EPC Contracts
Tim Steadman
Contract Management in
International Construction
Beijing, April 28, 2009
-
8/10/2019 03 Epc Contract Management
2/37
EPC Contracts - 28 April 2009 1
General Overview
Introduction to CC Construction Group Purpose of presentation
Outline of presentation
Context
Roles Philosophy
Structure
Form
Key risks and contract terms
-
8/10/2019 03 Epc Contract Management
3/37
EPC Contracts - 28 April 2009 2
Context - Economic
Effect of cycles Participants
Procurement methods and structures
Price
Risk allocation
Funding sources and methods
-
8/10/2019 03 Epc Contract Management
4/37
EPC Contracts - 28 April 2009 3
ContextBusiness Culture
Most countries embrace market economics (intheory)
In practice there are exceptionshelpful and
otherwise
So relationships are to some extentadversarial/competitive
And negotiations can be complex (especially if
lenders are involved)
-
8/10/2019 03 Epc Contract Management
5/37
EPC Contracts - 28 April 2009 4
ContextLegal/Regulatory
Legal system is part of business culture The rule of law/contract is important, especially in
project financed deals
Civil and common law systems differ in form and
substance Impact of procurement rules
On owners behaviour
On bidding tactics
-
8/10/2019 03 Epc Contract Management
6/37
EPC Contracts - 28 April 2009 5
Roles
Prime contractor (not always EPC) Vendor
Technology licensor
Investor
Funder (deliberate or by default)
-
8/10/2019 03 Epc Contract Management
7/37
EPC Contracts - 28 April 2009 6
Philosophy
As a contractor Open bidding or sole source?
Immediate profit or market penetration/profile?
Sole or in consortium?
Legal and practical consequences of joint liability?
Equity or contracting role only?
-
8/10/2019 03 Epc Contract Management
8/37
EPC Contracts - 28 April 2009 7
Philosophy (contd)
As an owner Alliance or risk transfer?
Linked to funding method
Some sectoral patterns
Also varies between public and private sector
Philosophy is influential only if shared within
supply chain
-
8/10/2019 03 Epc Contract Management
9/37
EPC Contracts - 28 April 2009 8
Structurethe Project
Privately procured On balance sheet
Off balance sheet
Publicly procured
May still be accounting considerations, eg in PPP
Combinations
PPP projects
Concessions
Otherseg PPAs
-
8/10/2019 03 Epc Contract Management
10/37
EPC Contracts - 28 April 2009 9
Typical PPP Structure
PUBLIC ENTITY
CONCESSION
CONTRACT
SPV
SPONSOREQUITY
THIRD PARTY
EQUITY
INVESTORS
DUE DILIGENCE
ADVISER 1
MEZZANINE
FUNDERS
INSURERS
CONSTRUCTION
SENIOR
FUNDERS
(BANK/BOND)
SURPLUS REAL ESTATE
DISPOSAL
DUE DILIGENCE
ADVISER 2
SUBCONTRACTOR 1
DESIGNERS
EQUIPMENT SUPPLY
OPERATION &
MAINTENANC
E
DEVELOPER
DUE DILIGENCE
ADVISER 3
INVESTORS
SUBCONTRACTOR 2
SUBCONTRACTOR 3
BONDS &
GUARANTEE
S
SURETIES &
GUARANTORS
-
8/10/2019 03 Epc Contract Management
11/37
EPC Contracts - 28 April 2009 10
Structurethe Main Construction Contract(s)
EPC/design and build Owner designed
EPCM/CM
Other variants
-
8/10/2019 03 Epc Contract Management
12/37
EPC Contracts - 28 April 2009 11
KEY
Traditional
OWNER
CONTRACTOR
SUB-CONTRACTORS
ARCHITECT/ENGINEER
=Appointments
= Sub-Contracts
= Building Contract
EPC Structure
-
8/10/2019 03 Epc Contract Management
13/37
EPC Contracts - 28 April 2009 12
Where does EPC fit in?
