albay governor salceda presentation at the focap-phap forum on the “public health impact of...
DESCRIPTION
Organized by: Foreign Correspondents Association of the Philippines (FOCAP) & the Pharmaceutical and Healthcare Association of the Philippines (PHAP) September 27, 2014 @ Marco Polo Hotel, Ortigas Center, Pasig CityTRANSCRIPT
Governor Joey Sarte SalcedaClimate Change Academy - DRRM Training Institute
Province of Albay, Philippines
FOCAP and PHAP Forum on the “Public Health Impact of Disasters”Marco Polo Hotel, Ortigas Center, Pasig City27 September 2014
ALBAY DRR-CCA AND DEVELOPMENT
MAYON ERUPTION 2014“to achieve zero casualty
goal”
Day 13GOV JOEY SARTE SALCEDA
Chairman, PDRRMC ALBAY
APEC-NOC MEETINGSep 25, 2014 @ DOT Central Office
Affirms Albay as host of APEC-ISOM on 08-09 December 2014
4
Lava Flows
Pyroclastic Flows
MAYON VOLCANO DESTRUCTIVE HAZARDS
5
Effects Threatened Areas(6 km r PDZ only) Counter Measure Impact
Lava Flow LegazpiDaragaSto. Domingo
Distance > Life threatening.> Destructive to Structures and agriculture.
Pyroclastic Flow Areas Around Mayon Volcano Evacuation Outside Danger Zone
> Highly destructive to human lives and properties. > 500-700kph at 1,200cc
Ash Fall First/part of 2nd Dist (SE wind)Third/part of 2nd Dist (NE wind)
Damped cloth > Health hazard and destructive to houses , fisheries and agriculture.
Lahar River Channels during weather disturbances
Evacuation to higher ground
> Life threatening.> Highly destructive to properties, structures and agriculture.
Bush Fire Bushy Areas Distance/Evacuation
> Life threatening. Destructive to forest, agriculture and properties.
Tephra Fall Within 3-4 km radius Distance/Evacuation
Non-destructive
Potential Impacts:IF YOU DONT EVACUATE, YOU’RE DEAD
6
7
8
9
10
11
12
13
14
15
Occupied
Available
16
• Volcanic Risks– No air traffic pattern near
Mayon– But: No history of “no fly
zone”
RISK ANALYSIS
17
45DEPED
SCHOOLSIN 6-PDZ& EDZ
38DEPED
SCHOOLS USEDAS EVAC CEN
SCHOOLS/CLASSROOMS EFFECTED
AS OF SEPT 25, 2014
17,980PUPILS
AFFECTED 29schools remaining
0TENTS NEEDED AS
TEMPORARYCLASSROOMSFOR DEPED
36,924PUPILS
AFFECTED
54 back2 shifts
Unicef - 155w/ add’l 25
83DEPED
SCHOOLSIN 6-PDZ& EDZ
18
7LGUs
AFFECTED(2 CITIES; 5 MUN.)
46EVAC
CENTERSUSED
39BRGYS
12,303FAMILIES
EVACUATEDEVACUATION STATUS
AS OF SEPT 26, 2014
19
Number of
FAMILIES PERSONS EVAC CENTERS
1. GUINOBATAN 7 2,742 10,525 15 2. MALILIPOT 3 746 3,121 3 3. CAMALIG 6 2,393 12,120 4 4. LIGAO CITY 4 831 3,786 7 5. TABACO CITY 8 1,147 4,765 8 6. DARAGA 6 2,864 14,890 6 7. STO. DOMINGO 5 1,580 6,313 3
TOTAL 39 12,303 55,520 46
Provincial Disaster Operation Center ALBAY PUBLIC SAFETY AND EMERGENCY MANAGEMENT OFFICE
POPULATION
as of September 26, 2014PARTIAL EVACUATION REPORT : MAYON ERUPTION 2014
Legazpi City
CITY / MUNICIPALITYAFFECTED
BARANGAYS
20
NEEDED SUPPORT/REQUIREMENTS FOR EVACUATION CENTERS
AS OF SEPT 25, 2014
732TOILETSNEEDED
4DRINKING
WATERSOURCES
6COMM.
KITCHEN57
TOILETSPROVIDED 3
DEEPWELLS
21
5,809NO. OF
LIVESTOCKFARMER
19,931TOTAL NO. OFLIVESTOCK TO
BE EVAC8
LIVESTOCK EVAC
CENTERS
EVACUATION ON LIVESTOCK
AS OF SEPT 25, 2014
6,633 dogs2,088 accounted
6,000 owner-driven
5,200 to go
LIST OF FARMERS/LIVESTOCK INSIDE 6 KM. PERMANENT DANGER ZONE
22
23
24
Protracted Evacuation Period:Mayon, 2006 and 2009
• In 2006 eruption, evacuation lasted from May 6 to Sep 30 = 147 days
• In 2009 eruption, evacuation lasted from July 10 to Jan 12, 2010 = 185 days
• On the average: 94 days under Alert 2 (2,728 families), and 47 days under Alert 3 (9,946 families)
• Easily: P133.5m versus Albay CF of P43m
25
Financial Projection for Mayon Eruption 2014ALERT LEVEL Basis Alert 3
FAMILIES 12,303 12,303 12,303 12,303EVAC DAYS 47 94 141 188
Rice Incentive to Evacuees 5 kg/day 57,824 115,648 173,472 231,296 Bags 1,568 1,568 1,568 1,568 Amount 90,668 181,336 272,005 362,673 No. of Bags 58 116 173 231Econ Displaced Families 17,526 17,526 17,526 17,526Onetime assistance 25 kg 8763 8763 8763 8763 Amount 13,740 13,740 13,740 13,740 No. of Bags 9 9 9 9Supplemental to LGUs QRFCF 28,912 57,824 86,736 115,648
Operating Expenses Fuel- AFP 3,640 5,280 6,920 8,560Fuel- BFP 600 1,200 1,800 2,400FUEL PNP 600 1,200 1,800 2,400Camp Management 336 672 1,008 1,344Livestock Evac (a) 4,313 18,778 28,167 37,556Medicines 8,674 17,347 26,021 34,694Health Emergency Personnel 4,738 14,551 21,827 29,102Water 8,674 17,347 26,021 34,694Firewood 5,782 11,565 17,347 23,130Portalet Rentals/CR Repairs 5,782 11,565 17,347 23,130
TOTAL 174,924 352,406 520,739 689,702
26
Breakdown of Supplemental LGU QRFCF (49,825 ) to Affected Municipalities
MUNICIPALITY EVACUEES SUPP QRF/LGU Aug 15 Meals/Person
Tabaco City 962 4,521 4,019 150Ligao City 646 3,036 1,800 170Malilipot 746 3,506 N/A 112
Sto Domingo 448 2,106 400 80Daraga 2,853 13,409 5,900 600Camalig 2,393 11,247 1,500 350
Guinobatan 2,553 11,999 1500 350Total 10,601 49,825 15,119 1,812
PGA REQUIREMENT (M) 72,506
27
Additional Requirements
Blankets 12,303 Mats 12,303 Water Jugs 12,303 Hygience Kits 12,303 Armchairs 54,000 Tent Classrooms 1,025
600
500
15,000
28
NG COST OF ASSISTANCE (as of September 26, 2014)
29
NG Assistance for Mayon Eruption
• In Mayon 2009, total NG transfers to Albay province reached P85m: P47m cash for camp maintenance operations from
GAA contingency funds 10,000 bags from NDCC (P850/bag) P5m from OCD 6,000 bags (P850/bag) from DSWD and P14m
cash-for-work at P1,400 ea for 10,000 families P3m from DOH for medicines.
30
Tourism Advisory
• Strictly prohibited:1. ATV ride activities going towards
Mayon Volcano;2. Mayon Climbing/Trekking;3. Playing golf at the Doña Pepita Golf
Course; and4. All other recreational/exploratory
activities within the PDZ and EDZ
31
Tourism Advisory
• Safe vantage points for visitors/tourists:1. Ligñon Hill2. Cagsawa Ruins Park3. Daraga Church4. Legazpi City Boulevard5. Taysan Hills6. Quituinan Hills
32
Cluster Approach: Lead and Members1. EVACUATION AND CAMP MANAGEMENT : DR. CEDRIC D DAEP Cluster Lead - LGUs/Deped Members - PNP, AFP, Barangay Officials, PEO, DPWH, PGSO, OCD, PNRC, INGOs/NGOs 2. SOCIAL PROTECTION : DSWD DIR. ARNEL GARCIA
Cluster Lead - PSWDO /DSWDMembers - DOH, Simon of Cyrene, PHO, PNP, DepEd,
INGO/NGOs
3. COMMUNITY BUILDING CLUSTER : PSSUPT MARLO MENESESCluster Lead - PNP PCR, AFP CMOMembers - SAC, DSWD, PSWDO, World Vision
Save the Children, PAF-TOG 5, NAVFORSOL
4. WATER, HEALTH, SANITATION AND NUTRITION : DR. NATALIO REMPILLO Cluster Lead - PHO/DOH Members - WHO rep, UNFPA, PEO, BFP, PNRC, Water Districts, Oxfam, AFP Engineers, POPCOM
33
5. LIVELIHOOD AND ECONOMIC OPPORTUNITIES : MR. JAMES AGUILAR Cluster Lead - PCEDO / DOLE Members - PAS, PVS, TESDA, DTI, DOST, PSWDO, TESDA, NEDA,
BFAR, PCA, FIDA, NFA, NIA, PAFC, PCIC, DAR, DSWD,
DA, DOLE, CDA 5.a. SUB CLUSTER ON ANIMAL WELFARE: DR. ANTONIO BASANTA
Sub Cluster Lead - PVSMembers - Albay K9 CLUB, Mayon
kennel club, ASRRA, Albay
Dairy Coop.
