1Franklin Road ImprovementsCommunity Liaison Group meeting5 July 2016
Update from Watercare
Franklin Road Upgrades
Water Main Renewals and Wastewater Separation Works
July 2016
What do we have planned for July 2016?• Discuss with Auckland Council a method to streamline the building consent processing required for private drainage works.
• Start to meet with the residents to obtain sign-off for the individual building consents for each property.
• Contractor will finalise all the requirements of the Resource Consent prior to mobilising on site – for example completion of construction management plans
• Identify and mark out of existing services in Franklin Road starting from the lower end
• Site establishment by the contractor in preparation for start of works.
AT Works Progress Update
6
• Cycleway design further developed at upper and lower Franklin Rd
• Internal AT technical inputs included• Scheme road safety audit - initial feedback included
• Bus stop relocation anticipated for mid 2017• Wellington Street roundabout modified • Additional parking spaces identified• New World entrance discussions commenced
Design Progress
7
Franklin Road Improvements
8
Upper Franklin Scheme Design
9
Upper Franklin Scheme Design• Added a central lead in lane for confident cyclists
• Added a facility to provide less confident cyclists with the opportunity to move off the road and onto the footpath
• Bus stops outside nos. 2 and 11 removed due to changes in bus routes expected in mid-2017
• Added one parking space near intersection on north side
10
Wellington St Roundabout
11
• Added facilities for confident and non- confident to move through the roundabout
• Kerb lines modified to accommodate bus tracking • Heavy vehicles can now track over the roundabout
Wellington St Roundabout
12
Lower Franklin Scheme Design
13
• Removed separator islands near Victoria Street West intersection
• Added eastbound central lead in lane for confident cyclists• Added a facility to provide less confident cyclists with the opportunity to move off the road and onto the footpath
• Westbound cycleway starts on concrete on berm area by Birdcage
• Gateway treatment inserted to restrict excessive 2 lane stacking
• New bus stop located at No.97 (subject approval from AT’s public transport staff)
• New World entrance discussions progressing
Lower Franklin Scheme Design
14
• Finalise New World discussions • Progress landscape design• Consider road safety audit feed back • Further discussions with AT’s Public Transport team on bus stop relocation
• Final agreement on the scheme design• Commence detailed design
Next Steps
15
Scheduled Communications
16
• Next couple of weeks - windscreen flyers letting people who park on Franklin Road know that construction will be commencing soon
• Community BBQ – agree a date so we can organiseand invite residents
• Pre-construction newsletter from AT• Pre-construction letter from Watercare
Pre-construction communications
Thank you.