Blackdog Progress Report - July Page 1 of 5
Aberdeen Offshore Wind Farm
Construction Progress Report-July 17
14/07/17
Prepared by: Allan Macdonald Site Manager 14/07/17
NAME ROLE DATE
Prepared by: Tom Ivey Construction Engineer 14/07/17
NAME ROLE DATE
Blackdog Progress Report - July Page 2 of 5
1.0 ONSHORE ACTIVITIES
The main activities on site this month were completing 132kv Building cladding, completing all
internal blockwork and preparation of rooms for installation of Mechanical and Electrical
equipment to commence in August.
All concrete foundation works were completed in the 66kv building. The surrounds of the structure
was backfilled in preperation for Structural Steel erection commencing later this month.
The design for the Filter Compound is nearing completion with construction to follow.
Safety checks on cladding specification undertaken.
Figure 1.1 –132kV Substation Cladding Figure 1.2 - 132kv Substation East Elevation
Figure 1.3 - 66kV Substation reinforcement fixing Figure 1.4 –132kV Substation internal Blockwork
Blackdog Progress Report - July Page 3 of 5
Figure 1.5 –66kV Substation Concrete Finishing Figure 1.6 –132kV Substation Internal Blockwork ongoing
Figure 1.7 –66kV Concrete foundations complete Figure 1.8 –132kV Substation Blockwork
Figure 1.9 –132kV Substation South Elevation Figure 1.10 –66kv Substation ready for Structural Steel
Blackdog Progress Report - July Page 4 of 5
2.0 OFFSHORE ACTIVITIES
The main activities this month are fabrication of foundations, manufacturing of cables and
planning works for foundation installation, cable installation, scour protection installation and
seabed inspection and clearance.
2.1 Seabed Inspection and Clearance
Figure 2.22 Inspection ROV
This work aims to start in August and finish around October.
2.2 Scour Protection
Figure 2.23 Fall pipe type of vessel (not AOWF)
Installation is expected to start in October.
Figure 2.24 The jacket foundation can be seen in yel-
low, the brown is the area where rocks will be placed
around the base of the foundation.
Blackdog Progress Report - July Page 5 of 5
2.3 Foundation Fabrication and Installation
Fabrication of the foundation jackets and suction buckets is progressing in various fabrica tions
yards across Europe.
Figure 2.31 Jacket top section being Figure 2.32 Jacket sections (before painting)
lifted onto bottom section
Foundation installation is due to start November once seabed preparation and scour protec-
tion has been installed.
2.4 Cable Manufacture
Cable manufacturing is progressing. The different materials are manufactured in several lo-
cations across Europe before being assembled at JDR factory in Hartlepool
Figure 2.41 Test of cable protection system