Aloha Proof Module Design
Cabled Observatory Mechanical Presentation
School of Ocean and Earth Science and TechnologyFebruary 2006
Aloha Phase 1 Mechanical Systems
Main Assemblies:Float Package
Proof Module
Cable Termination Frame
Bottom Line:-Mechanicals have gone smoothly-Manufacturing and testing complete-Final assembly remains-Quick tour or three main assemblies
Buoyancy Test
•Float allows for the retrieval of the proof module .•Link between termination frameand proof module will be cut byROV.
Seawater Return
Hydrophone
Proof Module ElectronicsHousing Assembly
Status:-Manufacturing completed-Passed pressure testing-Partially assembled
AT&T
MUX
Endcap(tube not shown)
Strong-back
UH Electronics
Titanium Shackle
Proof Module Cable Termination Frame
Status:-Manufacturing and tension testing complete-Waiting for Tyco/ODI cable harness for final assembly
Termination Frame Tension Test
-Frame is inverted inside railway
20Kpounds-Passed