Identifying Information
Project Title - ALTERNATIVE LEARNING SYSTEM (ALS) FOR A BIG CHANGE (ALS ABC)
Project Beneficiaries - Approximately 700 OSYA aged 8 to 60 and over
3 - District Supervisors 49 - School Heads
3 - District ALS Coordinators 49 - ALS Coordinators (School Level)
3 - Mobile Teachers 5 - Instructional Managers/
Literacy Facilitators
Project Duration - CY 2010 – 2013 (3 years)
Proposed Budget - Year 1- 2010 – 2011 P 400,000.00Year 2- 2011 – 2012 P 500,000.00Year 3- 2012 – 2013 P 600,000.00
Sources of Funds - Local School Board/Special Education FundSchool/Division MOOEDonors and Benefactors
Project Proponents - Divina F. Borbon, Ph.D.Education Supervisor I (Alternative Learning System)
Ma. Luz M. de los Reyes Asst. Schools Division Superintendent
DepEd, Division of Roxas City
Contact Person - DR. JESSE M. GOMEZ, CESO VSchools Division SuperintendentDepEd, Division of Roxas CityBanica, City of RoxasContact Number: Telefax - (036) 6210 -360
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
1
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
I Background/Rationale
Family Mapping result reveals that in the locality, drop outs of every school year do not go back to school for reasons like: distance of school from home, lack of education of parents, child labor, sickness, malnutrition, etc., which are mostly attributed to poverty.
For SY 2009 – 2010 alone almost 10% of high school students dropped out of school while the rest of the out-of- school youth who dropped from school in the last 5 years have not been recorded and traced as to their whereabouts and status in the community – whether they have been working or enrolled in other municipalities and cities.
ALS Surveys and Family Mapping were conducted to know where the children and OSY of Roxas City and these number shall become the target clientele of the project “ALS ABC” for Roxas City. Approximately there are seven hundred (700) OSYs and adults aged 8 to 60 years old potential learners for ALS. This number shall compose the students in the Basic Literacy and Functional Literacy Programs of the ALS managed by the Education Supervisor of ALS (1), District ALS Coordinators (3), School ALS Coordinators (49), Mobile Teachers (3), and Instructional Managers and Literacy Facilitators (5).
Other clientele will come from the pupils/students who drop out of the formal school of the current school year. They will be transferred to ALS after screening and evaluation is conducted. (N.B. Mechanics of the Program is enclosed, for approval by the authorities.) Proposed project is patterned from “Sagip Eskwela” of Ilocos Region in support to Project REACH (Reaching All Children) of DepEd in the attainment of Millennium Development Goals (MDG) of 2015.
II Objectives
In support to MDG 2015 and Project REACH of the Department of Education, project “ALS ABC” for Roxas City will be implemented starting CY 2010 – 2013 with the following objectives:
To arrest increasing incidents of drop-out, particularly in the secondary schools;
To increase participation in the schools; To provide access to education, especially to those who are
underprivileged and underserved; To increase literacy rate in the City of Roxas;
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
2
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
To provide basic literacy programs to adults and functional literacy to out-of-school youth;
To improve performance indicators of the department (i.e. drop-out rate, retention rate, survival, participation and literacy)
Goals:
improved participation and retention; zero-illiteracy in 2013
III Project Components
A. Awareness and Advocacy Campaign and Community Involvement
Awareness and advocacy campaign will be done in all barangays of Roxas City. ALS Summit will be held in the Division to be participated in by community and barangay officials, local government officials, prospective and active donors and benefactors and non-government organizations which are into programs and projects in support to literacy and livelihood programs of the Department of Education. Streamers and Flyers will be prepared to enhance the drive. For CY 2010, Summit shall be held sometime September or October and for the next 2 years summits will be held sometime in February or March.
Proposed Budget for this component is P 78,140.00 for CY 2010 only. (Copy of the Proposed Budget is also enclosed for approval.)
B. Training Workshop
Training Workshop will be attended by School Guidance Counselors (49), Instructional Managers/Literacy Facilitators (5), Mobile Teachers (3), School ALS Coordinators (49), District ALS Coordinators (3), School Heads (49), District Supervisors (3) and Supervisor (1). They shall be trained on the mechanics of implementation of project “ALS ABC” as patterned in the Sagip Eskwela. This training will be conducted once every calendar year in December in preparation for the next calendar year.
