July 28, 2011 | www.I-80Will.com | 1

I-80 Phase I StudyProject Working Group Meeting #6

December 5, 2017December 5, 2017

w w w . I - 8 0 W i l l . c o m

July 28, 2011 | www.I-80Will.com | 2December 5, 2017 | www.I-80Will.com | 2

Agenda

• Study Update• Development and Evaluation of

Alternatives to be Carried Forward• Next Steps and Schedule

July 28, 2011 | www.I-80Will.com | 3December 5, 2017 | www.I-80Will.com | 3

July 28, 2011 | www.I-80Will.com | 4December 5, 2017 | www.I-80Will.com | 4

Plainfield

Lockport

Crest Hill

Manhattan

ShorewoodJoliet

MinookaChannahon

Rockdale

New Lenox

Study Area

July 28, 2011 | www.I-80Will.com | 5December 5, 2017 | www.I-80Will.com | 5

RID

GE

RD

I-5

5

HO

UB

OLT

RD

LAR

KIN

AV

E

CEN

TER

ST

CH

ICA

GO

ST

RIC

HA

RD

S S

T

BR

IGG

S S

T

Roc

k R

un

Cre

ek

Near Term Improvement –Package A

Scope of Project: • Bridge rehabilitation and/or replacement• Isolated pavement reconstruction• Safety improvements

Jolie

t Ju

nct

ion

Tra

il

Near-Term Phase I Study

July 28, 2011 | www.I-80Will.com | 6December 5, 2017 | www.I-80Will.com | 6

Near-Term Phase I Study

July 28, 2011 | www.I-80Will.com | 7December 5, 2017 | www.I-80Will.com | 7

PHASE I:Preliminary Engineering and Environmental Study

PHASE I:Preliminary Engineering and Environmental Study

PHASE II: Contract Plan Preparation and Land Acquisition

PHASE II: Contract Plan Preparation and Land Acquisition

PHASE III: ConstructionPHASE III:

Construction

CONTRACT PLANS

COMPLETEDPROJECT

DESIGNAPPROVAL

Phase I Study

July 28, 2011 | www.I-80Will.com | 8December 5, 2017 | www.I-80Will.com | 8

Follow National Environmental

Policy Act (NEPA)

Assess Natural, Built, Human Environment

Consider Environmental

Impact

Integrate Environmental

Values

Phase I Study

Step 5Design

Approval

Step 4Preferred

Alternative

Step 3Range of

Alternatives

*

Step 2Purpose

and Need

Step 1Data

Collection

*We are here

July 28, 2011 | www.I-80Will.com | 9December 5, 2017 | www.I-80Will.com | 9

Stakeholder Involvement:Public Meetings

• Public Meeting #1: August 18, 2010– Corridor Issues and Transportation Problems

• Public Meeting #2: July 28, 2011– Sought Public Comments for Project Alternatives

Residents view exhibits at Public Meeting #2

July 28, 2011 | www.I-80Will.com | 10December 5, 2017 | www.I-80Will.com | 10

Stakeholder Involvement: Project Working Group (PWG)

• PWG #1: September 14, 2010• PWG #2: February 8, 2011• PWG #3: May 3, 2011• PWG #4: May 20, 2011• PWG #5: September 19, 2011

July 28, 2011 | www.I-80Will.com | 11December 5, 2017 | www.I-80Will.com | 11

Project PurposeThe purpose of the project is to provide an improved transportation system along Interstate 80 from Ridge Road to U.S. Route 30. This will be accomplished by addressing facility condition and design to improve regional and local travel and access, as well as safety for all users.

Project Need• Improve regional and local travel and access;• Improve facility condition and design; and• Improve safety for all users.

