Albuquerque Public Schools Capital Master Plan Review Committee 2012

Meeting 1: SB9 13-19 & GO 13

November 1, 2012

Page 2: Albuquerque Public Schools Capital Master Plan Review

2

Purpose • Capital recommendations for:

• SB9 14-19, 2 mill levy

• GO Bond 13

• Formerly GO 14

• Accelerated a year to realign the CMP to accelerate project delivery

• Consolidate two elections and save taxpayer / district resources

Page 3: Albuquerque Public Schools Capital Master Plan Review

3

Agenda • Background

• CMP Update (Reprioritized)

• District Growth Outlook (See Growth section)

• SB-9 14–19 2 Mill levy & 2013 GO Bond

• Financial and Revenue Outlook

• CMP Obligations

• Where we are now (Project update)

• Proposed priority categories

• Next meeting – Wednesday, November 7, 11:30 a.m.

Page 4: Albuquerque Public Schools Capital Master Plan Review

4

Background • CMP Update (Reprioritized, November 2011)

• Why?

• Realign CMP project obligations to revised lowered revenue collections

• Realign CMP to account for new Charter school legislative obligations

• Realign CMP to account for increased costs to complete projects undertaken between 2006 to 2009 (peak of construction inflation)

• Strengthen and maintain financial processes

Page 5: Albuquerque Public Schools Capital Master Plan Review

5

Background • Total impact 2010 to 2018 = $152.5 million

Decreased Revenues

• $47.1 million less than previously projected to be collected from tax payers from 2010 to 2016

• +$40 million will flow directly from County Assessor to Charter Schools between 2010 and 2018 and not to CMP/Construction

• +$18 million from 2010 HB33 election

• +22 million from 2013 SB-9 election

Increased Expenses

• $65.4 million to complete and make up for inflation obligation of projects from 2006-10 Strategy

Page 6: Albuquerque Public Schools Capital Master Plan Review

6

SB-9 14–19 2 Mill levy & 2013 GO Bond

Page 7: Albuquerque Public Schools Capital Master Plan Review

7

SB-9 14–19 2 Mill levy & 2013 GO Bond

Will be asking voters to approve a total of $368.4 million (No Tax Increase) $200 million in School General Obligation Bonds $168.4 million in the reauthorization of a 2 Mill Local property tax levy over the next six years

• Revenue outlook

• GO Bond

• $200 million (four years)

• $170 million for capital projects

• $30 million for Educational Technology Notes

• Projects have been prioritized and assigned to available revenue during the 2011 reprioritization

• SB 9 14-19 = $180.4 million

• $168.4 million over 6 years projected (@ 0% revenue growth) local tax collection

• Reduced approximately 10% due to economic downturn

• Anticipate $12 million in state match ($2 million / year)

Page 8: Albuquerque Public Schools Capital Master Plan Review

8

SB-9 14–19 2 Mill levy & 2013 GO Bond

• CMP Obligations

• Maintenance of 14+ million square feet of educational facilities

• Additional 4 million square feet since 2005

• Decreased maintenance personnel due to operational budget reductions by the state

• Completion of the 2011-16 CMP capital strategy as reprioritized and approved in 2010 and 2011

• New statutory mandate that distributes a portion of the mill levy directly to charter schools ($20.2 million over 6 years)

Page 9: Albuquerque Public Schools Capital Master Plan Review

9

Ongoing Construction Projects

1. Sandia High School 2. Del Notre High School 3. Chaparral Elementary School 4. APS Community Stadium 5. Inez Elementary School 6. Montessori of the Rio Grande Charter School 7. South Valley Academy Charter School

Where we are Now

Upcoming 2012 Construction projects

•McKinley Middle School •Eldorado High School •Adobe Acres Elementary •Sandia Base Elementary School •Monte Vista Elementary School •Jefferson Middle School •Central Kitchen •e-Academy Alternative School •MacArthur Elementary School •SW K – 8 School •Lincoln Complex Buildings A1 and G Roof

Page 10: Albuquerque Public Schools Capital Master Plan Review

10

On-Going Construction Projects

Page 11: Albuquerque Public Schools Capital Master Plan Review

11

Construction Schedule

Page 12: Albuquerque Public Schools Capital Master Plan Review

12

Sandia High School Address: 7801 Candelaria Rd NE

Square Footage: 330,699

Year Opened: 1958

Current Projects: • New Site Master Plan Study • New Science/Math classroom Building & New