This component proposes a budget of P 35,641.00 to cover subsistence, supplies and materials.
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
3
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
C. Reproduction and Provision of Modules, Reviewer, Practice Set and Forms
The Project will require modules, reviewer, practice sets and forms to be accomplished and utilized both by students and teachers. These are Basic Literacy materials of 43 modules; Accreditation and Equivalency, 141 modules; Reviewer for elementary and secondary, 75 copies; Practice Set for elementary and secondary, 475 sets; and different forms to be accomplished for entry and reporting, 472 sets; and copies of CD/school, 51.
The materials shall be replenished once destroyed/damaged; thus a new budget for materials will be necessary every calendar year of implementation. Three-Year and Annual Implementation Plans are enclosed for reference.
Proposed budget for this component is P 165,454.00.
D. Assessment and Evaluation of Clientele
Prospective clientele shall be assessed in order to provide appropriate intervention and instruction as to categorization: Basic Literacy vs Functional Literacy and Accreditation and Equivalency (A & E).
Assessment result will determine placement of students and adults. As regards students who drop out school of the current school year and prefer to be enrolled in the ALS, they shall be screened in terms of age, level of literacy, address, and certification of the barangay captain or employer, that the student or adult is working and thus there is a demand to transfer for reasons of work, distance from school, etc. that hinder attendance in the formal schooling. Students who are below 18 shall be required to present parent’s consent. In the absence of parents, a close relative or guardian will issue the consent.
Post test will also be given to clientele to determine readiness for the A & E Test
E. Implementation of project “ALS ABC” in Roxas City
The Project will be implemented in all schools and barangays in Roxas City under the supervision of Department of Education, Division of Roxas City. The Project will run for three (3) years – CYs 2010 – 2013. This will be initially funded by the Local School Board - Special Education Fund (SEF) and Division/Schools MOOE and is hoped to gain and gather support by the NGOs, Donors and Benefactors in the following years.
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
4
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
F. Monitoring and Evaluation
Project “ALS ABC” will be monitored by District and Education Supervisors, School Heads (Please refer to the implementing structure of this proposal.), and DepEd Regional and Central Offices. Implementation will be reported care of the Bureau of Alternative Learning System and the ALS Division of the Regional Office.
Monitoring at the Division Level shall be headed by the Project Proponents under the Office of the Schools Division Superintendent. Implementing Structure follows for your reference.
Evaluation of implementation shall be done every quarter: September, December and March of the SY.
IV Implementing Structure
Roles Tasks/Responsibilities Name
Project Director
Approves plans/proposals
Oversees project implementation
Approves/allocates budget
Sources funds
Establishes linkages with donors and benefactors
Submits reports of progress
Hon. Angel Alan B. CelinoCity Mayor
Dr. Jesse M. Gomez, CESO VSchools Division Superintendent
Asst. Project Director
Hon. Emmanuel Billones, Jr.City CouncilorChair, Committee on Education
Project Managers
Proposes project for approval
Prepares annual and three year implementation plan
Ensures implementation of components in the districts and schools
Coordinates plans with the schools, district, division, central office and with the local government
Provides technical assistance to
Hon. Ronnie T. Dadivas City Vice Mayor
Ma. Luz M. de los Reyes Assistant Schools Division Superintendent
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
5
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
implementers
Monitors and evaluates project
Prepares progress reports
Asst. Project Manager
Divina F. Borbon, Ph.D.Education Supervisor IAlternative Learning System
Division Project Coordinators
Monitors implementation of the project in the schools/district
Consolidates reports and submits to the Asst. project manager
Recommends and suggests interventions, solutions or next steps
Mrs. Nerissa A. ResenteDistrict Supervisor – District I
Emma P. PagdilaoDistrict Supervisor – District II
Annabelle R. DelfinDistrict Supervisor – District III
Administrators in-Charge of ALS
Monitors implementation of ALS classes
Supervises classes
Assists District Supervisors in monitoring and supervision
Prepares and submits reports of the schools in the district
Dr. Jocelyn D. SunsonaDistrict I
Amparo D. DivinoDistrict II
Antonia P. CapapasDistrict III
District ALS Coordinators
(DALCs)
Advocates the program
Organizes Classes
Conducts orientation
Conducts Classes
Submits reports on status of program
Assesses learners
Conducts A & E
Keeps track whereabouts of completers and passers
Erleenmeyer B. ArigoraDistrict I
Clemencia A. DivinaDistrict II
Nida A. AlbaDistrict III
School ALS
Conducts classes for ALS
Handles would –be drop outs of the school following the scheme in the 49 teachers in the formal
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
6
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
Facilitators implementation of the project
Submits reports
Conducts class assessment
school with additional load for the implementation of ALS program
Division ALS Data and BEIS Coordinators
Consolidates data coming from the districts
Analyzes data
Publishes data
Prepares tables, graphs and analysis for submission to authorities and stakeholders
Noraida A. MalawiPlanning Officer IIDepEd Roxas City
Nicasio S. FrioEducation Supervisor I(ICT, Research & Secondary Science)
Division Accountant
Checks in-flow and out-flow of cash during the pre, during and post implementation
Recommends approval of budget for training, seminar, orientation, etc. for teachers and project management team
Rosana L. MartizanoAccountant II
V. Budget/Sources of Funds
Refer to Annex B for the Budget Proposal for Project “ALS ABC”
VI. Sustainability Plan
The project shall run for three (3) years to commence in SY 2010 – 2011 and to end in SY 2013 – 2014.
