MEETING NOTES
PROJECT : Bungasari Flour Mills Indonesia
Meeting
Date
:
:
Main Works Meeting No.006
Thursday, 10th January 2013
Attendees: Company:
Time : 11.00am Finished Rod Buchanan PT. Meinhardt Indonesia (MI)
Location : Bungasari Head Office Mugi Akbar Diaseano PT. Meinhardt Indonesia (MI)
Tony Ellie PT. Meinhardt Indonesia (MI)
Indra Gunawan PT. Bungasari Flour Mills (BS)Setia Budi S PT. MK Develindo (MKD)
Frans PT. MK Develindo (MKD)
Safirda Yasmih PT Bita Enarcon (BITA)
Denny Aes PT Bita Enarcon (BITA)
Eko Wicaksono PT Bita Enarcon (BITA)
NO. MINUTESACTION
WHO WHEN
1.0 Site Organizational Chart and Chain of Command.
a. MKD to submit organization chart by Wednesday 5th December 2012complete with curriculum vitaes. For vacant positions MKD to advise
on expected date to be filled.MKD yet to complete organization chart as MI notesome positionsare still un-filled. Urgent positions for structuralengineer and RC schedulers needed to be filledimmediately as MKD must start toproduce shop drawings prior to commencing the per-manent works.Note: MI instructs MKD that all site personnelmust be present on site and responsible forduties. MKD confirms that organization chart90% completed.
MKD 15/01/2013
b. MI highlighted on urgent position for scheduler mustbe filled assoon as possible. MKD confirms that still on process tofill up thisposition. One person base on MKD main office withMKD projectdirector will responsible for this duty until positionfilled.Note: Done. MKD confirms this position already filled.
MKD
2.0 Method of Statement.
/var/www/apps/conversion/tmp/scratch_5/131731023.doc
-
7/29/2019 130110 - MWM 006
2/4
PT. Meinhardt Indonesia Meeting Notes Page 2
NO. MINUTESACTION
WHO WHEN
a. MKD to submit method statement for : Breaking piles/Excavation/List of proposed main
structure
by 7th
December 2012.Note: Done.Site settlement/ Formworks/Concreteworks/Surveying by12th December 2012.Note: Done, review by MI. MKD to providelist of method statement with date ofsubmitted and approved. All submissionmust be submitted to MI head office.
MKD 15/01/2013
3.0 Program.
a. Overall program will be submitted on 12th December 2012. For Branpollard warehouse MI instruct MKD to spilt schedule between4000m2 and the rest of warehouse building.
Note: Done, MKD submitted main program andflour mills building program base on meetingwhich held on Friday, 4th January 2013 with BS.MI requested for special meeting to discussabout this program as MI has comment on theprogram, Wednesday 16th January 2013.
MKD 15/01/2013
b. MKD to start producing S Curve and construction progress togetherwith weekly report.
MKD 15/01/2013
c. Related to steel frame work for bran pollard (refer to coordination
meeting Blue Scope/Gerbang/MKD/PBS/MI on 18
th
Dec 2012):1. 4000 m2 (Gl. A I) :- Breaking pile should be finished 2nd Jan 2013(Done).- Pile cap and tie beam should be finished 16th Jan
2013(Still on progress).2. 8000 m2 (Gl. J W) :
- Breaking pile should be finished 9 th Jan 2013 (Still onprogress).
- Pile cap and tie beam should be finished 6th Feb 2013(Stillon progress).
MKD
d. Urgent matter :1. Related to temporary drainage sloping pavement by river
stone west side should be finished 31 Dec 2012 (Done).2. Mock up for permanent fence should be finished on 31 Dec2012 (Done).
3. Site Office should be finished on 13rd January 2013(Still onprogress).Delayed to 19th January
4. Hold area may continue using embankment system and reducenumber of motorcycle parking lot.Not confirm with finaldrawing form MI
5. MKD to continue with fence construction. MKD informs thatLion mesh production will be delay for 1 month. Scheduledabout 30% of material can delivered by 21st this month
6. BS confirms sliding gate will be use for both, front and backentrance.
7. BS confirms traffic study given by BITA.
MKD
e. MKD to submit weekly works planning completed with percentagecompleted for each items.
MKD 15/01/2013
/var/www/apps/conversion/tmp/scratch_5/131731023.doc
-
7/29/2019 130110 - MWM 006
3/4
PT. Meinhardt Indonesia Meeting Notes Page 3
NO. MINUTESACTION
WHO WHEN
4.0 Material Approvals.
a. Schedule of material approvals to be submitted partially by next week.Note: Outstanding from MOM 005.
MKD 15/01/2013
5.0 Shop Drawings.
a. List of shop drawings to be provided highlighting when this will besubmitted in line with construction program.Note: Done for submission until 6th Jan 2013, MKD to be submit
progressively for the other.
MKD 15/01/2013
b. MKD to submit set up site grids and transferinformation on to sitedimension.Note: Done for Bran Pollard Warehouse andFlour Mill Building, on progress for others.
MKD
6.0 Equipment/Machinery/Batching Plant.a. Batching plant on site will start commencing by second
week ofJanuary (tentative date). MKD informs that they willuse batchingplant from Siam Cement Group (SCG). MKD need toclarifyresources for raw material with SCG in order to supportbatchingplant and meet MI standard quality. Meeting to be heldwith SCG
tomorrow, MKD to advise all on outcome.Note: SGC started on 8th January 2013 andshould be finished by 28th January 2013 still on
progress
MKD 28/01/2013
b. MI reminds MKD a full technical submission will berequired fortower crane.Note: MKD has already issued tower crane designcalculation, MI has reviewed and comment. MKD tofollow up and update.Still on progress ordered material piles
MKD / MI 15/01/2013
8.0 Manpower.a. MKD to submit list of worker and sub-contractors that involved with
site activity. Separate meeting will be held to discuss about Man pow-er on Friday, 7th December 2012 at MI office.Note: MKD confirms to submit by 5th January 2013. Outstandingfrom MOM 005.
MKD 15/01/2013
9.0 Health, Safety and Environmental
a. MKD to ensure construction activity comply withhealth, safety andenvironmental regulation.Note: MKD reminds to be strict on safety issue
as MI notes thatbreaking down pile didnt comply with safetyregulation.
/var/www/apps/conversion/tmp/scratch_5/131731023.doc
-
7/29/2019 130110 - MWM 006
4/4
PT. Meinhardt Indonesia Meeting Notes Page 4
NO. MINUTESACTION
WHO WHEN
10.0 A.O.B
a. MKD to submit short term (i.e. day to day) programuntil the end of
January 2013. MI reminds MKD the aim of this is tokeep your teamfocused and in order to get the correctprocedure/method ofworks/documentation to facilitate permit to work to beissuedsuccessfully by the MI CM team.Note: Outstanding from MOM 005.
MKD 15/01/2013
b. MKD to review and respond minutes of meeting(MOM)latest 24hours before next meeting.
MKD
c. MKD to conduct daily meeting and day to daycoordination/priorityissues with MI CM. Minutes of daily coordination meet-ing need to issue as reference.
MKD/MI
These minutes were prepared by James Holloway/Mugi Akbar of PT Meinhardt Indonesia. These notes reflectthe writer understanding of discussions at the meeting. In case any of those present have different recollections,
please advise the writer within 5 days.