Route CR-25 ProjectDescription
NEW ALIGNMENT OF CR-25 (MCFARLAND ROAD) FROM CR-28 (OLD PASCAGOULA ROAD) TO CR-358 (THREE NOTCH ROAD)
Type of Work GRADE, DRAIN, BASE AND PAVE
Project Length in Miles 8.000 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100059788 STPMB 4918 (250) PRELIMINARY ENGINEERING
GRADE, DRAIN, BASE AND PAVE
2018 $2,000 $500 $2,500
100059789 STPMB 4918 (250) RIGHT OF WAY
GRADE, DRAIN, BASE AND PAVE
2019 $4,800 $1,200 $6,000
TOTAL COST: $6,800 $1,700 $8,500
Route CR-32 ProjectDescription
THREE NOTCH ROAD (CR-32) ADDITIONAL LANES FROM SCHILLINGER ROAD TO MCDONALD ROAD.
Type of Work ADDITIONAL ROADWAY LANES
Project Length in Miles 2.000 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100052461 STPMB 7502 () PRELIMINARY ENGINEERING
ADDITIONAL ROADWAY LANES
2019 $224 $56 $280
100052462 STPMB 7502 () RIGHT OF WAY
ADDITIONAL ROADWAY LANES
2019 $732 $183 $915
TOTAL COST: $956 $239 $1,195
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
1 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route CR-372 ProjectDescription
CR-372 (SCHILLINGER RD) ADD LANES FROM SR-42 (US-98) TO SR-217 (LOTT RD)
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 3.322 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100046890 STPMBF-STPAAF 7503 (601)
UTILITIES
GRADE, DRAIN, BASE, PAVE AND BRG
2016 $244 $61 $305
100046891 STPMBF-STPAAF 7503 (601)
CONSTRUCTION
GRADE, DRAIN, BASE, PAVE AND BRG
2016 $10,036 $2,509 $12,546
TOTAL COST: $10,280 $2,570 $12,851
Route CR-39 ProjectDescription
MCDONALD ROAD (CR-39) ADDITIONAL LANES FROM NORTH OF I-10 TO OLD PASCAGOULA ROAD.
Type of Work GRADE, DRAIN, BASE AND PAVE
Project Length in Miles 1.500 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100052448 STPMB 7612 (600) RIGHT OF WAY
GRADE, DRAIN, BASE AND PAVE
2018 $936 $234 $1,170
100052449 STPMB 7612 (600) UTILITIES
GRADE, DRAIN, BASE AND PAVE
2019 $560 $140 $700
100052450 STPMB 7612 (600) CONSTRUCTION
GRADE, DRAIN, BASE AND PAVE
2019 $3,840 $960 $4,800
TOTAL COST: $5,336 $1,334 $6,670
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
2 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route CR-63 ProjectDescription
BRIDGE AND APPROACHES CR-63 (WILMER-GEORGETOWN ROAD) OVER BIG CREEK BIN # 4901
Type of Work BRIDGES AND APPROACHES
Project Length in Miles 0.000 Urban Area COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100061186 ACBRZ61186 ATRP (010)
CONSTRUCTION
BRIDGES AND APPROACHES
2016 $2,831 $713 $3,544
TOTAL COST: $2,831 $713 $3,544
Route CR-656 ProjectDescription
CR-656 (ZEIGLER BLVD) ADD LANES FROM ATHEY RD TO FORREST HILL DRIVE
Type of Work ADDITIONAL ROADWAY LANES
Project Length in Miles 6.820 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100043178 DBMB-STPMB 7550 (600)
UTILITIES
ADDITIONAL ROADWAY LANES
2019 $1,600 $400 $2,000
100037215 DBMB-STPMB 7550 (600)
CONSTRUCTION
ADDITIONAL ROADWAY LANES
2019 $10,959 $2,740 $13,698
TOTAL COST: $12,559 $3,140 $15,698
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
3 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route CR-656 ProjectDescription
CR-656 (ZEIGLER BLVD) ADD LANES FROM CR-372 (SCHILLINGER RD) TO CR-429 (CODY RD)
Type of Work GRADE, DRAIN, BASE AND PAVE
Project Length in Miles 3.600 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100046893 STPMB 7550 (601) RIGHT OF WAY
GRADE, DRAIN, BASE AND PAVE
2016 $668 $167 $835
100046894 STPMB 7550 (601) UTILITIES
GRADE, DRAIN, BASE AND PAVE
2019 $304 $76 $380
100046895 STPMB 7550 (601) CONSTRUCTION
GRADE, DRAIN, BASE AND PAVE
2019 $3,356 $839 $4,195
TOTAL COST: $4,328 $1,082 $5,410