Project gains shall be sustained by schools thru its local community initiatives such as support from the local school board and external benefactors like, foundations, benefactors/donors, etc.
Review and evaluation of the project Plan shall be done every school year.Impact study shall be conducted towards the end of the project by the
Research and ALS Supervisors. Best practices shall be recognized and published. These shall be reported to
the Regional and Central Offices. Gains shall be the bases for recommendation for institutionalization.
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
7
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
Project Alternative Learning System (ALS) for A Big Change (ALS ABC)
Proposed by:
DIVINA F. BORBON, Ph.D.Education Supervisor I (ALS)
Asst. Project Manager
MA. LUZ M. DE LOS REYESAsst. Schools Division Superintendent
DepEd City of RoxasProject Manager
___________________________________________________________________
APPROVED:
DR. JESSE M. GOMEZ, CESO VSchools Division Superintendent
DepEd Division of Roxas CityProject Director, DepEd
HONORABLE ANGEL ALAN B. CELINOCity Mayor
City of RoxasChair, Local School Board
Project Director, LGU
______________Date:
Attachment A to project ALS ABC
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
8
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
MECHANICS OF THE PROGRAM
1. Identification of the probable drop-outsThe teachers of the formal school will identify probable drop-outs in
their classes. With the approval of the principal, these pupils/students will be referred to the guidance counselor for counseling and will be indorsed to the school ALS coordinator for possible entry to the ALS program
2. Communication to parentsThe guidance counselor will write a formal letter of invitation to the
parents regarding the status of their children in school
3. Orientation of parents and students about the ALS programThe school ALS coordinator will conduct orientation to the parents and
students on the details of the ALS program: its objectives, delivery modes, materials used, target learners, etc. and other benefits the children could avail from the program
4. Drop- outs in the formal school will be transferred to ALSThe pupils/students who would like to transfer to the ALS program will
not be dropped from the list but rather be noted “transferred to ALS” in the School Register (Form I) of the teacher.
5. Registration to ALS programThe probable drop-out pupils/students will then be formally enrolled to
the ALS program
6. Implementation of ALS programThe school ALS coordinator will organize ALS classes. Pupils/students
will sign Individual Learning Agreement (ILA) as to their learning goals and availability of time for their learning session in the school ALS center
7. Those not in the formal/ALS program will be dropped from enrolment list.
Pupils/students who are no longer attending either in the formal or ALS classes will be marked “dropped” in the School Register (Form I)
8. Granting option to pupils/students
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
9
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
If pupils/students choose to go back to the formal school, he/she will return to the grade/year where he/she was enrolled
9. Conduct of the Accreditation and Equivalency (A&E) Test In the conduct of the Accreditation and Equivalency (A&E) Test,
learners aged 12 years old and above in the elementary level and 15 years old and above in the secondary level will be encouraged to take the test. Elementary level passers are accredited and their schooling is equivalent to elementary graduates while the secondary level passers are accredited and their schooling is equivalent to secondary graduates.
