taken by M/s SAIL.
This issues with the approval of the Competent Authority.
Copy to: The Chairman, ChhattisgarhNagar, Shiv Mandir Chowk,Chhattisgarh
Environment Conservation Board, 1-TilakMain Road, Avanti Vihar, Raipul,- 392001,
(Dr. P.L. Ahujarai)Scientist'F'
(Dr.
g-(,u-*-----
Page 6Annexure 2
a>9FC
E*iff r-&
Eoi'1rr r -
5'p:€,I
tr
F. No. J-11011128120074A Il (t)Government of lndia
Ministry of Environment and Forests(1.A. Division)
Paryavaran BhawanCGO Complex, Lodhi Road
New Delhi- f i0 003
E-mail : r.sundar@nic.inTelefax: 011:2436 6739
Dated: Sth July, 2013
It{r. R.K. AgrawalDGM l/C, Room No.540,lspat Bhawan, Bhilai Steel Plant,Bhilai-49000 1, Chhattisgarh.
E-mail: rkagrawal4@sail-bhilaisteel.com Fax: 0G51 33078
Sub : Modernization-cum-expansion of Bhilai Steel Plant (4.00 to 7.00 MTPA) along withCaptive Power Plant (72 MW) at Bhilai, Chhattisgarh by M/s Steel Authority oflndia Limited (SAIL) - regarding extension of validity of the Environmenta!Clearance
Ref. : (i) Ministry's EC letter of even no. dated 31.9.2009(ii) Your letter no. No. B,-101131189 dated 2.3.ZO1Z
Sir,This is in continuation of this Ministry's letter referred above and your letter under
reference, wherein you have requested for extension of validity of the aforesaidEnvironmental Clearance (EC).
2. The above proposal was placed before the Reconstituted Expert AppraisalCommittee (lndustry) in its 8th meeting held during 16-171h May, 2013. lt was noted that theproposed project could not be established within validity period of the granted EnvironmentalClearance marnly because of:-
i. Major packages of the Modernisation-cum-expansion projects were either retenderedor time extension has been provided due to higher price bid or technology consortiumissues.
ii. The modernisation of plant involves relocation of some of the existing units suitably.iii' The project is integrated in nature and various packages are intertint<ed. itreprogress of packages depends on upstream and downstream progress of otherpackages also. Contractors/ suppliers of some of these packages could not achievethe desired progress causing time over run in other packages.
3. After taking into consideration the aforesaid facts, the committee recommended forthe extension of validity of EC by a period of five years with effect from 30.3.2013 subject toenvironmental safeguards.
4. The Ministry accepts the recommendation of the REAC (lndustry) and extends thevalidity of the Environmental Clearance letter no. J-1101112812007 - tA ll (l) dated 31.3.2008
g. !,*-
Page 7Annexure 2
-2-
for a period of five years with effect from 30.3.2013 subject to the specific and generalenvironmental conditions.
5. All other conditions stipulated in the environmental clearance letter no, J-1141112812007 - lA ll (l) dated 31.3.2008 shatt remains the same.
6 The eompany shali obtain fresh environmental clearance in case of any change inthe scope of the project.
This issues with the approval of the Competent Authority.
Dq-(.|."^}_(Sundar Ramanathan)
Deputy Director(S)Copv to:
1. The Secretary, Department of Environment, Govt. of Chhattisgarh, Chhattisgarh.2. The Chairman, Central Pollution Control Board, Parivesh Bhavan, CBD-cum-Office
Complex, East Arjun Nagar, Delhi-110032.3. The Chairman, Chhattisgarh Environment Conservation Board, Nanak Niwas, Civil
Lines, Raipur, Chhattisgarh.4. The Additional Principal Chief Conservator of Forests (Eastern), Regional Office
(Western Zone), E-31240, Arera Colony, Bhopal - 462 01G, Madhya pradesh.5. Monitoring Cell, Ministry of Environment & Forests, Paryavaran Bhavan, CGO
Complex, New Delhi.6. Guard file i Record file.
?(Sundar Ramanathan) t
Deputy Director(S)
Page 8Annexure 2
#''i'i
F. No. J-tl-l{;il,/28/2007-tA Il (t}
Gover,l4rerrt of lndia
Min jstrrr of E nvironnrell-::, ;Forests'anrl Cli mate ChanBe'1fi dirfi f aryavara.n sharru* rr
Jor Bagh Road. Ali Ganj.
t'lew Delhi - l"l"0$0lE-mail: "f chand20O3 @vahrrr:.co. u k.--*-=:--;l:-. -_-
r ete; rriJ.; .145953'i 3
Dated: ?3'o luly ?0:r4
,,To
r'"'' ti* ,li, ooo* *o. t*0, ,'lM/s$teen,&ut[tority'ea${ndia,[tS,.':.,ispat Bhawan, Eirilai Steel Piant,Bhilai-z!90001, Chfu attisga rh.f-maiil rkagrai,va,l4@saii"bhilaisreel;toi]:l $ax:' tJSS$.,:33078
$vlh ; Mudernization-c({ni:expa,nsion,of Bhilai Stcel Plant (4.00 to 7.00 MTPA) along with.[ap{iv*Fower PIa$t i72 MW)'at Bhjla!, Chttxtlllgarh hy M/s'$[eel Authority of india l-inrlted {$A${-}'.s.rneyrdrnerlt in't$'re,shvirsnsnert{al,$i*laranae dated $$,S3i?0$$ and S5-$7,201"3 ir.r respecterf Sxygen Ffant.fraga(it$* reg ' -l'
I
sii:, ,.,,,
Yhis is With relerence to tiris [,4ini;,tryis envirofilnental clearances of even nr;. earecl3ll.s3-7008 and 0s.s7.2013 and your letter n-. No. s-L0/L3/7gs dated S4.09:?il1,3, wherein y.Juhave tequested for auendment i; the'Envirorr;]ental Clearance ief,) dated 3l"3.zgi)B in respect oicapacity of the oxygen plant,
i
?- The abave propolai was placed be{;re the Reconstituled Expert Appraisal Conimittet:{industry) in its t$.!h rneeting heirl during 28-30:l May J*14. lt was noted that the amendnrenr soughris as given below;
tI was infortned that chang,liig rapacily r:f tire axygen plap{ frorn 1N55* TFD ts 1-x7$S TF* w*snecessairy due to stahdard mod.ule.capacitty oT t,nits *f r:rranufaetr:res/ sr-rppliers,and there,vviil not beincrease in poJlution load due to the increhs,'in rapacity of the oxygen plant, Afler taking ir: ic;consideratton the ailove, tlre Comnrittee recr,-nfitcnded for the amenriment in the EC date.r3tr.3.200B as referrerJ above subject to environmeriial sa{eguards.
