allowances, unit prices, and alternates act 380 1
DESCRIPTION
Related Considerations O Once a project has been analyzed to determine where changes may occur, then an allowance, alternate, or unit price can be used to minimize the impact of such variables O These special procedures SHOULD NOT become a substitute for accurate and complete documents (drawings & specifications) O Using these items tend to add complexity to the bidding and contract award process 3TRANSCRIPT
Allowances, Unit Prices, and Alternates
ACT 380
1
ObjectivesO Recognize specifying techniques
which meet the needs of dealing with the lack of adequate information, unknowns, and contingencies on a construction project
2
Related ConsiderationsO Once a project has been analyzed to
determine where changes may occur, then an allowance, alternate , or unit price can be used to minimize the impact of such variables
O These special procedures SHOULD NOT become a substitute for accurate and complete documents (drawings & specifications)
O Using these items tend to add complexity to the bidding and contract award process
3
Major TopicsO Allowances
O Cash allowanceO Quantity allowance
O Unit PricesO Alternates
4
Allowance DefinedA monetary amount or a quantity that is not otherwise defined by specifications and drawings, but which the contractor is required to include in the project
5
Cash Allowance Defined
A monetary amount that the contractor includes as part of the contract sum to cover the cost of certain items to be determined at a later time
6
When to Use Cash Allowances
O Inclusion of items that cannot be designed or selected until the project is partially complete
O Cover cost of items for which the owner or architect wants to arrange separate procurement
O Cover items where the magnitude of the item can only be determined during construction
7
When to Use Cash Allowances
O Accelerate construction schedule when short design period outweighs potential higher cost for cash allowances items
O Substitute for complicated specification that is difficult to produce
8
A/E Must Clearly Indicate Which of the Following are Included in
allowance:O Actual material costO TaxesO DeliveryO UnloadingO UncratingO Storage and HandlingO Installation
9
Typical Cash AllowanceGenerally covers only cost of material delivered to the site including any taxes
10
When Cash Allowances Used:
O Items that cannot be designed or selected until the project is partially complete (e.g., murals, sculptures, furnishings & accessories, & landscaping)
O Items such as testing, the magnitude of which can only be determined during construction
O Acceleration of the design schedule when the benefit of a short design period outweighs the potentially higher cost involved with cash allowance items
11
Quantity Allowance Defined
Requires the contractor to include a specific quantity of a product in the scope of the work even though location of the product is not defined on drawings or in the specifications
12
Quantity Allowance Example
A multi-story office building is being constructed
O The exact layout of the interior partitions often can’t be determined until the space is leased and each tenant’s requirements are determined
O In such as case…bidder will be asked to provide a quantity allowance for linear feet of finished interior partitions, doors & frames, sq. ft. of acoustical ceilings, and recessed lighting
13
Specifying AllowancesO Written provisions must be included
in several of the bidding documents:O Bidding requirementsO Conditions of the Contract (both AIA &
EJCDC forms provide articles for this)O Div 1 – General requirementsO Individual specifications sections for
products
14
Unit PriceO A cost quoted by a contractor for a
single, specified unit of workO Useful where the nature of the work
is defined but the extent of work is not known or is likely to change
O When the quantity of the work is known, the total cost of the item is determined by multiplying the quantity by the unit price
15
AlternatesO A defined portion of the work that is
priced separately and thus provides an option for the owner in selecting the final scope of the project
O An alternate can simply be a choice between two products or can be the deletion or addition of a portion of the work (this reduces the total contract amount – stay within budget)
16
Sample UsesO Allowances
O See page 4.34; Fig 4.6-AO Unit Prices
O See page 5.54; Section 5.6.7; also see Fig 5.6-H
O AlternatesO See page 4.35; Section 4.64
17