LS1 DAY
F. Duval / EN-EL on behalf of EN/EL group
Activités EN-EL
1 12/06/2012
Summary
Network infrastructure consolidation & upgrade 66 kV et 18 kV UPS SILCON replacement project Projects and maintenance work on substation 400 kV & 66 kV Maintenance works on 18 kV, 3.3 kV and LV networks Yearly tests Other EN/EL consolidation & upgrade projects Projects for other groups R2E Cables & fibres projects Schedule Workloads Increase of manpower
EN/EL activities during LS1
2 12/06/2012LS1 Day - François Duval EN-EL
3 LS1 Day - François Duval EN-EL
66 et 18 kV Networks Consolidation & Upgrade
power cables replacement18 kV SPS New substation BE91in Prévessin (Safe feeding of CCC safety network
for SPS) Repowering CCC 66 kV Protection system consolidation (Prévessin and LHC 1-2-4-6-8) Extension of the 66 kV substation Prevessin New 66 kV feeder on Meyrin site + upgrade of the18 kV substation in
the west area ME59 New power link18 kV ME9 –ME59 in Meyrin and Autotransfert
modification accordingly Upgrade main18 kV substation in Prévessin du BE Consolidation of fire protection systems for power transformers and
for the 400 kV substation Consolidation of the18 kV substations BA4 et BA5
requirements depending mainly on the injector schedule (2013 !) Total budget = 20 MCHF
12 Juin 2012
4 LS1 Day - François Duval EN-EL
66 et 18 kV Networks Consolidation & Upgrade
12 Juin 2012
2013Upgrade sous
station BE
2012-2013Réseau secours Prevessin et SPS
2012-2013 Sous station BE91
2012-2013SPS consolidation
2012-2013Rénovation protection
66 kV
2012-2013Nouvelles lignes 66 kV et
18 kV vers Meyrin
5 LS1 Day - François Duval EN-EL
66 et 18 kV Networks Consolidation & Upgrade
12 Juin 2012
2012-2013Nouvelles lignes 66 kV
et18 kV vers Prevessin
2012-2013Nouvelle sous station
66 kV MEH59
2013-2014Nouvelles liaison 18 KV
entre ME9 –ME59
2012-2014Upgrade sous station
ME59
6 LS1 Day - François Duval EN-EL 12 Juin 2012
LS1 EN-EL activities Power distribution and Operation
7 LS1 Day - François Duval EN-EL
Replacement of SILCON UPSs
All cryo and machine : 82 UPS
Any new UPS connections Requests must be done before end of June 2012
12 Juin 2012
UPS machine : 2 UPS in RE (x16)2 UPS in UA (x8)2 UPS each LHC point (US, UW ou UJ) (x8)
UPS cryo :2 UPS on LHC even points (US, UW) (x4)2 UPS on surface even points (SA, SH) (x4)2 UPS in PM18
8 LS1 Day - François Duval EN-EL
Replacement of SILCON UPSs
Impact on other activities: 6 weeks per area (for 2 UPS)
Distribution downstream off during works
Possible refeeding from diesel network (subject to request justified by safety)
Transport and handling: ~ 660 kg for an UPS and 2000 kg for battery sets (removal of old ones as well ) Lifts on Points 3, 5 et 7 too small for UPS : Width > 800 mm
Alcoves RE : A safety issue has to be considered: Charging batteries may lead to hydrogen production. Ventilation must be dimensioned so that the risk of explosion is eliminated (EN/EL, GS/ASE, HSE)
12 Juin 2012
9 LS1 Day - François Duval EN-EL
66 & 400 kV Substations Maintenance & Projects
Maintenance 400 kV & 66kV substations Tests of the protection and signals on the RTE interfaces On-site maintenance of two 400 kV circuit breakers Factory maintenance of three 400 kV circuit breakers Maintenance of the 400 kV & 66kV transformers
Projects Consolidation of the66 kV protection (BE & LHC 1-2-4-6-8) Extension of the 66 kV substation Consolidation of the fire detection of the 400 kV substation & its transformers
Schedule contraints
12 Juin 2012
RTE (400 kV) Disconnected during 3-4 weeks
ALPIQ (SIG) 60 MVA max during 8 weeks after the LHC warm-up
Réseau de transport 66 kV Off during 8 weeks
AUTOTRANSFERT Inoperable during 8 weeks
Tests AUG LHC Cannot be done during this time
10 07/06/2012
66 & 400 kV Substations Maintenance & Projects
11 LS1 Day - François Duval EN-EL
18 kV, 3.3 kV & LV Networks Maintenance
1/3 of the equipment 18 kV et 3.3kV : 400 cubicles LHC General Services LV switchgears LHC Safety Network LV switchgears Replacement of all breakers dedicated to the LHC safety network
switching LHC Diesel PLC consolidation LHC 18 kV & 400 V switchgears in the alcoves
Planning - requirements Slots of 5 to 6 days for each LHC points (including the AUG tests on the
last day) No underground access for 2 to 3 days (safety network not available) No handling operations for 5 days (distribution off cranes off) No 18 KV maintenance during 400/66 kV maintenance operations No safety network maintenance while AUTOTRANSFERT is off Necessary coordination with CRG & CV
12 Juin 2012
12 LS1 Day - François Duval EN-EL
Yearly Test Campaigns
Diesel and safety network AUTOTRANSFERT AUG
Schedule - requirements PS / SPS magnet tests and run CTF3 until december 2012 Warm-up LHC Cryo To be scheduled:
end 2012 or early 2013 end 2013 or early 2014 end 2014 ? No AUG tests during maintenance on 400 kV
12 Juin 2012
13 LS1 Day - François Duval EN-EL
Other EL Consolidation Projects
12 Juin 2012
Description Confirmed ?
