Page 1: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

ALLPLAN DESIGN2COSTA working method to be in conformity with BIM

Andreas Damrau, E-Mail: [email protected] GmbH, 72108 Rottenburg, www.dacoda.net

Page 2: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ SOLUTIONS FOR COSTING

Differentiation between work stages

Solutions in diffenrent levels of detail

Different stages can be shown parallely

Page 3: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ BUDGET

Bewertung

für die Grundlagenermittlung über Kennwerte

Page 4: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ PROJECT DEVELOPMENT

18/03/2019

Project develoment wizardminimal expenditure of input

Projection of the costs with valuesBRI, BGF (or NF) possible

can be completed with more information

Visual depiction

First plan presentation

Industrie- / Gewerbebau – Projektentwicklungs-Assistent

Page 5: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ PROJECT DEVELOPMENT

18/03/2019

Industrie- / Gewerbebau – Projektentwicklungs-Assistent

Page 6: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ PROJECT DEVELOPMENT

18/03/2019

Industrie- / Gewerbebau – Projektentwicklungs-Assistent

Page 7: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ WIZARDS OF PRELIMINARY DRAFTING

18/03/2019

Cost estimate with values to be in conformity with DIN 276 values are coordinated to the geometry of the building

Easy handling for perfect preliminary draftsonly 4 wizards to start the project immediately

The building model can be taken to the next work stagescompleting the building model with more details and information is easily

Graphically resultsplans, views and sections combined with the graphically animation

complete the cost estimate

Industrie- / Gewerbebau – Vorentwurfs-Assistenten

Page 8: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ WIZARDS OF PRELIMINARY DRAFTINGIT IS AN WIZARD TO GET ALL COST-VALUES AND TO BE IN CONFORMITY WITH DIN 276

ALLPLAN DESIGN2COST

Page 9: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ BIM-SOLUTION - DESIGN2COSTONLY THREE STEPS TO WORK WITH A BIM CONFORMING METHOD

ALLPLAN DESIGN2COST

WIZARDS BUILDING MODEL QUANTITIES AND COSTS

Page 10: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ WIZARDSPREDEFINED BIM-BUILDING PARTS ARE TAKEN OVER EASILY

ALLPLAN DESIGN2COST

Page 11: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ PLANSDIFFERENT DEPICTIONS DIRECTLY OUT OF THE BUILDING MODEL

ALLPLAN DESIGN2COST

Page 12: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ VIEWS AND SECTIONS

ALLPLAN DESIGN2COST

ALWAYS THE LATEST PROJECT STATUS – WHEN UPDATING THE 2-D SUPPLEMETINGS WILL

NOT BE CHANGED

Page 13: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ VISUALISATIONQUICKLY AND EASILY– DIRECTLY OUT OF THE BUILDING MODEL

ALLPLAN DESIGN2COST

Page 14: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ REPORTS OF THE BUILDING PARTSBEING CONSISTENT BECAUSE OF THE PREDEFINED REPORTS AND PRINTING TEMPLATES

ALLPLAN DESIGN2COST

Page 15: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ REPORTS OF THE BUILDING PARTSLIST OF WINDOWS AND DOORS – MORE OUTPUT FORMATES: PDF, WORD AND EXCEL

ALLPLAN DESIGN2COST

Page 16: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ CALCULATION OF THE QUANTITIES AND COSTSAND THE FINAL MEASUREMENTSONLY AVAILABLE AFTER ENTERING THE MAJOR BUILDING PARTS INTO THE BUILDING MODEL

ALLPLAN DESIGN2COST

Page 17: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ BUILDING SPECIFICATION AND ROOM DATA SHEETDIRECTLY OUT OF THE BUILDING MODEL – FLEXIBLE AND INDIVIDUAL CHANGES AT ANY TIME

ALLPLAN DESIGN2COST

Page 18: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ DIN276: LEVEL 1 - 3OUT OF THE MODEL

ALLPLAN DESIGN2COST

Page 19: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ SPECIFICATION OF PRICESALL SPECIFICATIONS OF PRICES FOR ALL TRADES IN AN UNFINISHED STATE – ALREADY

DURING THE DESIGN STAGE – ALREADY PRICED

ALLPLAN DESIGN2COST

Page 20: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ RANKING LIST / TOP TEN – POSITIONSREPORT TO SEE THE „BIG POINTS“ OF THE COSTS WITH JUST A GLANCE

ALLPLAN DESIGN2COST

Page 21: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ COMPARISON OF DIFFERENT VARIANTSCOST CONTROL BETWEEN DIFFERENT WORK STAGES OR VARIANTS POSSIBLE

ALLPLAN DESIGN2COST

Page 22: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

Intelligent taking over of the IBD-building parts to the

energy consulants

with the attributes

Visual check of the building parts

starting the project immediately, no definition necessary

Fast check of the building envelope

Lambda-values are already preset in the IBD-building parts

Energy performance certificate

redidential buildings and non-residential buildings

Classification of the rooms and the different ways of heating

different areas are easily made

CONNECTION TO THE ENERGY PERFORMANCECERTIFICATE

BUILDING INFORMATION MODELING (BIM) – PLANEN NEUESTER STAND

18.03.2019

19

ALLPLAN DESIGN2COST

Page 23: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ DESIGN2COST - ELEMENTS

ALLPLAN DESIGN2COST

11 times in a row TÜV-Süd-certificatedhaving a VOB conforming determination of valuesof selected building partsas the only company in this sector

Page 24: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

\ DESIGN2COST - SOLUTIONS

ALLPLAN DESIGN2COST

Bauen im Bestand

Hochbau

IngenieurbauIndustrie- / Gewerbebau

Page 25: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

… already by design modelling!\ ALL RESULTSBASED ON THE BIM-MODEL!

Page 26: ALLPLAN DESIGN2COST - CADENAS · ALLPLAN DESIGN2COST A working method to be in conformity with BIM Andreas Damrau, E-Mail: ad@dacoda.net DACODA GmbH, 72108 Rottenburg,

ROHBAU: AUSBAU:

HAUSTECHNIK: AUSSENANLAGEN:

\ WORKING METHOD:

18.0

10TITLE OF BUILDING INFORMATION MODELING (BIM) –PLANEN NEUESTER STAND

Allplan design2cost