Route CR-656 ProjectDescription
ADDITIONAL LANES ON CR-656 (ZEIGLER BLVD) FROM CR-70 (TANNER WILLIAMS RD) TO CR-31 (SCHILLINGER RD)
Type of Work GRADE, DRAIN, BASE AND PAVE
Project Length in Miles 4.200 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100055881 STPMB 7550 (602) RIGHT OF WAY
GRADE, DRAIN, BASE AND PAVE
2019 $1,504 $376 $1,880
100055882 STPMB 7550 (602) UTILITIES
GRADE, DRAIN, BASE AND PAVE
2019 $896 $224 $1,120
100055883 STPMB 7550 (602) CONSTRUCTION
GRADE, DRAIN, BASE AND PAVE
2019 $4,000 $1,000 $5,000
TOTAL COST: $6,400 $1,600 $8,000
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
4 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route CR-NA ProjectDescription
DAUPHIN STREET ADDITIONAL LANES FROM SAGE AVENUE TO WEST OF I-65 AT SPRINGHILL MEMORIAL HOSPITAL.
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 3.300 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100052458 STPMB 7533 () RIGHT OF WAY
GRADE, DRAIN, BASE, PAVE AND BRG
2019 $216 $54 $270
100052459 STPMB 7533 () UTILITIES
GRADE, DRAIN, BASE, PAVE AND BRG
2021 $225 $56 $281
100052460 STPMB 7533 () CONSTRUCTION
GRADE, DRAIN, BASE, PAVE AND BRG
2021 $2,920 $730 $3,650
TOTAL COST: $3,361 $840 $4,201
Route CR-NA ProjectDescription
MCGREGOR AVENUE WIDENING FROM AIRPORT BOULEVARD TO DAUPHIN STREET AND INSTALLATION OF A ROUNDABOUT AT DAUPHIN STREET
Type of Work GRADE, DRAIN, BASE AND PAVE
Project Length in Miles 1.470 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100052600 STPMBF 7508 (600) RIGHT OF WAY
GRADE, DRAIN, BASE AND PAVE
2018 $2,200 $550 $2,750
100052601 STPMBF 7508 (600) UTILITIES
GRADE, DRAIN, BASE AND PAVE
2019 $1,200 $300 $1,500
100052602 STPMBF 7508 (600) CONSTRUCTION
GRADE, DRAIN, BASE AND PAVE
2019 $2,706 $676 $3,382
TOTAL COST: $6,106 $1,526 $7,632
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
5 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route CR-NA ProjectDescription
GRADE, DRAIN, BASE AND PAVE LOTT ROAD FROM BEVERLY JEFFERIES HWY TO BROWN-BLANKENCHIP ROAD
Type of Work GRADE, DRAIN, BASE AND PAVE
Project Length in Miles 2.250 Urban Area COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100061189 ACNU61189 ATRP (006) CONSTRUCTION
GRADE, DRAIN, BASE AND PAVE
2017 $1,498 $704 $2,202
TOTAL COST: $1,498 $704 $2,202
Route I -10 ProjectDescription
RESURFACE I-10 FROM WEST OF CR-39 (MCDONALD ROAD) TO CR-59 (CAROL PLANTATION ROAD)
Type of Work PAVEMENT MINOR REHABILITATION
Project Length in Miles 8.920 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100057810 IM-HSIP I010 (338) PRELIMINARY ENGINEERING
PAVEMENT MINOR REHABILITATION
2016 $155 $17 $172
100057811 IM-HSIP I010 (338) CONSTRUCTION
PAVEMENT MINOR REHABILITATION
2018 $9,256 $1,028 $10,284
TOTAL COST: $9,411 $1,046 $10,456
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
6 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route I -10 ProjectDescription
I-10 EAST TUNNEL INTERCHANGE BRIDGE BEARING REHABILITATION
Type of Work BRIDGE REHABILITATION
Project Length in Miles 0.828 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100056331 IM I010 () PRELIMINARY ENGINEERING
BRIDGE REHABILITATION
2018 $301 $33 $334
TOTAL COST: $301 $33 $334
Route I -10 ProjectDescription
I-10 MOBILE RIVER BRIDGE AND I-10 BAYWAY WIDENING FROM EXIT 24 (BROAD STREET) TO MOBILE COUNTY LINE
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 13.227 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100062408 ACNH I010 () PRELIMINARY ENGINEERING
GRADE, DRAIN, BASE, PAVE AND BRG
2019 $41,291 $10,323
$51,614
100062410 DPI I010 () RIGHT OF WAY
