AL-HASSAN ENGINEERING CO. S.A.O.G PROJECT: AMAL POWER STATION
PDO CONTRACT NO: C-310987
DOCUMENT NO.
AML-391-AA -6944-0032-000
21st
March 12 – 20th
April 12
AL-HASSAN ENGINEERNG CO. SAOG PROJECT: AMAL POWER STATION
(PDO CONTRACT NO: C-310987)
AML-391-AA-6944-0032-000
01 25.04.12 1 to 57 For Approval A.R.D K.G.B.
Document No Rev
No Date
No. of
`Pages Description
Prepared
By
Reviewed
by
Approved
by PDO
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 3 of 57
TABLE OF CONTENTS
Page
Section 1 Contract Particulars
1.01 Salient Features of the Contract 7
1.02 Contract Scope of Work in brief 8
Section 2 Project Summary Report
2.01 Project Progress Statistics 11
2.02 Narrative Summary Report 12
2.03 Over-all Progress Curve for the Project 12
2.04 Areas of Concern 12
Section 3 Detailed Report
3.01 Health, Safety and Environment (HSE) 14
3.02 Engineering & Design Documents 14
3.03 Procurement 14
3.04 Manufacturing 14
3.05 Delivery 14
3.06 Mobilization 14
3.07 On plot construction and commissioning 15
3.08 Off Plot construction and Commissioning 17
3.09 Equipment Deployment 17
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 4 of 57
3.10 Manpower Deployment 19
3.11 Quality Assurance 20
3.12 Plan for Next month 21
3.13 Contract Financials 23
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 5 of 57
Section 4 Appendices
I Project Milestone Dates 26
II Project Schedule (Updated) 31
III Drawing Control Register 32
IV Material Tracking Register 33
V Critical Project Material List 34
VI Health & Safety Statistics (Monthly Return) 35
VII HSE Audit / Inspection Schedule 36
VIII HSE Training Matrix 38
IX Quality internal and external audit schedule 39
X Summary of progress 40
XI S-curve for Engineering Progress 42
XII S-curve for Procurement Progress 43
XIII S-curve for Construction progress 44
XIV S-curve for Overall progress 45
XV S-curve for VOWD 46
XVI Manpower & Equipment Histogram 47
XVII Subcontract Details 48
XVIII Variations Register 50
XIX Omanisation Requirement 51
XX SPIR Progress 53
XXI Progress Photographs 55
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 6 of 57
SECTION 1
CONTRACT PARTICULARS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 7 of 57
1.01 Salient Features of the Contract
Project Title : Amal Power Station
Company / Employer : Petroleum Development Oman
LLC
Company Contract Holder : Mr. Harith M Al Amry – UIE/5
Company Representative : Mr. Saud Al Habsi – UIE/52
Contractor : Al-Hassan Engg. Co. S.A.O.G
Contract Value : Rial Omani 22,950,786/-
Effective Date of Contract : 24th
June 2009
Commencement Date : 4th
July 2009
Contract Duration : 730 Days
Substantial Completion : 5th
April 2011
Completion Date : 4th
July 2011
Engineering Sub-Contractor : Mott MacDonald & Company LLC,
Oman
SAP Purchase Order No : 4500439405
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 8 of 57
1.02: Contract Scope of Work in Brief:
The Amal Power Station will be of modular construction and will comprise initially of
two Frame 9E Gas Turbine Generator (GTG) units.
Construction and commissioning of Amal Power plant comprising two
frame 9E Gas turbine units– Installed capacity 252 MW.
Provision will be made for the future addition of Once through Heat
Recovery Generators (OTHRS’s) on the back end of the GTG.
Amal Power Station with Frame 9E GTG’s will have an ISO rated installed
capacity of 252MW. At a site ambient temperature of 48 deg C,
corresponding to maximum summer temperatures, this will drop to
197.4MW.
Each GTG unit will be unitised such that any equipment failures
associated with one GTG unit will not cause a trip of an adjacent GTG
unit.