Technically defined?
Consolidation following task force «48V LHC2» (LHC)
yes yes (2012)
obsolete LV switchgears (ME23, ME24) yes yes
Replacement of obsolete switchgears (LHC, MEY)
yes yes
Replacement of LHC safety network PLC & Circuit breakers
yes yes
Consolidation of LHC Diesel PLC no no (LS2)
Increase reliability of AUG in LHC yes yes
Consolidation of EL SCADA system yes yes
14 LS1 Day - François Duval EN-EL
Projects for other groups EN/CV
12 Juin 2012
EL & CV meeting on 04/05/2012 New meeting to be scheduled asap
Description Confirmed ? Technically defined for EL?
Upgrade pumping station PM32 yes yes
SU2 & SU8 TRANE motors replacement yes yes
New cooling tower SHM LHC4 yes no (on its way)
New cooling tower LHC6 & LHC8 yes no (on its way)
New chiller SPS-BA3 no no
Closing collimators area LHC7 no no (Major issue)
Upgrade ventilation PS : Design and supply the new power supply for the ventilation units.
yes no
Safety measures for LHC: deltap tunnel UX85: New power line
yes no
New chillers SU2 for Alice no no (on its way)
15 LS1 Day - François Duval EN-EL
Projects for other groups TE/EPC
12 Juin 2012
Description Confirmed ? Technically defined for EL?
LHC filters protections from FIR to TENCH (new sepams ?)
yes yes
Converters replacement FMCM SR1 et SR5 no no
Control cabling for transformers SMB ? yes no
BEQ2 et BEQ3 protections from baycontroler to PLC
yes no
SVC : 18 kV cables LHC2 replacement yes yes
New feeder18 kV SMB for SPS 3 yes no
SPS Mains Converters: Consolidation : Supply and installation of Earthing Switches and 18kV cables
yes no
EPC High Voltage Power Converter Test Bench: Construction in building 377
yes yes
EPC Medium Power Converter Test Bench: Construction in building 287
yes no
Last meeting 7th of June 2012: Most of the requests clarified and will be defined soon.
Most of the requests scheduled on 1st semester 2014
16 LS1 Day - François Duval EN-EL
Projects for other groups various
12 Juin 2012
Description Confirmed ?
Technically defined for EL?
513 Upgrade automatic Normal / Secours yes yes
HIE ISOLDE yes yes
LV infrastructures for bungalows SMACC yes No, but on its
way(2012)
LINAC 4 yes yes
Moving transformer Civil Engineering on the Route Goward over the PS
no no
Electrical power supplies to new cranes. HE consolidation yes no
ELENA Extra Low Energy Antiproton (hall 193) no no
COMPASS no no
17 LS1 Day - François Duval EN-EL
R2E Relocation of equipment
Locations UJ14, 16, US15, UJ56, USC55, UL55, UL557, UJ76, TZ76, PM76, US85, UL84.
Work scheduled during all LS1. Contractors EMTE (Points 1, 7, 8) & SPIE (Point 5).
Impact on other activities: Difficult access to the work zone, transport not easy, limited co-activity (pts 5
(UP, UL) & 7 (TZ))
Coordination: Works done with MEF, MTE, EPC, CV, HE, EN-EL (consignation/déconsignation)
12 Juin 2012
18 LS1 Day - François Duval EN-EL
R2E Interruption of Service
Locations UJ14, 16 – UJ56 (+ adjacent tunnel area) – UJ76 (+ adjacent tunnel area) –
US85 (+ adjacent tunnel area)
Impact on networks and personnel safety: UPS network (EOD) : consignation schedule compatible with WARM-UP
cryo & other works? Converter network (ERD) en UJ14-15, UJ56, UJ76 Réseaux canalis racks – consignation schedule compatible with WARM-UP
cryo & other works?
The safety network (ESD) & general services networks (EBD – plugs & Lighting) will be operational during works but during 2 weeks, including one week without any EL safety systems: 48 VDC, AUG and safety lighting .
Presently scheduled : October / November 2013
12 Juin 2012
Replacement of water cooled cable hoses:
19 07/06/2012
Locations: UA/RA47, 63, 67, 83 et 87 12.5 months. Contractor: FLOHE, Supply: FLOHE & Contitech -
3200m. Impact on other activities:
Access to UAs & RAs, scaffolding around converters, access to RA tunnel close to DFBs
Coordination: Works done with CV, EPC, MEF, HE, MTE & EN-EL (consignation/décons.)