6. EDUCATION : DIR. RAMON FIEL G. ABCEDECluster Lead - DepEdMembers - LGUs, UNICEF, PSWDO
(ECCD), CHED, TESDA, INGO/NGOs
7. LOGISTICS: DIR. BERNARDO R. ALEJANDRO IVCluster Lead - APSEMO / OCDMembers - PNRC, PIA, PNP, AFP,
DPWH, PEO, RESCUE ORGS., NTC, ALECO,
BJMP,BFP, DOTC, PCG, DBM, DOF , RADIO GRPS, GFIs,
ATO, PPA, INGOs/NGOs
Cluster Approach: Lead and Members
34
8. ENVIRONMENT AND ECO-CULTURAL TOURISM : DIR. MARIA O. RAVANILLA
Cluster Lead - PTCAOMembers - ENRO, PPDO, PEO, DENR, PTA, PCVC, EMB,
DOT, INGOs/NGOs
9. HAZARD REVIEW AND UPDATE : DR. RENATO U. SOLIDUM Cluster Lead - PHIVOLCSMembers - PAGASA, MGB
10. SECURITY : CAMPS, EVACUATED AREAS & GENERAL POPULATION :
COL RAUL FARNACIOCluster Lead - AFP/PNPMembers - MDRRMOs action teams, BPSOs
Cluster Approach: Lead and Members
35
Cluster 3: Community Building / Family Bonding Cluster Lead: PNP/AFP
1. Mascot team rotate to 10 of 45 ECs or 5 in the morning and 5 in afternoon
2. Religious Celebration/Holy Mass Mascot Show Magic Show Story Telling Games Live Band Acoustics Film Showing
36
37
38
39
40
41
42
43
GLENDA Zero Casualty Zero Missing Cleared roads of debris in 2 days NGCP back on 3rd night, but distribution should
take 2 weeks to town centers but 45 days to outer areas
Flights back to normal 2 days after Hotels did not close
44
Typhoon Glenda Damage Report
45
Dead 0Missing 0Injured 38
Families 136,825Persons 711,490
Families 100,936Persons 500,506
Cost (PhP)Totally Damaged 25,656 769,680,000.00Critically Damaged 77,496 2,324,880,000.00
Sub-Total 103,152 3,094,560,000.00
PARTIAL DAMAGE AND ACTIVITY MONITORING REPORT - TYPHOON GLENDAas of August 04, 2014
PROVINCIAL DISASTER RISK REDUCTION AMD MANAGEMENT COUNCILALBAY PUBLIC SAFETY AND EMERGENCY MANAGEMENT OFFICE
Provincial Disaster Operation CenterLegazpi City
I- CASUALTIES:
II- AFFECTED POPULATION:
III- EVACUATED POPULATION:
IV- DAMAGED HOUSES
Typhoon Glenda Damage Report
46
Type Affected area Production LossCoconut (PCA est.) 9,417 has 1,300,000,000.00Rice 10,420.47 178,712,643.34Corn 1,333 31,455,716.00Vegies, etc 11,051.45 905,215,430.00Fisheries 50 1,845,500.00
Sub-Total 2,417,229,289.34
Type Heads Cost (PhP)Misc 4,942,175.00
Sub-Total 4,942,175.00
VI- DAMAGE TO LIVESTOCK AND POULTRY:
V- DAMAGE TO AGRICULTURE FISHERIES:
PARTIAL DAMAGE AND ACTIVITY MONITORING REPORT - TYPHOON GLENDAas of August 04, 2014
PROVINCIAL DISASTER RISK REDUCTION AMD MANAGEMENT COUNCILALBAY PUBLIC SAFETY AND EMERGENCY MANAGEMENT OFFICE
Provincial Disaster Operation CenterLegazpi City
Typhoon Glenda Damage Report
47
DPWH Public infra 1,210,017,000.00 Other Govt Facilities 1,200,000,000.00PEO Roads 288,200,009.00
Bridges 68,500,000.00Spillways, Ripraps, slope protection 117,850,000.00
Flood Control 282,850,000.00Water System 17,600,000.00Irrigation System 48,700,000.00Provincial Buildings 80,150,000.00City/Municipal Infra Facilities 142,500,000.00
Oas Misc facilities & Water system 2,150,000.00Bacacay Water System 15,000,000.00Guinobatan 105,500,000.00Polangui 190,000,000.00Sto Domingo 67,500,000.00Ligao City 18,010,000.00Legazpi City 100,000,000.00Tabaco City 31,571,980.00Camalig 9,050,000.00Malinao 14,098,709.75
Water System 570,000.00Tiwi 14,625,000.00Rapu-rapu 50,000,000.00Jovellar 9,725,000.00DEPED Totally Damaged 17,880,000.00
Partially Damaged 43,150,870.00PVS Facilities 2,122,500.00
8,700,200.00
Sub-Total 4,156,021,268.75
9,672,752,733.09
Communication Equipments (base, HH radios, antenna, repeaters & other paraphernalia
GRAND TOTAL
VII- DAMAGE TO INFRASTRUCTURE:
POST GLENDA
48
DANA (Damage and Needs Assessment) completed in 1 week
PAGERR (Plan for Albay Glenda Early Recovery and Reconstruction) by Aug. 30 (45 days)
Monetarist Approaches to Early Recovery
MONETARIST APPROACHES to EARLY RELIEF1. Emergency loan of P20,000 to all 27,000 GSIS
members2. 6-months loan repayment moratorium worth P72,000
cash flow savings for 27,000 GSIS members3. P20,000 emergency loan to all 3,000 GSIS pensioners4. P16,000 emergency loan to all 200,000 Pag-Ibig
members5. P100,000 Home Improvement Loan payable in 30
years to all 200,000 Pag-Ibig members6. P30 million ERF for small and medium enterprises7. P37 million from Deped for school repairs8. 10,000 bags of rice for Food for Work program
49
50
51
52
53
SB Corp. approved a P37M Enterprise Rehabilitation Fund (ERF 2) enterprises affected by Typhoon Glenda. It will carry an 8% interest rate per annum; 5 years repayment period with a 6 to 9 months grace period.
54
55
Land Bank of the Philippines
The Super Typhoon Reming EventNovember 29, 2006
Affected Areas Cities : 3 Municipalities : 15
Casualties were Confirmed Dead: 618 Injured : 1,465 Missing : 419
Damaged Houses Totally Damaged : 112,074 Substantially Destroyed : 99,986
Affected Population Families : 203,496 Persons : 1,060,875
56
57
TYPHOON DURIAN (Reming): IMPACTS ON ALBAYFormal / Recorded
Sources of Recovery
1. Public Infrastructure 4,005 27% 3,872 97% Natl Roads/Bridges 2,700 DPWH 1,400 Spcl Item in Natl Budget
980 Realignment/Augmentation 250 Supplemental Natl Budget
Provincial Facilities 98 GSIS 28 Insurance Claim Natl Health Facilities 148 DOH 78 Spcl Item in Natl Budget Local Health Facilities 219 Transfer 160 Spcl Item in Natl Budget
AECID 28 Grant Educational Facilities Basic 630 Deped 630 Spcl Item in Natl Budget
AECID 170 Grant College 210 CHED 148 Spcl Item in Natl Budget2. Agriculture 903 6% 340 38% Crops 570 DA 160 Spcl Item in Natl Budget
DAR 180 Spcl Item in Natl BudgetPCIC 13 Insurance Claim
Irrigation 333 NIA 180 Spcl Item in Natl Budget3. Private Housing 10,045 67% 2,225 22% Totally Damaged: 112,074 7,845 NHA 750 Spcl Item in Natl Budget Partlly Damaged: 99,986 2,200 DSWD 750 Spcl Item in Natl Budget
USAID 125 GrantNGOs 300 GrantsHDMF 300 P100T home improvement loans
Total 14,952 6,437 Recovery rate from formal sources 43%5,078 Recovery from HH sources 34%
11,515 Total Recovery 77%3,437 Unrecovered 23%
Damage Sustained
Rate of Recovery
ItemAmount
5846% of Albay GDP
46% recovery from public
0.00%
0.20%
0.40%
0.60%
0.80%
1.00%
1.20%
1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Total Damages to GDP
-
5,000.0
10,000.0
15,000.0
20,000.0
25,000.0
30,000.0
1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Total Damages (Pm)
Disaster Damages: RisingTOTAL
DAMAGES (Pm)GDP (Pm)
Damages to GDP
1994 5,245.9 1,692,932 0.31%1995 19,001.6 1,905,951 1.00%1996 1,678.4 2,171,922 0.08%1997 5,586.7 2,426,743 0.23%1998 28,368.0 2,665,060 1.06%1999 5,668.0 2,976,905 0.19%2000 9,406.0 3,354,727 0.28%2001 9,267.2 3,631,474 0.26%2002 3,420.2 3,963,873 0.09%2003 5,192.9 4,316,402 0.12%2004 14,244.3 4,871,555 0.29%2005 3,367.3 5,444,039 0.06%2006 21,651.1 6,032,835 0.36%2007 4,533.2 6,648,245 0.07%2008 23,512.6 7,497,535 0.31%Total 160,143.4 0.31%
-
5,000.0
10,000.0
15,000.0
20,000.0
25,000.0
30,000.0
1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Total Damages (Pm)
0.00%
0.20%
0.40%
0.60%
0.80%
1.00%
1.20%
Total Damages to GDPPeaks of 1%
in 1995 and 1998…
15-year average of 0.31% of GDP
0.61%
..but, average of 0.20% from 1998 to 2008
DRR succeeding? Or something else!
