alternative dispute resolution and arbitration

Upload: sa-reddi

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    1/11

    Alternative Dispute Resolution and Arbitration

    Some Personal Experiences

    S.A.ReddiDy.Managing Director (retd), Gammon India Ltd

    Introduction

    Indian construction contracts have traditionally been based on the Indian Contracts Act

    1872. Though in force for more than a century, there has been hardly any worthwhileamendment to reflect the societal changes that have taken place particularly after

    independence. The concept of master servant relationship is still reflected while

    interpreting many provisions of the Contract Agreement. Same is the case in respect of

    General Conditions of Contract. Every State P.W.D., every Department of CentralGovernment, every Public Section Undertaking, whether State or Central and every

    Consulting Engineers / Architects have their own Standard Conditions of Contract.

    There are more than 100 such documents in operation in India.

    Each of developed countries operates not more than five different sets of General

    Conditions of Contract. FIDIC General Conditions of Contract closed the gap further,bringing it to a single set of General Conditions of Contract. Majority of the International

    Contracts and domestic contracts in many countries are based on FIDIC; not so in India.

    Even International financial institutions such as the World Bank, Asian DevelopmentBank, etc. have standardized their General Conditions, broadly based on FIDIC

    FIDIC Conditions of Contract

    FIDIC conditions hold a reasonable balance between the requirements & interests of the

    parties concerned. FIDIC allocates fairly the risk & responsibilities between thecontracting parties. The contracting parties will react favorably to clearly statedobligations. Avoids unsatisfactory performance, increased costs & disputes

    FIDIC conditions address generic issues concerning in project implementation:

    o Working relationship between different parties, protocol for communication

    o Rights & obligations of employers, contractors

    o Insurance risk mitigation & risk sharing

    o Quality Control, Engineering & structural failure

    o Delays, damages, Claims, Disputes

    o Safety, security of plant, machinery & personnel

    Uniqueness of Construction Activity

    Every construction project is unique; no two sites / designs are alike. The quality of the

    Employers, Consultants, Contractors vary widely. The construction period is decided

    on adhoc basis and not based on any scientific system. There are uncertainties in land

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    2/11

    acquisition, Right of way, Law and order, conflicts between state and central

    Government, vagaries of weather and a host of other issues. Every construction

    contract is uniquely related to a particular site & ground conditions which may notbe fully defined when the work is designed. Despite modern methods of site

    investigation, uncertainties exist throughout the operation of contract. Construction

    work is exposed to weather and subject to its constraints. Claims arise out of aboveuncertainties, among others.

    Claims in Civil Engineering Contracts

    Claims appear to be inescapable components of almost all construction contracts. A

    successful claim may turn the fortunes of the contract; or indifferent processing may be

    sufficient to turn profit into loss. Claims may be negotiated, amicably settled or may leadto arbitration or litigation.

    A claim is a request, within an existing contract, for additional payment, or additional

    time, for a task which is additional to agreed work & for which the existing contract doesnot make provision- or does not appear to do so. Claims may be

    o For additional payment or for additional time to complete the contract (Time,

    Money, or for both time & money)

    o Due to design changes, changes in working circumstances, changes to contract

    conditions.

    oFor events that do not affect the current work, but which can bring all work to a

    standstill in future

    Claims may arise out of Contractual Right, Breach of Contract - The Reasonable

    Expectation, Oversights and Omissions in the contract agreement etc.

    Disputes

    A dispute is a disagreement that arises out of an agreement. In construction industry,

    disputes are unavoidable despite best of intentions, due to large number of uncertainties.Provisions for settlement of disputes are laid down in the contract agreement. Mere

    silence may amount to repudiation in many cases. Disputes which are capable of

    reference to arbitration must necessarily arise between the parties in respect of a definedlegal relationship, whether contractual or not

    The Arbitration and Conciliation Act, 1996

    The Arbitration Act of 1940 was being adopted in contracts until the Act was revised in

    1996. There have been numerous complaints about the unsatisfactory nature of the

    earlier Act. There were many untenable provisions concerning challenging the award.Neither party was satisfied. In almost all cases, the award used to be challenged.

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    3/11

    The 1996 Act is based on UNCITRAL (United Nations Commission on International

    Trade Law) covers International / Domestic Arbitration and Conciliation and provides for

    reasoned award, minimizes the supervisory role of Courts, permits mediation,conciliation etc during arbitral proceedings to encourage settlement of disputes

    Award is enforceable as if it were a decree of the court.

