allowances, unit prices, and alternates act 380 1

17
Allowances, Unit Prices, and Alternates ACT 380 1

Upload: ashley-chapman

Post on 17-Jan-2018

223 views

Category:

Documents


0 download

DESCRIPTION

Related Considerations O Once a project has been analyzed to determine where changes may occur, then an allowance, alternate, or unit price can be used to minimize the impact of such variables O These special procedures SHOULD NOT become a substitute for accurate and complete documents (drawings & specifications) O Using these items tend to add complexity to the bidding and contract award process 3

TRANSCRIPT

Page 1: Allowances, Unit Prices, and Alternates ACT 380 1

Allowances, Unit Prices, and Alternates

ACT 380

1

Page 2: Allowances, Unit Prices, and Alternates ACT 380 1

ObjectivesO Recognize specifying techniques

which meet the needs of dealing with the lack of adequate information, unknowns, and contingencies on a construction project

2

Page 3: Allowances, Unit Prices, and Alternates ACT 380 1

Related ConsiderationsO Once a project has been analyzed to

determine where changes may occur, then an allowance, alternate , or unit price can be used to minimize the impact of such variables

O These special procedures SHOULD NOT become a substitute for accurate and complete documents (drawings & specifications)

O Using these items tend to add complexity to the bidding and contract award process

3

Page 4: Allowances, Unit Prices, and Alternates ACT 380 1

Major TopicsO Allowances

O Cash allowanceO Quantity allowance

O Unit PricesO Alternates

4

Page 5: Allowances, Unit Prices, and Alternates ACT 380 1

Allowance DefinedA monetary amount or a quantity that is not otherwise defined by specifications and drawings, but which the contractor is required to include in the project

5

Page 6: Allowances, Unit Prices, and Alternates ACT 380 1

Cash Allowance Defined

A monetary amount that the contractor includes as part of the contract sum to cover the cost of certain items to be determined at a later time

6

Page 7: Allowances, Unit Prices, and Alternates ACT 380 1

When to Use Cash Allowances

O Inclusion of items that cannot be designed or selected until the project is partially complete

O Cover cost of items for which the owner or architect wants to arrange separate procurement

O Cover items where the magnitude of the item can only be determined during construction

7

Page 8: Allowances, Unit Prices, and Alternates ACT 380 1

When to Use Cash Allowances

O Accelerate construction schedule when short design period outweighs potential higher cost for cash allowances items

O Substitute for complicated specification that is difficult to produce

8

Page 9: Allowances, Unit Prices, and Alternates ACT 380 1

A/E Must Clearly Indicate Which of the Following are Included in

allowance:O Actual material costO TaxesO DeliveryO UnloadingO UncratingO Storage and HandlingO Installation

9

Page 10: Allowances, Unit Prices, and Alternates ACT 380 1

Typical Cash AllowanceGenerally covers only cost of material delivered to the site including any taxes

10

Page 11: Allowances, Unit Prices, and Alternates ACT 380 1

When Cash Allowances Used:

O Items that cannot be designed or selected until the project is partially complete (e.g., murals, sculptures, furnishings & accessories, & landscaping)

O Items such as testing, the magnitude of which can only be determined during construction

O Acceleration of the design schedule when the benefit of a short design period outweighs the potentially higher cost involved with cash allowance items

11

Page 12: Allowances, Unit Prices, and Alternates ACT 380 1

Quantity Allowance Defined

Requires the contractor to include a specific quantity of a product in the scope of the work even though location of the product is not defined on drawings or in the specifications

12

Page 13: Allowances, Unit Prices, and Alternates ACT 380 1

Quantity Allowance Example

A multi-story office building is being constructed

O The exact layout of the interior partitions often can’t be determined until the space is leased and each tenant’s requirements are determined

O In such as case…bidder will be asked to provide a quantity allowance for linear feet of finished interior partitions, doors & frames, sq. ft. of acoustical ceilings, and recessed lighting

13

Page 14: Allowances, Unit Prices, and Alternates ACT 380 1

Specifying AllowancesO Written provisions must be included

in several of the bidding documents:O Bidding requirementsO Conditions of the Contract (both AIA &

EJCDC forms provide articles for this)O Div 1 – General requirementsO Individual specifications sections for

products

14

Page 15: Allowances, Unit Prices, and Alternates ACT 380 1

Unit PriceO A cost quoted by a contractor for a

single, specified unit of workO Useful where the nature of the work

is defined but the extent of work is not known or is likely to change

O When the quantity of the work is known, the total cost of the item is determined by multiplying the quantity by the unit price

15

Page 16: Allowances, Unit Prices, and Alternates ACT 380 1

AlternatesO A defined portion of the work that is

priced separately and thus provides an option for the owner in selecting the final scope of the project

O An alternate can simply be a choice between two products or can be the deletion or addition of a portion of the work (this reduces the total contract amount – stay within budget)

16

Page 17: Allowances, Unit Prices, and Alternates ACT 380 1

Sample UsesO Allowances

O See page 4.34; Fig 4.6-AO Unit Prices

O See page 5.54; Section 5.6.7; also see Fig 5.6-H

O AlternatesO See page 4.35; Section 4.64

17