GRADE, DRAIN, BASE, PAVE AND BRG
2019 $20,332 $5,083 $25,415
100062411 DPI I010 () UTILITIES
GRADE, DRAIN, BASE, PAVE AND BRG
2019 $3,893 $973 $4,867
TOTAL COST: $65,516 $16,379
$81,895
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
7 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route I -165 ProjectDescription
RESURFACING I-165 SERVICE ROADS FROM .04 MILE SOUTH OF BAY BRIDGE ROAD TO .08 MILE NORTH OF WHISTLER STREET
Type of Work PAVEMENT MINOR REHABILITATION
Project Length in Miles 3.400 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100062514 IM I165 (303) PRELIMINARY ENGINEERING
PAVEMENT MINOR REHABILITATION
2017 $516 $57 $573
100058195 IM I165 (303) CONSTRUCTION
PAVEMENT MINOR REHABILITATION
2019 $5,478 $609 $6,086
TOTAL COST: $5,993 $666 $6,659
Route I -65 ProjectDescription
I-65 AT CR-41 (CELESTE RD) INTERCHANGE MODIFICATIONS.
Type of Work INTERCHANGE
Project Length in Miles 0.500 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100039475 ACNH39475F I065 (388) CONSTRUCTION
INTERCHANGE
2016 $5,669 $1,664 $7,333
TOTAL COST: $5,669 $1,664 $7,333
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
8 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route I -65 ProjectDescription
I-65 AT CR-41 (CELESTE RD) INTERCHANGE MODIFICATIONS.
Type of Work INTERCHANGE
Project Length in Miles 0.500 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100039476 ACNH39475F I065 (388) UTILITIES
INTERCHANGE
2016 $207 $52 $259
TOTAL COST: $207 $52 $259
Route I -65 ProjectDescription
RESURFACING I-65 FROM MAIN STREET TO NORTH OF SR-158
Type of Work RESURFACING
Project Length in Miles 9.148 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100062513 IM I065 (466) PRELIMINARY ENGINEERING
RESURFACING
2016 $533 $60 $592
100058747 IM I065 (466) CONSTRUCTION
PAVEMENT MINOR REHABILITATION
2017 $7,520 $836 $8,355
TOTAL COST: $8,052 $895 $8,948
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
9 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route SR-13 ProjectDescription
CULVERT REPLACMENT, BIN 5715, SR-13 (US-43) OVER STEELE CREEK
Type of Work BRIDGE REPLACEMENT
Project Length in Miles 0.010 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100061587 BR 0013 (601) PRELIMINARY ENGINEERING
BRIDGE REPLACEMENT
2016 $303 $76 $379
100061588 BR 0013 (601) CONSTRUCTION
BRIDGE REPLACEMENT
2019 $2,167 $542 $2,709
TOTAL COST: $2,470 $618 $3,088
Route SR-16 ProjectDescription
REPLACE BRIDGE, BIN 008714, SR-16 (US-90) WESTBOUND OVER TENSAW-SPANISH RIVER. (SUFF=49.7, STATUS=SD)
Type of Work BRIDGE REPLACEMENT
Project Length in Miles 1.306 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100056130 BRF 0016 (522) UTILITIES
BRIDGE REPLACEMENT
2019 $451 $113 $564
100049566 BRF 0016 (522) CONSTRUCTION
BRIDGE REPLACEMENT
2019 $19,677 $4,919 $24,596
TOTAL COST: $20,127 $5,032 $25,159
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
10 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route SR-17 ProjectDescription
BRIDGE REPL SR-17(US-45) (STR#17-49-35.7) OVER BENNETTS CK BIN 003218
Type of Work BRIDGE REPLACEMENT
Project Length in Miles 0.020 Urban Area COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100063583 BR 0017 (574) PRELIMINARY ENGINEERING
BRIDGE REPLACEMENT
2018 $62 $15 $77
TOTAL COST: $62 $15 $77
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
11 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Original
Route CR-31 ProjectDescription
ADDITIONAL LANES ON SCHILLINGER ROAD SOUTH (CR-31) FROM THREE NOTCH ROAD (CR-32) TO APPROXIMATELY 0.2 MILES SOUTH OF HALLS MILL CREEK.