59
Albay Provincial BudgetBuild Better > Build Back Better
EDF (roads)8% EDF (health)
7%
Non-EDF infra0%
Health24%
Education20%
Agriculture4%
Tourism2%
DRR/CCA11%
Social Services14%
Gen. Adm10%
2012
EDF (roads)19%
EDF (health)1%
Non-EDF infra16%
Health14%
Education1%
Agriculture3%
Tourism1%
DRR/CCA5%
Social Services21%
Gen. Adm19%
2007
60
Programmatic Themes ALBAY MABUHAY (ensure boat is safe) – recovery from disasters with
focus on DRR - CCA
ALBAY RISING (ensure everyone in the boat) – to regain capacity with focus on Health Education
ALBAY BOOM (push boat to the destination) – to expand economic base through Tourism Rich Agriculture SMEs
ALBAY ROCKS (fortify the boat for the bigger sea) – to flex competitiveness for light industrialization Energy Development More infra
61
Zero casualty in 18 of 20 years 8,700 foreign tourists in 2006 to 339,000 in 2013 Environmental Protection: Forest cover increased by 88% and
Mangrove by 4x NAT from 177th in 2007 to 19th in 2012 UNICEF-PIDS: 98% participation rate and dropout rate of 0.3% College grads from 34,000 to 188,000 with 77,137 assisted since
2007 Philhealth from 17,000 to 172,000 MMR of 33 versus 224 national or only 9 mother deaths out of
26,826 live births Population: +66,580 in 7 years from 1.2m to 1.26m or less than
10,000 pa Rice self sufficiency from 73% in 2008 to 94% in 2013; 2nd highest
producer of camote Multi-awarded
7 YEARS AFTER REMING
62
Persons Dead Typhoon Mameng Sep 28 1995 10,126 0 71,499,797 Typhoon Rosing Nov 1 1995 440,372 0 539,599,785 Typhoon Pining Nov 12 1997 1800 0 37,663,000 Typhoon Loleng Oct 15 1998 201,834 0 303,950,141 Typhoon Sendang Nov 7 1999 1,122 0 110,000 Mayon Volcano Eruption 1999 68,626 0 284,076,061 Mayon Volcano Eruption 2001 46,914 0 11,937,460 Typhoon Dindo May 13 2004 33,892 0 226,712,081 Typhoon Unding Nov 14 2004 1744 0 42,394,231 Typhoon Yoyong Dec 4 2004 18,372 0 50,590,299 Tropical Storm Caloy May 9 2006 47,065 0 99,346,841 Mayon Volcano Eruption 2006 40,451 0 50,590,299 Typhoon Milenyo Sep 25 2006 698,460 14 1,665,316,133 Typhoon Reming Nov 28 2006 1,060,875 618 3,230,435,702 Typhoon Mina Nov 21 2008 214,734 0 22,800,000 Typhoon Frank Jun 18 2008 138,937 0 21,789,000 Typhoon Dante May 1 2009 49,712 0 238,316,148 Typhoon Pepeng Oct 9 2009 89,926 0 9,000,719 Typhoon Santi Oct 30 2009 671,314 0 6,510,000 Mayon Volcano Eruption July 2009 47,563 0 16,659,000 TS Chedeng May 25 2011 221,094 0 5,710,768 TS Falcon June 22 2011 107,253 0 46,762,630 TY Glenda July 15 2014 711, 490 0 9,117,017,374
Affected Population Calamities Date
Damage Cost (Php)
Major Disaster Events in Albay Province 1994-2014:Zero Casualty in 18 years out of 20
63
Goal Indicator Bicol Region Albay
1 Poverty Incidence M H
Subsistence Incidence H H
Underweight (IRS) H H
2 Participation - Elementary L H
Cohort survival - elementary M M
3 Gender parity - elementary H H
4 Under-five mortality H H
Infant mortality H H
Proportion of fully-immunized children M H
5 Maternal mortality rate L H
Contraceptive prevalence rate L M
Condom use rate L M
6 Deaths due to TB L H
Malaria positive cases H H
7 Household with access to sanitary toilets H L
Household with access to safe drinking water H H
Legend:
L low probability H high probability
M medium probability no data
MDGs have been achieved early through ownership of beneficiaries
64
MDGs: Achieved ahead of 2015 exc. MDG 7
HEALTH
MDG Health Indicators: 2006 2013 Target Remarks
Under-Five mortality rate (UFMR)
16.5% (357/1,000 live births)
11%(295 / 1,000 live births)
27/1,000Live births Achieved
Infant mortality rate (IMR)
9.43% (237 deaths / 25,132 live
births) * 1,000
7.49%(201/26,826 live births) * 1,000
19/1,000Live births Achieved
Maternal mortality rate (MMR)
87% (22 / 25,132 live
births) * 100,000
33.55%(9 / 26,826 live
births) * 100,000
52/100,000Live births Achieved
Skilled-Birth Attendance (SBA)
43%(10,922 / 25,132 live
births) * 100
90%(24,316 / 26,826 live
births) * 10080% Achieved
Facility-Based Deliveries (FBD)
14%(3,483 / 25,132 live
births) * 100
90%(24,117 / 26,826 live
births) * 10080% Achieved
ALBAY MDG ACHIEVEMENTSCY 2006 VS 2013
65
HEALTH
MDG Health Indicators: 2006 2013 Target Remarks
HIV Prevalence Rate
0.0004(5 / 1% of total pop=12,120)
0.00101(13 / % of total pop=12,786)
< 1% of total pop. Achieved
TB Case Detection Rate (CDR) 90% 108% 100 Achieved
TB Cure Rate (CR) 91% 85% 85% AchievedPrevalence of Malnutrition 21% 14.01% 17% Achieved
Households without Access to Safe Water
7.5% 3.8% 6% Achieved
Households without Access to Sanitary Toilets
16.30% 12.44% 13% Achieved
ALBAY MDG ACHIEVEMENTSCY 2006 VS 2013
66
HEALTHALBAY MDG ACHIEVEMENTS
CY 2006 VS 2013MDG Health Indicators: 2006 2013 Target Remarks
Fully-Immunized Child (FIC) 77.84% 85% 95%
Anti-Measles Vaccination 83.54% 84.195 95%
Contraceptive Prevalence Rate (CPR)
43% 35% 65%
67
HEALTH PHILHEALTH ENROLMENT
2006 2013
18,510 173,262
Albay has been declared Malaria-free in 2008 and Filarias-free in 2012
Pioneered - Alis Excess policy esp. free hospitalization during calamities
68
HEALTH Population: +66,580 in 7 years
Live Births
Other health indicators
2006 2013
1,212,020 1,278,600
2006 2013
25,132 26,826
Other health indicators 2006 2013National Voluntary Blood Donation 39% 54%Dengue cases 55 cases 10 casesRabies (Deaths) 7 deaths 5 deaths
69
ENVIRONMENT Forest Cover Change, Albay Province
(2003 vs 2010)
Description Land Area (Hectares) % againsttotal land area
Total land area 256,677.00 100%2003 forest cover 26,298.71 10.25%2010 forest cover 44,891.16 17.49%
Forest cover change: Land Area (Hectares) % over total Increase in forest cover in 7 years 18,592.45 88%
Annual rate of gross forest cover increase 2,656.06 ha/year 5.92 percent /year
70
ENVIRONMENT Mangrove Reforestation, Albay Province
(2009 vs 2013)Description Land Area (Hectares)
1950’s 5,100 50% were converted to Fishponds Leaving on 700 ha. vegetated
2009 7002013 2,400
Increase in forest cover in 4 years 1,700 More than 3x mangrove forests
Source: Gilbert Gonzales, DENR V
71
TOURISM Albay is the center of tourism boom in the Philippines
from only 8,765 foreign tourists in 2006 (36,608 in 2007), Albay foreign arrivals are now at 383,000 of which 300,000 were added from 2010-2013.
Year Tourist Arrivals
2009 235,8572010 299,3632011 350,6292012 523,8322013 874,458
Legazpi City 259,078 rest of Albay 615,380
72
EDUCATION From 177th (in 2007) out of 193, Albay leapt to Rank
19th in 2012 out of 203 and 35 in 2013, although it placed 35th in the National Achievement Test (NAT) results in 2013.
From only 34,000 college graduates in 2000, we are now 184,000 principally due to the aggressive funding assistance programs of the PGA.
Based on PIDS UNICEF study, participation rate in Elementary has jumped from 72% to 98% and 0.3% dropout rate versus national average of 1.3%.
