7/28/2019 Add BTSs- New Cells
1/30
Alcatel BSS
Add BTS(s), newcell(s)
O&MDocumentation
Scenario
3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
2/30
Status RELEASED
Short title MPI 84 / 1 7
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel.
BLANK PAGE BREAK
2 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
3/30
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.1 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.2 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.3 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.4 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.2.2 Site Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.4 Telecom / Supervision Outage and Operating Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.5 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
1.5.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
1.5.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.5.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
2 Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
2.1 Before Going On-site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.2 Before you start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.3 Scenario Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
2.3.1 Perform initial checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.3.2 Create Abis (Case 1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.3.3 Create BTS(s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.3.4 Create Cell(s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 222.3.5 Insert BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.3.6 Call Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
2.3.7 Create Adjacencies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 262.3.8 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
2.4 Reverse procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 282.4.1 Lock Cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 282.4.2 Disconnect BTS(s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 282.4.3 Unlock Cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 282.4.4 Delete Cell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.4.5 Delete BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.4.6 Delete Abis (Case 1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.4.7 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
3BK 17416 0841 RJZZA Ed.03 3 / 30
-
7/28/2019 Add BTSs- New Cells
4/30
Figures
Figures
Figure 1: Grouped Task Sequence for Add BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
4 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
5/30
Tables
Tables
Table 1: Sites/Personnel/Duration in Minutes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Table 2: Traffic Outage, Loss of Supervision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Table 3: Software tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Table 4: Forms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
3BK 17416 0841 RJZZA Ed.03 5 / 30
-
7/28/2019 Add BTSs- New Cells
6/30
Tables
6 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
7/30
Preface
Preface
Purpose To add a BTS.
Audience This document is intented for:
Field service technicians
Specialists
Project managers
Foremen.
AssumedKnowledge You must have a basic understanding of the following:For planification purpose
Network architecture and reshuffling principles
Basic knowledge for scheduling.
For realization purpose
Alcatel operations and maintenance concepts for BSS
Alcatel 1353RA OMC-R
Equipment (BSC, BTS, MFS) hardware configurations
Windows environment.
3BK 17416 0841 RJZZA Ed.03 7 / 30
-
7/28/2019 Add BTSs- New Cells
8/30
Preface
8 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
9/30
1 Overview
1 Overview
This chapter gives information needed for project managers and foremen, forpresentation to the customer and site planning.
3BK 17416 0841 RJZZA Ed.03 9 / 30
-
7/28/2019 Add BTSs- New Cells
10/30
1 Overview
1.1 Presentation
Note: The logical configuration can be activated completely independently from thephysical connection of the BTS. Creating adjacencies and call tests must beconducted after the BTS is functional and connected to the network.
Coordination is needed between BTS and OMC-R sites to define the initialsettings. The Qmux address must always be set. For A9100/A910 BTSs, thetransmission mode is configured via OML.
The GPRS option is not applicable when the Abis chain to the BTS is passingthrough a satellite connection.
G1 MKII BTSs can only be used if they have a BIUMD card (Chain) and if theyare equipped with DRFU. They cannot be used if they have a BIU2M card (Star).If they have the BIU2M card, either the BTS or the card must be replaced.
G2 BTSs can only be used if they have a FUMO or DRFU card. They cannotbe used if they have a FUCO card, in this case either the BTS or the cardmust be replaced.
In order to create a required configuration it is also possible to add more thanone new BTS and more than one cell. In this case it is better to perform all thelogical parameters modification into a single PRC.
1.1.1 Cases
The following cases apply:
C1: BTS is installed on a new Abis. There is no traffic outage.
C2: BTS is installed on an existing Abis with downstream BTSs. This case
causes a traffic outage on the downstream BTSs.
C3: BTS is installed at the end of an Abis chain (no downstream BTSs).There is no traffic outage.
1.1.2 Options
The method takes into account one option:
O1 : Configuring the GPRS for the cells
O2 : Abis connection via satellite.
O3: Create cell(s) shared (applicable only for A9100 BTSs ).
1.1.3 Restrictions
None.
10 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
11/30
1 Overview
1.1.4 Grouped Task Sequence
Figure 1 shows the grouped task sequence for the Add BTS scenario.