Type of Work ADDITIONAL ROADWAY LANES
Project Length in Miles 1.742 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100064999 ST-049-888-013 () CONSTRUCTION
ADDITIONAL ROADWAY LANES
2016 $0 $10,000
$10,000
TOTAL COST: $0 $10,000
$10,000
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
12 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 1
Route I -10 ProjectDescription
I-10 MOBILE RIVER BRIDGE CORRIDOR PRESERVATION
Type of Work BRIDGE
Project Length in Miles 2.460 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100065672 HPPF AL06 (903) RIGHT OF WAY
BRIDGE 2016 $1,538 $385 $1,923
TOTAL COST: $1,538 $385 $1,923
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
13 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 5
Route I -10 ProjectDescription
I-10 EASTBOUND WATER STREET ON-RAMP CLOSURE AND IMPROVEMENTS TO CANAL STREET, CLAIBORNE STREET, AND TEXAS STREET INTERCHANGE
Type of Work INTERCHANGE
Project Length in Miles 1.500 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100064990 HPPF AL06 (902) CONSTRUCTION
INTERCHANGE
2016 $1,326 $336 $1,662
TOTAL COST: $1,326 $336 $1,662
Route I -165 ProjectDescription
INSTALLATION OF PRECAST CONCRETE PAVEMENT SYSTEM ON I-165 SB SERVICE ROAD LEFT TURN LANES JUST WEST OF BAY BRIDGE ROAD SR-16 (US-90)
Type of Work PAVEMENT REHABILITATION
Project Length in Miles 0.121 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100065216 TIDP-IM I165 (302) CONSTRUCTION
PAVEMENT REHABILITATION
2017 $1,152 $95 $1,247
TOTAL COST: $1,152 $95 $1,247
Route I -65 ProjectDescription
I-65 NORTHBOUND/SOUTHBOUND BRIDGES (BIN #13807) OVER COTTAGE HILL ROAD MP 2.496 TO MP 2.728 PARTIAL BRIDGE DECK REPAIR/REPLACEMENT
Type of Work BRIDGE REHABILITATION
Project Length in Miles 0.232 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100065774 IM I065 (470) CONSTRUCTION
BRIDGE REHABILITATION
2016 $3,707 $412 $4,119
TOTAL COST: $3,707 $412 $4,119
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
14 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 8
Route SR-158X ProjectDescription
SR-158 EXTENSION FROM EAST OF LOTT ROAD (SR-217) TO SCHILLINGER ROAD. GRADE, DRAIN, BASE, PAVE, AND BRIDGE (EB SEABURY CREEK, EB ROGERS ROAD, AND SCHILLINGER ROAD INTERSECTION)
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 1.219 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100060152 NHF 0158 (502) CONSTRUCTION
GRADE, DRAIN, BASE, PAVE AND BRG
2018 $17,695 $4,424 $22,119
TOTAL COST: $17,695 $4,424 $22,119
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
15 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 8
Route CR-656 ProjectDescription
CLEARING AND GRUBBING ON CR-656 (ZEIGLER BOULEVARD) FROM ATHEY ROAD TO FORREST HILL DRIVE
Type of Work CLEARING AND GRUBBING
Project Length in Miles 3.410 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100065368 STPMB 7550 (603) CONSTRUCTION
CLEARING AND GRUBBING
2017 $102 $25 $127
TOTAL COST: $102 $25 $127
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
16 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 9
Route I -10 ProjectDescription
DESIGN OF VARIOUS INTELLIGENT TRANSPORTATION SYSTEM DEVICES AND FIBER BACKBONE ALONG I-10, I-65, I-165, SR-16 (US-90), SR-42 (US-98), SR-59 WITHIN THE MOBILE AND BALDWIN URBAN AREA
Type of Work UNCLASSIFIED
Project Length in Miles 0.000 Urban Area COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100057418 IM MR17 (900) PRELIMINARY ENGINEERING
UNCLASSIFIED 2017 $0 $0 $0
100057419 IM MR17 () CONSTRUCTION
UNCLASSIFIED 2019 $8,263 $918 $9,181
TOTAL COST: $8,263 $918 $9,181
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
17 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 13
Route SR-16 ProjectDescription
REPLACE BRIDGE, BIN 008714, SR-16 (US-90) WESTBOUND OVER TENSAW-SPANISH RIVER.