The fuel gas for Amal Power Plant will be supplied from 18” Hubara to
Amal Pipeline and the tie-in point for fuel gas will be provided on 18”
bypass line near Amal pie receiver A-2075.
A unitized gas treatment trains will be provided to ensure the gas
delivered to the gas turbine meets the gas turbine Original Equipment
Manufacturer’s (OEM) requirements at all times.
The Amal Power Station is designed for unmanned operation and under
normal operation will be remotely controlled by SCADA and monitored
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 9 of 57
from the Yibal/QA Master Control Room with backup from the
Marmul\Nimr Control Room.
Facilities Service water, DM water, Instrument air system incorporating
screw type compressors and membrane dryers will be provided.
Facilities for transferring Diesel fuel to the Emergency DG set will be
provided.
Gas turbines shall be free issued by PDO. Design, supply of BOP is part
of AHEC scope.
Design and construction of Unit Electrical buildings and Gas treatment
plant building.
Design, supply and construction of OHL from Nimr Central to LILO
location AP05(28 KM) and from LILO location AP05 to Thuleilat ( 70 KM)
HVAC System.
Power Station internal and external communication with provision of
CCTV.
Fire detection and alarm system.
Scope includes interfacing with GTG OEM supplier/ Vendor.
Pre commissioning and commissioning.
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 10 of 57
SECTION 2
PROJECT SUMMARY REPORT
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 11 of 57
2.01 Project Progress Highlights:
Highlights of April, 2012.
10.1 KM New OHL erection and bolt tightening 34 / 34 no’s completed.
10.1 KM New OHL ELM conductor stringing completed except 2 shut
down location.
10.1 KM OHL OPGW installation works in progress.
Unit # 1 & 2 punch point attending in progress.
2.02 Narrative Summary Report
Project progress during the month of March 21st to April 20th
is summarized as follows
Overall project progress for the month has reported 0.05% against the
planned progress 0.10%.
Cumulative overall progress for the month has reported 99.85% against
the planned progress 100%.
Cumulative engineering progress for the month has reported 100%
against the planned progress 100%.
Cumulative Procurement /Manufacturing/ delivery progress is 100%
against the planned progress 100%.
Cumulative construction progress for the month is 99.58% against the
planned progress 100%
2.03 Overall progress curve for the project
As per section 4, Appendix XII
2.04 AREAS OF CONCERN
Receipt of inputs from PDO/BHEL –
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 12 of 57
1. Unit # 2 - CO2 system connecting Hose. CO2 panel battery back up for
unit # 1 & 2.
2. Unit # 2 - 125V - DCDB - Variable Resistor - 01 set. (3 no’s) for DC
Jacking oil pump cubicle.
3. Lube oil NRV, Step down transformer (220V/110V) for the MOV's in U#2
Accessory Base. Shaft for ABOC Fan#7 bearing block
4. Refer critical material list for balance materials.
Other area of concerns –
1. Communication between Marks V1 and DCS.
2. MFM – SCADA communication.
3. Passing of ESD valve in GTP
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 13 of 57
SECTION 3
DETAILED REPORTS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 14 of 57
3.01: Health, Safety and Environment (HSE).
Major highlights of the month:
Weekly HSE gate meeting conducting on every Saturday.
Conducting daily tool box for driver and work force before starting of
work.
HSE Monthly meeting conducted.
Vehicle inspection completed 50% along with plant department.
3.02: Engineering & design documents
Major highlights of the month:
3.03: Procurement
Major highlights of the month:
3.04: Manufacturing
Major highlights of the month:
3.05: Delivery
3.06: Mobilization:
Major highlights of the month:
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 15 of 57
Mobilization and demobilization of manpower and equipment in progress.
3.07: On plot Construction and commissioning.
Major highlights of the month:
Civil
Unit # 2 - Punch point attending in progress.
Unit # 2 – Test pack submission completed.
Mechanical
Unit # 2
Unit # 2 – Punch point attending works completed.
Unit # 2 – Test pack submission completed.
ELECTRICAL
Unit -1
Punch point attending in progress.