MSC OMCR
Initial checks
BTS
Create Abis (Case 1)
Create cell
Create BTS
Final checks
Insert BTS
Figure 1: Grouped Task Sequence for Add BTS
3BK 17416 0841 RJZZA Ed.03 11 / 30
-
7/28/2019 Add BTSs- New Cells
12/30
1 Overview
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply:
BTS sites are clean, tidy and easily reachable.
The Abis is installed and tested.
For Case 2, the jumper linking the upstream and downstream BTSs has
been installed. This jumper is removed during this scenario.
BTS(s) is installed and commissioned.
For option O3: Clock synchronization cable(s) must be already installed
between BTSs involved into cell shared .
BTS(s) must be configured with the correct initial settings.
There are adequate resources to handle the new traffic channels and LapD.
All BTS SW packages and OMU-CPF are loaded in BSC memory.
12 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
13/30
1 Overview
1.2.2 Site Specific Information
You need the following site specific information:
Identification of cases and options to perform
BTS site topology
Case 1: Characteristics of the Abis (name, Qmux TS if BTS(s) to insert is
G1/G2 BTS).
Characteristics of the BTS(s) (family, HW generation, name, Qmux address,
number of sectors, mode of transmission, antenna diversity, master or
slave, Qmux TS for G1/G2 BTS).
List of cells to create with parameters value ( LAC, CI, frequency, TS
definition). The list has to be exhaustive.
List of cells supporting GPRS and parameters value ( RA code, RA color,
Min_Pdch, Max_Pdch_High_Load, Max_Pdch )List of adjacencies with parameters (list of impacted cells, direction of
the HO)
1.2.3 External Tasks
The following external task is to be taken into account:
1. All cells are declared at MSC site
2. Ask the personnel at MSC to perform a MSC database update for takinginto account the parameters for the new BTS.
3. In case of Option 2, check and update if needed the CRC4 for the Abis atthe BSC site.
4. Update adjacencies on neighbours OMCs if necessary
1.3 Scheduling
Table 1 describes the sites, personnel and duration of each Grouped task andthe total time to perform the scenario.
Time based on technical constraintsThe times in the following table do not take into account individual customer or
safety requirements.
GroupedTask
MSC TSC BSC BTS Imp.BTS
OMC -R Time/ Task
Perform InitialChecks
- - - - - 1 op
15
15
Create Abis(C1)
- - - - - 1 op
C1:6
6, only for case C1
3BK 17416 0841 RJZZA Ed.03 13 / 30
-
7/28/2019 Add BTSs- New Cells
14/30
1 Overview
GroupedTask
MSC TSC BSC BTS Imp.BTS
OMC -R Time/ Task
Create BTS(s) - - - - - 1 op
8/ BTS+1
C2,C3:+2/BTS
O2: +3
8/ BTS+1
C2,C3:+2/BTS
O2: +3
Create Cell(s) 1 op
(3)
- - - - 1 op
17/cell+2/BTS+6
O1: +7/cell
O3: +3/cell
17/cell+2/BTS+6
O1: +7/cell
O3: +3/cell
Insert BTS(s) - - 1 com
C1:5
C2:10
C3:5
- 1 op
7/BTS+1/cell+1
C2:+1+5/cell+2/BTS*
7/BTS+1/cell+1
C1:+5
C2:+10+5/cell+2/BTS*
C3:+5/BTS
Call Tests - - - 1 com
5/cell
- 1 op
5
5+5/cell
CreateAdjancencies
- - - - - 1 op
9/cell
9/cell
Final Checks - - - 1 com - 1 op
15
15
TOTAL TIME 49+17/BTS+32/cellC1:+11
C2: +2/BTS*+13+5/cell
C3: +7
O1: +7/cell
O2: +3
O3: +3/ cell(shared)
Table 1: Sites/Personnel/Duration in Minutes
Note :
BTS for added BTS
BTS* for downstream BTS.
14 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
15/30
1 Overview
1.4 Telecom / Supervision Outage and Operating Impact
The following table describes the traffic outage and loss of supervision causedby each Grouped task.
Out.ReF.
GroupedTask
Tel Out/ GPRSOut.
TelRed Sup Out OM Out Impacts...
