20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
Steel pile day 20.05.2010
RD-PILE WALL – NEW WAY TO BUILD
Lars JohanssonRamboll Sverige ABin co-operation withJuha ForsmanRamboll Finland Ay
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
AMC – Analysis Modelling Calculation Group
Grundvatten-Ytvatten-
Dagvatten-Spill
Bygg-konstruktionGeokonstruktion
Trafik
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
AMC – Analysis Modelling Calculation Group
•Samverkansanalyser – samverkan mellan jord och konstruktioner.
•Nära samarbete mellan geotekniker och konstruktörer
•Eurokoder (EC7)
• Funktionsdesign mer än brottdesign
• Krav på mer avancerade analyser (finita element analyser)
•Särskild satsning med bas i Malmö
•Spänner över Norden, Baltikum och UK
•Samarbete (andra aktörer på marknaden, Högskolor/Universitet/ Forskningsinstitut)
•Bättre kvalitet
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
EXAMPLES OF ”TRADITIONAL” SHEET PILE WALL
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
TRADITIONAL BUILDING PIT SUPPORTED BY SHEET PILE WALL
•Insecure method to penetrate through rocky boulderly soil layers = contact to bedrock through moraine
is often hard to achieve
•Outer walls of building must have their own foundations
•Basement walls cannot extend to the boundary of the excavation pit (sheet pile wall requires space)
•Many support levels (struts). Steel bars/dowels are needed for anchoring of the lower end into bedrock
•Problems to control ground water
fill
clay
moraine
rock anchors sheet pile wall
pit
boundary
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
NEW, ALTERNATIVE SOLUTION
TRADITIONAL SOLUTION
fill
clay
moraine
rock anchors
plo
t boundary
bedrock
RD-pile wall
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
ACHIEVED BENEFITS • RD-pile wall can be
installed near the excavation boundary and ”in open space” in plot boundary
• Distance of ground water flow increases => amount of water decreases. Water-tight structure as a whole.
• Act as bearing structure (foundations, basement wall, good stiffness)
• External anchoring is not allways needed (for instance upper deck acts as inside strut)
• Penetration of all soil layers
• Contact to bedrock is secured
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
example 2: BUILDING SITE AND DESIGNED UNDERGROUND SPACE
GW
Sa
Mr
Tä
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
1. INSTALLATION OF RD-PILE WALL
GW
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
2. INSTALLATION OF REST OF THE DRILLED PILES AND CONSTRUCTION OF FIRST LEVEL FLOOR
GW
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
3. EXCAVATION OF FIRST BASEMENT LEVEL AND CONSTRUCTION OF FLOOR DECK
GW
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
4. EXCAVATION AND BLAST BREAKING OF SECOND BASEMENT LEVEL AND CONSTRUCTION OF FLOOR DECK
GW
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
5. AT A SAME TIME CONSTUCTION UPWARDS IS POSSIBLE
GW
20th MAY 2010
RUUKKI STEEL PILE DAY STOCKHOLM
THANK YOU