Test pack submission completed except 1 package.
Unit -2
Punch point attending in progress.
Test pack submission in progress for 6 packages.
Instrumentation
Unit # 1 & 2 – Punch point attending works 95% completed.
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 16 of 57
Unit # 1 & 2 Test pack preparation and submission in progress for 10
packages.
Testing
Pre Commissioning and Commissioning
Unit-1 & 2
Unit # 1 & 2 - DCS punch point attending in progress
DCS SAT 84% completed.
Alarm rationalization 45% completed.
3.08: Off plot Construction and commissioning.
Major highlights of the month:
AP07 to Nimr Central OHL
Tower assembly 34/ 34 completed. Tower erection 34 /34 completed.
Stringing for 9 section completed out of 10 sections.
FOC stringing works in progress.
Spacer damper installation works completed.
3.09: Plant And Equipment Deployed At Site:
1. Station wagon 5
2. Pickup 3
3. Potable water tanker 5000 Gallon 1
4. Tipper 1
5. Diesel Tanker 1
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 17 of 57
6. Shovel/Loader 1
7. Grader 0
8. Bucket truck 0
9. 62 Seat Big bus 0
10. Crew cab 3
11. 7 Ton Truck 1
12. Box Tailor 1
13 7 Ton Hiab 1
14 Brackish water tanker 1
15 Excavator 1
16 1 T Roller 1
17 JCB 1
18 10 T Roller 0
19 Concrete Mixture machine 0
20 Power generator portable 2
21 Plate compactor 2
22 Jumping compactor 2
23 Welding machine 2
24 Air compressor 3
25 24 Seater Bus 2
26 Crane 140 T 0
27 Crane 50/25 T 2
28 Generator 225 KV 0
29 Ambulance 1
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 18 of 57
30 Folk lift 1
31 Transit Mixer 1
32 Cement Bulker 0
33 Batching plant 1
34 Waste Disposal Truck 1
35 60 Seated Big Bus 1
36 Bobcat 0
37 Vibrator 2
38 Generator 350 KVA 0
39 Hydra 1
40 Truck Gas 0
3.10: Manpower Deployment:
Project Office at Muscat
1. Project Manager 1
2. Interface Manager
3. Planning Manager 1
4. Procurement Manager
5. Design Manager
6. Design Electrical Engineer
7. Design Civil Engineer
8. Project Coordinator
9. Cost Accountant 1
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 19 of 57
10. Draughts man 1
11 Secretary
12 Drivers (Omani) 2
MMC (Engg. Consultant) Office at Muscat 1. Project Manager
2. Civil Discipline
3. Electrical Discipline
4. Mechanical Discipline
5. Process Discipline
6. C & I Discipline
7. Piping Discipline
Manpower Deployed at Site
1. Staff ( Expat) 30
2. Staff (Omani) 10
3. JE (Expat) 92
4. JE (Omani) 59
5 Sub contract 35
3.11: Quality Assurance:
Major Highlights of the Month:
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 20 of 57
Unit # 2 - Tests pack preparation and submission for Electrical and
instrumentation in progress.
Mark up drawings preparation and submission works in progress.
3.12, Plan for Next Month:
Health, Safety and Environment.
Inspection of plant and equipments.
Conducting monthly HSE Meeting.
Gate meeting on every Saturday
Tool box talk for driver and work force
Driver’s forum.
Mobilization:
Manpower and equipment mobilization and demobilization.
On Plot Construction / Commissioning:
Civil
Punch point attending works to complete.
Mechanical
Punch point close out.
Electrical
UEB # 1 & 2
De energizing of temporary transformer. Termination of cables for SUAT.
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 21 of 57
Punch point attending
Commissioning
Unit # 1 – Reliability run to start
Unit # 2 – DLN tuning.
Unit # 1 & 2 – Marks V1 e and DCS communication establishment through
Matrikon.
Instrumentation
Punch point close out.