Construction
Management
Owner
assumes
risk
Contractor
retains risk
Traditional Design &Build LSTK/EPC
R I S K S P E C T R U M
Except as otherwise stated in the Contract:
a) the Contractor shall be deemed to have obtained all necessary information as to risks, contingencies and other
circumstances which may influence or affect the Works;
b) by signing the Contract, the Contractor accepts total responsibility for having foreseen all difficulties and costs of
successfully completing the Works; and
c) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs.
LSTKLump Sum Turnkey
EPCEngineering Procurement and Construction
EPC Structure (contd)
-
8/10/2019 03 Epc Contract Management
14/37
EPC Contracts - 28 April 2009 13
EPC Key Features
Single point responsibility
Subject to caps and carve-outs
High degree of risk for contractor
Also high (but not absolute) degree of contractor
control Priced accordingly
The preferred structure for project finance/PPP
transactions
Linkage to shareholder support
-
8/10/2019 03 Epc Contract Management
15/37
EPC Contracts - 28 April 2009 14
EPC Key Features (contd)
Sensitive to market conditionsrecent history
Wide choice of standard contracts (eg FIDIC
Silver and Yellow)
Commonly used in infrastructure, thermal power
and downstream petchem
-
8/10/2019 03 Epc Contract Management
16/37
EPC Contracts - 28 April 2009 15
KEY
Traditional
OWNER
CONTRACTOR
SUB-CONTRACTORS
ARCHITECT/ENGINEER
=Appointments
= Sub-Contracts
= Building Contract
Owner Design
-
8/10/2019 03 Epc Contract Management
17/37
EPC Contracts - 28 April 2009 16
Owner Design Key Features
More control for owner Design and other risks also retained by owner
History of disputes
Use has declined in recent decades but still used
in, eg, public civil works and technology projects
Incompatible with project finance approach
-
8/10/2019 03 Epc Contract Management
18/37
EPC Contracts - 28 April 2009 17
OWNER
TC
PROFESSIONAL TEAM
ARCHITECTSTRUCTURAL ENGINEER
M&E ENGINEER
QUANTITY SURVEYOR
CDM CO-ORDINATOR
CONSTRUCTION MANAGER
TC = TRADE CONTRACTOR
= Trade Contract
=Appointments
= CMA
KEY
EPCM/CM
TC TC TC TC TC TC TC TC
-
8/10/2019 03 Epc Contract Management
19/37
EPC Contracts - 28 April 2009 18
EPCM/CM Key Features
EPCM contractor is essentially a consultant Owner bears substantial risk
Interface
Recourse/leverage
Can produce the lowest cost and fastest completion
But is heavily dependent on specialist skills,
experience and resources
Can be disastrous if those are not present
examples
Widely used in upstream oil and gas, renewables
and some real estate markets
-
8/10/2019 03 Epc Contract Management
20/37
EPC Contracts - 28 April 2009 19
Variants
Timingtwo-stage contracting Market driven and mixed feedback
Conversion mechanism
Scopeis FEED included?
Can be attractive for contractors
Pricingtarget cost/GMP
Usually a consequence rather than a choice
Exampleseg 2012
Link to philosophy
-
8/10/2019 03 Epc Contract Management
21/37
EPC Contracts - 28 April 200920
Forms of Contract
a profusion of colour and variety!
-
8/10/2019 03 Epc Contract Management
22/37
EPC Contracts - 28 April 200921
Forms of Contract
Standard or specially drafted? Relevance of wider structure
Origin of standard forms
Example of FIDIC
Other standard forms, eg NEC, AIA, ENAA, EIC
Why amend a proven form?
To correct perceived anomalies or bias (examples)
-
8/10/2019 03 Epc Contract Management
23/37
EPC Contracts - 28 April 200922
Forms of Contract (contd)
To reflect deal specifics or sector practice
(examples)
To incorporate material from other contracts (eg in
PPP)
To reflect requirements of funding (which may be
owner or contractor sourced)
For legal reasons (examples)
Who draftsowner or contractor?