    Grounds for Challenge

    Award is in conflict with the Public Policy of IndiaA party is under some incapacity

    The arbitration agreement is not valid

    The party is unable to present his case

    The dispute does not arise out of contractThe subject matter of the dispute is not capable of settlement by arbitration under the law

    An interim award is permitted but reasons for the award shall be stated. The award may

    include, in the sum for which award is made, interest at such rates as it deems reasonable,on the whole or part of the money, for the whole or part of the period. The sum shall,

    unless the award otherwise directs, carry interest @ 18% p.a. from the date of the awardto the date of payment

    Enforcement of the Award

    Award shall be final and binding on the parties. Award shall be enforced under the Code

    of Civil Procedure, 1908 as if it were a decree of the court; in case award is neither

    challenged nor payment made, execution petition can be filed in court. Unfortunately,the reality is not that simple. Almost all the arbitration award relating to construction is

    challenged and the dispute takes a long time to get resolved. Despite the well intended

    provisions of the 1996 Act, habits die hard; there are numerous cases of the Awardsbeing challenged, mostly on grounds that the Award is in conflict with the Public Policy

    of India. Alternatives are being considered, including Dispute Resolution Board,

    Mediation etc.

    Dispute Resolution Board (DRB)

    DRB is formed at the very beginning of the Contract operation, before disputes arise.DRB Members have strong construction & technical background, have no interest in

    taking sides and can come up with more equitable findings than the arbitrators without

    such background. Disputes are settled during construction, relieving owners, contractorsfrom entering into litigation. Parties are expected to get quick, early read on what to

    expect if dispute moves to arbitration or litigation. Parties can resort to arbitration if not

    satisfied. Expenses are very low as compared to those of arbitration, results in lower bidprices and reduction in number of claims.

    In case of failure to agree upon appointment of DRB, the appointing entity or official

    named in the Contract Agreement shall, upon request of either or both parties and after

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    4/11

    due consultation with both parties, appoint this member of the DRB. This appointment

    shall be final and conclusive.

    Some selected Case Histories:

    Some of the case histories have been selected, reflecting various aspects of arbitration,

    conciliation, alternate dispute resolution, etc. The description is based on theauthors involvement in many of the cases cited

    Case 1: Bassien Creek Bridge, Mumbai

    Contract awarded based on tenders without PQ. The Contractor was financially sound but

    new to bridge construction in marine environment. He employed a British consultant for

    designs. There was a vacuum regarding construction. Two caissons collapsed duringsinking; could not be corrected. Contract terminated at the contractors risk and cost

    Fresh tenders invited. Alternative layout was adopted to avoid two failed foundations.

    Bridge completed by the second contractor in three years, at more than double the

    original cost. The first contractor raised a dispute. Arbitration award was in his favour,despite the PWDs intention to recover the cost. The Contractor kept contemporary

    records and appointed a senior legal counsel to fight the arbitration case.

    Case 2: NHAI contracts - Ambiguity in price variation clauses

    There were more than 100 contracts spread over the country, but no uniformity in

    drafting price variation clauses. In consequence, some contractors were paid for pricevariation while others were denied. This resulted in stalemate & retarded progress; some

    contractors suspended work pending settlement of dispute. The matter is under

    arbitration.

    There was abnormal price rise in steel and the price variation clauses were based on

    indices which did not reflect a ground reality. Many Contractors typically lost several

    crores of rupees. Matter referred to arbitration. Results are uncertain; even if thearbitrator awards, the same will be challenged by the aggrieved party.

    Case 3: Pamban Bridge, Tamilnadu

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    5/11

    History of Tendering, Construction, Revised Tendering, Arbitration

    The first Contract was awarded in 1974 to a local Contractor, competent but with noexperience in bridges in marine environment. Contract terminated mid-way due to non-

    performance. The Contractor contented that delay was due to cyclones and referred the

    dispute to Arbitration. Almost the full value of contract was awarded in favour of thecontractor. Award contested by the Department. After attempting departmental work

    unsuccessfully, the job was re-tendered and awarded to the Second Contractor.

    Contract was not awarded within validity period; repeated extensions sought from lowest

    bidder who was reluctant as in the mean while he had better opportunities elsewhere. He

    offered a conditional extension; if the job is not awarded within the extended period, the

    contract price will be increased by 10% for each month of delay in award of work .thecontract price was increased on account of delayed acceptance of the tender.