- Perform InitialChecks
- - - - None
- Create Abis(Case C1)
- - - - None
- Create BTS(s) - - - - None
- Create Cell(s) - - 1/30 - Sup.out. 130 duringthe PRC activation
1 Insert BTS 2/BTS*+2/cell+10- 10+2/BTS* - For C2, outage ondownstream BTSs
For O2+C2 telcomand GPRS outagefor downstream BTSs(same value)
- Call Tests - - - - None
- CreateAdjacencies
- - - - None
- Final Checks - - - - None
- Total C2:2/BTS*+2/cell+10
- C2: 10+2/BTS*
for all cases:+1/30
- C2:2/BTS*+2/cell+10
O2+C2:2/BTS*+2/cell+10GPRS +telecomoutage
During the activationsupervisionoutage:130.
Table 2: Traffic Outage, Loss of Supervision
Note :
BTS for added BTS
BTS* for downstream BTS.
3BK 17416 0841 RJZZA Ed.03 15 / 30
-
7/28/2019 Add BTSs- New Cells
16/30
1 Overview
1.5 Resources
1.5.1 Tools
The following tables describe the tools that are needed.
HardwareTools
Item Part Number Use at ...
Wiring tools for disconnection and reconnectionof PCM
- BTS
Mobiles for call testing - BTS
PC with associated cables - BTS
Item Part Number Use at ...
BTS Terminal for B7.2 - BTS
LMT-CT (Craft Terminal) for B7.2 - BSC
Table 3: Software tools
Item Part Number Use at ...
None
Table 4: Forms
1.5.2 Supplies
The following table describes the supplies needed for this operation.
Item Part Number Use at ...
Topology regarding operation - BTS
16 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
17/30
1 Overview
1.5.3 Applicable Documents
The following documents are needed:
A1353-RA Configuration Handbook
A1353-RA Surveillance Handbook
B7 BSS Methods Handbook .
Network Configuration Recommendations
BTS Terminal User Guide
Transmission Terminal User Guide
BTS Site Master/ Slave Synchronization
3BK 17416 0841 RJZZA Ed.03 17 / 30
-
7/28/2019 Add BTSs- New Cells
18/30
1 Overview
18 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
19/30
2 Scenario
2 Scenario
This chapter presents all checks needed before beginning the scenario, and alldetailed tasks to be performed on each site.
3BK 17416 0841 RJZZA Ed.03 19 / 30
-
7/28/2019 Add BTSs- New Cells
20/30
2 Scenario
2.1 Before Going On-site
Before going on-site, you must check the following information are available.
All Prerequisites (Section 1.2.1) are fulfilled.
The customer has been informed about the:
Date
Time
Site name
Site address
Purpose of the operation.
Personnel are available and ready for the operation (see Scheduling
(Section 1.3)).
Site Specific Information (Section 1.2.2) is available and ready for operation.
Tools (Section 1.5.1) are available and ready for operation.
Supplies (Section 1.5.2) are available and ready for operation.
Documentation is available and ready for operation.
2.2 Before you start
Check that all Prerequisites (Section 1.2.1) in the overview are fulfilled.
Well check the availability of all necessary tools and material
Inform the operator.
Among the cases (C1, C2, C3) described within Overview chapter 1.1.1,identify which are your cases. Identify as well the option you have choosen.
RequiredKnowledge You must be familiar with the following:
Safety Rules and Precautions
Telecom / Supervision Outage and Operating Impact (Section 1.4)
Instruction for reverse procedure decision
Grouped Task Sequence (Section 1.1.4)
Operating Hints
How to document Faults and Anomalies.
20 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
21/30
2 Scenario
2.3 Scenario Description
The detailed tasks for adding a BTS are described below.
Note: Case specific tasks are marked with a C1, C2 or C3 in the Note column.Detailed Tasks that do not have C1, C2 and C3 in the note column are common
to all three cases and must be performed.To add a BTS to:
A new Abis, use Case 1 (C1)
An existing Abis with downstream BTSs, use Case 2 (C2)
A BTS to the end of an existing Abis (no downstream BTSs), use Case 3
(C3).
Options are marked with O1, O2, O3 in the Note column. Detailed tasks thathave O1, O2, O3 are applied only if that option is choosen.
2.3.1 Perform initial checks
Note Task Description Site To Do Outage
Perform an Audit Alarm State on BSS. OMC-R 10 None
View Status of Managed Objects and Alarmsonall the BTSs of the TSU and for the Abis, print it.