-
8/10/2019 03 Epc Contract Management
24/37
EPC Contracts - 28 April 200923
Key Risks and Contract Terms
Law and language English language and style commonly used
Precedence and integration of documents
Distinguish language of contract and of
communications Common law preferred but less strongly these days
Impact of local law in any event
Wide choice of methods and places for dispute
resolution
-
8/10/2019 03 Epc Contract Management
25/37
EPC Contracts - 28 April 200924
Key Risks and Contract Terms (contd)
Quality and scope Wrapping eg of technology or existing works or
design
Fitness for purpose and reasonable skill and care
Insurance and risk retention implications Compliance with laws and consents
Special importance of environmental requirements
Pass-down from other project documents
-
8/10/2019 03 Epc Contract Management
26/37
EPC Contracts - 28 April 200925
Key Risks and Contract Terms (contd)
Intellectual property Ownership by contractor
Assigned or licensed to owner?
Scope of license
Indemnities for infringementcapped or not?
-
8/10/2019 03 Epc Contract Management
27/37
EPC Contracts - 28 April 200926
Key Risks and Contract Terms (contd)
Performance Security Joint liability
Guarantees
Bonds
Types and purposes
Issues with on-demand bonds
Credit issues in current market
Retention funds
-
8/10/2019 03 Epc Contract Management
28/37
EPC Contracts - 28 April 2009
Key Risks and Contract Terms (contd)
SubcontractingApproval
Step-in rights
Site conditions
Can threaten viability of project/parties Mitigants
An open-minded approach
Government support
Surveys and staging
Flexibility in design
27
-
8/10/2019 03 Epc Contract Management
29/37
EPC Contracts - 28 April 200928
Key Risks and Contract Terms (contd)
Labour Local laws
Local preference
Time
Status of programme Remedies for delay
Liquidated damages (LDs) for delay
Enforceability issues with delay LDs
Acceleration
Milestones
Look-forward default
Calculation and capping of LDS
-
8/10/2019 03 Epc Contract Management
30/37
EPC Contracts - 28 April 200929
Key Risks and Contract Terms (contd)
Completion, commissioning and testing Sector differences
Performance LDs and make-good
Defects liability
Typical periods Evergreen clauses
Latent and patent defects
Remedies under the general law
-
8/10/2019 03 Epc Contract Management
31/37
EPC Contracts - 28 April 200930
Key Risks and Contract Terms (contd)
Variations Instructed by the owner
Resulting from changes in law or standards
Examples of risk allocation
Price and payment Lump sum or other?
Currency issues
Input cost fluctuation
Milestones or measurement?
Offsite materials
-
8/10/2019 03 Epc Contract Management
32/37
EPC Contracts - 28 April 200931
Key Risks and Contract Terms (contd)
Advance payments
Cashflow neutrality
Payment security for contractor
Set-off and correction
ECA requirements Remedies for non-payment
Role of lenders engineer
-
8/10/2019 03 Epc Contract Management
33/37
EPC Contracts - 28 April 200932
Key Risks and Contract Terms (contd)
Termination For owner convenience
Payment of profit
For force majeure
For owner default Typical grounds
Remedies
For contractor default
Typical grounds Remedies (to include rejection?)
-
8/10/2019 03 Epc Contract Management
34/37
EPC Contracts - 28 April 200933
Key Risks and Contract Terms (contd)
Risk Indemnities
Treatment of hazardous sites
Care of the works
Excepted risks Link to insurance
Liability
Liability cap
Exclusion of consequential loss
Exceptions
-
8/10/2019 03 Epc Contract Management
35/37
EPC Contracts - 28 April 200934
Key Risks and Contract Terms (contd)
Insurance Main categories
CAR/EAR
TPL/PL
PII
Plant and vehicles
DSA/ALOP
Latent defects
Operational insurance
Who arranges cover?
Other contract terms
-
8/10/2019 03 Epc Contract Management
36/37
EPC Contracts - 28 April 200935
Key Risks and Contract Terms (contd)
Force Majeure
Open or closed clause?
Territorial limits?
Exclusions
Consequences
-
8/10/2019 03 Epc Contract Management
37/37
Clifford Chance, 10 Upper Bank Street, Canary Wharf, London, E14 5JJ, UK
Clifford Chance LLP 2007
Clifford Chance Limited Liability Partnership
www.cliffordchance.com
EPC Contracts
Contract Management in
International ConstructionBeijing, April 28, 2009