Off Plot Construction:
AP07 to NIMR CENTRAL(TWIN ELM)
Shut down jobs at Tower location 2 & 3 and 34 & 35 to complete.
OPGW stringing works to complete.
Aviation light and sphere installation works to complete.
QUALITY ASSURANCE
Unit # 1 – Balance test pack submission for CO2, EDG and CEMS.
Unit # 2 – Test pack submission for Electrical and instrumentation
packages.
Unit # 1 & 2 – As built drawings submission and approval.
CONTRACT FINANCIALS:
Milestone 1 payment invoice submitted on 26.08.09 payment received on
05.10.09.
Milestone 2a payment invoice submitted on 26.08.09 payment received on
05.10.09.
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 22 of 57
Milestone 02B payment invoice submitted on 18.11.09, payment received
on 26.12.09.
Milestone 03 invoice submitted on 05.03.10, payment received on
09.04.10.
Milestone 02D payment invoice submitted on 10.04.10, payment received
on 28.05.2010.
Milestone 02C payment invoice submitted on 15.05.10, Payment received
on 14.06.10.
Milestone 05A payment invoice submitted on 24.04.10, payment received
on 28.05.10.
Mile stone 06A payment invoice submitted on 16.07.2010, payment
received on 06th
September 2010.
Mile stone 04 A documents submitted and approved, Invoice submitted on
19th
August 2010, payment received on 30th
September 2010.
Mile stone 05 B documents submitted for approval, payment received on
26th
December 2010.
Mile stone MS 04B completion certificate received. Payment received on
30th
April 2011.
Mile stone MS 06 C completion certificate received. Payment received on
30th
April 2011.
Mile stone MS 06 D completion certificate received. Payment received on
27th
August 2011.
Mile stone MS 06 E completion certificate received. Payment received on
27th
August 2011.
Mile stone MS 06 B completion certificate received. Payment received on
13th
September 2011.
Mile stone MS 07 B completion certificate received. Payment received on
23rd
October 2011.
Mile stone MS 05 C completion certificate received. Payment due on 12th
December 2011.
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 23 of 57
Mile Stone 07 A and 08 completion certificate received 50%. Payment
received on 9th
January 2012.
Mile Stone 07 A and 08 completion certificate for balance 50% received.
Invoice submitted for payment.
Mile stone 09 completion certificate for 50% received. Invoice submitted for
payment.
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 24 of 57
SECTION 4
APPENDICES
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 25 of 57
APPENDICES-I
PROJECT MILESTONE DATES
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 26 of 57
Project Milestone Schedule / Dates
Milesto
ne
Description Weight
-age
Amount
in
Million
R.O
Sch.
Comple
tion
Act
Completi
on date
Payment
Receive
d
Remarks
MS-1 Mobilization 6% 1.377 15-Aug-
09 15-Aug-
09 05-Oct-
09
MS-2a
PO for 3 critical items ( Generator transformer,GCB,6.6KV switchgear
6% 1.377 18-Aug-
09
18-Aug-
09
05-Oct-
09
MS-2b
PO issue for wooden poles and steel towers of OHL
4% 0.918 17-Nov-
09 17-Nov-
09 26-Dec-
09
MS-2c
Upon completion of issue of PO for remaining engineered item purchase order for electrical ,C &
4% 0.918 15-Feb-
10 02-May-
10 14-Jun-
10
MS-2d
Upon the completion of issue of PO for remaining engineered item purchase orders for mechanical
5% 1.147
13-Jan-10
25-Mar-
10
28-May-
10
MS-3 Site Establishment
5% 1.147 11-Dec-
09 02-Mar-
10 09-Apr-
10
MS-4a
Upon Completion of Engineering activities for Design review, IPF/HAZOP,SAFOP
2% 0.459 31-Mar-
10 19-Aug-
10 30 –
Sep-10
MS-4b
Upon Completion of Remaining Engineering activities
4% 0.918
29-Jul-10
16-Mar-11
30-Apr-11
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 27 of 57
Milesto
ne
Description Weight
-age
Amount
in
Million
R.O
Sch.
complet
ion
Act
Completi
on date
Payment
Receive
d
Remarks
Ms-5a
Upon Completion of following Civil work Amal power station site leveling & grading
2% 0.459 24-Feb-
10
15-Apr-
10
28-May-10
Ms-5b
Upon Completion of following Civil work UEB, GTP, GTG and Off base foundation.