OMC-R 5 None
2.3.2 Create Abis (Case 1)
Note Task Description Site To Do Outage
C1 Create Abis Chain/Ring . Wait for thetransmission programming flag to change fromAbis to idle.
OMC-R 6 None
2.3.3 Create BTS(s)
In order to create a required configuration it is also possible to add morethan one new BTS .
Note Task Description Site To Do Outage
C2, C3 If the BTS(s) to add is G1 or G2, check if theAbis is set with a TS for Qmux. If not, reserveone Qmux TS by Modify Abis Chain/RingCharacteristics
OMC-R 2 None
3BK 17416 0841 RJZZA Ed.03 21 / 30
-
7/28/2019 Add BTSs- New Cells
22/30
2 Scenario
Note Task Description Site To Do Outage
Create BTS . Always set the Qmux address.
For option O3 : Declare the new BTS in slaveand select the concerned Master BTS name, if
is necessary.
If you receive any error messages, see Checkingfor Sufficient Resources on Abis.
Wait for the Information window confirming thecreation of the new BTS, click on &ok.
Wait for the transmission programming flag tochange from Abis to idle
OMC-R 7/ BTS None
Verify with the BTS site that the initial settingsare correct. If it is not correct, change the Qmuxaddress (see Modify Initial Settings ) at the BTS
site for each new BTS.
OMC-R/BTS 1 / BTS None
O2 If the Abis is connected via satellite Check CyclicRedundancy at the BSC side using LMT-CTtool, and, if needed, Modify CRC4
OMC-R /BSC
3 None
Check that the newly created BTSs appear inthe hierarchy view of the Radio ConfigurationBrowser (SC).
OMC-R 1 None
2.3.4 Create Cell(s)
In order to create a required configuration it is also possible to create morethan one cell. In this case it is better to perform all the logical parametersmodification into a single PRC
Note Task Description Site To Do Outage
Create PRC(PRC1). Enable the buttonAutomatic opening in the Create PRC window.The PRC is opened once created.
OMC-R 1 None
O3 Copy OMC cells to PRC
, the cell(s) which becoming shared with the newBTS, if is necessary.
OMC-R 2/ cell None
Use Copy BTS to PRC , to copy the new BTSsfrom the SC to the PRC1.
OMC-R 2/ BTS None
OMC-R 1/ cell NoneO3 Link Cell to a secondary BTS Sector
Note: for each cell which becoming shared
22 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
23/30
2 Scenario
Note Task Description Site To Do Outage
Create Provisioning Cell or Duplicate Cell . Thecell is created/duplicated in the PRC1 and is ina locked state. Create one cell for each sector
is necessary.
OMC-R 2/ cell None
Use Set Cell Telecom Parameters. OMC-R 2/ cell None
Create Radio Frequency. OMC-R 30/ cell None
Create Frequency Hopping System , if you useFrequency Hopping.
OMC-R 1 30/ cell None
OMC-R 30/ TRX NoneCreate TRX.
Note : For O3 select the TRX in[Secondary] TRX on a shared BTS sector,
if is necessary.
Configure TRX Channel Hopping Law , tohopping or no hopping.
OMC-R 1 30/ cell None
Specify TRX Preference. OMC-R 30/ TRX None
Configure Logical Channels. OMC-R 1/ cell None
OMC-R 5/ cell NoneO1 Set BSS/BSC Telecom Parameters in PRC1 toupdate GPRS parameters if needed. This taskincludes the modification of CAE data specificto the MFS.
Notice: the duration depends of thenumber of parameters to modify. Hereis considered 10 parameters in differentwindows
OMC-R 2/ cell NoneO1 If GPRS parameters have to be modifiedon cell(s) then, Edit n Cells in PRC.Modify parameters such as Min_Pdch andMax_Pdch_High_Load, Max_Pdch, RoutingArea Code or Routing Area Color
Notice1: To have GPRS on the cell GPRSPref.mark must be different from 0. Tomodify it, use the java script Set/UpdateGPRS pref. Mark using script
Notice2: to modify only one cell, theoperator can use the edit cell command(see Set Cell Telecom Parameters )
Notice3:For O3 : GPRS Pref. mark =0, forsecondary sector.