Library • Landscaping/Site stabilization/ Infrastructure

Upgrades • Athletic Fields Reconstruction

Budget: $22,316,937.00

Architect: Mahlman Studio

General Contractor: TBD

Est. Date of Completion: Aug 2014

Page 13: Albuquerque Public Schools Capital Master Plan Review

13

Address: 5323 Montgomery Blvd NE Square Footage: 280,744 Year Opened: 1964-65 Current Project: Rebuild school (3 phases) Phase 1 - COMPLETE Construct new classroom building Demolish a portion of 100 Building Construct new administration building Architect: Dekker/Perich, Greg T. Hicks O/E, and Allison

Eng. O/E General Contractor: Shumate Constructors

Phase 2- On-Going Demolish rest of 100 Building and 500 Building Remove portables

Phase 3 Demolish 300, 400 and 500 buildings Finish student commons Kitchen/Cafeteria Est. Date of Completion: Aug 2013

Total Budget: $58,911,244

Del Norte High School

Page 14: Albuquerque Public Schools Capital Master Plan Review

Address: 6325 Milne Rd NW Square Footage: 54,299 Year Opened: 1984 Site Traffic Improvements & Site Development

Plan Kindergarten, Classroom and Cafeteria

Additions, Design Services Architect: Cherry/See/Reames General Contractor: TBD Budget: $14,529,000 Est. Date of Completion: Aug 2014

15

Chaparral Elementary School

Page 15: Albuquerque Public Schools Capital Master Plan Review

15

Address: 1601 Arroyo Vista Blvd NW Current Projects: Football Stadium Track and Field Softball court Tennis court

Budget: $36,361,300 Architect: SMPC General Contractor: Shumate

Constructors, inc Est. Date of Completion: Apr. 2013

Albuquerque Public Schools Community Stadium

Page 16: Albuquerque Public Schools Capital Master Plan Review

16

Inez Elementary School

Address: 1700 Pennsylvania St NE Square Footage: 51,841 Year Opened: 1952 CMP 2011-16 Strategy Projects: Kindergarten addition Renovation of existing buildings Drainage/Site Improvements Budget: $3,568,580 Architect: NCA Architects General Contractor: T.A. Cole& Sons Est. Date for Completion: Sept 2013

Page 17: Albuquerque Public Schools Capital Master Plan Review

17

2012 Upcoming Projects

Page 18: Albuquerque Public Schools Capital Master Plan Review

Address: 3426 Blake SW Year Opened: 1999 Grade Levels: 9 -12th CMP 2011-16 Strategy Project: Phase 1A - Library, Administration,

Special Programs and Food Services Spaces

Budget: $7,214,377 Architect: Studio SW General Contractor: TBD Est. Date of Completion: Fall 2013

South Valley Academy Charter School

Page 19: Albuquerque Public Schools Capital Master Plan Review

Address: 16550 Gabaldon Dr NW Square Footage: 12,000 Year Opened: 2004 Grade Levels: K-5 This school is one of 6 pilot charter schools that

are currently undergoing design for new permanent public facilities in partnership with Albuquerque Public Schools.

Currently the charter school is on APS owned facility.

CMP 2011-16 Strategy Project: School Improvements Budget: $2,614,218 Architect : G. Don Dudley General Contractor: Famco Inc Est. Date of Completion: July 2013

20

Montessori of the Rio Grande Charter School

Page 20: Albuquerque Public Schools Capital Master Plan Review

Address: 4500 Comanche NE Square Footage: 78,124 Year Opened: 1956 Current Projects: Science Lab Renovations Electrical Improvements

Budget: $710,157 Architect: Architect Studio Contractor: TBD

CMP 2011-16 Strategy Project Classroom Addition Budget: $ 6,281,190

Architect: TBD (Requesting RFP) General Contractor: TBD Est. Date of Completion: Fall 2014

McKinley Middle School

21

Page 21: Albuquerque Public Schools Capital Master Plan Review

21

Eldorado High School

Address: 11300 Montgomery NE Square Footage: 324,085 Year Opened: 1970 CMP 2011-16 Strategy Projects: Renovate Math, Fine Arts & Humanities Buildings Asbestos removal Budget: $6,479,667 Architect: Van Gilbert General Contractor: TBD Est. Date for Completion: Fall 2013

Page 22: Albuquerque Public Schools Capital Master Plan Review

22

Adobe Acres Elementary School

Address: 1724 Camino Del Valle SW Square Footage: 43,451 Year Opened: 1964 CMP 2011-16 Strategy Projects: Classroom and Cafeteria Addition School Wide General Renovations Health & Safety Drainage corrections Budget: $3,612,433 Architect: RMKM General Contractor: TBD Est. Date for Completion: Fall 2013