3. The, Mir:istry acc€pt$ the recornnreibation of the REAC {industry} arrd arrerrds tileEnvironrnental Ctearance letter no, J-LLSIUi,3/2007 - tA Il (l) dared 31",3.A0Sg.'The capacitrT *f ih*"Oxygen Phint .* 1 x 650 TPS" men'tloned in ii'l*:column 3 & 4 of the tahle given in ttre para ? of th*environffi€ilLa{ clearanct'letter dated 31.3,2u\0fi,stanrts deleted'afld it ir}ay be read as',Oxygen Fla6t
4, AII oth$r conditions $tipr{lated'iri the ert,rirolmental clearailce lettet nfi- J-1I01:ll2$/2S{I, -rA {i (l) dated 31.3.2008 shall remains the same
i.j -
il.'
xs per the, Se datsd:,$$*$;2s08
oxveen Plant'550TPD
Page 9Annexure 2
l"I
,, ,,)., ., . , I .
, . r:: ,.::tt :i.:..:.,, .. ' ..] : ili:
5; ., 'Th$r:c.qrnpany,shall ohEi,n,flesh envirloilEeittal c,le,,dil*n.ce,in,sase *f elrllichange.jfirthe,,$$ope,pf,the pe?JjF.ctr
.: --. I r ' j: :
This iisues with the appr:oval of the Csmpetent AuthoriW:::
I : 'r :l "''i'
:
;i\.! {*r.,T,;.[hatdiu!]
: ' . .Sir-ect6r
{s*:, f,ifili5v#iyli}..':: i Sif€ftsf
L. The$Ffffll.1.y1:1*epaq enl 9f tnvirolnrgfr, {$o.vf, gf,cfihari$Calh,,chhar1ipga.r:t!.,, ,.2. The Chairman, cen{1f follutjol Contr+li.sggrc{*:pqrive*li-:Uhaqir6, C*$i**m ee,,€oRtpJex,
EastArjun..l$aga.r;,0elhi;I10032,'1,,,.;3, The chairmanr: chhatlisg;rh Envhronrne'4t €onservatioJr Board, fi;qnak Niwas, civjl Lines,
,Baigur,,ChhEtttsearh, , ,',,. ,,,i ' :4, The Additianal rrinclpal Chiet'Cgnse;;v3i;,rlof toJests {Easter.n}, ftegiot-ral:Office (Western
Zone},E;3/2+s,.Areraiolony,.,Bhopat,-.*e2ota,Ma]utryqr,-rdoeitr.',5, Monitoring CeJt,,Ministry of Environrnerit Sr"Foresis; Faryava[an Bl"iavan, CGO domplex, New
r".-! j
tirj.;:.ir
ti,
'l
it-'*
rll
:l ,
:jt..' ,1s
: lr:'
..ll
lfi ,,
,..'l I
: rii.:
:r:t" t 'l
r: ''ri
.;;
t"" Ji;il.t
Page 10Annexure 2
EW
S N
Toposheet Index
F44P7F44P11
F44P8F44P12
21°30'
81°15'81°30'
81°45'
21°30'
21°15'
21°15'
21°0'
21°0'
81°15'81°30'
81°45'
LEG
EN
D
PLANT AR
EA
10 km STU
DY AR
EA
81°15'21°15'81°15'
81°30'
81°30'
21°15'
02.5
5.0Kilom
etersScaleSTE
EL A
UTH
OR
ITY OF IN
DIA
LIMITE
D - B
HILA
I STEE
L PLAN
T
ME
CO
N LIM
ITED
Elm oTeffid d,mffifrflTTkSTEEL AUTHORITY OF INDIA LIMITED
fW $srd ddaBHILAI STEEL PLANT
Authorization
Ms, Uma Katoch, DGM, Environment Management Department, Bhilai Steel Plant,
M/s Steel Authority of lndia Limited, is competent and hereby authorised to submrt
the application/s for getting Terms of Reference(ToR)/ Environment Clearance etc,
from Ministry of Environment, Forests & Climate Chpnge, Government of lndia
For M/s SAIL, Bhilai Steel Plant
(M Ravi )
Chief Executive Officer
M +go oor, umq.tE, $-w : ozag-zzzz Bso, o7 88-2223491, iq vEc : www.sail.co.in
Bhilai 490 001 , Chhattisgarh, Fax 0788-2222890,0788-2223491, website : www.sail.co.in
5rrffi 6ffi dg.srg.andub There's little bit of SAIL in everybody's life
top related