10% 2.295 27-Sep-
10 27-Sep-
10
26-Dec-10
Ms-5c
Upon Completion of following Civil work balance foundation, fencing on plot and off plot, Road works.
3% 0.688 11-Mar-
11 10-Nov-
11
09-Jan-12
Ms-6a
Upon receipt at Site of following Equipment (including documentation) materials for OHL (wooden poles, steel towers, FOC)
4% 0.918
19-Jun-10
16-Jul-10
6-Sep-10
MS-6b
Upon receipt at Site of following Equipment (including documentation) ( Generator transformers,15/6.6KV transformer, Control & automation cable, bus duct )
10%
2.295 16-Nov-
10 25-Jun-
11
13-Sep-11
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 28 of 57
Milesto
ne
Description Weight
-age
Amount
in
Million
R.O
Sch.
complet
ion
Act
Completi
on date
Payment
Receive
d
Remarks
Ms-6c
Upon receipt at Site of following Equipment (including documentation)(GCB,6.6KV switchgear,415V switchgear,6.6KV cables & termination)
4% 0.918 3-Oct-10
20-Mar-11
30-Apr-11
Ms-6d
Upon receipt at Site of following Equipment (including documentation)( vent system ,drain system)
3% 0.688 22-Jul-
10
25-Jun-11
27-Aug-11
Ms-6e
Upon receipt at Site of following Equipment (including documentation)( DC and AC UPS, EDG, Instrument air compressor, DCS)
4% 0.918 03-Sep-
10
23-Jun-11
27-Aug-11
Ms-7a
Upon completion of 132kv switchyard works at Nimr West 132kv Substation including
2% 0.459 03-Nov-
10
Ms-7b
Upon completion of 132kv OHL’S
2% 0.459 23-Oct-
10 15-Jul -
11
23-Oct-
11
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 29 of 57
Milesto
ne
Description Weight
-age
Amount
in
Million
R.O
Sch.
complet
ion
Act
Completi
on date
Payment
Receive
d
Remarks
Ms-8
Upon completion of pre-commissioning of GTG package including all auxiliaries (pre-commissioning completed, ready for introduction of hydrocarbons)
5% 1.147 16-Jan-
11
30-Jan-12
Ms-9
Upon Substantial Completion of the Work for GTG Package
9% 2.065 05-Apr-
11
Ms-10
Upon Completion of the Work (Demobilization)
6%
1.377 04-Jul-
11
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 30 of 57
APPENDICES II
INTERGRATED OVERALL PROJECT SCHEDULE
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 31 of 57
APPENDICES-III
DRAWING CONTROL REGISTER
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 32 of 57
APPENDICES-IV
MATERIAL TRACKING REGISTER
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 33 of 57
APPENDICES-V
CRITICAL PROJECT MATERIAL LIST
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 34 of 57
APPENDICES-VI
HEALTH & SAFETY STATISTICS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 35 of 57
APPENDICES-VII
HSE AUDIT/INSPECTION SCHEDULE
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 36 of 57
# Subject Auditor Schedule
Month
Actual
Month
Remarks
1 Journey management
HSE Advisor + Site Manager
August 09 October 09
2 Road transport safety
HSE Advisor + Manager HSE+ Construction Manager
October 09
November 09
3 Lifting equipment and lifting gears
Site HSE Advisor + Project Manager
November 09
November 09
4 Welding and gas cutting
Site HSE Advisor + Corp. HSE Manager
December 09
April 2010
5 Catering Site HSE Advisor February 2010
March 2010
6 Welding Site HSE Manager March 2010
April 2010
7 Transportation of compressed gas cylinder
Site HSE Manager + Project Manager May 2010 May 2010
8 Radiography Site HSE Manager + Construction Manager
June 2010 Nov 2010
9 Scaffolding Site HSE Manager July 2010 July 2010
10 Waste Disposal Site HSE Manager Aug 2010 Oct 2010
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 37 of 57
APPENDICES-VIII
HSE TRAINING MATRIX