Purpose & Need

July 28, 2011 | www.I-80Will.com | 12December 5, 2017 | www.I-80Will.com | 12

National Environmental Policy Act (NEPA) • Concurrence Point #1:

Purpose and Need - March 1, 2012• Alternative Development• Concurrence Point #2:

Alternatives to be Carried Forward –February 22, 2017

Progress to Date

July 28, 2011 | www.I-80Will.com | 13December 5, 2017 | www.I-80Will.com | 13

• No-Build Alternative– Routine maintenance only– Does not meet the Purpose and Need

• Study Alternative(s) comprised of:– Mainline Alternatives– Bridge Alternatives including Des Plaines River

Bridge Alternatives – Interchange Alternatives

Alternative Objectives

July 28, 2011 | www.I-80Will.com | 14December 5, 2017 | www.I-80Will.com | 14

July 28, 2011 | www.I-80Will.com | 15December 5, 2017 | www.I-80Will.com | 15

Mainline Alternatives

• Pavement Replacement– Address Pavement Age– Address Pavement Condition

• Add-Lanes– Not Carried Forward

• Auxiliary Lanes– Improve Traffic Flow– Improve Safety

July 28, 2011 | www.I-80Will.com | 16December 5, 2017 | www.I-80Will.com | 16

Proposed Laneage for I-80 General Purpose Widening

RID

GE

RD

I-5

5

HO

UB

OLT

RD

LAR

KIN

AV

E

CEN

TER

ST

CH

ICA

GO

ST

RIC

HA

RD

S S

T

BR

IGG

S S

T

Add Aux Lane

Existing 6 Lanes

Add Aux Lane

EB/WB

Mainline Alternatives: Add Auxiliary Lanes

Houbolt Road Extension

PROJECT LIMIT

PROJECT LIMIT

July 28, 2011 | www.I-80Will.com | 17December 5, 2017 | www.I-80Will.com | 17

/ potential future lane

Mainline Alternatives:Proposed 2 Lane Sections

July 28, 2011 | www.I-80Will.com | 18December 5, 2017 | www.I-80Will.com | 18

July 28, 2011 | www.I-80Will.com | 19December 5, 2017 | www.I-80Will.com | 19

• Near Term Work– Minor Repairs– Deck Replacement– Some bridges will be reconstructed

• Widening• Major Repairs/Rehab• Total Replacement

Mainline Alternatives: Bridges

Mainline bridge along I-55

July 28, 2011 | www.I-80Will.com | 20December 5, 2017 | www.I-80Will.com | 20

• North Alignment• South Alignment• Refined North Alignment (new)

Des Plaines River Bridge Alternatives

Des Plaines River Bridge

July 28, 2011 | www.I-80Will.com | 21December 5, 2017 | www.I-80Will.com | 21

Des Plaines River Bridge Alternative #1 North

July 28, 2011 | www.I-80Will.com | 22December 5, 2017 | www.I-80Will.com | 22

Des Plaines River Bridge Alternative #2 South

July 28, 2011 | www.I-80Will.com | 23December 5, 2017 | www.I-80Will.com | 23

Des Plaines River Bridge Alternative #3 Refined North

July 28, 2011 | www.I-80Will.com | 24December 5, 2017 | www.I-80Will.com | 24

Category North South Refined North

Residential Relocations 16 8 28

CommercialRelocations 2 0 2

Speed Limit 60 mph 60 mph 65 mph

Center Street 25 mph Ramp Curve

25 mph Ramp Curve

50 mph Ramp Curve

Constructability Constrained Constrained Standard

Wetland Impacts 0.2 acre 0.2 acre 0 acres

Des Plaines River Bridge Alternatives

July 28, 2011 | www.I-80Will.com | 25December 5, 2017 | www.I-80Will.com | 25

July 28, 2011 | www.I-80Will.com | 26December 5, 2017 | www.I-80Will.com | 26

Interchange Alternatives

• Preliminary preferred alternatives have been identified at these interchanges:

