Americas Region Detector Hall CONVENTIONAL FACILITIES AND SITING T. Lackowski. 03/2012 CFS BASELINE TECHNICAL REVIEW. Please excuse use of this Old Drawing . - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

Americas Region Detector HallCONVENTIONAL FACILITIES

AND SITING

T. Lackowski

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 2: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

03/2012 CFS BASELINE TECHNICAL REVIEW

Please excuse use of this Old Drawing

Page 3: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

ILD 9000 shaft should read 10000

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 4: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

Cross Section ThruIR Hall

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 5: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

Cross Section Thru ILD Garage

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 6: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 7: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 8: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 9: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

Draft CFS TDR Preparation Schedule• XXX

XXX XXX

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 10: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 11: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 12: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

Cost of Shaft Excavation• Includes excavation, lining, pre-grouting

Costs are for projected depth FY 12 dollars

Cost of impact on crown not included Crown support cost may increase due to stress

concentration

Shaft Diameter in Meters

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 13: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

Detector Hall Excavation• RDR volume = 116,167 CM• Hall as shown = 121, 940 CM

Cranes and Platforms• ILD and SID Platforms in Hall• Additional Crane in Hall

Two 40 Tons, one in each Garage areas Plus one 40 Tons in IR Region

Additional Cranes in Building 4000 Ton Main Hoist Two 400 Ton. One in each Assembly Building Plus 40 Ton over Cryostat Shaft

03/2012 CFS BASELINE TECHNICAL REVIEW

Page 14: Americas Region Detector Hall CONVENTIONAL FACILITIES AND  SITING T. Lackowski

Global Design Effort - CFS

Catwalks and Access • All platforms and stairs/ladders for the Detector are

provided by each detector group• CFS will provide catwalk in IR Hall and access to cranes

Finishes (unless needed for structural support)• Floors

Cast in Place Concrete, Steel Troweled Finish Walls

Formed Cast in Place Concrete in IR Hall Shotcrete in Garage Spaces

Roofs Shotcrete, Rolling Drip Ceilings at shafts

Platforms Four platforms, two in IR Hall and two at surface to be in

CFS costs, including moving system.

03/2012 CFS BASELINE TECHNICAL REVIEW