ammonia purge near miss - the source s/2015spring/clarke_ammonia.pdf–the contractor arrived on...
TRANSCRIPT
Ammonia Purge Near Miss
Jason Clarke, Gulf Power Co.
• Four generating units
2 - 82 MW
1 - 320 MW
1 - 500 MW
• All four units run through a common scrubber
• The two large units utilize SCR technology and
have anhydrous ammonia injection systems
Plant Crist Overview
• 11/5/2014
–SCR System Owner put in a Clearance request to
replace multiple pressure relief valves on the
ammonia system according to maintenance strategy
schedule.
Incident Overview
• 11/10/2014
–Plant Operations discovered a small ammonia leak
during the nightshift.
–Operations barricaded the area from a safe distance
and placed a clearance on the system thereby
isolating ammonia.
Incident Overview
• 11/11/2014 (Dayshift)
–With the ammonia system out of service and no
pressure on the system, the location of the small
leak could not be determined.
–The various pressure relief valve replacement job
was completed as planned.
–As the system was returned to service, no leak was
detected.
Incident Overview
• 11/11/2014 (Nightshift)
–The same crew working the previous night noticed
that the leak reappeared.
Incident Overview
• Subsequently, the following events occurred that
same night:
–The operations team leader contacted the team
leader on call, which informed him to contact the
manager on call.
–The manager on call was notified and instructed the
operations team leader to contact the emergency
response contractor to make the necessary repairs.
Incident Overview
• 2130 hours
–The contractor arrived on plant site and made
contact with the operations team leader and
proceeded to the leak site. It was determined that
the leak was coming from a hose that was located
on the grating. This hose was attached to a fitting
that was used to purge ammonia from the system
prior to performing needed work.
Incident Overview
• The perceived lack of necessary parts did not
allow the contractor to make the immediate
repairs. However, the contractor did temporarily
mitigate the situation by placing the hose in a
drum of water.
Incident Overview
Incident Overview
Drum of
water
Hose
Valve
• 2300 hours
–Contractor left the plant site.
• Leak was determined to be mitigated and system left
in service.
• 2330 hours
– Plant operations visually determined that the
ammonia leak had reappeared
• Calls placed to plant environmental group
Incident Overview
• The information conveyed from environmental
compliance was that the ammonia system could
be isolated and left out of service until the
morning for protection of personnel.
– Lastly, it was suggested to contact the system
owner to inform him of the current situation.
Incident Overview
• 2345 hours
– Operations team leader made contact with the
system owner.
• The system owner informed the team leader that the
parts necessary for repair were on plant site.
Incident Overview
• The system owner also confirmed that a C&R
technician, which was working on plant site that
night, was capable of making the repairs.
Incident Overview
• 0120 hours
– C&R employee approached the area of the leak and found
that the hose was no longer vented into the drum of water.
Instead, it had come out of the water and was located on
the top of the drum.
Incident Overview
Incident Overview
Drum of
water
Hose
Valve
• 0130
– The C&R employee placed the hose back into the drum of
water, unaware that a small amount of liquid ammonia was
in the hose.
Consequently, the mixture of ammonia and water reacted
causing a plume of vapor.
Incident Overview
Latent Conditions • Bleed off hose was never removed from equipment
from prior outage.
• Hose discharge elevation allowed accumulation of
liquid NH3.
• Recognition for potential of liquid ammonia
accumulation in the hose.
• Lack of awareness to level of reaction.
Incident Overview
Latent Conditions • Specialized contractor successfully performed same
task earlier in the night.
• Specialized contractor successfully performed same
task with only respirator as task specific PPE.
• Time of event – event occurred on night shift.
• Infrequent task
Incident Overview
Latent Conditions • Repair expectations
• Criticality not identified: Identification and repair of leak
on Tuesday day shift
• Condition report not generated upon discovery of the
initial ammonia leak.
• Limited visibility
Incident Overview
Latent Conditions • T.L. had multiple concerns (Distractive Environment )
• Inaccurate Risk Versus Reward Assessment
• Hose did not appear secured to barrel of water by
contractor.
• Operations team leader was not aware of onsite
material.
Incident Overview
Root Causes • Hose used for purging ammonia left in place from
previous outage
• Ammonia valve leaking by
• Chain of command protocol/experience
Incident Overview
Corrective Actions • Purge checklist procedure for ammonia system and
miscellaneous ammonia purging.
• Inspect and repair leaking valve
• Perform broadness review of other similar valves in the
system
Incident Overview
Corrective Actions • Technical evaluation for upgraded purging
equipment/system
• Supervisors and managers, in discussion of this RCA
with their employees, are to emphasize the importance
of full circle communication (chain of command and
subject matter experts).
• Technical Evaluation: Event Notification to Generation
Fleet for review
Incident Overview
Incident Overview
Purge
flange
Valve
Questions?
Incident Overview