Page 23: Albuquerque Public Schools Capital Master Plan Review

23

Address: 21001 Wyoming SE - KAFB East Square Footage: 46,632 Year Opened: 1950 CMP 2011-16 Strategy Projects:

Parent Drop Off

New Classroom Building (phase 1a)

Athletic Field Replacement (phase 1b)

Budget: $1,212,769 Architect: Claudio Vigil Architects General Contractor: TBD Est. Date for Completion: Fall 2013

Sandia Base Elementary School

Page 24: Albuquerque Public Schools Capital Master Plan Review

Address: 3211 Monte Vista Blvd NE Square Footage: 51,805 Year Opened: 1931 CMP 2011-16 Strategy Projects:

Roofing Repairs

Restroom Upgrades

Refurbish classrooms and offices

Budget: $1,447,595 Architect: Westwork General Contractor: TBD Est. Date for Completion: Fall 2013

Monte Vista Elementary School

Page 25: Albuquerque Public Schools Capital Master Plan Review

25

Address: 712 Girard NE Square Footage: 116,204 Year Opened: 1938 CMP 2011-16 Strategy Projects:

New Track with Drainage System

Parent Drop Off

Budget: $808,194 Architect/ Engineer: High Mesa Consulting

Group General Contractor: TBD Est. Date for Completion: Spring 2013

Jefferson Middle School

Page 26: Albuquerque Public Schools Capital Master Plan Review

26

Address: 5200 Cutler Ave NE Square Footage: 44,369 sq. ft. Year Opened: 1915

CMP 2011-16 Strategy Project: Phase 2 Cafeteria and Site development Budget: $4,552,167 Architect: Greg T. Hicks General Contractor: TBD

Est. Date of Completion: Dec 2013

eAcademy Alternative School

Page 27: Albuquerque Public Schools Capital Master Plan Review

27

MacArthur Elementary School Address: 1100 MacArthur Rd NW Square Footage: 42,604 Year Opened: 1948 Current Projects: • Kindergarten Classroom & Play Lot • Cafeteria Addition / Kitchen Upgrades • Improve Site Lighting for Security • Install Security Fencing • Site Improvements Budget: $3,689,297 Est. Date of Completion: Dec 2013 Architect: Wright & Hammer General Contractor: TBD

Page 28: Albuquerque Public Schools Capital Master Plan Review

28

Address: 800 Louisiana St NE Year Opened: 2012 CMP 2011-16 Strategy Projects:

New food services facility

Budget: $14.4 Million Architect: TBD ( Programming phase) General Contractor: TBD Est. Date for Completion: Summer 2014

Central Kitchen

Page 29: Albuquerque Public Schools Capital Master Plan Review

29

Recently Completed Projects

Page 30: Albuquerque Public Schools Capital Master Plan Review

30

Address: 12015-B Tivoli Ave NE Square Footage: 44,601 Year Opened: 1970 Completed Projects: Classroom addition Art room Playground Improvements Restroom Renovations

Date of Completion: July 2011 Budget: $7,020,251 Architect: Greg T. Hicks O/E General Contractor: Makwa Builders

John Baker Elementary School

Page 31: Albuquerque Public Schools Capital Master Plan Review

31

Address: 24 Public School Rd Tijeras, NM 87059

Square Footage: 64,002 Year Opened: 1991 Completed Projects: Kindergarten and Computer Lab

Addition Electrical Upgrade

Date of Completion: June 2011 Budget: $2,809,999 Architect: Design Plus Contractor: Janstar Builders, Inc.

A. Montoya Elementary School

Page 32: Albuquerque Public Schools Capital Master Plan Review

32

Address: 620 Georgia Street SE Square Footage: 58,500 Year Opened: 1952 Completed Projects: Kindergarten Addition Site Work - LEED Art Room Refurbish Restrooms Playground Improvements

Date of Completion: Jan 2011 Budget: $2,938,667 Architect: AECOM General Contractor: Vigil & Rio Conchos

Emerson Elementary School

Page 33: Albuquerque Public Schools Capital Master Plan Review

33

Address: 721 Tomasita NE 87123 Square Footage: 84,416 Year Opened: 1965 Completed Projects: HVAC Improvements Admin. Addition and Refurbish

Date of Completion: July 2011 Budget: $2,406,547 Architect/Eng: WH Pacific General Contractor: Michael S. Rich CMP 2011-16 Strategy Projects: Supplemental Admin addition Upgrade science area Music area renovation Budget: $2,320,147 Architect: TBD General Contractor: TBD