73
EDUCATION Land Bank of the Philippines has released P380.685 million
out its P700 million loan grant to the Provincial Government of Albay through its Albay Higher Education Contribution Scheme (AHECS). Balance is still with the bank.
76,137 student-grantees in the tertiary level have already received loan assistance under the program since 2010.
School Year No. of scholars / beneficiary Amount (Pm)
2010-2011 20,608 102.042011-2012 27,410 137.052012-2013 17,822 89.12013-2014 10,297 51.48
74
EDUCATION Based on their records, some P264,000 have already been
paid by those who have graduated under the program, especially those who took technical vocational courses.
The first payment record was on January 31, 2011 and the latest was on March 25, 2013.
75
EDUCATION: BU College of Medicine
76
1. Rice Self-sufficiency from 74% to 93%2. Irrigated from 17,000 hectares to 19,433 hectares 3. 2nd biggest producer of camote and biggest
exporter 4. Largest pili hectarage at 2,972 from 1,200 has. 5. On-going programs to make Albay - the GEONET
CAPITAL OF THE WORLD seeking 30% or P12bn revenues versus current market leader Sri Lanka
6. 15-year irrigation program targets 51,000 hectares including 3 degree slope areas
77
AGRICULTURE & FOOD SECURITY
AGRICULTURE & FOOD SECURITYPARTICULARS 2008 2009 2010 2011 2012 2013
Net Production (Palay) 147,291 174,165 147,422 155,340 188,532 200,088Net Production (Rice) 95,739 113,207 95,824 100,971 122,546 130,059
Total Consumption 129,730 131,968 132,126 131,579 136,094 140,145Population 1,190,185 1,199,706 1,201,143 1,207,149 1,215,127 1,229,343Per Capita (mt) 109 110 110 109 112 114
Sufficiency Ratio 74% 86% 73% 77% 90% 93%Sufficiency Ratio = ratio between net production (rice) and total consumption
78
5-YEAR IRRIGATION DEVELOPMENT PROGRAMSUMMARY of CAPITAL OUTLAY for 2011 to 2015
79
TOTAL- 1,706,800,000
MEDIUM-TERM IRRIGATION DEVELOPMENT MATRIXSUMMARY for 2014 to 2018
TOTAL- 2,073,872,000
80
1. Secured 104,000 4Ps in 2014 from 3,500 in 2008
2. CBMS Poverty Benchmarks for all towns (P15m)
3. Albay Mayon Surety Fund for SME loan guaranty (P35m)
4. Albay Packaging Common Service Facility in Cabangan (P24m)
5. Albay Blue encompassing CRABS... awaiting release of BUB/GPBP P464m
SOCIAL EQUITY
Pantawid Pamilya Household
Started with only 2,533 beneficiaries in 2008 and lobbied for its increase to 75,600 (P 1.315bn) as of April 30, 2014. And possibly to 113,234 (P 1.785bn) in 2015.
81
MUNICIPALITY SET 1 SET 2 SET 3 SET 4 SET 5 SET 6 SET 7
Bacacay 424 10 2 3,642 119 2,162 6,359 Camalig 1 1 3 4 3,170 96 893 2,010 6,178 City of Ligao 1 909 5 2 5,147 136 3,047 9,247 City of Tabaco 1 1,249 31 2 6,194 212 3,855 11,544 Daraga(Locsin) 1 829 46 3 4,278 120 2,536 7,813 Guinobatan 2 2 4,004 100 1,096 2,505 7,709 Jovellar 1 321 3 1,422 49 913 2,709 Legazpi City 2 1,333 13 6,690 289 145 4,158 12,630 Libon 2,526 1 3 4 2,696 78 2,847 8,155 Malilipot 431 20 2 1,866 39 1,198 3,556 Malinao 440 13 3 2,065 57 1,291 3,869 Manito 1 450 6 1 1,240 26 891 2,615 Oas 2 3,825 146 1,207 2,516 7,696 Pioduran 3 1 660 6 2 3,555 98 2,133 6,458 Polangui 434 5 2 3,475 57 1,949 5,922 Rapu-Rapu 450 1 1,952 31 1,216 3,650 Sto.Domingo (Libog) 387 9 2 1,685 74 961 3,118 Tiwi 2 2,516 37 25 1,426 4,006 TOTAL 2,533 6 8,323 180 20,231 39,885 4,462 37,614 113,234
Potential HH Beneficiaries (Extended Age Coverage 15-
18 years old)
Grand Total
Community-Based Monitoring System (CBMS)
82
MODULE 4
Data Collection %
Field Editing % Encoding % Digitizing %Data Processing
%Data Validation
%BDP-SEP
Preparation %
Malilipot 18Malinao 29 100% 100% 100% 89.70% 70% 70% 40%Sto. Domingo 23 100% 100% 100% 100% 100% 100% 100% Sti l l to submit the database and SEPs
Bacacay 56 100% 100% 100% 100%Tiwi 25 100% 100% 100% 100% 100% 100% 100% Sti l l to submit the database and SEPs
TOTAL BARANGAYS 151
Rapu-Rapu 34 100% 100% 100% 100% 100% 100% 100% 18 Brgys . With SEPP; On-going fi na l i zation for the remaining SEPPs
Manito 15 100% 100% 100% 53% 6.60%
Camalig 50 100% 66% 46% 42% 20% Val idati on of activities resched on June 2013
Daraga 54 100% 100% 100% 100% 100% 100% 40% SEPP Preparation on-going
TOTAL BARANGAYS 153
Guinobatan 44Libon 47 100% 100% 100% 100% 100% 100% 100% Round 2: On-going SEPP Preparation
Pioduran 33Polangui 44 100% 100% 91% 95% 66% 52% 2.30%Jovellar 23Oas 53 100% 100% 100% 94% 100% 100% 5.60%TOTAL BARANGAYS 244
Tabaco 47 100% 100% 85% Round 3
Legazpi 70 100% 100% 61% On-going digitizing & encoding
Ligao 55 100% 100% 100% 100% 100% 100% 20%TOTAL BARANGAYS 172
CITIES
FIRST DISTRICT
SECOND DISTRICT
THIRD DISTRICT
MODULE 1 MODULE 2 MODULE 3
MUNICIPALITIESTOTAL NO. OF BRGYS.
REMARKS
STATUS REPORT ON CBMS IMPLEMENTATION (as of July 2013)
Community-Based Monitoring System (CBMS)
83
Percentage of
Compliance based on initial ten (10) Brgys.
Percentage of
Compliance based on the entire
Brgys.
Percentage of
Compliance based on Initial ten (10) Brgys.
Percentage of
Compliance based on the entire
Brgys.
Percentage of
Compliance based on initial ten (10) Brgys.
Percentage of
Compliance based on the entire
Brgys.
Percentage of
Compliance based on Initial ten (10) Brgys.
Percentage of
Compliance based on the entire
Brgys.
Percentage of
Compliance based on initial ten (10) Brgys required.
Percentage of
Compliance based on the entire
Brgys.
Percentage of
Compliance based on initial ten (10) Brgys required.
Percentage of
Compliance based on the entire
Brgys.
Percentage of
Compliance based on initial ten (10) Brgys required.
Percentage of
Compliance based on the entire
Brgys.
MALINAO 29 100% 100% 100% 89.70%STO. DOMINGO 23 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%TIWI 25 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%BACACAY 56 100% 100% 100%CAMALIG 50 100% 70% 62% 50% 20% NAPC FocusDARAGA 54 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 50% on-goingMANITO 15 100% 100% 100% 100% 100% 100% 100% 50% NAPC FocusRAPU-RAPU 34 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%OAS 43 100% 100% 100% 94% 100% 100% 30% 11.20% NAPC FocusLIBON 47 100% 100% 100% 100% 100% 100% 100% SEPP On-goingPOLANGUI 44 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 10% 2.20% NAPC FocusGUINOBATAN 44PIODURAN 33JOVELLAR 23MALILIPOT 18
REMARKSMUNICIPALITYNo. of Brgys.
MODULE 1DATA COLLECTION FIELD EDITING
MODULE 2ENCODING DIGITIZING
MODULE 3DATA PROCESSING DATA VALIDATION SEPP
MODULE 4
CBMS STATUS OF 15 MUNICIPALITIES (as of December 2013)
DRR - CCA OCD NDRRMC has designated Albay’s CCA-DRRM
Training Institute (CCA-DRRM TI) as training institute as mandated in R.A. 10121 Sec. 9 “I“
We have provided skills training to 7 countries (Laos, Myanmar, Cambodia, Vietnam, Kenya, Nigeria and Timor Leste ), while locally: 7 regions, 26 provinces, 31 cities, 210 municipalities and hundreds of barangays; and in partnerships with NGOs like CNDR -- provided training to firms and communities
Zero casualty achieved in 18 out of 20 years since 1994.