Click on in the Edit Cellwindow to save cell modifications in the PRC1.Wait for the message No error or warningand click on &ok. If the check produces errormessages, correct the configuration as requiredand re-attempt the check. Continue correctionsand checks until no errors occur.
OMC-R 30/ cell None
Click on to exit from the Edit Cellwindow.
OMC-R 30/ cell None
3BK 17416 0841 RJZZA Ed.03 23 / 30
-
7/28/2019 Add BTSs- New Cells
24/30
2 Scenario
Note Task Description Site To Do Outage
OMC-R 1/ cell NoneMap Cell to a BTS Sector.
Note:map each new cell
Use the Check All option ( without forcing celladministrative state) in Check PRC to check theparameters, hardware and telecom impact ofyour PRC1.
If the check produces error messages, correctthe configuration as required and re-attempt thecheck. Continue corrections and checks until noerrors occur.
OMC-R 1 None
Ask the MSC personnel to update the parametersin the MSC DB.
OMC-R/MSC 3 None
24 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
25/30
2 Scenario
2.3.5 Insert BTS
To minimize traffic outage, you must keep the time between the lock andunlock cells to a minimum.
For option O 3: Clock synchronization cable(s) must be already installed
between BTSs involved into cell shared . If the cables are not installed performthis installation using chapter Install Synchronization Cables form BTS SiteMaster/ Slave Synchronization scenario.
Note Task Description Site To Do Outage
C1, C3 If not done previously, the BTS must bephysically connected to the new Abis link(use BTS Connection ).
BTS 5 None
C2 Inform the OMC-R you are ready to insert the
BTS into the Abis link.
BTS/
OMC-R
1 None
C2 In the Abis Interface View Window, selectthe Abis chain/ring where you insert thenew BTS. Write down the BTSs that aredownstream from the new BTS. Go to theSC and lock the cells, use Shut Down Cellof these downstream BTSs (WTC=3 min ).Inform the BTS site when the cells are locked.
OMC-R 4/cell START 1, starttelecom+ GPRSoutage fordownstreamBTSs.
C2 Lock BTS O&M Capability of the downstreamBTSs.
OMC-R 1/ BTS* OUTAGE 1
C2 Inhibit Alarm Reporting on Abis TP, ( selectInhibit Alarm Reporting on TP Down)
OMC-R 1 OUTAGE 1
C2 Jumper Disconnection. BTS 5 OUTAGE 1
C2 BTS Connection. BTS 5 OUTAGE 1
C2 Unlock BTS O&M Capability of thedownstream BTSs.
OMC-R 1/ BTS* OUTAGE 1
C2 Use Unlock Cell, to unlock the cells of thedownstream BTSs.
OMC-R 1/cell END1
After connection the new BTS will enable itsOML link. Unlock BTS O&M Capabilityof theadded BTSs.
OMC-R 1/ BTS None
It starts the download for each new BTS. Aftera time the OMC-R will automatically trigger aHW and alarm audit for the each new BTS.All the boards of the BTS must appear onOMC-R BSS equipment view. Wait until theend of BTS(s) audit.
OMC-R 6/ BTS None
3BK 17416 0841 RJZZA Ed.03 25 / 30
-
7/28/2019 Add BTSs- New Cells
26/30
2 Scenario
Note Task Description Site To Do Outage
OMC-R 5 / cell NoneActivate PRC (PRC1). Choose to activateusing the option Without forcing celladministrative state. This option keeps the
cells locked.
The activation time depends on the number of
cells activated.During the activation supervision outage(130).
Close PRC(PRC1). OMC-R 1 None
C1, C2 Allow Alarm Reporting on Abis TP, ( selectAllow Alarm Reporting on TP Down)
OMC-R 1 None
Use Unlock Cell , to unlock the cells of thenew BTS(s).
OMC-R 1/ cell None
2.3.6 Call Tests
Note Task Description Site To Do Outage
BTS 5/cell NonePerform Call Test for the each new cell.
Task must be done in parallel with thenext task. .
Unlock cell from Call Test detailed tasknot necessary here.
CHECK Display USD Detailed Cell Information . Checkthat the new cells are in traffic. If not, go totheReverse procedure (Section 2.4) .
OMC-R 5 None
2.3.7 Create Adjacencies
Note Task Description Site To Do Outage
Create Adjacency for the new cell withnotes taken at preparation step assumingboth adjacencies towards new internalcells and adjacencies towards newexternal cells.