RID

GE

RD

I-5

5

HO

UB

OLT

RD

LAR

KIN

AV

E

CEN

TER

ST

CH

ICA

GO

ST

RIC

HA

RD

S S

T

BR

IGG

S S

T

PROJECT LIMIT

PROJECT LIMIT

July 28, 2011 | www.I-80Will.com | 27December 5, 2017 | www.I-80Will.com | 27

Interchange I-55

Alternative:SB to EB Turbine Ramp

July 28, 2011 | www.I-80Will.com | 28December 5, 2017 | www.I-80Will.com | 28

Interchange I-55: Alt #2

New Bridge

Auxiliary Lane to Houbolt Road

2 Lane Ramp

New Bridge

SB to EB Turbine Ramp

July 28, 2011 | www.I-80Will.com | 29December 5, 2017 | www.I-80Will.com | 29

Alternative 1Realign Westbound Exit Ramp

Alternative 2Remove Northwest Loop Ramp

Larkin Avenue Alternatives

July 28, 2011 | www.I-80Will.com | 30December 5, 2017 | www.I-80Will.com | 30

Larkin Avenue (IL-7): Alt #1

Realign Ramp for New Signal

Begin Additional Mainline Lane

July 28, 2011 | www.I-80Will.com | 31December 5, 2017 | www.I-80Will.com | 31

Larkin Avenue (IL-7): Alt #2

Realign Ramp for New Signal

Begin Additional Mainline Lane

Remove Loop Ramp

July 28, 2011 | www.I-80Will.com | 32December 5, 2017 | www.I-80Will.com | 32

Alternative 12Half-Diamond with Two loop Ramps

Alternative 6¾-Diamond with One Loop Ramp

Center Street Alternatives

July 28, 2011 | www.I-80Will.com | 33December 5, 2017 | www.I-80Will.com | 33

Center Street: Alt #12

July 28, 2011 | www.I-80Will.com | 34December 5, 2017 | www.I-80Will.com | 34

Center Street: Alt #6

July 28, 2011 | www.I-80Will.com | 35December 5, 2017 | www.I-80Will.com | 35

Alternative 2Partial Cloverleaf

Alternative 6DDI

Alternative 7Parclo with Directional Ramp

Alternative 8Partial Cloverleaf with Jughandle

Chicago Street Alternatives

July 28, 2011 | www.I-80Will.com | 36December 5, 2017 | www.I-80Will.com | 36

Alt. #2: Partial Cloverleaf

Chicago Street: Alt #2

July 28, 2011 | www.I-80Will.com | 37December 5, 2017 | www.I-80Will.com | 37

Alt. #6: Diverging Diamond (DDI)

Build Alternatives:Chicago Street Alternative #6

July 28, 2011 | www.I-80Will.com | 38December 5, 2017 | www.I-80Will.com | 38

Alt #7: Partial Cloverleaf w/ Directional Ramp

Build Alternatives:Chicago Street Alternative #7

July 28, 2011 | www.I-80Will.com | 39December 5, 2017 | www.I-80Will.com | 39

Alt #8: Partial Cloverleaf w/Jughandle Ramp

Build Alternatives:Chicago Street Alternative #8

July 28, 2011 | www.I-80Will.com | 40December 5, 2017 | www.I-80Will.com | 40

MainlinePavement Replacement Extend Existing Auxiliary Lanes

BridgesMainline Bridges (Long-Term Improvements)Des Plaines River Bridge North, South, and Refined North

InterchangesI-55 (1 alternative)Larkin Avenue (2 alternatives)Center Street (2 alternatives)Chicago Street (4 alternatives)

Alternatives to be Carried Forward

Summary

July 28, 2011 | www.I-80Will.com | 41December 5, 2017 | www.I-80Will.com | 41

EVALUATION CRITERA Range of Alternative (Impacts)Social / Economic ResourcesResidential Displacements 11 – 37Business Displacements 0 – 2Total ROW Acquisition (acres) 6 – 13Potential EJ Impacts – Minority YPotential EJ Impacts - Low-Income N

Special Lands / Section 4(f) / Section 6(f) LandsSection 4(f) Sites Potentially Impacted 2 TrailsNatural ResourcesT&E Species N

Waters of the U.S.

In-Stream Work (name)

Des Plaines RiverDuPage River

Rock Run CreekHickory Creek

Wetland Impacts ( # and acres) 7 (1.8 ac) - 11 (1.3 ac)High Quality Wetland Impacts 0ADID Wetland Impacts 0

Floodplain Impacts YSection 106 (NRHP) Properties Potentially Impacted

Brandon Road Lock and Dam Historic District

Range of AlternativesImpact Summary

July 28, 2011 | www.I-80Will.com | 42December 5, 2017 | www.I-80Will.com | 42

Next Steps

– Present the Alternatives atPublic Meeting #3 – January 31, 2018

– Project Working Group #7 – Spring 2018– Public Hearing – Summer 2018

July 28, 2011 | www.I-80Will.com | 43December 5, 2017 | www.I-80Will.com | 43

July 28, 2011 | www.I-80Will.com | 44

Thank you for attending.