Schedule
2 shifts will not be possible (limited FLOHE manpower)
LS1 Day - François Duval EN-EL
basket 1, 2
Cable tray
New cable baskets LHC 1, 3 et 5
20 07/06/2012
following ALARA 01/2012 Locations: R34, R36, R37 – 2 cable baskets on 550m. 3 full months . Contractor C209, supply C209. Other areas: RB14, 16, R542, 561: câblofil/télex installation on the
ground. Impact on other activities:
Access to the tunnel pt 3, difficult transport activities.
Coordination: Works done with MEF et EN-HE et EN-EL (Integration)
Schedule:Lead by RP. New cables to be installed in point 3 (TE-VSC)
LS1 Day - François Duval EN-EL
12 Flexwell cables replacement PM45
21 07/06/2012
Locations: SR4, SL42, SD4, PM45, UJ44, UJ46, RA43, RA47 4 full weeks. Contractor: EMTE, supply: CERN.
Impact on other activities: Access to PM45, RA up to 12 cell including areas behind DFBs.
Coordination: Works to be done with BE-RF, MEF, MTE, EPC (consignation/décons.)
Schedule: to be defined with MEF et BE-RF (tests and connectors mounting).
Removal of 10km and installation of 7.4 km of Flexwell cable 7/8.
LS1 Day - François Duval EN-EL
TOTEM: modification of WCC circuits
22 07/06/2012
circuits RQ 4, 5, 6, 7, 8, 9, 10 Locations: RR53 & 57 5 full months on both sides Contractor FLOHE, supply: Technical Specification to be written.
Impact on other activities: Access to RR53 et 57, transport. Works above converters.
Coordination: Work to be done with MEF, HE, CV, TE-EPC, TE-MPE & EN-EL (Integration,
consignation/décons.)
Schedule: to be defined with MEF.
RR53
DFB+
-
+-
DFB
+-
DFB
+-
+
LS1 Day - François Duval EN-EL
Many requests from other groups and from the experiments to be finalised (CRG, ASE, etc.)
Experiments requests were not included in PLAN@CERN
LS1 EN-EL activities
23 07/06/2012LS1 Day - François Duval EN-EL
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8
Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.
Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.
20
13
20
14
EN
K. Foraz - LHC Performance Workshop 2012
24Feb. 8th 2012
PT PTPT PT
PT PTPT PT
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
-> 10K
CSCM
CSCM preparation
Warm-upWarm-up Warm-upWarm-up
Warm-up Warm-up Warm-up
Warm-up
Powering Tests Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-down Cool-
down Cool-down Cool-
down
Cool-down
Cool-down
Cool-down Cool-
down
Travaux 400 kV et 66 kV – Pas d’autotransfert – S CERN <60MVA
Consignations pour R2E ?
25 LS1 Day - François Duval EN-EL
Summary of HV, LV & Controls during LS1
12 Juin 2012
Pro
ject
s +
Main
ten
ance
+ T
est
sEL
& o
ther
gro
up
s
Work
load f
or
Hig
h
Volt
age,
Low
Volt
age &
C
ontr
ols
Sect
ions
Requirements / Resources > 1,2 In particular during 2nd semester 2013)
More resourcesMore requests are not affordable
26 LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from BE
12 Juin 2012
27 LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from TE
12 Juin 2012
VSC requests were not fully considered yet
28 LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from PH
12 Juin 2012
29 LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from IT
12 Juin 2012
30 LS1 Day - François Duval EN-EL
Cables & Fibres
The preparation work behind the cabling workload estimate
12 Juin 2012
31 LS1 Day - François Duval EN-EL
Cables & Fibres
12 Juin 2012
requirements/resources
The LS1 Project Leader decided
32 LS1 Day - François Duval EN-EL
Cables & Fibres
Additional resources AGH (12 project associates from Krakow) Fellows & associates (+10 in 2011/2012) 2 installation contracts (doubled manpower) FSU being prepared Specialists + project managers required (skilled
and experienced people)
12 Juin 2012
33 LS1 Day - François Duval EN-EL
Cables & Fibres
Help from other departments & experiments
We still want new people working with EL team in order to have coherent works done
Work supervisors Knowledge and experience of cable laying or fibre blowing technologies Experience in work site supervision Knowledge of site works
Project managers Project management People management Schedule & Budget management Knowledge of dedicated softwares(GESMAR, Câblothèque)
12 Juin 2012
34 LS1 Day - François Duval EN-EL
Cables & Fibres
But there are limits to the increase of manpower:
Lack of experience Increase of manpower of contractors CERN access, hotels, logistics bottle neck, Base vie? Schedule/coactivity
12 Juin 2012
35 LS1 Day - François Duval EN-EL
LS1 will be a very huge shutdown also for EN/EL
On the HV & LV infrastructure side, The program will be done with some additional resources
On the cables & fibres side, the situation is critical: prioritization is done but the effort is huge for the section in charge. Additional resources have been deployed from other departments: more are needed.
We are worried about the flow of requests which are still popping up in PLAN@CERN or elsewhere
12 Juin 2012
EN/EL activities during LS1: Conclusion