    The second contract (1984-88) involved few months time overruns; extension granted

    with proviso of no payment for escalation. Dispute referred to sole arbitrator in 1992settled in 1995. The employer challenged the award. The court ruled in favour of the

    contractor. The employer appealed; pending decision, court directed payment of Rs 25lacs + other Rs 25 lacs against BGB. Final decision is pending (2008)

    Case 4: Mandovi Bridge, Goa

    The old bridge, completed in 1970 collapsed in 1986 due to corrosion of reinforcement.

    Government decided to re-commission the bridge by dismantling the deck and piers andconstructing new piers and decks on existing foundations which were assumed to be safe.

    Tenders were invited in 1986 for based on FIDIC Conditions; unconditional offer

    requested which was complied with.

    LOA contained additional stipulations, despite the bidder offering unconditional quote.The Employer wanted stacking & disposal of debris at locations decided by the

    Engineer Bidder treated LOA as counter offer and declined. After protracted discussions;the conditional LOA was withdrawn and a new unconditional LOA was issued

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    6/11

    Case 5: Trombay Power Plant Civil Works

    Dispute Resolution by Amicable Settlement

    Issue No.1: short weight of cement

    As per tender documents, cement bags as

    received from the manufacturers will be

    issued to the Contractor; no claims will beentertained regarding any shortage in weight

    Actually, cement (packed in jute bags) issued to

    the Contractor had a shortfall of 5 10%. Dueto weigh batching, contractor had to make good

    the shortfall by using more bags of cement.

    The Employer recovered cost of cement from contractors bills without considering theshortfall in weight. Contractor claimed for the excess number of bags actually used.

    Owner rejected claim, citing the Special Conditions of Contract. Contractor rebutted byciting Technical Specifications of the Contract IS 456 and IS 8112

    Issue 2: Dispute regarding reinforcement wastage :

    Reinforcement steel was supplied by Owner. Wastage % specified in contract with penal

    recovery for unaccounted wastage. Large wastage was experienced during execution,

    due to varying column heights, beam spans, etc. Contractor protests penal recovery;since no detailed drawings were issued during tender, no allowance made in tender

    for increased wastage

    After completion the disputes were resolved by amicable settlement. Owner appointed a

    committee of two General Managers not connected with the project, said the claim will

    be accepted if Contractor was able to convince the committee, else Contractor wouldhave to give up his case. A Gentleman's agreement!. Contractor accepted the conditions

    Cement is an essential commodity, falls under Essential Commodities Act. Contractor

    cited the provisions of the Act and possibility of criminal prosecution. Owner retaliatedthat cement was not supplied by him but by the cement manufacturer. Contractor argued:

    since Owner recovered cost of cement from contractor, he was the supplier

    Construction drawings for various structures were prepared and issued by the

    consultant after the award of the work. Variety of column heights, beam spans etc

    resulted in substantial cut pieces of the reinforcement and consequent increase inwastages not contemplated at tender stage. Contractor submitted such increased

    wastages should be to the Owners account.

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    7/11

    The issues were amicably settled after only three sittings of the committee within one

    month. After careful consideration, Owner accepted contractors contentions on both the

    issues. The cost of additional bags of cement used due to short weight of cement bagswas reimbursed. Owner waived the penal recovery for excess wastage of reinforcement

    steel beyond the percentage stipulated in the contract.

    Case 6: Dam Project in Meghalaya

    Contract for construction of two dams, 15 km away from each other, awarded in 1977and completed in 1982. Three separate disputes were referred to arbitration in 1984:

    Compensation for Suspension / Stoppage of work

    Basis of Payment for extra work due raising of height of dam

    Claim for extra payment for aggregates

    Dispute 1: There were intermittent suspensions of work due to delay in power supply,

    explosives, cement & steel by owner. The following issues were referred to arbitration:

    - Whether compensation is payable for suspension in either of the two Damsindividually or together

    -.Basis of compensation for suspension beyond 12 hrs: simultaneous application ofhourly rate & flat rate in a day or only on daily basis

    - Payment of escalation on compensation amount

    Contractor argues: Dams on separate rivers, 15 km apart, different site conditions.

