© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Alignment of CPM Scheduling and Short Interval Planning
OCTOBER 18, 2017
Scott Kelly, Walt Disney Imagineering
Jeff Betts, Whiting-Turner Contracting Co.
Don Rote, Building Point Pacific
Steven Solloway, Whiting-Turner Contracting Co.
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Evolution of Planning Over a Career
2
Mobilization Dur Start complete 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Move on Temp Const Office Trailers x
Temp Const Office - Furniture x
Temp Const Office - Equipment x
Temp Const Office - Phone x x
Temp Const Office - Power x x x x x x x x
Temp Const Office - DSL x x x x x x x x x x x
Fencing at Bld. C & Cov'd Walk x
Fencing at Onsite Laydown Area x
Subcontractor Safety Orientation /
Planning Meeting x
Building C Phase 1
Safe / Disconnect Elec, Gas, HVAC,
Plumbing, Alarm x
Electrical Demo x x x x x x
Plumbing Demo & Cut-N-Cap x x x
HVAC Demo & Cut-N-Cap x x x x x
Phase 1 Soft Demo x x x x x x x
Phase 1 Hard Demo x x x x x x x
Layout Mech Roof Op.s to identify dimensions for ordering of pre-fab curb Pending Response to RFI
Elec/HVAC/Plumbing/Framer Coord Mt x
Electrical Rough x x x x x x
HVAC Rough x x x x x
Phase 3 Work
Utility Markout for New HC Ramp x
Barricade Work Area at New HC Ramp x x
Demo for New Ramp x x x
Layout & Excavate Footings New Ramp x x x
Footing Templates x
Footing Reinforcing
Elementary School Modernization- 2 Week Look Ahead 02/04/03
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Planning Successes and Lessons Learned
3
• Community College Theater and Art Center• Four-building summer sprint ($8M)
• CPM required by Specifications
• (+) Pull planning new but rapidly embraced
• (+) Daily coordination accomplished by pull planning
• Five rows of planning boards
• (-) Difficulty developing TIA without CPM
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Planning Successes and Lessons Learned
4
• Power Plant
• Multi Year Risk Project ($BBs)
• (+)Required robust Critical & Near Critical
Path Analyses
• (+) Evaluation of Required Schedule
Contingencies
• (+) Establishing In Field Need Dates for
Long Lead Equipment
• (+) Resource analysis of critical craft labor
• (-) Limited insight into near term discrete
activities and / or constraints
• (-) Limited communication & buy-in of near
term plans & activities
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Planning Successes and Lessons Learned
5
Last Planner System®
• Field-use look-ahead
• Simple spreadsheet
• “The REAL schedule”
CPM Schedule
• Office use contractual tool
• CPM software
• “The billing schedule”
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
6
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Important Questions and How to Answer Them
7
• What is the longest path to operation of the Gamma Ray?
• What constraints are there to getting the plasma vault dried in by next Friday?
• What is the late date to order the cyborg’s holoprojector?
• What is the turnover date of Lieutenant Raffi’s transport shuttle landing pad?
• What day will humanoid robot’s chest plate be welded to his rib supports?
• Will we delay completion of the Space Sasquatch’s village if we only mobilize one
rope bridge crew?
• How many crews will be working in the Little Green Men’s palace on second shift
this weekend?
• Are there any impacts to the pour date of the Warlocks’s hut foundation if we need to
remove and replace the tree branch elements?
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Important Questions and How to Answer Them
8
• What is the longest path to operation of the Gamma Ray?
• What constraints are there to getting the plasma vault dried in by next Friday?
• What is the late date to order the cyborg’s holoprojector?
• What is the turnover date of Lieutenant Raffi’s transport shuttle landing pad?
• What day will humanoid robot’s chest plate be welded to his rib supports?
• Will we delay completion of the Space Sasquatch’s village if we only mobilize one
rope bridge crew?
• How many crews will be working in the Little Green Men’s palace on second shift
this weekend?
• Are there any impacts to the pour date of the Warlocks’s hut foundation if we need to
remove and replace the tree branch elements?Some questions are best answered by the short interval plan…
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Important Questions and How to Answer Them
9
• What is the longest path to operation of the Gamma Ray?
• What constraints are there to getting the plasma vault dried in by next Friday?
• What is the late date to order the cyborg’s holoprojector?
• What is the turnover date of Lieutenant Raffi’s transport shuttle landing pad?
• What day will humanoid robot’s chest plate be welded to his rib supports?
• Will we delay completion of the Space Sasquatch’s village if we only mobilize one
rope bridge crew?
• How many crews will be working in the Little Green Men’s palace on second shift
this weekend?
• Are there any impacts to the pour date of the Warlocks’s hut foundation if we need to
remove and replace the tree branch elements?…and some by the Critical Path Method schedule.
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Strengths and Weaknesses of the Systems
10
PROS CONS PROS CONS
CRITICAL PATH METHOD SCHEDULING (CPM) LAST PLANNER SYSTEM® (LPS)
Logic Driven Lacks Details Daily Detail Lacks Logic
Big Picture Not Collaborative Group Effort Micro View
Critical Path Accountability Ownership Highly Detailed
Logic Driven
Big Picture
Critical Path
Daily Detail
Group Effort
Ownership
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Creating the Integrated Process
11
• Big Hairy Audacious Goals
• Defining the ideal
• Setting ground rules
• Communicating to the larger team
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
The Integrated Process Defined
12
• Development using both tools
• First pass (CPM)
• Trade informed (CPM)
• Phase planned (short interval)
• Pull planned (short interval)
• Actualized (both)
• Refinement and addition of detail
• Stickies
• Sandbox schedule
• Active schedule
• Current published
CPM
LPS
0
10
20
30
40
50
60
70
80
90
100
80
60
40
10 10 10
10
20
30
40
2010
1020
30
50
7080
Schedule Development Over Time
Initial Schedule Trade Partner Input Pull Planned
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Weekly Meeting Cycle
13
Monday
• Daily Check-in
Tuesday
• Daily Check-in
• Phase Plan
Wednesday
• Daily Check-in
Thursday
• Daily Check-in
• Weekly 6-week Plan
Friday
• Daily Check-in
• CPM & WWP Sync
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Integration with Other Processes
14
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Challenges
15
• Change!
• Integration of Varied Stakeholder Experience
• Software limitations
• Complexity of Project
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Successes
16
• Current Construction PPC: 82
• Communication to a diverse audience
• Transparency and trust
• Early warning system
• Smaller project staff
• Integration of many disciplines in schedule
• Smooth integration of phase plans into CPM
• Happy customer!
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Looking Forward
17
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
In the spirit of continuous improvement, we would like to remind you to complete this session’s survey in the Congress app! We look forward to receiving your feedback.