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 38 of 57
APPENDICES-IX
QUALITY INTERNAL AND EXTERNAL AUDIT
SCHEDULE
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 39 of 57
APPENDICES-X
SUMMARY OF PROGRESS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 40 of 57
DESCRIPTION MONTHLY
PLANNED
MONTHLY
ACTUAL
CUMULATIVE
PLANNED
CUMULATIVE
ACTUAL
ENGINEERING 100.00% 100%
PROCUREMENT 100.00% 100%
CONSTRUCTION 0.24% 0.12% 100% 99.58%
OVERALL 0.10% 0.05% 100% 99.85%
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 41 of 57
APPENDICES-XI
S-CURVE FOR ENGINEERING PROGRESS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 42 of 57
APPENDICES-XII
S-CURVE FOR PROCUREMENT PROGRESS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 43 of 57
APPENDICES-XIII
S-CURVE FOR CONSTRUCTION PROGRESS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 44 of 57
APPENDICES-XIV
S-CURVE FOR OVERALL PROGRESS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 45 of 57
APPENDICES-XV
S-CURVE FOR VOWD PROGRESS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 46 of 57
APPENDICES-XVI
MANPOWER & EQUIPMENT HISTOGRAM
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 47 of 57
APPENDICES-XVII
SUBCONTRACT DETAILS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 48 of 57
Sl no Description of subcontract Subcontractor
1 Design consultant Mott Macdonald & co LLC
2 Topographical survey AZD land survey LLC
3 Soil investigation Fugro middle east & Partners LLC
4 Lab Technician for soil testing Fugro middle east & Partners LLC
5 Grading and backfilling Sayouh Mahwees Trading and
contracting company LCC
6 Catering Socat universal sodexho
7 Pole hole drilling Ray Oman LLC
8 Block works & slope protection, Cable
trench works
Al Badea National trading & Cont.
Est
9 Block works Durat Al – Ghubra trading
10 Pole Hole drilling Powertech Engineering LLC
11 Rock Anchoring and Grouting for tower
foundation
IBN Salim Al Hadi trading
12 NDT Hi Tech Inspections services LLC
13 Back filling works & Cable trench works Harweel International LLC
14 Wadi protection works Al Badea National trading & Cont.
Est
15 Reaming works Singh Tool industries India
16 On plot Telecommunication M/s Bhawan projects and telecom
17 Off Plot Telecommunication ORB communications network LLC
18 Excavation and backfilling of tower
foundation
United International LLC
19 Tower Foundation concreting Global Design trading LLC
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 49 of 57
APPENDICES-XVIII
VARIATION REGISTER
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 50 of 57
APPENDICES-XIX
OMANISATION REQUIREMENTS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 51 of 57
OPAL – CVC certificate submitted to PDO.
All drivers shall be Omani nationals.
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 52 of 57
APPENDICES-XX
SPIR PROGRESS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 53 of 57
SPIR FORMS ATTACHED FOR FOLLOWING MATERIALS
125 V DC UPS
I P Bus Duct
142 MVA Generator Transformer
14 MVA M V UAT
1.6 MV LV Transformer
2.25 MV LV Transformer
240 V AC UPS
Generator circuit breaker
MAC system
HVAC system
Instrument air compressor
415 V GTP UAS
415 V GTP UAS Sub DB
6.6 KV MVUAS
415 V LVMCC
Emergency Diesel Generator
GTP skids
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 54 of 57
APPENDICES-XXI
PROGRESS PHOTOGRAPHS
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 55 of 57
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 56 of 57
MONTHLY PROGRESS REPORT
Doc. No: AML-394-AA-6944-0032-000
Rev. No : 01
Date: 25.04.12
Page 57 of 57