Prepared by:
DIVINA F. BORBON, Ph.D.Education Supervisor I (ALS)
Asst. Project Manager
MA. LUZ M. DE LOS REYESAsst. Schools Division Superintendent
DepEd, City of RoxasProject Manager
___________________________________________________________________
APPROVED:
DR. JESSE M. GOMEZ, CESO VSchools Division SuperintendentDepEd, Division of Roxas City
Project Director, DepEd
HONORABLE ANGEL ALAN B. CELINOCity Mayor
City of RoxasChair, Local School Board
Project Director, LGU______________
Date
Attachment B to project ALS ABC
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
10
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
Republic of the PhilippinesDepartment of Education
Region VI – Western VisayasDIVISION OF ROXAS CITY
City of Roxas
BUDGET FOR PROJECT ALTERNATIVE LEARNING SYSTEM (ALS) FOR A BIG CHANGE (ALS ABC)
I ADVOCACY CAMPAIGN P 78,140.00
A. Streamer (Tarpaulin)
47 pcs. Posters for 47 barangays @ P1,000.00 = P47,000.00
B. Flyer
Basic literacy Program (BLP) No. of copiesBarangay - 47LGU - 10Elementary & Secondary
Schools - 47Division & district Offices - 10 = 114 @ P5.00 = 570.00
Accreditation & Equivalency (A&E) SystemBarangay - 47LGU - 10Elementary & Secondary
Schools - 47Division & district Offices - 10 = 114 @ P5.00 = 570.00
C. Summit
Alternative Learning System (ALS) SummitSnacks and Lunch for 150 persons @ P200.00= 30,000.00
P 78,140.00
II TRAINING WORKSHOP P 35,641.00
A. Training
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
11
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
Pax RS 1st Day - Guidance Counselor & 5 LFs 52 6 = 58 @P200.00 =P11,600.00
2nd Day-Schools ALS Coor. & 5 LFs 52 6 = 58 @P200.00 = P11,600.00
3rd Day –Sch. Heads, PSDS & 5 LFs 55 6 = 61 @P200.00 = P12,200.00
B. Materials & Suplies
2 pcs. pentel pen @ P50.00 = P100.00
4 pcs manila paper @ P10.00 = P 40.00 4 pcs. cartolina @ P10.00 = P 40.00
1 pc. whiteboard pen @ P61.00 = P 61.00 = P 241.00
P 35,641.00
III REPRODUCTION OF MODULES, REVIEWER, PRACTICE SET AND FORMS P165,454.00
A. Basic Literacy (BLP) 43 modules @30.00 =P1,290x21sets = P27,090.00
B. Accreditation & Equivalency (A&E) 141 modules @P30.00 =P4,230.00x22 sets = 93,060.00
C. ALS reviewer for Elementary and Secondary 75 copies @ P200.00 = 15,000.00
D. Practice Set for Elem & Sec. 475 sets @ 32.00 = 15,200.00
E. Different Forms, FLT, Learner’s Profile, etc. 472 sets @ 32.00 = 15,104.00
P165,454.00
IV Copies of CD/ school P 765.00
51 School Heads @ P15.00 = 765.00
V Honorarium of Literacy Facilitators P 120,000.00 3 Literacy Facilitators (1per district)
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
12
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
@ P 4,000.00 for 10 months =P 40,000.00 = 120,000.00
-------------------- TOTAL P 400,000.00
Prepared by:
DIVINA F. BORBON, Ph.D.Education Supervisor I (ALS)
Asst. Project Manager
MA. LUZ M. DE LOS REYESAsst. Schools Division Superintendent
DepEd, City of RoxasProject Manager
___________________________________________________________________
APPROVED:
DR. JESSE M. GOMEZ, CESO VSchools Division SuperintendentDepEd, Division of Roxas City
Project Director, DepEd
HONORABLE ANGEL ALAN B. CELINOCity Mayor
City of RoxasChair, Local School Board
Project Director, LGU
______________Date:
Project Alternative Learning System (ALS)
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
13
ALS CY 2010 – 2013Department of EducationDIVISION OF ROXAS CITYVersion 0.1
for A Big Change (ALS ABC)
Proposed by:
DIVINA F. BORBON, Ph.D.Education Supervisor I (ALS)
Asst. Project Manager
MA. LUZ M. DE LOS REYESAsst. Schools Division Superintendent
DepEd City of RoxasProject Manager
______________________________________________________________________________________MMD/dfbJune 22/09, Roxas City
14