84
FLOODING LANDSLIDE MUDFLOW / LAHAR NAME OF CITY/ No. of No. of No. of MUNICIPALITY Bgys Bgys Bgys
Affected Affected Affected
1. TIWI 17 1987 10281 8 934 47942. MALINAO 26 2991 14589 12 1874 55473. TABACO CITY 40 1062 5535 2 122 645 11 5134 280084. MALILIPOT 17 608 3173 6 209 942 3 1476 72985. BACACAY 53 1193 6207 7 451 2396 1 2505 69806. STO. DOMINGO 15 644 2936 5 446 2087 5 2965 121587. LEGAZPI CITY 66 16372 84182 10 305 1611 8 5348 238148. RAPU- RAPU 33 1392 7993 5 522 26439. MANITO 12 958 5802 13 1063 637610. DARAGA 26 2393 11584 6 669 3450 17 10431 4788811. CAMALIG 23 4604 24105 10 822 4228 7 3220 1607512. GUINOBATAN 18 2923 15214 4 14 84 8 4545 1894813. J OVELLAR 13 302 1603 3 54 28214. LIGAO CITY 29 897 4608 21 1928 10052 7 2080 1082015. PIODURAN 17 3291 16375 9 134 69916. OAS 28 2597 17263 11 399 187617. POLANGUI 23 5742 29124 25 3781 1084418. LIBON 28 7465 38822 8 819 3345
TOTAL 484 57,421 299,396 165 14,546 61,901 67 37,704 171,989
Families Affected
Population Families Affected
Population Families Affeected
Population
Source: CDCCs/MDCCs/NSO 2007/BDCCs
Disaster Risk Assessmentfor Jan 2014
NOTE: Some of the population threatened by Mayon Volcano eruption are also threatened by other hazards like flood and lahar due to weather hazards. Some Coastal Barangays which are threatened by Storm Surge/Tsunami are also threatened by flooding. Hence, overlapping on total number of population (by barangay) affected by 2 or more types of hazards is possible.
85
Highlights of DRR/CCA ProgramsRisk Mapping
Comprehensive Land Use PlansIntegration into PDP, PDIP, AIP, PPMPGeostrategic Intervention Relocation Engineering Interventions Social Preparations
Community-based Warning and Evacuation PlanningClose coordination with Warning Agencies
Capacity Build-up Mobility AssetsPermanent Evacuation Center
Disaster ResponsePre-emptive EvacuationPre-emptive Healthcare
Cluster Approach to Early Recovery
86
87
88
Permanent Evacuation Centers
89
Model Relocation Sites (WB 2013, Oxford University) Taysan (Legazpi City) Banquerohan (Legazpi City) Sta. Monica (Legazpi City) Anislag Phases 1, 2,3 (Daraga) Baldo 1 (Daraga) Baldo 2 (Daraga) Amore (Daraga) Bascaran (Daraga) Penafrancia (Daraga) Pandan (Daraga) Cullat (Daraga) Balinad (Daraga) Banadero (Daraga) Tagaytay (Camalig) Baligang (Camalig) St. Francis of Assisi (Camalig) Mauraro (Guinobatan) Quitago (Guinobatan) Minto (Guinobatan) Tuburan (Ligao) Lanigay (Polangui) San Andres phases 1 & 2 (Sto. Domingo)
90
Team ALBAY Humanitarian Missions: 12 major deployments to Disaster Affected Areas)
1st Mission : Typhoon Frank (Fengshen) – Iloilo City on June, 2008
2nd Mission : Typhoon Ondoy (Ketsana) – Bagong Silangan, Quezon City and Cainta, Rizal on September, 2009
3rd Mission : Typhoon Juan (Megi) – Isabela on October, 2010
4th Mission : Typhoon Sendong (Washi) – Cagayan de Oro and Iligan City on December, 2011 [also includes Christmas Treat]
5th Mission : 6.9-Magnitude Earthquake – Guihulngan City, Negros Oriental on February, 2012 [also includes Valentines Treat]
6th Mission : Floods due to Habagat (Southwest Monsoon) – Marikina, Quezon City and Malabon on August, 2012
7th Mission : Cholera & Diarrhea Epidemic – Catanduanes on June, 2012
8th Mission : Typhoon Pablo (Bopha) – Davao Oriental and Compostela Valley on December, 2012
9th Mission : Typhoon Maring (Trami) – Laguna and Cavite on August 2013
10th Mission : 7.2-Magnitude Earthquake –Bohol on October, 2013
11th Mission : Typhoon Yolanda (Haiyan) – Leyte and Samar on November, 2013
12th Mission : Christmas Treat for Typhoon Yolanda Victims – Marabut-Basey, Samar on December, 2013
91
Guicadale: P4.4bn Naga-Polangui Freeway: P3.6bn Pres. Cory Road: P2.6bn Cagraray-Batan-Rapurapu: P20.8bn Arimbay-Misericordia Viaduct: P1.25bn Castilla Bridge: P17.1bn Almasor Tourism: P19.28bn
TOTAL ASPIRATION: P69.03bn
Regional Strategic Initiatives for Countryside Competitiveness
92
GUINOBATAN
CAMALIG
DARAGA LEGAZPI CITY
GUINOBATAN
CAMALIG
DARAGA LEGAZPI CITY
93
AMORERESETTLEMENT
(Tagaytay – Baligang – Taladong – Comun – Inarado – Gapo – de la Paz –
Dinoronan –Peñafrancia)
TOTAL LENGTH – 12 KmsPROJECT COST – 89.9 M
(Peñafrancia – Gabawan – Estanza)
TOTAL LENGTH – 4 KmsPROJECT COST – 37.2 M
(Marquez Street – Puro)TOTAL LENGTH – 2.9 Kms
PROJECT COST –27.0 M
(Taysan – Homapon)TOTAL LENGTH – 3.3 Kms
PROJECT COST –24.8 M
(Bascaran-Burgos-Mabini-Kinawitan-Panoypoy)
TOTAL LENGTH – 6.1 KmsPROJECT COST – 45.8 M
(Comun-Cotmon-Del Rosario- Panoypoy)
TOTAL LENGTH – 11.2 KmsPROJECT COST – 84.0 M
(Panoypoy-Florista-San Isidro-White Deer-Quitinday)
TOTAL LENGTH – 14.9 KmsPROJECT COST – 111.8 M
(Quitinday-Cabraran-Pariaan-Iluluan-Mauraro)
TOTAL LENGTH – 9 KmsPROJECT COST – 67.7 M
(Mauraro-Palanog-Bariw-Tagaytay)
TOTAL LENGTH – 5.9 KmsPROJECT COST –43.9 M
BICOL INTERNATIONAL
AIRPORT
BU RESETTLEMENT
FVR RESETTLEMENT
BANQUEROHANRESETTLEMENT
TAYSANRESETTLEMENT
BALDORESETTLEMENT
AMORERESETTLEMENT
PROPOSED REGIONAL CENTER
EXTENSION
Southline South Central Station
ROAD TO DONSOL
(Puro-Lamba-Maslog-Taysan)
TOTAL LENGTH – 7.5 Kms.PROJECT COST – 56.5 M
(Homapon-Mariawa-Talahib- Bascaran)
TOTAL LENGTH – 4.7 KmsPROJECT COST – 44.2 M
94
THANK YOU
15-story high Lava Dome
GUICADALE ECONOMIC PLATFORM
• This is the key geostrategic intervention of Albay for spatial integration of upland areas suitable to settlements and commercial development and expands the developeable land area of Albay by 81,123 hectares, mostly around the international airport undergoing construction. GUICADALE stands for Guinobatan, Camalig, Daraga and Legazpi. Guicadale road projects, proposed by the Provincial Government and whose feasibilities studies were conducted by Albay, were included in the 2014 General Appropriations Act.
96
NAME OF PROJECT GUICADALE PLATFORM, ALBAY
Proposed Structures Grand Total = 28 road section = 193.9 kms.a. PCCP = 117,126 cu.m.b. Slope Protection = 49,752.8 cu.m.c. Line Canal = 49,752.8 lm.d. Vented Spillway = 455 lm.e. RCBC = 3 30 lines
Breakdown:1 Major Roads = 16 road section = 133.2 kms.
a. PCCP = 79,860 cu.m.b. Slope Protection = 35,873.87 cu.m.c. Line Canal = 35,873.9 lm.d. Vented Spillway = 250 lm.e. RCBC = 15 lines 15 lines
2 Arterial Roads = 12 road section = 60.70 km.a. PCCP = 37,266 cu.m.b. Slope Protection = 13,879 cu.m.c. Line Canal = 13,879lm.d. Vented Spillway = 205 lm.e. RCBC = 15 lines
97
NAME OF PROJECT GUICADALE PLATFORM, ALBAY
Construction Cost Grand Total = 28 road section = 193.9 kms.a. Rehab/concreting P 971.58 Millionb. Bridges P 65.98 Millionc. Right-of-Way P 21.21 MillionTotal P 1,058.77 Million
1. Major Roads = 16 road section = 133.2 kms.a. Rehab/concreting P 668.26 Millionb. Bridges P 45.58 Millionc. Right-of-Way P 21.21 MillionSub-total P 735.05 Million
2. Arterial Roads = 12 road section = 60.7 kms.a. Rehab/concreting P 303.32 Millionb. Bridges P 20.40 MillionSub-total P 323.72 Million
98
NAME OF PROJECT GUICADALE PLATFORM, ALBAY
Economic and FinancialAnalysis
Whole project EIRR = 23.65% & NPV = PhP 872.54 M1 Major Roads EIRR = 21.08% & NPV = PhP 267.29 M2 Arterial Roads EIRR = 21.98% & NPV = PhP 181.71 M
All the 28 road sections also posted an EIRR greater than 15% and the NPVs are all positive.