    Suspension at one site would affect performance of contract

    Owner: As it is one composite contract, compensation clause would be effective only if

    work simultaneously stopped at both dam sitesAward upheld contractors compensation claim for suspension of work at either dam;

    simultaneous suspension at both dams not relevant

    Contract provided for two rates of compensation - an hourly rate for suspension up to 12

    hrs and per diem rate for suspension beyond 12 hrs

    For suspension beyond 12 hrs, Contractor claimed hourly rate for 12 hrs + per diem rateAward: Compensation for suspension / stoppage of work beyond 12 hrs in a day payable

    on per diem rate only

    Escalation on Compensation

    Contractors argument: Claim raised for labor wage escalation which was not covered in

    compensation ClauseArbitrators decision: Not entitled.

    - Contract clause silent on escalation

    - Compensation for suspension is a matter different from contractors right to bereimbursed on account of increased labor cost during suspension period

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    8/11

    Dispute 2: Raising the dam level

    Employer decides to raise height of dam by 8 m. Contractor asks for revised rateThe Employer makes provisional payment at revised rate subject to arbitration on

    following issues:

    - Whether work involved in raising the dam is within scope of contract.- If outside the scope, the rate payable

    Contractors argument: Tender rates worked out as per drawings issued by the Owners

    which clearly showed the height of dam, 704.26 mAward was given in favor of Contractor in 1990. These works to be paid at rates, terms

    and conditions already agreed to earlier with interest at 12 % p.a.. Award made Rule of

    Shillong Court. The Owners refuse to pay interest due. The issue is pending with District

    Court, Shillong for 13 years after the original award, several years after the concernedwork was executed & for 28 years after commencement of the work!!!

    Dispute 3: Extra lead for aggregates

    Contract envisaged collection of sand from 3 km upstream. Due to raising the damheight, the sand quarry submerged. Further sand was collected from lead of 55 km.

    Contractor claimed for increased cost (96 lacs). Owner refused to pay the amountContractor completed the work and the dispute is under arbitration since 1991

    Establishment of stone quarry: The project was located in Meghalaya (Assam-MeghalayaBorder).Contract specified stone quarry in Meghalaya. Mid way through the project,

    the State Government closed the quarry and subsequent procurement was done from

    quarry in Assam. Increased lead paid for by the Owner; relocation cost (Rs.27 lacs)

    denied. Matter referred to Committee set up by Owner. Committee recommends Rs.20.5 lacs; rejected by Owner. Matter referred to arbitration in 1991

    Employer brought stay-order in 1996 against arbitration proceedings citing misconductby contractor. Stay-order not vacated till 2005. Contractor appealed to Court to vacate

    stay order. Subject pending for 14 years after commencement of arbitration!!!

    Case 7: Ganga Bridge Patna 5575m, 4 Lanes

    Claim due to Introduction of PF settled by Conciliation

    PF rules applicable to construction labor were brought into force after award of the

    contract & during construction. Contractor claimed for additional expenses involved in

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    9/11

    enforcing PF rules including the Employers Contribution. The contract conditions

    included reimbursement of extra expenditure due to legislative changes. The Employer

    was unwilling to accept despite prolonged correspondence and justification. One optionwas to refer to arbitration, along with other outstanding issues; project completed in

    1992, the arbitration process is still on in 2008! Instead the issue was taken up directly

    with the Provident Fund Commissioner. Using the Commissioners goodwill it waspossible to settle the claim (Rs.3 crores) mutually

    Changes in Labour Laws Dispute referred to arbitration

    The contract provided for compensation due to variation in prices of labour, materials,

    and POL. Any changes in labour laws and regulation attracted price variation. During

    operation, the number of working hours for labour was reduced from 9 to 8 byLegislation. Disputes arose concerning compensation. Matter is under arbitration (as on

    2008), even though the event occurred 30 years ago.

