MLA – August 2017

Bathurst Inlet – August 2017

9 person temporary camp established August 2017

Ice Air Strip on Bathurst Inlet: Early-Mar 2018

100 Air freight flights including Hercules, ATR, 737 & Dash 7 aircraft

28 Hercules Air Transport Flights transporting MLA Camp, Temporary fuel Tanks & Construction Equipment

5000 Foot Air strip on Bathurst Inlet

Establishing a “Toe-hold” at MLA: Mar 2018

Unloading supplies on the ice Personnel Transport to MLA

45-Person CampFit for Purpose Dining Facility

Drill & Blast at the MLA Quarry: Apr 2018

Development Earthworks begin to support exploration and future development activities

6

Quarry

A-N storage road

Camp

Road works

Fuel Storage

Quarry

A-N storage

Quarry & Earthworks Construction at MLA – Apr 18

8

Completed Permanent 45 Person Camp at MLA

Completed Temporary Fuel Storage Depot at MLA

Completed Pad for Permanent Fuel Tanks - MLA

10

MLA June 2018 – Approximately mid-way through construction

11

From “pioneering” to finished works in 5 months

Aug 2018

Aug 2017

Staging / Loading Sealift at Hay River – July 2018

13

Equipment Loading at Hay River July 2018

14

Barges Loading at Hay River – July 2018

15

Barge Loading at Hay River – July 2018

16

Barges Loaded and ready for sealift – July 2018

17

First Barges received and unloaded – August 13 & 14, 2018

18

Barge Unloaded and Equipment Stored at MLA – August 2018

19

Equipment At MLA – August 2018

20

21

Equipment Stored at MLA- August 2018

Completed MLA – August 2018