99
Status of GUICADALE Platform Road Network
LENGTH WIDTH LENGTH WIDTH ROADS BRIDGES ROADS BRIDGESKM M KM M KM KM
T O T A L 24.40 - 165.93 - 3.50 193.83 992.79 65.98 4,458.09 65.98
MAJOR ROADS 24.40 105.20 3.50 133.10 689.47 45.58 3,061.30 45.58
1 Gabawan - Estanza 3.00 4.00 1.00 4.00 24.15 92.00
2 Marquez Street - Puro C 0.80 4.00 0.60 4.00 1.50 2.90 23.07 66.70
3 Puro - Lamba - Maslog - Taysan 6.70 4.00 0.80 4.00 7.50 45.53 172.50
4 Homapon - Mariawa - Talahib- Bascaran B 1.50 4.00 2.20 4.00 1.00 4.70 37.00 11.20 108.10 11.20
5 Bascaran - Burgos - Mabini - Kinawitan - Panoypoy 2.40 4.00 3.70 4.00 6.10 31.31 140.30
6 Comun - Cotmon - Del Rosario - Panoypoy-Florista P 4.00 4.00 7.20 4.00 11.20 56.09 257.60
7 Florista - San Isidro - White Deer - Quitinday P 14.90 4.00 14.90 69.74 6.30 342.70 6.30
8 Quitinday - Cabraran - Pariaan - Iluluan - Mauraro P 9.00 4.00 9.00 54.86 8.40 207.00 8.40
9 Mauraro - Palanog - Bariw - Tagaytay P 5.90 4.00 5.90 28.31 135.70
10 San Isidro - San Roque -Banuang Gurang (Donsol) B 4.50 4.00 4.50 20.41 103.50
11 Mayon - Bigao - San Vicente - Ibaugan - Gogon (Donsol) 12.20 4.00 12.20 54.89 280.60
12P 10.50 4.00 10.50 52.88 241.50
13 Kiwalo - Pinaric 4.70 4.00 4.70 19.54 108.10
14 Bascaran - Alobo (Airport Access Road) 5.70 4.00 5.70 25.32 131.10
15 Anislag - Maopi - Magogon - Panoypoy P 6.80 4.00 6.80 30.45 0.66 156.40 0.66
16B 22.50 4.00 22.50 115.91 19.02 517.50 19.02
ASPHALT/ GRAVEL
LENGTH TO BE
OPENEDPROPOSED
LENGTH
FS ESTIMATED PROJECT COST (P'MILLION)
DPWH ESTIMATED PROJECT COST
(P'MILLION)
Cotmon - Maninila - Taplacon - Taloto - Mabunga - Salvacion - White Deer
Quitinday - Bagacay - Villapaz - Buyo - Rawis - Mamlad - Lawinon - Buenavista - Malidong - Pioduran
NAME OF ROAD SECTIONSCATEGORY
EXISTING ROAD CONDITION
CONCRETE
LENGTH WIDTH LENGTH WIDTH ROADS BRIDGES ROADS BRIDGESKM M KM M KM KM
ARTERIAL ROADS 60.73 60.73 303.32 20.40 1,396.79 20.40
17.10 4.00 7.10 34.35 163.30
2 Inarado - Lacag - Malabog P 4.50 4.00 4.50 20.41 3.60 103.50 3.60
3 Kiwalo - Bagumbayan 3.30 4.00 3.30 28.83 14.00 75.90 14.00
4 Kinawitan-San Vicente P.-Maopi 4.53 4.00 4.53 25.94 2.80 104.19 2.80
5 Lacag - Pandan - Busay 1.90 4.00 1.90 12.09 43.70
6 Lacag-Bongalon - Pandan 1.40 4.00 1.40 8.61 32.20
7 Busay - Balinad - Peñafrancia 8.40 4.00 8.40 36.13 193.20
8 Lacag - Mina 1.91 4.00 1.91 12.09 43.93
9 Peñafrancia - Balinad - Kidaco 6.69 4.00 6.69 29.55 153.87
10 Busay - Pandan - Bongalon - Kidaco 3.00 4.00 3.00 13.33 69.00
11 Peñafrancia - Busay 9.10 4.00 9.10 41.11 209.30
12 Imalnod-Bariis-Villahermosa 8.90 4.00 8.90 40.88 204.70
(P'MILLION) (P'MILLION)
Inarado-Binitayan - Tagoytoy - Mina - Gotob - Ligban
NAME OF ROAD SECTIONSCATEGORY
EXISTING ROAD CONDITION LENGTH TO BE
OPENEDPROPOSED
LENGTH
FS ESTIMATED PROJECT COST
DPWH ESTIMATED PROJECT COST
CONCRETE ASPHALT/ GRAVEL
Note DPWH Estimated Project Cost is based on DO No. 22, s. 2011 “Minimum Pavement Thickness and Width of National Roads” for new road construction the minimum thickness shall be 230mm and 280mm with minimum width of 6.70 meters
Status of GUICADALE Platform Road Network
101
Spatial Development :Guicadale Economic Platform
• Bicol International Airport – ongoing construction with total budget of P3.4bn from DOTC
• Southline South Central Station – part of PNR Southrail modernization, it is targeted to be located at Comun, Camalig with spurs to Legazpi and Matnog
• Resettlement sites providing safe house and lots to 10,076 families at risk to Mayon eruption and lahar
• New Regional Center - 76 hectare lot repossessed being acquired by Albay Rrovince as site for expanding regional offices of the national government
102
103
• P2.2bn Airside to be completed by May 2015
• P1.2 bn Terminal construction to be bidded in September; construction to start by Jan 2016
• Partial inauguration by May 2016
• Full completion on 2017
BICOL INTERNATIONAL AIRPORT
BICOL INTERNATIONAL AIRPORT
104
BICOL INTERNATIONAL AIRPORT
105
106
• South Line is one of 3; the other 2 are North Line to Tuguegarao and North-South Commuter Rail from Malolos to Calamba
• P340bn with P102bn for SouthLine with Matnog Extension and Batangas Spur Line
• P78bn NPV and EIRR of 20% • To be bidded as PPP targeted by
1Q 2015 with NSCR and Southline as first priorites
North-South Railway Project
SOUTH LINE
107
Guicadale: P4.4bn Naga-Polangui Freeway: P3.6bn Pres. Cory Road: P2.6bn Cagraray-Batan-Rapurapu: P20.8bn Arimbay-Misericordia Viaduct: P1.25bn Castilla Bridge: P17.1bn Almasor Tourism: P19.28bn
TOTAL ASPIRATION: P69.03bn
Regional Strategic Initiatives for Countryside Competitiveness
108
NAGA-POLANGUI FREEWAY
CORY HIWAY (green) + NAGA-POLANGUI FREEWAY (red)
110
Location Map (Naga-Polangui Freeway) 56.0 kms
111
Guicadale: P4.4bn Naga-Polangui Freeway: P3.6bn Pres. Cory Road: P2.6bn Cagraray-Batan-Rapurapu: P20.8bn Arimbay-Misericordia Viaduct: P1.25bn Castilla Bridge: P17.1bn Almasor Tourism: P19.28bn
TOTAL ASPIRATION: P69.03bn
Regional Strategic Initiatives for Countryside Competitiveness
112
Cagraray-Batan-Rapu-Rapu Bridges
113
Proposed Cagraray-Batan-Rapu-Rapu Road Bridge Projects Province of Albay
ROADOPENING COST/LM COST/LM
20,276.20Million
NOTE: Project Length including Cost Estimates is subject to change depending on the result of actual survey. Assumed Parametric Cost for Bridge and Road Componentloss based on CY 2012 Costing.
12,750.0
TOTAL COST (Php
GRAND TOTAL (Php ROAD INPUT
BRIDGE COMPONENT ROAD COMPONENT
BRIDGE TYPENO. OF BRIDGE
BRIDGE LENGTH
COST/L.M.
VIADUCT 2 15.0
MILLION/L.M.
183 LM.
1,450 LM.
2,550 LM. 12,750.00
SAY 20.28 Billion
7,250.00VIADUCT 1 15.0
MILLION/L.M.7,250.0
24.0 lm. 1,686 M 276.20RCDG 91.5
MILLION/L.M.274.5 38.0 KM.
55.0 MILLION/LM.
46.5/LM.
TOTAL COST (Php
Location Map (Arimbay-Sta. Misericordia Viaduct, Albay) 2.5kmsEstimated Project Cost –P 1.25B
115
116
Proposed Castilla-Magallanes Roads/Bridge Project Estimated Funding Requirements (P’Million)
OPTION 1
ROAD OPENING COST/KM COST/KM
OPTION 2
ROAD OPENING COST/KM COST/KM
OPTION 3
ROAD OPENING COST/KM COST/KM
OPTION 4
ROAD OPENING COST/KM COST/KM
NOTE: ESTIMATED PROJECT COST IS SUBJECT TO CHANGE UPON ACTUAL FIELD SURVEY
TOTAL COST (Php
GRAND TOTAL (Php
BRIDGE TYPE LENGTH COST/L.M.TOTAL
COST (Php ROAD COMPONENT
IMPROVEMENTBRIDGE / VIADUCT
7,000.0 LM.