    Cess on Construction Power generated by the Contractor: Dispute settled bynegotiations with the State Government

    The Contractor obtained the power connection from SEB for operating construction

    equipment. The State Electricity Board supply was erratic, with frequent variations in

    voltage. These necessitated installation and operation of diesel generators by theContractor exclusively for fulfilling the bridge construction contract. However, the State

    Electricity Board demanded payment of electricity duty for the power generated by the

    contractor plus penalty. Though specifically exempted in the contract, SEB brought legal

    action, attaching all construction equipments. All works came to a stop and there was afuror in the local press. The Chief Minister intervened, conducted negotiations with all

    concerned and got an Ordinance issued, specifically exempting Ganga Bridge at Patna

    construction from the purview of the concerned provisions of the Electricity Act

    Applicability of Factories Act to construction:

    The definition of Factories Act is all pervasive. Any establishment employing 20 / 10

    persons with power is deemed to be a factory. Bridge construction involves labor &

    power. The Inspector of Factories defined the bridge construction as a factory! A notice

    was served on the Managing Director and all other Directors for non compliance ofprovisions of the Factories Act. .

    Mines Act applied to bridge construction:

    The foundation construction involved dredging of soil from inside the well foundations.

    Mines department demanded royalty for mining soil (a state property) from belowground. The dredged soil was mostly refilled inside the dredge hole after sinking the well

    foundation. Mines department demanded royalty once again for using state property for

    bridge construction

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    10/11

    The disputes were settled after prolonged litigation

    Case 8: A Bridge in UP - Constructed in 1960

    The project was completed with 8 months time overrun; full extension granted by the CE.

    However the SE is the Engineer as per contract. Due to personality conflicts, the SEgranted extension of time for 7.5 months and imposed penalty for balance 15 days; matter

    referred to arbitration. The arbitrator upheld the SEs decision

    Case 9: Irrigation Project in Orissa - Completed in the Early Sixties

    Daily labour working hours reduced from 9 to 8 after the award of contract; the Employer

    refused to compensate. Claims referred to arbitration. After more than 10 years oflitigation at various courts including the Supreme Court of India, the award went in favor

    of the contractor. The State government still refused to honor the award. The Contractor

    resorted to extreme measure of threatening to attach the government treasury to get paid

    Case 10: New Pattao Bridge at Goa Arbitration case

    The Contract was awarded in 1983. Due to collapse of Old Mandovi Bridge, Goa in

    1986, the authorities decided to revised the design criteria for the New Patto Bridge

    halfway through the contract. The revisions resulted in time and cost overruns;Contractor submitted claims in 1989 Rs.120 lacs. The negotiations were started and a

    compensation of Rs.90 lacs was almost agreed upon but not implemented due to

    procedural wrangles. The dispute was referred to arbitration in Aug 94. The Contractor

    claimed escalation for the time overrun of more than 100% due to exceptional changes indesign. This resulted in prolonged arbitration proceedings, challenge of the award, court

    cases etc during the next 10 yrs. The contractor ultimately received payment of Rs.1.91

    crores; including interest of more than Rs.1 crore.

    Case 11: Dam Project in Bihar

    The contract was awarded in the Nineties. The Employer paid mobilization advance and

    the contractor mobilized equipment, staff etc and actually commenced the work. In the

    meanwhile, the Employer ran out of funds. Further works suspended by the contractor

    indefinitely. The Contractor tries to remove his idle equipment but the Employer objectedand filed criminal case against the contractor, terminated the contract and declined to

    release the contractors equipment from site, blacklists the contractor. The disputes were

    referred to Court, arbitration in 2002, dormant in 2008!

    Issues referred to Arbitration by the contractor included:

    - Refund of mobilization advance

    - Reimbursement due to breach of contract on account of abandonment of work

    - Compensation on idle time, post-termination

    - Reimbursement of the overhead charges

  • 7/29/2019 Alternative Dispute Resolution and Arbitration

    11/11

    - Reimbursement of unrealized profit

    - Loss and humiliation due to criminal case

    - Interest by way of damages

    Case 12: Narmada Bridge at Kasrawad, MP - Narmada Bachao Andolan

    One km long bridge contract was awarded in the Seventies. After the site was established,

    there were obstructions to work by the Andolan, colony and offices were burnt down.

    The work was suspended for several years. When peace returned to site, the originallyquoted rates were found not workable; however; the Employer insisted on completion at

    old rates, resulting in suspension of work for several years The work was resumed after

    several years. After protracted negotiations for revision of rates spanning over a decade;

    the rates were increased by 83% and the bridge completed.

    Epilogue

    The experience of settlement of disputes through arbitration in India has been mostdisappointing Most of the arbitration awards are challenged, citing Public Policy of

    India, despite the 1996 Arbitration Act. Mediation, conciliation appears to be better.Dispute Resolution Board concept needs encouragement; both parties should honour the

    DRB decisions