Type of Work BRIDGE REPLACEMENT
Project Length in Miles 0.650 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100064691 BRF 0016 (522) PRELIMINARY ENGINEERING
BRIDGE REPLACEMENT
2017 $566 $141 $707
TOTAL COST: $566 $141 $707
Route SR-42R ProjectDescription
CONSTRUCT BRIDGE ON (CR-63) WILMER-GEORGETOWN ROAD OVER SR-42 (US-98) WITH JUGHANDLE INTERCHANGE ONTO SR-42 (US-98)
Type of Work BRIDGE
Project Length in Miles 0.010 Urban Area COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100060480 NHF 0042 (535) CONSTRUCTION
BRIDGE 2019 $6,910 $1,727 $8,637
TOTAL COST: $6,910 $1,727 $8,637
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
18 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 14
Route NA- ProjectDescription
ONE MOBILE - COMPLETE STREET INITIATIVE TIGER GRANT
Type of Work UNCLASSIFIED
Project Length in Miles 0.000 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100066565 TIGER-FAUP 4917 (250) CONSTRUCTION
UNCLASSIFIED 2018 $5,525 $1,303 $6,828
TOTAL COST: $5,525 $1,303 $6,828
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
19 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 19
Route SR-42R ProjectDescription
CONSTRUCT BRIDGE ON (CR-63) WILMER-GEORGETOWN ROAD OVER SR-42 (US-98) WITH JUGHANDLE INTERCHANGE ONTO SR-42 (US-98)
Type of Work BRIDGE
Project Length in Miles 0.010 Urban Area COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100066917 BP-049-042-015 () RIGHT OF WAY
BRIDGE 2019 $0 $240 $240
TOTAL COST: $0 $240 $240
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
20 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 21
Route SR-42R ProjectDescription
CONSTRUCT BRIDGE ON GLENWOOD ROAD OVER SR-42 (US-98)
Type of Work BRIDGE
Project Length in Miles 0.010 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100066916 BP-NHF 0042 (517) RIGHT OF WAY
BRIDGE 2018 $201 $66 $267
TOTAL COST: $201 $66 $267
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
21 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 22
Route SR-158X ProjectDescription
SR-158 EXTENSION FROM EAST OF LOTT ROAD (SR-217) TO SCHILLINGER ROAD GRADE, DRAIN, BASE, PAVE AND BRIDGE
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 1.220 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100067136 NHF 0158 (502) UTILITIES
GRADE, DRAIN, BASE, PAVE AND BRG
2018 $238 $59 $297
TOTAL COST: $238 $59 $297
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
22 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 26
Route I -10 ProjectDescription
I-10 MOBILE RIVER BRIDGE LOAD TEST PROGRAM
Type of Work UNCLASSIFIED
Project Length in Miles 2.460 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100067528 IM I010 (341) CONSTRUCTION
UNCLASSIFIED 2018 $3,997 $444 $4,441
TOTAL COST: $3,997 $444 $4,441
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
23 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 27
Route SR-158X ProjectDescription
SR-158 EXTENSION FROM 0.5 MILE EAST OF GLENWOOD ROAD TO WEST OF LOTT ROAD (SR-217). GRADE DRAIN, BASE, PAVE, AND BRIDGE (EB COLLINS CREEK, EB MCCRARY ROAD, AND EB COLLINS CREEK TRIBUTARY) (UTILITY WORK)
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 2.709 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100060153 NH 0158 (508) CONSTRUCTION
GRADE, DRAIN, BASE, PAVE AND BRG
2018 $158 $40 $198
TOTAL COST: $158 $40 $198
Route SR-42 ProjectDescription
EXTEND EASTBOUND BRIDGE ON SR-42 (US-98) OVER BIG CREEK EAST 1440'
Type of Work BRIDGE
Project Length in Miles 0.010 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100054972 NHF 0042 (511) CONSTRUCTION