5.0 MILLION/L.M.
35,000.0 5.0 KM. 195.05.0 KM.15.0
MILLION/KM.24.0
MILLION/KM.35,195.00
GRAND TOTAL (Php IMPROVEMENT
BRIDGE / VIADUCT
3,250 LM. 5.0 MILLION/L.M.
16,250.0 22.5 KM. 15.0 MILLION/KM.
22.5 KM. 24.0 MILLION/KM.
BRIDGE TYPE LENGTH COST/L.M.TOTAL
COST (Php ROAD COMPONENT TOTAL
COST (Php
877.5 17,127.50
BRIDGE TYPE LENGTH COST/L.M.TOTAL
COST (Php ROAD COMPONENT TOTAL
COST (Php GRAND
TOTAL (Php IMPROVEMENT
24,052.25
BRIDGE TYPE LENGTH COST/L.M.TOTAL
COST (Php ROAD COMPONENT TOTAL
COST (Php
BRIDGE / VIADUCT
4,750 LM. 5.0 MILLION/L.M.
23,750.0 7.75 KM. 15.0 MILLION/KM.
300.6 18,800.60
GRAND TOTAL (Php IMPROVEMENT
BRIDGE / VIADUCT
3,700 LM. 5.0 MILLION/L.M.
18,500.0 5.0 KM. 15.0 MILLION/KM.
9.4 KM. 24.0 MILLION/KM.
7.75 KM. 24.0 MILLION/KM.
302.25
Guicadale: P4.4bn Naga-Polangui Freeway: P3.6bn Pres. Cory Road: P2.6bn Cagraray-Batan-Rapurapu: P20.8bn Arimbay-Misericordia Viaduct: P1.25bn Castilla Bridge: P17.1bn Almasor Tourism: P19.28bn
TOTAL ASPIRATION: P69.03bn
Regional Strategic Initiatives for Countryside Competitiveness
118
ALMASORTourism Center of Luzon
120
Inter-Regional Connectivity
To Roxas City, Sibuyan and Romblon
To Roxas City and Estancia, IloiloTo Bogo City and Cebu City
To Bogo City, Cebu City, and Almagro and Tagapulan, Samar
To Batangas City, Lucena City, Manila
To Manila, Batangas City, and Lucena City
To San Isidro, Allen, Capul Is., and Biri
To Bogo City, and Cebu City
Intl port calls
AirportPortsRailwaysStrategic Roads
Tourism Hub, Service Centers and Gateways
STATUS OF ALBAY-MASBATE-SORSOGON TOURISM DEVELOPMENT AREA (ALMASOR)IDENTIFIED PRIORITY ROAD PROJECTS WITH RDC RES. NO. 36 (S. 2012)
PROVINCE/NAME OF PROJECTS PHYSICAL TARGET
ESTIMATED COST
(P'Million)
FY 2013 GAA FY 2014 GAA
Amount (P'Million)
Amount (P'Million)
I. INTER-PROVINCIAL
1 Four-Lane Naga-Legazpi Freeway System (FS for 6-
Lane requested to PMO-Feasibility Study, DPWH-CO) 78.70 km 3,620.200 Please see Note
2 Albay-Donsol Roads 138.64 km 3,188.700 a. Pioduran-Donsol Road 100.000 b. Camalig-Jovellar-Donsol Road 200.000 b.1. Cotmon-Maninila-Taplacon-Taloto Section 25.000 b.2. Salvacion-White Deer Section 25.000 c. Legazpi-Daraga-Donsol Road
c.1. Mayon-Bigao-San Vicente-Ibaugan-Gogon
Section 100.000 140.000
c.2. Embarcadero de Legaspi, Legaspi City (Tabon- tabon-Gabawan-Estanza-Taysan-Puro Road
80.800
d. Guinobatan-Jovellar- Donsol Road 100.000 100.000
3 Legazpi-Manito-Bacon-Sorsogon City 33.00 km 920.000 100.000 100.000
4 Tabaco-Malinao-Buhi Road, Camarines Sur & Albay 34.76 km 937.526
NOTE: Follow-up request for FS to CO dated 02-25-2014 : with letter reply dated 03-24-2014 informing that DPWH-CO has no staff yet for the newly created Project Preparation Division due to rationalization and the Technical Assistance for FS may be outsourced and oversight by our Planning Service.
STATUS OF ALBAY-MASBATE-SORSOGON TOURISM DEVELOPMENT AREA (ALMASOR)IDENTIFIED PRIORITY ROAD PROJECTS WITH RDC RES. NO. 36 (S. 2012)
PROVINCE/NAME OF PROJECTS PHYSICAL TARGET
ESTIMATED COST
(P'Million)
FY 2013 GAA
FY 2014 GAA
Amount (P’Million)
Amount (P’Million)
II. ALBAY
1 Albay West Coast Road 42.90 km 986.700 116.554 150.000 2 Cagraray Circumferential Road 13.95 km 320.850 75.000 250.000
3 Access Roads to Tourism Sites
a. Cagsawa Park 62.000
b. Camalig Caves (Hoyop-hoyopan,
Calabidongan, Solong) NO DATA YET
c. Jovellar Caves (Quitinday) NO DATA YET
d. Daraga (Naglaos Cave) NO DATA YET
e. Nagaso Boiling Lake NO DATA YET
f. Camalig Japan Tunnel NO DATA YET
g. Vera Falls, Malinao NO DATA YET
h. Busay Falls, Malilipot NO DATA YET
EMV-PDD-DPWHV
125
1. Albay West Coast Road (P874m)2. Guinobatan-Jovellar-Donsol Road (P878m)3. Pioduran-Donsol Road (300m)4. Legazpi Urban Flood Control (P1.4bn) -
funding
ALMASOR TOURISM ROADS
These are major provincial infra projects initiated by the provincial government of Albay; prepared feasibility studies; secured RDC/CABCOM approval and secured funding and budget strategy from the DBCC
BICOL COASTAL ROAD - INSERT
ALBAY WEST COAST ROAD
Albay West Coast Road
Initiated by the Provincial Government and whose feasibility study was conducted under Gov. Salceda. The Provincial Gov’t was instrumental in its approval by the RDC, by ICC Infracom, NEDA Cabcom and in securing a budget strategy from the DBCC, was included in the 2014 General Appropriations Act.
ALBAY WEST COAST ROAD
Camalig-Jovellar-Donsol RoadGuinobatan-Jovellar-Donsol RoadSan Isidro –San Roque – Banuang Gurang Road
Access to Donsol
Pioduran-Donsol Road
Jovellar-Donsol Road
These roads were initiated by the Provincial Government under the Almasor TRIPPC. The Province initiated the project proposal and feasibility study under Governor Salceda, secured approvals from RDC, Infracom TB, ICC TWG, NEDA Cabcom and DBCC and secure funding.
JOVELLAR-DONSOL ROAD
PIODURAN-DONSOL ROAD
131
ALMASOR TOURISM ROADS
1. Camalig Ecotourism Road2. Cagraray Circumferential Road3. Manito-Bacon Road4. Buhi-Polangui-Malinao Road
These are major provincial infra projects initiated by the provincial government of Albay; prepared feasibility studies; secured RDC/CABCOM approval and secured funding and budget strategy from the DBCC
Barangays: Busay - Pandan - Lacag - Tagoytoy - Mina - Tinago - Sumlang - Salvacion
Distance: 12.6 km
Cost: P145m
CAMALIG ECOTOURISM ROAD
Misibis Bay
Cagraray Circumferential Road (P100m)
CAGRARAY CIRCUMFERENTIAL ROAD
Cagraray Circumferential Road, Bacacay, Albay
135
136
137
ALMASOR: Bacon-Manito RoadP447m
Subject Road Section
ALMASOR: Buhi-Polangui Malinao Road P454m
Subject Road Section
STATUS OF ROAD SECTIONSNAME OF ROAD LENGTH (KM) STATUS1. Bacon-Manito Road a. Bacon, Sorsogon 24.25 km 5.188 km - concrete/asphalt
CY 2014 P100 M for road opening/const. with Notice of Award 9/9/2014
b. Manito, Albay 4.30 km Funding of P100M under CY 2013 for Albay @ Sorsogon side is for road opening, already completed.
2. Polangui-Buhi Road No available data a. Polangui, Albay 14.70 km Length measured based on google map b. Buhi, Camarines Sur 5.57 km Length measured based on google map3. Cagraray Circumferential Road, Bacacay, Island
39.90 km CY 2013 funding P75 M for const./improvement of road already completed as of Aug 7, 2014.CY 2014 plans for correction/rectification as per evaluation of Bureau of Design.