Kennedy Middle School

Page 34: Albuquerque Public Schools Capital Master Plan Review

34

Address: 1505 Candelaria NW Square Footage: 341,710 Year Opened: 1954-55 Completed Projects: HVAC in Gym Shop/Fine Arts Addition & Police

Facility Remodel Pool Locker Rooms

Date of Completion: Nov 2011 Budget: $10,760,888 Architect/Eng: NCA, Allison Engineers General Contractor: Shumate

Constructors

CMP 2011-16 Strategy Projects: Renovate Building Construction of New Classroom &

Soccer Field Relocate Tennis Courts and Police

Station Budget: $ 8,151,554

Valley High School

Page 35: Albuquerque Public Schools Capital Master Plan Review

35

Address: 1100 Solar NW Square Footage: 38,424 Year Opened: 1952 Projects: Kindergarten Addition Playground / Basketball Court

Improvements Date Completed: March 2010 Budget: $2,046,214 Architect: G. Donald Dudley General Contractor: Famco

Alvarado Elementary School LEED Silver Certified

Page 36: Albuquerque Public Schools Capital Master Plan Review

36

Address: 6300 Claremont Ave NE Square Footage: 53,058 Year Opened: 1960 Completed Projects: Cafeteria Kitchen Additions &

Renovations Site improvements Electrical upgrades

Budget: $1,613,624 Architect: Greg T. Hicks General Contractor: Jim Sena

Construction Co., Inc. Date of Completion: Aug 2012

Zuni Elementary School

Page 37: Albuquerque Public Schools Capital Master Plan Review

37

Address: 6700 Palomas NE Square Footage: 63,608 Year Opened: 1983 Current Projects: Administration Expansion Loop Road Improvements Electrical / Lighting Upgrade Site Health & Safety Projects

Budget: $1,237,354 Architect: Westwork General Contractor: CC Construction Date of Completion: Aug 2012

E. G. Ross Elementary School

Page 38: Albuquerque Public Schools Capital Master Plan Review

38

Truman Middle School

Address: 9400 Benavides SW Square Footage: 88,269 Year Opened: 1975 CMP 2011-16 Strategy Projects: Construct Classroom Wing Parent Drop-off/Pick-up Drainage Upgrades Budget: $7,268,941 Architect: Fanning Bard Tatum General Contractor: T.A. Cole & Sons Date of Completion: Dec 2011

Page 39: Albuquerque Public Schools Capital Master Plan Review

39

Address: 5200 Cutler Ave NE Square Footage: 44,369 sq. ft. Year Opened: 1915 Phase 1 completion: April 2011 Administration/Classroom Building

LEED Date of Completion: April 2011 Budget: $8,262,423 Architect: Integrated Design &

Architecture General Contractor: Longhorn

eAcademy Alternative School

Page 40: Albuquerque Public Schools Capital Master Plan Review

Address: 12015 Tivoli NE 87111 Square Footage: 10,0122 Year Opened: 1966 Current Projects: Cafeteria Kitchen Renovation and

Addition Gym and Locker room upgrades HVAC improvements

Date of Completion: December 2012 Budget: $1,202,464 Architect/Eng: DWL General Contractor: CC Construction

CMP 2011-16 Strategy Projects:

Supplement for Cafeteria/Kitchen renovation and Gym locker upgrades

Site improvements

Budget: $2,391,855

Date of Completion: May 2012

41

Hoover Middle School

Page 41: Albuquerque Public Schools Capital Master Plan Review

Address: Bldg. 25000- KAFB East Square Footage: 57,895 Year Opened: 1952 Grade Levels: K-5 Current Projects: New Parking and Drop-off improvements Classroom Addition

Total Budget: $3,190,511 Architect: Design Group General Contractor: Lockwood Date of Completion: Aug 2012

Wherry Elementary School

Page 42: Albuquerque Public Schools Capital Master Plan Review

42

Atrisco Heritage Academy High School Address: 10800 Dennis Chavez Blvd SW Square Footage: 463,000 Date of Opening: Aug 2008 for 9th grade Aug 2009 for 10th grade Aug 2010 for 11th grade Aug 2012 for 12th grade Budget: $132,000,000 Architect: Fanning Bard Tatum Architects/

Perkins & Will General Contractor: Phase 1: Gerald Martin-COMPLETE Phase 2: Bradbury-Stamm-COMPLETE Phase 3: McCarthy-COMPLETE

This school was constructed to relieve primarily West Mesa High School and the future growth areas of Rio Grande High School and the SW Mesa of Albuquerque

Completed PAC 12th Grade Academy

Page 43: Albuquerque Public Schools Capital Master Plan Review

43

Draft Recommendation

• SB9 14-19

• See handout