BRIDGE 2019 $8,130 $2,032 $10,162
TOTAL COST: $8,130 $2,032 $10,162
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
24 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 30
Route SR-42R ProjectDescription
CONSTRUCT BRIDGE ON GLENWOOD ROAD OVER SR-42 (US-98)
Type of Work BRIDGE
Project Length in Miles 0.010 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100052812 NHF 0042 (517) CONSTRUCTION
BRIDGE 2019 $4,385 $1,096 $5,481
TOTAL COST: $4,385 $1,096 $5,481
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
25 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 30
Route SR-158X ProjectDescription
SR-158 EXTENSION FROM 0.5 MILE EAST OF GLENWOOD ROAD TO WEST OF LOTT ROAD (SR-217). GRADE DRAIN, BASE, PAVE, AND BRIDGE (EB COLLINS CREEK, EB MCCRARY ROAD, AND EB COLLINS CREEK TRIBUTARY)
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 2.709 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100067717 NH 0158 (508) UTILITIES
GRADE, DRAIN, BASE, PAVE AND BRG
2018 $168 $42 $210
TOTAL COST: $168 $42 $210
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
26 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 31
Route CR-NA ProjectDescription
INTERSECTION IMPROVEMENTS - CONGESTION MANAGEMENT PROCESS - DAUPHIN STREET FROM SAGE AVENUE TO SPRINGHILL HOSPITAL
Type of Work INTERSECTION IMPROVEMENTS
Project Length in Miles 0.000 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100066704 STPMB 4918 () PRELIMINARY ENGINEERING
INTERSECTION IMPROVEMENTS
2018 $50 $13 $63
100066705 STPMB 4918 () CONSTRUCTION
INTERSECTION IMPROVEMENTS
2018 $450 $113 $563
TOTAL COST: $500 $125 $625
Route CR-NA ProjectDescription
INTERSECTION IMPROVEMENTS - CONGESTION MANAGEMENT PROCESS - AIRPORT BLVD FROM UNIVERSITY BLVD TO HILLCREST ROAD
Type of Work INTERSECTION IMPROVEMENTS
Project Length in Miles 0.000 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100066706 STPMB 4918 () PRELIMINARY ENGINEERING
INTERSECTION IMPROVEMENTS
2019 $51 $13 $63
100066707 STPMB 4918 () CONSTRUCTION
INTERSECTION IMPROVEMENTS
2019 $455 $114 $568
TOTAL COST: $505 $126 $631
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
27 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 36
Route SR-158X ProjectDescription
SR-158 EXTENSION LOTT ROAD OVERPASS AND JUG HANDLE. GRADE, DRAIN, BASE, PAVE AND BRIDGE (EB SEABURY CREEK TRIBUTARY AND PARTIAL LOTT ROAD)
Type of Work GRADE, DRAIN, BASE, PAVE AND BRG
Project Length in Miles 5.540 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100068084 NHF 0158 (505) UTILITIES
GRADE, DRAIN, BASE, PAVE AND BRG
2019 $291 $73 $364
100060154 NHF 0158 (505) CONSTRUCTION
GRADE, DRAIN, BASE, PAVE AND BRG
2019 $25,920 $6,480 $32,400
TOTAL COST: $26,211 $6,553 $32,764
Route SR-16 ProjectDescription
INTERSECTION IMPROVEMENTS - CONGESTION MANAGEMENT PROCESS - SR-16 (US-90) FROM BROAD STREET TO BANKHEAD TUNNEL
Type of Work INTERSECTION IMPROVEMENTS
Project Length in Miles 2.920 Urban Area MOBILE COST IN THOUSANDS
Project Reference Nbr
FA Number Scope of Work Type of Work Fiscal Year Federal
State-Other TOTAL
100066702 STPMB 0016 () PRELIMINARY ENGINEERING
INTERSECTION IMPROVEMENTS
2018 $119 $119 $238
100066703 STPMB 0016 () CONSTRUCTION
INTERSECTION IMPROVEMENTS
2018 $381 $509 $891
TOTAL COST: $500 $628 $1,128
9/5/2018 ALABAMA DEPARTMENT OF TRANSPORTATION STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
STIP YEARS from 10/1/2014-9/30/2019
28 of 28
COUNTY HIGHWAY PROJECTS - MOBILE
STIP PLAN: 2016 - Amendment # 36
top related