Sunshine Canyon Landfill 2020 LEA Board Meeting

June 25, 2020

Chris Coyle

General Manager

2

3

Enhanced Odor Controls

• 7 new Dust Cannons & additional odor neutralizing misting line

• Installing water & electric utilities for first 3 dust cannons

• Startup of first 3 cannons Anticipated by end of June

• Mobile Units to relocate based on active area and wind direction

4

New Landfill Gas Wells

• Installing 34 new vertical wells along the perimeter of the recent fill area & a larger header to provide add’l vacuum

• 16 wells have been installed so far

• Anticipate to complete well schedule Phase II by mid July while winds are favorable

5

6

2020 Projects• Scale Relocation (completed) & Administration and Employee Locker Room Relocation

(in progress)

• Cell CC4P4A (in progress)

• Odor Abatement Improvements (in progress)

• GCCS Improvements (completed 28 Wells and 16 in progress). Anticipate an add’l 20 more new collectors this year.

7

Cell Construction – CC4 Part 4a

Thank You