141
LEGAZPI URBAN DRAINAGE PROJECTType of Structure Amount
(P Million)
1. Construction of four (4) pumping stations at Tibu, Victory and Baybay
2. Dredging and construction of dike at Macabalo and Tibu River
3. Construction of Seawall4. Construction of Jetty
Estimated Project Cost
322.691
625.896
673.13361.155
2,241.136Note: Proposed projects was based on the updated final report, detailed engineering design of Flood Control & Drainage system of Legazpi City
142
Tibu River Channel Improvement
Construction of Jetties
Baybay Pumping Station
Tibu Pumping Station
144
PLGU-led Kalahi CIDSS with ADBRANK MUNICIPALITY PROPOSED SUB - PROJECT TOTAL PROJECT
COST MLGU DSWD PLGU
1 POLANGUIREHABILITATION/IMPROVEMENT OF DANAO-MATACON FARM TO MARKET ROAD
66,882,623.46 14,486,654.67 29,940,553.59 22,455,415.20
2 JOVELLARCONSTRUCTION (REHABILITATION/ IMPROVEMENT) OF BAUTISTA- SAN VICENTE FARM-TO-MARKET ROAD
17,367,793.86 1,500,000.00 9,067,310.78 6,800,483.08
3 PIODURANREHABILITATION/IMPROVEMENT OF BUYO - PALAPAS FARM TO MARKET ROAD
28,968,135.97 2,896,813.60 14,897,898.50 11,173,423.87
4 MANITOCONCRETING OF CENTRO-NAGOTGOT -BANAO-INANGMAHARANG FARM TO MARKET ROAD
41,831,448.26 4,183,144.83 21,513,316.25 16,134,987.19
5 OAS IMPROVEMENT/REPAIR OF BADBAD -BANGIAWON-PANTAO ROAD 25,357,255.48 7,607,176.64 10,142,902.19 7,607,176.64
6 GUINOBATANREPAIR/IMPROVEMENT OF BATBAT -CABALOAON-BALANAC FARM TO MARKET ROAD
28,776,475.21 5,755,295.04 13,154,960.10 9,866,220.07
7 STO. DOMINGOIMPROVEMENT/REHABILITATION/ EXPANSION OFSAN ISIDRO – SAN VICENTE ROAD
8,688,626.49 2,134,146.06 3,745,417.39 2,809,063.04
TOTAL 217,872,358.73 38,563,230.84 102,462,358.80 76,846,769.09
145
OAS-CAGMANABA ROAD
• Initial investments from Kalahi CIDSS and DPWH releases
• P540m was largest project approved by World Bank under the NCDDP
• P200m for bidding in 2014• P340m for procuremnet in 2015
146
OAS-CAGMANABA ROAD
147
OAS-CAGMANABA ROAD
Pistola-TablonFMR
Pistola-Tablon FMR Oas Municipal Hall
Start of Project
End of Project
Pistola
Camagong
Banao
Del Rosario
Tobgon
Badbad
Ramay
San Miguel
TalisayTablon
150
1. One-Step USAID for Cagsawa Ruins and Daraga tourism development (160m)
2. Mayon Rest House, Mayon Skyline Hotel and other provincial facilities (240m LBP loan)
3. Agri-Ethno Village, Cagsawa Ruins Rehab and Town Parks/Plazas Improvement (TIEZA 135m)
TOURISM FACILITIES DEVELOPMENT
ONE-STEP USAID
PROJECTDARAGA TOURISM
PROPOSED ONE-STEP PROJECTS
Name of Project Project Cost
1. Cagsawa Ruins Park Rehabilitation 35,000,000.002. Mayon - San Ramon - San Vicente
Grande - Nabasan Road 156,000,000.00 3. Peñafrancia - Gabawan - Bagumbayan - Ilawod Road 69,750,000.00 4. Busay - Pandan - Lacag - Inarado Road 61,500,000.00
TOTAL 322,250,000.00
ITEM PROJECT COST
1. Construction of Tourist Visitors Center 7,000,000.002. Construction of Ayuntamiento Function Hall 9,000,000.00 3. Construction of Comfort Rooms 800,000.004. Construction Welcome Arch 350,000.005. Construction of Perimeter Fence, Gate, Ticket Booth
and Guard House 6,000,000.006. Construction of Drainage System 1,350,000.00 7. Landscaping (removal of concrete pavements, clearing
& grubbing of trees, embankment & relocation of existing structures) 7,000,000.00
8. Construction of Water Facilities and Installation of Water Tank 1,500,000.00
9. Construction of Platform & Installation of Transformer & Other Electrical Facilities 2,000,000.00
TOTAL35,000,000.0
0
Rehabilitation & Improvement ofCagsawa Ruins Park
154
Rehabilitation & Improvement ofCagsawa Ruins Park
155
Rehabilitation & Improvement ofCagsawa Ruins Park
Tourist Visitors Center
Ayuntamiento Function Hall
156
Rehabilitation & Improvement ofCagsawa Ruins Park
Perimeter Fence
Gate, Ticket Booth and Guard House
157
Rehabilitation & Improvement of Cagsawa Ruins Park
Water Facility
Electrical Facility
ROAD SECTIONS
Name of Project Project Cost
1. Cagsawa Ruins Park Development 35,000,000.002. Mayon - San Ramon - San Vicente
Grande - Nabasan Road 156,000,000.00 3. Peñafrancia - Gabawan - Bagumbayan - Ilawod Road 69,750,000.00 4. Busay - Pandan - Lacag - Inarado Road 61,500,000.00
TOTAL 322,250,000.00
NABASAN CAVETOURISM DEVELOPMENT
Pan Philippine Highway
Nabasan Cave
Mayon - San Ramon - San Vicente Grande - Nabasan Road
Road length: 10.40 kmsTotal Cost : P 156,000,000.00
NABASAN CAVETOURISM DEVELOPMENT
ROAD SECTIONS
Name of Project Project Cost
1. Cagsawa Ruins Park Development 35,000,000.002. Nabasan Cave Development (access road) 156,000,000.00 3. Peñafrancia - Gabawan - Bagumbayan - Ilawod Road 69,750,000.00 4. Busay - Pandan - Lacag - Inarado Road 61,500,000.00
TOTAL 322,250,000.00
Peñafrancia - Gabawan - Bagumbayan - Ilawod Road
Road length: 4.65 kmsTotal Cost : P 69,750,000.00
Pan Philippine Highway
GABAWAN LAKE
ROAD SECTIONS
Name of Project Project Cost
1. Cagsawa Ruins Park Development 35,000,000.002. Nabasan Cave Development (access road) 156,000,000.00 3. Peñafrancia - Gabawan - Bagumbayan - Ilawod Road 69,750,000.00 4. Busay - Pandan - Lacag - Inarado Road 61,500,000.00
TOTAL 322,250,000.00
Pan Philippine Highway
Busay - Pandan - Lacag - Inarado RoadRoad length: 4.10 kmsTotal Cost : P 61,500,000.00
166
ALBAY AGRO ETHNO VILLAGE
167
Project Location Amount
1) Rehabilitation/Improvement of Mayon Skyline Hotel, Convention Center, Parks and Ground Tabaco City 60,000,000.00
2) Rehabilitation/Improvement of High Value Commercial Crops (HVCC) Tabaco City 30,000,000.00
3) Rehabilitation/Improvement of Livestock & Poultry Production, Training Center & Theme Park (LPPTC) 30,000,000.00
4) Rehabilitation/Improvement of Danao Lake Polangui 10,000,000.005) Rehabilitation/Improvement of Barubo View Park Polangui 5,000,000.006) Rehabilitation/Improvement of Nag-aso Lake Manito 8,000,000.007) Rehabilitation/Improvement of Agri-Training Center Tula-tula,
Ligao City 20,000,000.00
8) Rehabilitation/Improvement of Wildlife Park Legazpi City 77,000,000.00TOTAL 240,000,000.00
ALBAY ECO-TOURISM PROJECTS(240m LBP Loan)
168
ALBAY ECO-TOURISM PROJECTS
169
ALBAY ECO-TOURISM PROJECTS
170
ALBAY ECO-TOURISM PROJECTS
171
ALBAY ECO-TOURISM PROJECTS
172
ALBAY ECO-TOURISM PROJECTS
173
ALBAY ECO-TOURISM PROJECTS
174
ALBAY ECO-TOURISM PROJECTS
175
ALBAY ECO-TOURISM PROJECTS
176
TOURISM LANES
177
1. APEC ISOM Meeting on Dec 20142. XTERRA Off-Road Triathlon on Feb 20153. APEC Transportation Working Group
Meeting on 20154. PATA Conference on Nov 2015
TOURISM EVENTS MANAGEMENT
178
1. Champion of Palaro Bicol in 2011 after 26 years. Champion in 2012 and 2014.
2. Governor’s Cup is most participated sports event
3. Revitalized Albay Sports Office4. Football competition in Daragang Magayon,
Karangahan and Cagsawa Festivals5. Hosting of 2016 Palarong Pambansa
SPORTS
179
PALARONG PAMBANSA 2016
180
1. Daragang Magayon Festival, Karangahan and Cagsawa Festivals; and financial and logistical support to 18 LGU led festivals
2. Commissioned history books for Albay and 15 towns/cities3. Epic of 3 Mountains (Tulong Bulod) and Higantes4. Albay Poet Laureate5. Albay Historic-Cultural Unit6. Albay Social Media Group7. BU Magayon Dancers, Albay Volcanoes Chorale, Albay
Pageant Academy and Albay Rondalla8. UNESCO Heritage site as Biosphere Reserve9. Partnerships with NHCP, NCCA and KWF
ARTS, CULTURE and HISTORY
181
ALBAY PLANET
FESTIVAL
182
ALBAY BRANDS
183
ALBAY BRANDS
184
ALBAY BRANDS
185
ALBAY BRANDS
186
• UNESCO accreditation• REDD project with GIZ• Mayon Volcano Natural
Park – provincial co-management
• Cagraray Forest Reserve• Rapu-rapu mining
decommissioning and transformation to eco-tourism
THANK YOU
Mayon Volcano @ Sep 16 2014