OMC-R 5 /new cell(s) None
For each cell on the same OMC thatmust be adjacent to the new added ones,Modify Adjacency to include the newadded cells.
OMC-R 2 /cell None
For each cell on the neighbour OMCsthat must be adjacent to the new addedcells, Modify Adjacency on neighbour
OMCs to include the new added cells.
neighbourOMC-R
2 /cell None
26 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
27/30
2 Scenario
2.3.8 Final Checks
Note Task Description Site To Do Outage
Perform an Audit Alarm State on BSS. OMC-R 10 None
View Status of Managed Objects and Alarmsonall the BTSs of the TSU. Compare this check tothe initial check.
OMC-R 5 None
3BK 17416 0841 RJZZA Ed.03 27 / 30
-
7/28/2019 Add BTSs- New Cells
28/30
2 Scenario
2.4 Reverse procedure
2.4.1 Lock Cells
Note Task Description Site To Do Outage
In the SC, use Lock Cell to lock all the cellsthat correspond to the added BTSs.
OMC-R 1/cell -
C2 In the SC, use Shut Down Cell for each cellof the downstream BTSs (WTC=3).
OMC-R 4/ cell -
C2 Lock BTS O&M Capability of thedownstream BTSs.
OMC-R 1/BTS* -
Lock BTS O&M Capability of the addedBTSs.
OMC-R 1 -
2.4.2 Disconnect BTS(s)
Note Task Description Site To Do Outage
BTS Disconnection ( for each added BTS). BTS 5 -
C2 Inhibit Alarm Reporting on Abis TP, ( selectAllow Alarm Reporting on TP Down)
OMC-R 1 -
C2 Jumper Connection. BTS 5 -
2.4.3 Unlock Cells
Note Task Description Site To Do Outage
C2 Unlock BTS O&M Capability of thedownstream BTSs.
OMC-R 1/BTS* -
C2 Allow Alarm Reporting on Abis TP, ( select
Allow Alarm Reporting on TP Down)
OMC-R 1 -
C2 In the SC, use Unlock Cell to unlock allcells of the downstream BTSs. Traffic isrestarted on the cells of the downstreamBTSs.
OMC-R 1 Traffic Restarts
28 / 30 3BK 17416 0841 RJZZA Ed.03
-
7/28/2019 Add BTSs- New Cells
29/30
2 Scenario
2.4.4 Delete Cell
Note Task Description Site To Do Outage
Use Open PRC to open the PRC1 OMC-R 1 -
O3 Unlink Cell from a secondary BTS Sector ,unlink the cell(s) which is shared with theadded BTS(s)
OMC-R 1/ cell -
O3 Delete TRX, to delete all TRXs for thesecondary sector
OMC-R 1/cell -
O3 Delete Radio Fraquency, to delete allfrequency for the secondary sector
OMC-R 1/cell -
Delete OMC Cell from PRC, delete all thecell(s) from the added BTS(s).
OMC-R 1/ cell -
Activate PRC(PRC1).
The activation time depends on the numberof cells activated.
OMC-R 5 / cell -
Close PRC(PRC1). OMC-R 1 -
Delete PRC(PRC1). OMC-R 2 -
Ask the MSC personnel to update theparameters in the MSC DB.
MSC 3 -
2.4.5 Delete BTS
Note Task Description Site To Do Outage
Delete BTS(s) from OMC-R . Wait for thetransmission programming flag to changefrom Abis to idle.
OMC-R 6/ BTS -
2.4.6 Delete Abis (Case 1)
Note Task Description Site To Do Outage
C1 Delete Abis Chain / Ringyou created. Waitfor the transmission programming flag tochange from Abis to idle.
OMC-R 6 -
3BK 17416 0841 RJZZA Ed.03 29 / 30
-
7/28/2019 Add BTSs- New Cells
30/30
2 Scenario
2.4.7 Final Checks
Note Task Description Site To Do Outage
Display USD detailed Cell Information .
Check that the downstream BTSs are intraffic.
BTS 5 -
Perform an Audit Alarm State on BSS. OMC-R 10 -
View Status of Managed Objects and Alarmson all the BTSs of the TSU. Compare thischeck to the initial check.
OMC-R 5 -